Notice of Violation from Insp on 850401-30
ML20126C041
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 06/10/1985
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20126C009 List:
References
50-368-85-07, 50-368-85-7, NUDOCS 8506140289
Download: ML20126C041 (2)


Text

I APPENDIX A NOTICE OF VIOLATION

, Arkansas Power & Light Company Docket: 50-368/85-07 Arkansas Nuclear One, Unit 2 License: NPF-6 Based on the results of an NRC inspection during the period of April 1-30, 1985, and in accordance with the NRC Enforcement Policy (10 CFR Part 2, Appendix C), 49 FR 8583, dated March 8, 1984, the following violations were identified:

1. Failure to Follow Procedural Requirements for Design Change Control (Unit 2) 10 CFR Part 50, Appendix B, Criterion V and Section 5.1.1 of the AP&L Quality Assurance Manual-Operations (APL-TOP-1A) require that activities affecting quality.shall be prescribed by documented instructions, procedures, or' drawings, of a type appropriate. to the circumstances,- and shall be accomplished in accordance with these procedures, instructions, and drawings.

Overall Plant Administrative Procedure 1000.13, " Control of Station Modifications," has,been established in accordance with Criterion V and APL-TOP-1A.

Section 6.4.11 of Procedure 1000.l'3 requires that all design changes be installed as described in the design change package (DCP).

Contrary to the above, fire door 210 was installed and the DCP closed out; but the type of latching mechanism specified in the DCP was not installed.

-This is a Severity Level IV Violation. (Supplement I.0) (368/8507-01)

2. Failure to Follow Procedural' Requirements for Radiation Protection (Unit-2) 10 CFR Part 50, Appendix B, Criterion V and Section 5.1.1 of the AP&L Quality Assurance Manual-Operations (APL-TOP-1A) require that activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances, and shall be accomplished in accordance with procedures, instructions, and drawings.

Overall Plant Administrative Procedur 1300.31, " Radiation Protection

~ Manual," has been established in accordance with Criterion V and ADL-TOP-1A.

Section 9.3.8.C of Procedure 1000.31 requires that personnel comply with the posted area entrance requirements.

8506140289 850610 PDR ADOCK 05000313 G PDR

_ __ _________________ _ _ _-_ _ _ -w

Notice of Violation Contrary to the above, on or'about April 7,1985, the NRC inspector observed an individual working in an area posted as beta protection required, without the proper beta' protection equipment.

'This is a Severity Level V Violation. (Supplement I.E) (368/8507-02)

^

Pursuant to the provisions of 10 CFR 2.201, Arkansas Power & Light Company is hereby required to submit to this office, within 30 days of the date of this Notice, a written statement or explanation in reply, including: (1)'the corrective steps which have been taken and:the results achieved; (2)'the corrective steps.which will be.taken.to avoid further violations; and (3) the date when full compliance will be achieved. Consideration may be given to extending your response time for good ca'use shown.

Dated: