ML20195G390

From kanterella
Revision as of 11:15, 16 December 2020 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Startup Rept for Callaway Plant Uprating
ML20195G390
Person / Time
Site: Callaway Ameren icon.png
Issue date: 06/17/1988
From: Schnell D
UNION ELECTRIC CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
ULNRC-1793, NUDOCS 8806270331
Download: ML20195G390 (6)


Text

_ . .

$ Attachment to ULNRC-1793 Page.1 of 3 STARTUP REPORT FOR CALLAWAY PLANT UPRATING INTRODUCTION This report describes the testing which supported the increase in licensed power at Union Electric's Callaway l'Innt from 3411 MWt to 3565 MWt. It is submitted as required by Sections 6.9.1.1. 6.9.1.2 and 6.9.1.3 of the Callaway Technical Specifications.

The licensing submittal for approval to operate at 3565 MWt was made March 31. 1987 (ULNRC-1471). This submittal contained evaluations demonstrating that the NSSS and BOP systems had been reviewed and found to be capable of meeting all applicable safety design bases and power generation bases as defined in the FSAR at the uprated conditions without hardware changes.

-A separate licensing submittal (ULNRC-1470) to allow use of VANTAGE 5 fuel, also made on March 31. 1987. contained additional accident, radiological and nuclear evaluations.

The NRC approved the uprating on March 30. 1988. Power was suc-cessfully increased to the new licensed level on April 8. 1988.

IMPLEMENTATION OF UPRATING Procedure changes and instrument loop calibrations which were prerequisites for implementation of the uprating were implemented from April 4 through April 7. 1988. Core power was increased to 3565 MWt in two increments on April 8. 1988.

Although the uprating was approved by the NRC on March 30. 1988, implementation did not begin until April 4.- The first step of the uprating revision of affected software, was executed on April 4.

Affected sof tware included precedures, operating curves and computer software. All changes had been identified and prepared prior to this date so that issuance of revisions occurred in an orderly and expeditious manner.

Following completion of software revision, a heat balance calcula-tion was performed per the revised plant procedure OSP-SE-00004. NIS Power Range Heat Balance. This adjusted the nuclear instrumentation to -

indicate power as a percent of 3565 MWt. the new rated power level.

I A

g)

F

\

  • D Attachment to ULNRC-1793 Page 2 of 3 Scaling changes were made to plant instrumentation during the subsequent 3 days. Differential temperature indications for all 4 reactor coolant loops, the rod control program, the steam dump program, and pressurizer level control were rescaled. A flux map was taken to verify that F and F would not exceed their limits when extrapolated totheupratekpowerSevel. On April 8, power was increased to approx-imately 3565 MWt. Concurrent with and following the power increase, extensive testing was performed to verify the plant's capability to operate at a reactor power of 3565 MWt.

SUMMARY

OF TESTING Reactor After power had been raised to approximately 3565 MWt and plant conditions were stable, an incore flux map was taken to verify that F and F g did not exceed their limits. F was determined to be 1.7680.0 O which was below the limit of 1.9773. F was 1.3767, compared to a AH limit of 1.4909.

During and after the power increase, calorimetric data was taken and the power range nuclear instrumentation adjusted to ensure proper indication. After full power was reached, new setpoints were calculated for intermediate range trip and rod stop, which are 25% and 20% of full power, respectively.

Primary Systems The highest reactor coolant loop outlet temperature. T , was monitored continuously during the power increase. Alimit$9620*Fwas established to minimize potential steam generator tube degradation. The maximum loop outlet temperature recorded was 617.1*F.

Differential temperature was measured for each reactor coolant loop after power was increased to verify that it had been rescaled correctly, Measured AT was within l'F of the scaled full power AT for all loops.

Data was also taken to characterize the Callaway thermal hydraulic flow ancmaly and ecepared to similar data taken prior to the uproting.

The magnitude of the changes in core exit thermocouple temperatures, reactor vessel differential pressure and excore nuclear power were no:

affected by the upvating.

