MONTHYEARML24295A0862024-10-21021 October 2024 Notification of NRC Baseline Inspection and Request for Information Inspection Report 0500026/2025002 IR 05000266/20240052024-08-21021 August 2024 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2024005 and 05000301/2024005) IR 05000266/20230062024-02-28028 February 2024 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2023006 and 05000301/2023006) ML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 IR 05000266/20220062023-03-0101 March 2023 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022006 and 05000301/2022006) ML23003A8022023-01-0303 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22256A3182022-09-13013 September 2022 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection Report 05000266/2023010 05000301/2023010 IR 05000266/20220052022-08-26026 August 2022 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022005 and 05000301/2022005) ML22175A2002022-06-27027 June 2022 Request for Information for an NRC Triennial Heat Exchanger/Sink Performance Inspection and Request for Information: Inspection Report 05000266/2022004: 05000301/2022004 ML22173A0172022-06-22022 June 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Point Beach Nuclear Plant ML22172A2132022-06-22022 June 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection IR 05000266/20210062022-03-0202 March 2022 Annual Assessment Letter for Point Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021006 and 05000301/2021006) ML22041B0752022-02-10010 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000266/2022002 ML21253A1672021-09-10010 September 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information Inspection Report 05000266/2022010 05000301/2022010 IR 05000266/20210052021-09-0101 September 2021 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021005 and 05000301/2021005) ML21214A2812021-08-0202 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21180A2302021-06-29029 June 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2021004 and 05000301/2021004 ML21074A3962021-03-15015 March 2021 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection; Inspection Report 05000266/2021010; 05000301/2021010 IR 05000266/20200062021-03-0404 March 2021 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020006 and 05000301/2020006) IR 05000266/20200052020-09-0101 September 2020 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020005 and 05000301/2020005) ML20218A4322020-08-0505 August 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2020004 ML20168A8912020-06-15015 June 2020 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Point Beach Nuclear Plant, Units 1 and 2 IR 05000266/20190062020-03-0303 March 2020 Annual Assessment Letter for Point Beach Nuclear Plants, Units 1 and 2 (Report 05000266/2019006 and 05000301/2019006) IR 05000266/20190052019-08-28028 August 2019 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2019005 and 05000301/2019005) ML19190A1532019-07-0909 July 2019 Ltr. 07/09/19 Point Beach Nuclear Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000266/2019012; 05000301/2019012 (DRS-G.Hausman) ML19136A1402019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19094B1182019-04-0404 April 2019 Ltr. 04/04/19 Point Beach Nuclear Plant, Units 1 and 2 - Request for Information for an NRC Design Bases Assurance Inspection (Program): Implementation of the EQ Program; Inspection Report 05000266/2019013 and 05000301/2019013 (DRS-B.Jose) IR 05000266/20180062019-03-0404 March 2019 Annual Assessment Letter for Point Beach Nuclear Plant (Report 05000266/2018006 and 05000301/2018006) ML19037A3102019-02-0505 February 2019 Ltr. 02/05/19 Point Beach Nuclear Plant, Units 1 and 2 - Information Request for the Cyber-Security Full Implementation Inspection, Notification to Perform Inspection; Inspection Report 05000266/2019412; 05000301/2019412 (DRS-G.Hausman) ML19024A2772019-01-24024 January 2019 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2019001 (DRS-M.Domke) IR 05000266/20180052018-08-28028 August 2018 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2018005 and 05000301/2018005) IR 05000266/20170062018-03-0202 March 2018 Annual Assessment Letter for Point Beach Plant, Units 1 and 2 (Report 05000266/2017006 and 05000301/2017006) IR 05000266/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000266/2017005 and 05000301/2017005) ML17088A7242017-03-29029 March 2017 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000266/2017007; 05000301/2017007 IR 05000266/20160062017-03-0101 March 2017 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2016006 and 05000301/2016006) ML17039B0182017-02-0808 February 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Point Beach Nuclear Plant, Units 1 and 2 - Inspection Report 05000266/2017008; 05000301/2017008 IR 05000266/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant Units 1 and 2 (Report 05000266/2016005; 05000301/2016005) IR 05000266/20150062016-03-0202 March 2016 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Inspection Report 05000266/2015006 and 05000301/2015006) IR 05000266/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2015005; 05000301/2015005) ML15131A3132015-05-0808 May 2015 Ltr. 05/08/15 Point Beach Nuclear Plant, Units 1 and 2 - Information Request for an NRC Triennial Permanent Modifications and 10 CFR 50.59 (Mod/50.59) Baseline Inspection 05000266/2015010; 05000301/2015010 (Jjc) ML15124A9012015-05-0101 May 2015 Ltr. 05/01/15 Point Beach Nuclear Plant, Unit 2 - Notification of NRC Inspection and Request for Information (Msh) IR 05000266/20140012015-03-0404 March 2015 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2014001; 05000301/2014001) ML15050A2702015-02-19019 February 2015 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Point Beach Nuclear Plant, Units 1 and 2 ML14245A1662014-09-0202 September 2014 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 IR 05000266/20130012014-03-0404 March 2014 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2013001; 05000301/2013001) ML14038A3472014-02-0606 February 2014 ISI Request for Information ML13246A2212013-09-0303 September 2013 2013 Point Beach MOC Letter Combined 2024-08-21
