MONTHYEARIR 05000458/20230402024-01-18018 January 2024 95001 Supplemental Inspection Supplemental Report 05000458/2023040 and Follow-Up Assessment Letter IR 05000458/20230102023-12-12012 December 2023 Biennial Problem Identification and Resolution Inspection Report 05000458/2023010 IR 05000458/20230032023-11-13013 November 2023 Integrated Inspection Report 05000458/2023003 IR 05000458/20234012023-09-26026 September 2023 Cyber Security Inspection Report 05000458/2023401 IR 05000458/20234032023-09-21021 September 2023 NRC Security Inspection Report 05000458/2023403 (Cover Letter) IR 05000458/20230012023-09-21021 September 2023 NRC Inspection Report 05000458/2023001, Disputed Non-Cited Violation Rescinded IR 05000458/20230122023-09-0101 September 2023 Comprehensive Engineering Team Inspection Report 05000458/2023012 IR 05000458/20230052023-08-21021 August 2023 Updated Inspection Plan for River Bend Station (Report 05000458/2023005) - Mid Cycle Letter IR 05000458/20230922023-08-15015 August 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023092 IR 05000458/20230022023-08-0909 August 2023 Integrated Inspection Report 05000458/2023002 IR 05000458/20230912023-07-20020 July 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023091 IR 05000458/20234042023-07-11011 July 2023 NRC Security Inspection Report 05000458/2023404 (Cover Letter Only) IR 05000458/20230902023-06-26026 June 2023 NRC Inspection Report 05000458/2023090 and Preliminary White Finding ML23116A2352023-05-0101 May 2023 Integrated Inspection Report 05000458/2023001 IR 05000458/20230112023-04-12012 April 2023 NRC License Renewal Phase 1 Inspection Report 05000458/2023011 IR 05000458/20220062023-03-0101 March 2023 Annual Assessment Letter for River Bend Station Report 05000458/2022006 IR 05000458/20220042023-02-0101 February 2023 Integrated Inspection Report 05000458/2022004 IR 05000458/20223012023-01-0303 January 2023 NRC Examination Report 05000458/2022301 IR 05000458/20220102022-12-12012 December 2022 Triennial Fire Protection Inspection Report 05000458/2022010 IR 05000458/20220032022-11-0303 November 2022 and Independent Spent Fuel Storage Installation Integrated Inspection Report 05000458/2022003 and 07200049/2022001 IR 05000458/20224022022-09-12012 September 2022 NRC Security Inspection Report 05000458/2022402 (Full Report) IR 05000458/20220022022-08-0909 August 2022 Integrated Inspection Report 05000458/2022002 IR 05000458/20220112022-06-0202 June 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000458/2022011 IR 05000458/20220012022-04-27027 April 2022 Integrated Inspection Report 05000458/2022001 IR 05000458/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000458/2021006) IR 05000458/20210042022-01-25025 January 2022 Integrated Inspection Report 05000458/2021004 ML22011A0992022-01-14014 January 2022 IR 2021012 EOI CO3 IR 05000458/20214022021-12-15015 December 2021 Security Baseline Inspection Report 05000458/2021402 IR 05000458/20214042021-12-0707 December 2021 Material Control and Accounting Program Inspection Report 05000458/2021404, Publicly Available IR 05000458/20214012021-12-0303 December 2021 Security Baseline Inspection Report 05000458/2021401 IR 05000458/20210032021-11-0404 November 2021 Integrated Inspection Report 05000458/2021003 IR 05000458/20210912021-09-30030 September 2021 Notice of Violation and Proposed Imposition of $150,000 Civil Penalty, NRC Inspection Report 05000458/2021091 and Investigation Reports 4-2020-008, 4-2020-009, and 4-2020-019 IR 05000458/20210022021-08-11011 August 2021 Integrated Inspection Report 05000458/2021002 IR 05000458/20210902021-07-0101 July 2021 NRC Inspection Report 05000458/2021090 and Investigation Reports 4-2020-008, 4-2020-009, and 4-2020-019 