Other primary system data trended during the power increase includ-ed reactor coolant flow, reactor coolant pump current, and reactor coolant pump vibration. No significant changes were noted in these parameters.

After power was increased, new baseline data was taken for the loose parts monitoring system.

Balance of Plant Systems Extensive data was taken on the turbine systems prior to and during l

. ~

Attachment to ULNRC-1793 Page 3 of 3 the power increase, including steam pressure and temperature at various locations. bearing temperatures, lube oil temperatures, lube oil pressurcs, bearing vibration, and control valve position. No unexpected changes were observed and operation of the turbine at the uprated power level was satisfactory.

The generator and associated components were also monitored close-ly. Generator output, winding temperatures, gas temperatures, gas pressure, isophase bus temperatures, and transformer temperatures were recorded. All changes were within the expected range.

Flow, temperature and pressure data were taken in the condensate, feedwater and main steam systems. Also recorded were differential pressure ac~oss the condensate polishers, steam generator levels, levels in feedwater heaters, and heater level control valve positions. These parameters were within expected ranges.

Data was taken to verify no adverse affects on containment temper-ature due to the uprating. Temperatures were recorded at containment cooler fan inlets, control rod drive mechanism shroud return, reactor cavity cooling return, and steam and feedwater piping torsional re-straints. Reactor cavity concrete temperatures were monitored. Average containment temperature was also recorded. All temperatures met accep-tance criteria.

Pipe vibration data was taken on steam and feed flow piping. There were no significant changes in piping vibration. In addition, new baseline data was taken for vibration of rotating equipment.

A biological shield survey was performed at the uprated power level, Radiation levels did not significantly increase inside contain-ment, and changes in dose rates outside containment were not detectable.

i l

1 I

~

Umcw Etscraic a1901 Gratet Street. St. Lours Donald F. Schnell Vce President June 17, 1988 U.S. NucleGr Regulatory Commission Document Uontrol Desk Washing *.on, DC 20555 ULNRC-1793 Gentlemen:

DOCKET NUMBER 50-483 CALLAWAY PLANT UNIT 1 FACILITY OPERATING LICENSE NPF-30 STARTUP REPORT The enclosed Startup Report is submitted pursuant to Sections 6.9.1.1, 6.9.1.2, and 6.9.1.3 of the Callaway Unit 1 Technical Specifications.

Very truly yours, Donald F. Schnell DFS/JDB/bjp Enclosure cc: Distribution attached h

}

I

\

Afading Address: P.O. Box 149, St. Louis, MO 63166

  • I' ULNRC- 179 3 Page 2 June 17, 1988 cc: Mr. A. Bert Davis, Regional Administrator U.S. Nuclear Regulatory Commission Region III 799 Roosevelt' Road Glen Ellyn, IL 60137 Mr. R. W. DeFayette Chief, Project Section 3A U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137 Mr. T. W. Alexion'(2) '

Licensing Project Manager, Callaway office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 13-E-21 Washington, DC 20555 ,

Messrs. B. H. Little/C. H. Brown Resident NRC Inspector, Callaway Plant U.S. Nuclear Regulatory Commission RR #1' Steedman, MO 65077 Manager, Electric Department Missouri Public Service Commission P. O. Box 360

  • Jefferson City, MO 65102 i

L e r

.- - , . . , , ,. .,,,-----,-..-.c,,,. - ,

( . .'

ULNRC-1793 Page 3 June 17, 1988 bec: Distribution for ULNRC- 1793 N. Date (S. L. Auston) (470)

E210.01 A160.761 DFS/ Chrono R. J. Schukai G. L. Randolph F. D. Field A. P. Neuhalfen Licensing and Fuels (A. C. Passwater/

D. E. Shafer/D. J. Walker)

T. P. Sharkey NSRB (S. L. Auston (470)

H. Wuertenbaccher (100)

O. Maynard (WCNOC)

K. R. Bryant (CA-460)

J. D. Blosser (CA-460)