[Table view] Category:Letter
MONTHYEARIR 05000266/20244022024-11-14014 November 2024 Security Baseline Inspection Report 05000266/2024402 and 05000301/2024402 IR 05000266/20240032024-11-0505 November 2024 Integrated Inspection Report 05000266/2024003 and 05000301/2024003 ML24295A1142024-10-31031 October 2024 Suppl Env Audit Summary Letter W/Enclosure 1 L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums ML24295A0862024-10-21021 October 2024 Notification of NRC Baseline Inspection and Request for Information Inspection Report 0500026/2025002 L-2024-160, Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41)2024-10-21021 October 2024 Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41) L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-120, LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization2024-10-0808 October 2024 LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000266/2024011 and 05000301/2024011 L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-145, Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency2024-09-0909 September 2024 Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency ML24207A0202024-08-28028 August 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Point Beach Nuclear Plant, Units 1 and 2 (Docket Numbers: 50-0266 and 50-0301) IR 05000266/20240052024-08-21021 August 2024 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2024005 and 05000301/2024005) IR 05000266/20240022024-08-13013 August 2024 Integrated Inspection Report 05000266/2024002 and 05000301/2024002 L-2024-131, Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-08-0909 August 2024 Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review ML24214A3092024-08-0202 August 2024 Confirmation of Initial License Examination L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24194A1802024-07-24024 July 2024 – Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule L-2024-113, License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections2024-07-24024 July 2024 License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections IR 05000266/20244012024-07-23023 July 2024 Public - Point Beach Nuclear Plant Cyber Security Inspection Report 05000266/2024401 and 05000301/2024401 ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-116, Preparation and Scheduling of Operator Licensing Examinations2024-07-11011 July 2024 Preparation and Scheduling of Operator Licensing Examinations IR 05000266/20240102024-07-10010 July 2024 Age-Related Degradation Inspection Report 05000266/2024010 and 05000301/2024010 L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-105, License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-06-26026 June 2024 License Amendment Request 300, Modify Containment Average Air Temperature Requirements L-2024-107, Schedule for Subsequent License Renewal Environmental Review2024-06-25025 June 2024 Schedule for Subsequent License Renewal Environmental Review ML24176A2242024-06-24024 June 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-093, Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision2024-06-10010 June 2024 Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision IR 05000266/20244202024-06-0505 June 2024 Security Baseline Inspection Report 05000266/2024420 and 05000301/2024420 ML24149A1922024-05-28028 May 2024 Notification of NRC Baseline Inspection and Request for Information ML24141A1382024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection.Docx ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000266/2024301; 05000301/2024301 L-2024-067, Annual Monitoring Report2024-04-26026 April 2024 Annual Monitoring Report ML24116A0402024-04-23023 April 2024 Periodic Update of the Updated Final Safety Analysis Report ML24071A0912024-04-22022 April 2024 Issuance of Relief Request I6-RR-03 - Extension of the Unit 2 Steam Generator Primary Nozzle Dissimilar Metal Welds Sixth 10-Year Inservice Inspection Program Interval IR 05000266/20240012024-04-11011 April 2024 Integrated Inspection Report 05000266/2024001 and 05000301/2024001 L-2024-030, Supplement to Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-03-27027 March 2024 Supplement to Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements L-2024-043, Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules2024-03-25025 March 2024 Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules L-2024-011, And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications IR 05000266/20230062024-02-28028 February 2024 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2023006 and 05000301/2023006) ML24053A3732024-02-22022 February 2024 Operator Licensing Examination Approval Point Beach, March 2024 L-2024-020, Refueling Outage Owners Activity Report (OAR-1) Unit 1 for Inservice Inspections2024-02-22022 February 2024 Refueling Outage Owners Activity Report (OAR-1) Unit 1 for Inservice Inspections ML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 IR 05000266/20230042024-02-0101 February 2024 Integrated Inspection Report 05000266/2023004 and 05000301/2023004 2024-09-09
[Table view] |
Text
rch 4, 2003
SUBJECT:
ANNUAL ASSESSMENT LETTER - POINT BEACH NUCLEAR PLANT (REPORT 50-266/03-01, 50-301/03-01)
Dear Mr. Cayia:
On February 12, 2003, the NRC staff completed its end-of-cycle plant performance assessment of the Point Beach Nuclear Plant. The end-of-cycle review for the Point Beach Nuclear Plant involved the participation of all technical divisions in evaluating performance indicators for the most recent quarter and inspection results for the period from January 1 through December 31, 2002. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections that may conflict with your plant activities.