IR 05000458/20210132021-05-25025 May 2021 Rriver Bend Station - NRC Baseline Inspection Report 05000458/2021013 IR 05000458/20214032021-05-24024 May 2021 Security Baseline Inspection Report 05000458/2021403 IR 05000458/20210012021-05-0505 May 2021 RBS2021001-RP-RJK, River Bend Station - Integrated Inspection Report 05000458/2021001 IR 05000458/20210102021-03-18018 March 2021 2021 River Bend Station - Biennial Problem Identification and Resolution Inspection Report 05000458/2021010 and Notice of Violation IR 05000458/20200042021-02-11011 February 2021 RBS2020004-RP-RJK, River Bend Station - Integrated Inspection Report 05000458/2020004 IR 05000458/20200032020-11-16016 November 2020 Revised Integrated Inspection Report 05000458/2020003 ML20303A1402020-10-30030 October 2020 Integrated Inspection Report 05000458/2020003 IR 05000458/20200112020-10-0606 October 2020 Design Basis Assurance Inspection (Teams) Inspection Report 05000458/2020011 IR 05000458/20200122020-09-29029 September 2020 NRC Inspection Report 05000458/2020012, Investigation Report 4-2019-013 and Notice of Violation ML20273A2352020-09-29029 September 2020 NRC Inspection Report 05000458/2020012, Investigation Report 4-2019-013 and Notice of Violation IR 05000458/20204122020-09-28028 September 2020 Security Baseline Inspection Report 05000458/2020412 IR 05000458/20200502020-09-0303 September 2020 Special Inspection Report 05000458/2020050 IR 05000458/20204102020-09-0303 September 2020 Security Baseline Inspection Report 05000458/2020410 IR 05000458/20204112020-09-0303 September 2020 NRC Security Inspection Report 05000458/2020411 IR 05000458/20200052020-09-0101 September 2020 Updated Inspection Plan for River Bend Station (Report 05000458/2020005) IR 05000458/20200022020-07-30030 July 2020 Integrated Inspection Report 05000458/2020002 2024-01-18
[Table view] Category:Letter
MONTHYEARIR 05000458/20230402024-01-18018 January 2024 95001 Supplemental Inspection Supplemental Report 05000458/2023040 and Follow-Up Assessment Letter RBG-48271, Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk2024-01-12012 January 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML24011A1742024-01-11011 January 2024 Security Baseline Inspection Report (Cover Letter) ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection IR 05000458/20230102023-12-12012 December 2023 Biennial Problem Identification and Resolution Inspection Report 05000458/2023010 RBG-48267, Reply to a Notice of Violation, NRC Inspection Report 05000458/20230032023-12-0707 December 2023 Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1432023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23310A0322023-11-13013 November 2023 Integrated Inspection Report 05000458/2023003 IR 05000458/20230032023-11-13013 November 2023 Integrated Inspection Report 05000458/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23311A4322023-11-0909 November 2023 Notification of NRC Supplemental Inspection (95001) and Request for Information RBG-48264, Core Operating Limits Report (COLR) - Cycle 23, Revision 12023-11-0606 November 2023 Core Operating Limits Report (COLR) - Cycle 23, Revision 1 RBG-48260, Notification of Readiness for Supplemental Inspection2023-10-12012 October 2023 Notification of Readiness for Supplemental Inspection ML23278A2402023-10-0606 October 2023 Regulatory Audit Plan in Support of License Amendment Requests to Revise TSs to Adopt Risk-Informed Completion Times and Implement the Provisions of 10 CFR 50.69 RBG-48258, Notification of Readiness for Supplemental Inspection2023-10-0505 October 2023 Notification of Readiness for Supplemental Inspection RBG-48259, Revision to Reply to Notice of Violation; EA-23-0552023-10-0303 October 2023 