ML20195J17429 November 1988Provides Supplemental Response to Violations Noted in Insp Rept 50-518/87-01.Corrective Actions:Completion of Procedure on Prescribing Preventive Maintenance Requirements Rescheduled for 890301
ML20151E75114 July 1988Responds to NRC Re Violations Noted in Insp Repts 50-518/87-01 & 50-520/87-01.Corrective Actions:Reviewed Vendors Storage & Preventive Maint Instructions Against Tech Spec 01.00.15.14.03 & Revised Topical Rept TVA-TR75-1ACoatings
ML20150B9001 March 1988Forwards Insp Rept 50-518/87-01 on 871216-18 & Notice of Violation.Allegation Partially Substantiated.Problem Re Practice of Allowing Nuclear safety-related Equipment to Be Downgraded & Moved Out of Storage to Weather Revealed
ML20235B45322 September 1987Final Response to FOIA Request for Documents Re Specified Dockets.Documents in App a Already Available in Pdr.Forwards App B Documents.App B Documents Also Available in Pdr. Documents for Listed Dockets Could Not Be Located
ML20235B36225 August 1987FOIA Request for Listed Documents for Specified Dockets
ML20215A1589 December 1986Final FOIA Response to Request for Documents Re Welding,Mfg & Const Deficiencies Concerning Tdi.Forwards App E Documents.Documents Also Available in PDR
ML20211K5533 December 1986Partial Response to FOIA Request for Records from Vendor Insp Branch,Ie,Re Tdi.Documents Identified in App C Available in Pdr.Documents in App D Available in PDR Under FOIA Number 86-656 & Requester Name
ML20205F7578 August 1986Forwards Insp Repts 50-518/86-01 & 50-520/86-01 on 860717- 18.No Violations or Deviations Noted
ML20206H8009 June 1986Forwards Request for Addl Info Required to Complete Review of Site Stablilzation Plan.Site Visit Requested 2 Wks After Receipt of Response
ML20138Q8303 December 1985Further Response to FOIA Request for Records Re Voluntary or Required Redress of Sites Where Const Was Terminated, Including Crbr & Legal Analysis.Forwards App E Documents.App D & E Documents Available in Pdr.Photographs Also Available
ML20133N73224 October 1985Forwards Proposed Cancellation Plans for Plants Officially Canceled on 840829.Requests Withdrawal of CPPR-150,CPPR-152, CPPR-172 & CPPR-173.W/two Oversize Drawings
ML18029A39827 February 1985Responds to RM Diggs 850117 & 0211 Ltrs Re Determination of Fees for Const Extension Requests.Util Supports NRC Determination & Will Submit Fees
ML20096F8475 September 1984Forwards Motion to Terminate Appellate Jurisdiction.W/O Encl.Related Correspondence
ML20090B35522 May 1984Forwards Response to Unresolved Items in IE Insp Repts 50-518/84-01 & 50-520/84-01.Corrective Actions:Util Prepared Preventive Maint Document Establishing Guidance for Protection,Preservation & Periodic Insp of Matls
ML20093F09222 May 1984Responds to NRC Re Violations Noted in IE Insp Repts 50-518/84-01 & 50-520/84-01.Corrective Actions:Matl & Equipment Will Be Maintained Per Requirement Documents & Permanent Structures Will Be Thoroughly Inspected Annually
ML20084R65224 February 1984FOIA Request for Computer Printout from Sept 1980 to Present of Civil Penalty Info on 27 Listed Nuclear Facilities.Sample Format Encl
ML20077G66627 July 1983Part 21 Rept Re Circuit Breakers Mfg Between Nov 1981 & Feb 1982.Breakers Should Be Inspected for Broken Puffer Linkage Studs.Stud Identified as Part Number 192247A.List of Circuit Breakers for Nuclear Plants Encl
ML20073S8595 May 1983Forwards Details of Deferral Plans for Hartsville Nuclear Plant A. Yellow Creek Plan Submittal Delayed Until 830513
ML20071B97424 February 1983Reiterates 830121 Request for CP Extension Until 870901 to Permit Final Decision Re Future of Nuclear Units Based on Load Growth/Demand.Deferral Plan Details to Be Submitted by 830506
ML20069Q36630 November 1982Forwards Socioeconomic Monitoring & Mitigation Rept, & Const Employee Monitoring Errata Rept
ML20065S37926 October 1982Informs of Discussions Re Leasing Portions of Site to Lansdowne Steel & Iron Co for 10 Yrs.Description of Site Portions Under Consideration Encl.Cp for Sites Withdrawn
ML20065F83713 September 1982Forwards Response to NRC Re Violations Noted in IE Insp Repts 50-518/82-08 & 50-520/82-08.Corrective Actions:Qc Investigation Rept Written to Prevent Use of Protective Coatings & PVC Conduit Covered & StoredCoatings
ML20069D51610 September 1982Forwards Socioeconomic Monitoring & Mitigating Rept,Sept 1981
ML20055C0616 August 1982Forwards Info Re QA for Deferred Plants,In Response to NRC .Possible Cancellation of Some Units Will Be Discussed at Future Meeting of TVA Board of Directors
ML20062H75416 July 1982Forwards IE Insp Repts 50-518/82-09,50-519/82-08, 50-520/82-09 & 50-521/82-08 on 820601-04 & 28-30.No Noncompliance Noted
ML20054M21229 June 1982Responds to Appeal Re Denial of FOIA Request for Documents Re Atlas Machine & Iron Works,Inc.Forwards Me Resner 811109 & 820113 Memos to File