Overall, Point Beach Nuclear Plant operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter was within the Regulatory Response Column of the NRCs Action Matrix based on two White findings, one in the Mitigating Systems Cornerstone associated with Unit 2, and one in the Emergency Preparedness Cornerstone associated with both units. However, a determination will soon be made as to whether or not the final Red finding, associated with the potential for common mode failure of the auxiliary feed water system due to a loss of instrument air and previously communicated to you in our final significance determination letter of July 12, 2002, will be treated as an Old Design Issue. Also, in the near term, we expect to complete our initial risk evaluation and assessment of a current issue associated with another potential common mode failure of the auxiliary feed water (AFW) system. This potential common mode failure was identified in October 2002 and is associated with the potential plugging of system recirculation orifices. If the final Red finding associated with the loss of instrument air does not warrant treatment as an Old Design Issue, then Point Beach will be placed in the Multiple/Repetitive Degraded Cornerstone Column of the Action Matrix and appropriate actions will be taken. We will notify you via separate correspondence of our determination regarding the Old Design Issue and our preliminary risk evaluation and assessment of the current orifice plugging potential common mode failure issue.
While plant performance for the most recent quarter is within the Regulatory Response Column of the Action Matrix, there were additional safety significant inspection findings and performance indicators during the first three quarters of the assessment cycle that kept Point Beach within the Regulatory Response Column. Associated with Unit 1, the performance indicator for Scrams With Loss of Normal Heat Removal was White during the first quarter.
This performance indicator returned to Green in the second quarter, but Unit 1 remained in the Regulatory Response Column during the remainder of the assessment period due to a White Emergency Preparedness inspection finding from the second quarter. This White Emergency Preparedness finding was associated with a February 2002 biennial exercise. For Unit 2, there was one White finding in the Mitigating Systems Cornerstone associated with failure of a Safety Injection pump during the first quarter and the White Emergency Preparedness inspection finding from the second quarter.
Additionally, the staff has identified a substantive cross-cutting issue in the area of Problem Identification and Resolution. This was based on the White findings involving the Safety Injection pump and Emergency Preparedness and four Green findings. The four Green findings involved the flooding of manholes containing plant equipment, repeat problems with cold weather preparations, delayed maintenance rule action for the G05 gas turbine, and an inadequate extent of condition review when addressing a steam generator narrow range level detector problem. The White and Green findings are substantive in that ineffective evaluation of performance deficiencies, untimely and ineffective corrective actions, and lack of coordination between licensee departments are causally linked in more than one cornerstone.
The enclosed inspection plan details the inspections scheduled through March 31, 2004. In addition to baseline inspections, there will be a 95001 Supplemental Inspection conducted in March 2003 to review the White inspection finding in the Emergency Preparedness area. Also, there will be inspections of plant security in August 2003, and of the Unit 2 reactor head and head penetration nozzles in October 2003. The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last six months of the inspection plan are tentative and may be revised at the mid-cycle review meeting. Additional inspections not shown on the plan may be required if the NRC concludes that the Red AFW finding is not an Old Design Issue, or if the current AFW recirculation orifice plugging issue results in a finding of more than very low safety significance. You will be notified by separate correspondence if additional inspections are to be conducted.
As you are aware, since the terrorist attacks on September 11, 2001, the NRC has issued several Orders and Threat Advisories to enhance security capabilities and improve guard force readiness. We have conducted inspections to review your implementation of these requirements and have monitored your actions in response to changing threat conditions. For calendar year 2003, we plan to continue these inspections and conduct portions of the security baseline inspection program, as well as perform additional inspections to evaluate your compliance with new requirements that may be ordered. Based on our final determinations in this regard, we will notify you of any inspection plan changes. In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Kenneth Riemer at 630-829-9757 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
J. E. Dyer Regional Administrator Docket Nos. 50-266, 50-301 License Nos. DPR-24; DPR-27 Enclosure: Point Beach Nuclear Plant Inspection/Activity Plan See Attached Distribution