Revision to Reply to Notice of Violation; EA-23-055 ML23270B9932023-09-29029 September 2023 Request to Update ASME Boiler & Pressure Vessel Code Relief Request SE with NRC-Approved Revision of Bwrip Guidelines (GG-ISI-020 & RBS-ISI-019) (EPID L-2022-LLR-0090) - Non-Proprietary ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000458/20234012023-09-26026 September 2023 Cyber Security Inspection Report 05000458/2023401 IR 05000458/20230012023-09-21021 September 2023 NRC Inspection Report 05000458/2023001, Disputed Non-Cited Violation Rescinded RBG-48254, Report of Changes and Errors to 10CFR50.462023-09-21021 September 2023 Report of Changes and Errors to 10CFR50.46 IR 05000458/20234032023-09-21021 September 2023 NRC Security Inspection Report 05000458/2023403 (Cover Letter) RBG-48249, Reply to a Notice of Violation, EA-23-0712023-09-14014 September 2023 Reply to a Notice of Violation, EA-23-071 RBG-48253, Submittal of Owner'S Activity Report Form for Cycle 222023-09-12012 September 2023 Submittal of Owner'S Activity Report Form for Cycle 22 IR 05000458/20230122023-09-0101 September 2023 Comprehensive Engineering Team Inspection Report 05000458/2023012 IR 05000458/20230052023-08-21021 August 2023 Updated Inspection Plan for River Bend Station (Report 05000458/2023005) - Mid Cycle Letter RBG-48247, Reply to Notice of Violation; EA-23-0552023-08-21021 August 2023 Reply to Notice of Violation; EA-23-055 IR 05000458/20230922023-08-15015 August 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023092 IR 05000458/20230022023-08-0909 August 2023 Integrated Inspection Report 05000458/2023002 ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23195A0692023-07-24024 July 2023 2023 River Bend Station Notification of Biennial Problem Identification and Resolution Inspection and Request for Information IR 05000458/20230912023-07-20020 July 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023091 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23195A0222023-07-11011 July 2023 4-2022-012 Letter - OI Closure to Licensee IR 05000458/20234042023-07-11011 July 2023 NRC Security Inspection Report 05000458/2023404 (Cover Letter Only) IR 05000458/20230902023-06-26026 June 2023 NRC Inspection Report 05000458/2023090 and Preliminary White Finding ML23159A2302023-06-0808 June 2023 Response to Request for Additional Information Concerning Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined RBG-48226, Core Operating Limits Report (COLR) - Cycle 23, Revision 02023-05-31031 May 2023 Core Operating Limits Report (COLR) - Cycle 23, Revision 0 RBG-48237, Response to NRC Integrated Inspection Report 05000458/20230012023-05-25025 May 2023 Response to NRC Integrated Inspection Report 05000458/2023001 ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23116A2352023-05-0101 May 2023 Integrated Inspection Report 05000458/2023001 RBG-48220, Submittal of 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report 2024-01-18
[Table view] |
Text
December 15, 2021
SUBJECT:
RIVER BEND STATION - SECURITY BASELINE INSPECTION REPORT 05000458/2021402
Dear Mr. Scott:
On November 11, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at River Bend Station and discussed the results of this inspection with Ms. Bonnie Bryant, General Manager of Plant Operations, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Digitally signed by Ray L.
Ray L. Kellar Kellar Date: 2021.12.15 08:26:29-06'00'
Ray L. Kellar, P.E., Chief Plant Support Branch 1 Division of Reactor Safety Docket No. 05000458 License No. NPF-47
Enclosure:
As stated
Inspection Report
Docket Number: 05000458 License Number: NPF-47 Report Number: 05000458/2021402 Enterprise Identifier: I-2021-402-0010 Licensee: Entergy Operations, Inc.
