Forwards Final Deficiency Rept Re Tensile Anchor Capacities Lower than Assumed in Design Allowables
ML19210D104
Person / Time
Site: Hartsville, Phipps Bend  Tennessee Valley Authority icon.png
Issue date: 10/26/1979
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19210D105 List:
References
NCR-CEB-79-16, NCR-CEB-79-17, NUDOCS 7911200541
Download: ML19210D104 (1)


Text

77':CC6- 0 3b 71-CCW 63h d'#- '

TENNESSEE VALLEY AUTHORITY 7 9.-Co S 63 b CHATTANOOGA, TENNESSEE 374ot 400 Chestnut Street Tower II 79 0$3-05 _

October 26, 1979 ] _Q

,n

,-s~ -@

c 5)

.- 7 3 7 Mr. James P. O'Reilly, Director Office of Inspection and Enforcement -

U.S. Nuclear Regulatory Commission Region II - Suite 3100 101 Marietta Street ~

Atlanta, Georgia 30303

Dear Mr. O'Reilly:

HARTSVILLE AND PHIPPS BEND NUCLEAR PLANTS - REPORTABLE DEFICIENCY -

TENSILE ANCHOR CAPACITIES LOWER THAN ASSUMED IN DESIGN ALLOWABLES (NCR CEB-79-16 AND NCR CEB 79-17)

Initial report of the subject deficiency was made to Mike Gouge, NRC-01E, Region II on May 7,1979. The first and second interim reports were submitted on May 24, 1979, and August 13, 1979, respectively.

In compliance with paragraph 50.55(e) of 10 CFR Part 50, we are enclosing the final report of the subject deficiency. If you have any questions concerning this matter, please call Tish Jenkins at FTS 854-2014.

Very truly yours, TENNESSEE VALLEY AUTHORITY b

L. M. Mills, Manager M

Nuclear Regulation and Safety Enclosure 13/3 >:,.;

\

b \\

'54j 7911200 ' ' '

ONS I ' ' ' ' '

An Equal Opportunity Employer