Notice of Violation from Insp on 860701-31
ML20206M870
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 08/21/1986
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20206M866 List:
References
50-313-86-22, 50-368-86-23, NUDOCS 8608260004
Download: ML20206M870 (2)


Text

P APPENDIX A NOTICE OF VIOLATION Arkansas Power & Light Company Dockets: 50-313/86-22 Arkansas Nuclear One, Units 1 & 2 50-368/86-23 Licenses: DPR-51 NPF-6 During an NRC inspection conducted during the period July 1-31, 1986, violations of the NRC requirements were identified. The violations ir.volved failure to properly maintain an operating procedure and failure to obey a radiological posting. In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1985), the violations are listed below:

A. Unit 1 Technical Specification 6.8.1.a requires, in part, that written procedures shall be established, implemented, and maintained covering activities recommended in Appendix 'A' of Regulatory Guide 1.33, November 1972.

Paragraph C of this appendix recommends having written procedures for .

operation of the service water system.

Operating Procedure' 1104.29, " Service Water and Auxiliary Cooling System,"

has been established in accordance with this Technical Specification.

Contrary to the-above, Procedure 1104.29 was not adequately maintained by the licensee.' During a system walkdown, the NRC inspectors found that five manual valvss listed in Attachment A of Procedure 1104.29, " Valve

~

Lineup for SW and ACW Systems," are not installed in the plant. These valves had been noted as not installed in January 1985, by licensee operators conducting a system alignment using Revision 16 of Procedure 1104.29, but they were still listed on Revision 22 of this procedure dated July 3, 19,86.

This is a Severity Level IV violation. (Supplement I.D) (313/8622-01)

B. Unit 2 Technical Specification 6.11 requires, in part, that procedures for personnel radiation protection shall be prepared and adhered to for all operations involving personnel radiation exposure.

Licensee Procedure 1000.31, " Radiation Protection Manual," Section 9.3.8, paragraph C under " General Radiation Protection Rules" requires all personnel to comply with posted area entrance requirements.

The pressure vessel head stud cleaning tent was posted " airborne area, respiratory protection required" for entry.

8608260004 860821 PDR ADOCK0500g3 G

P e-4 s ,

Contrary to the above, _on July 9,1986, two licensee contract maintenance personnel entered the tent without respiratory protection.

This is a Severity Level V violation. (Supplement I.D) (368/8623-01)

Pursuant to the provisions of 10 CFR 2.201, Arkansas Power and Light Company is hereby required to submit to this Office within 30 days of the date of the letter transmitting this Notice, a written statement or explanation in reply, including for each violation: (1) the reason for the violation if admitted, (2) the corrective steps which have been taken and the results achieved, (3) the corrective steps which will be taken to avoid further violations, and (4) the date when full compliance will be achieved. Where good cause is shown, consideration will be given to extending the response time.