Facility: River Bend Station Location: St. Francisville, LA Inspection Dates: September 13, 2021 to November 11, 2021 Inspectors: D. Holman, Sr Physical Security Inspector C. Jewett, Physical Security Inspector Approved By: Ray L. Kellar, P.E., Chief Plant Support Branch 1 Division of Reactor Safety Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at River Bend Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
SAFEGUARDS
71130.01 - Access Authorization
The inspectors evaluated the access authorization program. The following elements were evaluated:
Access Authorization
Main article: IP 71130.01
(1)
- Tier I: All [or list requirements]
- Tier II: All [or list requirements]
- Tier III: All [or list requirements]
71130.02 - Access Control
The inspectors evaluated the access control program through completion of the following
inspection elements: Access Control
Main article: IP 71130.02
(1)
- Tier II: All Requirements
- Tier III: All Requirements
71130.09 - Security Plan Changes
The inspectors evaluated the security plan changes through completion of the following
procedure elements: Review Security Plan Changes (IP Section 02.01)
Main article: IP 71130.09
- (1) Since the last NRC inspection of this program area, Security Plan Revision 13 to 14 were implemented based on your determination, in accordance with 10 CFR 50.54(p)(2), that the changes resulted in no decrease in safeguards effectiveness of the security plan, and that the revised security plan changed continues to meet the requirements of 10 CFR 73.55(b). The inspectors conducted a review of the security plan changes to evaluate for potential decrease in safeguards effectiveness of the security plan. However, this review does not constitute formal NRC approval of the changes. Therefore, these changes remain subject to future NRC inspection in their entirety.
OTHER ACTIVITIES - BASELINE
71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17) (1 Sample)
- (1) July 20, 2020 through November 08,
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On November 11, 2021, the inspectors presented the security baseline inspection results to Ms. Bonnie Bryant, General Manager of Plant Operations, and other members of the licensee staff.
- On September 16, 2021, the inspectors presented the Access Authorization inspection results to Mr. Jeff Reynolds, Regulatory Assurance & Performance Improvement Director and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
71130.01 Corrective Action HQN-2018- Condition Report
Documents 00245, HQN-
2018-00253,
RBS-2018-00842,
HQN-2018-
291, RBS-
2018-03643,
RBS-2018-00586,
RBS-2019-00775,
RBS-2019-06539,
RBS-2019-07953,
RBS-2019-06792,
RBS-2019-07800,
RBS-2020-00522
Miscellaneous Entergy Quest Diagnostics Incorporated Contract, Norristown, PA 03/18/2009
Operations, INC.
Professional
General Services
Agreement,
Agreement NO.
230425
FF-125 Form - Contingency Processing Flow 004
Quest How long are my results and images stored in ESP?
Diagnostics
Frequently Asked
Questions,
Employer
Solutions Portal
Resources
Procedures EN-NS-101 Unescorted Access Authorization Program 31
EN-NS-101-03 Processing Individuals for UAA/UA and SGI Access 10
EN-NS-101-04 Processing Potentially Disqualifying Information (PDI) 5
Inspection Type Designation Description or Title Revision or
Procedure Date
EN-NS-102-03 Processing of Fitness for Duty Test Results 3
SPI-06 Alarm Station Supervisor 69
71130.02 Corrective Action CR-RBS-2021-
Documents 06824. CR-RBS-
Resulting from 2021-06853
Inspection
Procedures EN-NS 236 Warehouse Material Search 000
EN-NS-101-01 AA/FFD Facility Controls 013
EN-NS-224 SOCA Access Controls 003
EN-NS-231 Protected Area Search 003
EN-NS-237 Lock and Key 000
SPI-09 Vehicle/Material Search 43
STI-017-07-02-01 X-Ray Equipment Image Test -Warehouse 003
STI-017-07-07 Portable Explosive Detector Operability Test 003
71130.09 Miscellaneous RBS Physical Security Plan 014
71151 Corrective Action CR-RBS-2020-
Documents 05204, CR-RBS-
21-02689, CR-
RBS-2021-04793,
CR-RBS-2021-
05610, CR-RBS-
21-06173
6