ML20054K15323 June 1982Informs That Final Deficiency Repts for Listed Nonconformances Will Not Be Submitted Until Final Decision Is Made Re Const of Projects
ML20055A10617 June 1982Forwards IE Insp Repts 50-518/82-07,50-519/82-07, 50-520/82-07 & 50-521/82-07 on 820503-14 & 21-28.No Noncompliance Noted
ML20054D65019 February 1982Submits Final Response Re IE Bulletin 80-20, Failures of Westinghouse Type W-2 Spring Return to Neutral Control Switches. No Westinghouse Type Switches Used in Facilities
ML20041C10918 February 1982Forwards Hartsville Nuclear Plants Socioeconomic Monitoring & Mitigation Rept,Hnp SMR-10,810331, as Required by Cps. Continuing Info Will Be Provided on Semiannual Basis
ML20040G8154 February 1982Forwards Revision 2 to, Geologic Foundation Rept,Fault Descriptions, Per 780531 Meeting Request
ML20040E8386 January 1982Ack Receipt of IE Insp Repts 50-518/81-20,50-519/81-20, 50-520/81-20 & 50-521/81-20.Corrective Actions:Insp & Const Personnel Instructed to Begin Lightly Scarifying Layers on All Backfill
ML20040C13629 December 1981Responds to NRC 811117 Ltr Re Violations Noted in IE Insp Repts 50-518/81-18,50-519/81-18,50-520/81-18 & 50-521/81-18. Corrective Actions:Preventive Maint Requirements for RHR Pumps Will Be Performed QuarterlyCoatings
ML20039A2814 December 1981Notifies That Environ Const Noise Monitoring Procedures Will Be Revised at Hartsville & Yellow Creek & Terminated at Phipps Bend.Changes Caused by Slowdown & Cessation of Const. Summary of Const Noise Monitoring Program History Encl
ML20040C26516 November 1981Submits Final Response to IE Bulletin 81-02,Suppl 1,re Potentially Deficient Valves.No Subj Valves Installed at Plants
ML20010H34814 August 1981Responds to IE Bulletin 80-20, Failures of Westinghouse Type W-2 Spring Return to Neutral Control Switches. No Subj Switches Have Been Identified at Facilities.Util Awaits Info from GE for Final Resolution.Next Response by 811030
ML20010A32930 July 1981Forwards HNP SMR - 9, Socioeconomic Monitoring & Mitigation Rept for Apr-Sept 1980
ML20009G32923 July 1981Submits Final Response to IE Bulletin 80-21,per NRC 801106 Ltr.Ge & Valve Vendors Indicate No safety-related Valves Have Parts Mfg by Malcolm Foundry Co,Inc
ML20009E98721 July 1981Advises That Planned Start of Excavation for Intake & Discharge in Cumberland River Will Be Delayed Until Aug 1982,per Attachment C of CP
ML20009G12715 July 1981Interim Deficiency Rept Re High Pressure Core Spray Component Wiring Discrepancies.Corrective Action Date for Hardware & Software Will Be 810730 Instead of 810630. Revised Vendor Drawings Have Not Been Received
ML20009D9318 July 1981Forwards Response to IE Bulletin 81-03, Flow Blockage of Cooling Water to Safety Sys Components by Corbicula Sp (Asiatic Clam) & Mytilus Sp (Mussel).Biofouling
ML20009D7328 July 1981Responds to IE Bulletin 81-02, Failure of Gate Type Valves to Close Against Differential Pressure. No Deficient Valves Are Being Supplied for Use at Facility.Addl Rept Will Be Provided by 811016
ML20009G7576 July 1981Responds to NRC 810604 Ltr Re Violations Noted in IE Insp Repts 50-518/81-08,50-519/81-08,50-520/81-08 & 50-521/81-08. Corrective Actions:Procedure Revised to Include Requirement for Writing Notification of Change Rept within Three Days
ML20009A4882 July 1981Forwards Info Re Implementation of NUREG-0313,Revision 1,in Response to NRC 810226 Ltr.Addl Info for Hartsville & Phipps Bend Will Be Provided in Respective FSARs Tentatively Scheduled for Sept 1983 SubmittalDissimilar Metal Weld
ML20009D94615 June 1981Submits Third Interim Response to IE Bulletin 80-20 Re Failure of Westinghouse W-2 Control Switches.Work Continuing W/Westinghouse on Resolution of Control Switches. GE Collecting Requested Info.Final Rept Ready by 810814
ML20004E93827 May 1981Submits Second Interim Response to IE Bulletin 80-21, Valve Yokes Supplied by Malcolm Foundry Co,Inc. No Valves W/Vendor Parts Found at Plants.Final Rept,Including GE Input on NSSS Valves, Will Be Filed by 810731
ML20004E71222 May 1981Forwards Final Supplemental Response to NRC 810114 Ltr Re Violations Noted in IE Insp Repts 50-518/80-24 & 50-520/80-24.Corrective Actions:Mod to Be Encircled on ECN to Improve Visual Identification of Affected Change Areas
ML20004E62822 May 1981Responds to NRC 810114 Ltr Re Violations Noted in IE Insp Repts 50-518/80-24 & 50-520/80-24.Corrective Actions:Mods Will Be Enriched on Engineering Change Notifications to Improve Visual Identifications
ML20126L01622 May 1981Forwards Addl Info Re Flammability of Suspended Ceiling Tile in Control Rooms & Replacement Panels to Be Used at Browns Ferry.Interim Rept on Hartsville & Phipps Bend Sent 810114. Info Constitutes Final Response to
ML19346A11515 May 1981Responds to NRC 810320 Ltr Re Violations Noted in IE Insp Repts 50-518/81-04,50-519/81-04,50-520/81-04 & 50-521/81-04. Corrective Actions:Qcirs Will Be Reviewed & Upgraded as Required & Audit Will Be Conducted by QA Unit