Summary of July 15-18, 2013, Arkansas Nuclear One, Unit 2, Audit Associated with License Amendment Request to Transition to National Fire Protection Association Standard 805
ML15007A478
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 01/15/2015
From: Andrea George
Plant Licensing Branch IV
To:
George A
References
TAC MF0404
Download: ML15007A478 (8)


Text

LICENSEE: Entergy Operations, Inc.

FACILITY: Arkansas Nuclear One, Unit No. 2

SUBJECT:

SUMMARY

OF ARKANSAS NUCLEAR ONE, UNIT NO. 2, JULY 15- 18, 2013, AUDIT ASSOCIATED WITH LICENSE AMENDMENT REQUEST TO TRANSITION TO NATIONAL FIRE PROTECTION ASSOCIATION 805 STANDARDS (TAC NO. MF0404)

The purpose of this summary is to document the results of an audit performed at Arkansas Nuclear One, Unit No. 2 (AN0-2) associated with a National Fire Protection Association Standard 805 (NFPA 805) license amendment request (LAR) dated December 17, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12353A041), as supplemented.

A review team, consisting of U.S. Nuclear Regulatory Commission (NRC) staff and contractors from the Pacific Northwest National Laboratory (PNNL) and Southwest Research Institute (SwRI)/Center for Nuclear Waste Regulatory Analyses (CNWRA), participated in a regulatory audit of AN0-2, located in Russellville, Arkansas, from July 15-18, 2013. The regulatory audit supports the review of the LAR dated December 17, 2012, submitted by Entergy Operations, Inc. (Entergy, the licensee), to transition the plant's fire protection licensing basis to Title 10 of the Code of Federal Regulations (CFR) 50.48(c), which endorses with exceptions NFPA 805, "Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants," 2001 Edition.

The purpose of the audit was to gain an understanding of the information needed to support the NRC staff's licensing decision regarding the LAR and to develop high quality requests for additional information (RAis), as needed. The information submitted in support of the AN0-2 LAR is under final review, and any additional information needed to support the LAR review will be formally requested by the staff in accordance with Office of Nuclear Reactor Regulation Office Instruction LIC-1 01, "License Amendment Review Procedures."

The audit team consisted of 11 NRC, three PNNL, and three CNWRA staff. Enclosure 1 provides the schedule of activities during the audit. Enclosure 2 lists NRC staff, PNNL staff, CNWRA staff, and the licensee's staff, and contractors who participated in the audit. contains a list of documents reviewed by the team.

The audit team held an entrance meeting on Monday, July 15, 2013, with the licensee's staff and contractors, and NRC resident inspectors. During the remainder of the audit, team members met in smaller groups according to the audit plan (ADAMS Accession No. ML13178A325). AN0-2 staff provided plant walk-downs focusing on fire protection engineering (FPE), safe shutdown (SSD), fire probabilistic risk assessment (PRA), and fire modeling.

Technical discussions were focused on five major areas: FPE, SSD/circuit analysis (CA), fire PRA, fire modeling, and programmatic review.

At the conclusion of the audit, the audit team participated in a summary exit meeting with AN0-2 staff and management on July 18, 2013. The NRC staff expressed its appreciation to the AN0-2 staff for providing informative walk-downs and presentations for the regulatory audit team.

Please direct any inquiries to me at 301-415-1081 or at Andrea.George@nrc.gov.

h~

Andrea E. George, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-368

Enclosures:

1. Audit Schedule
2. Audit Participants
3. Audit Documents cc w/encls: Distribution via Listserv

Schedule of Activities Monday. July 15. 2013 8:00a.m. Audit team members met onsite at the AN0-2 plant established computer connections, and began document reviews 9:30a.m. Audit entrance meeting Plant overview discussions (plant overview presentations were completed the previous week as teleconferenced-presentations) 10:00 a.m. Started review of fire probabilistic risk assessment (PRA), fire modeling in support of fire PRA, NFPA 805 Chapter 3, radioactive release, recovery actions, non-power operations (NPO), safe shutdown (SSD), nuclear safety capability assessment (NSCA) 12:30 p.m. Badging, review of several proposed walk-down areas by videos and photos to maintain as low as reasonably achievable (ALARA) criteria, continue reviews:

fire modeling, radioactive release, SSD, fire PRA, control room abandonment, multiple spurious operations (MSO), recovery actions, NPO, NSCA, fire protection engineering (FPE) 4:30p.m. Licensee wrap-up meeting 5:00p.m. Adjourn for the day Tuesday, July 16. 2013 8:00a.m. Preparation for AN0-2 plant walk-downs 9:00a.m. Plant tour briefing, security briefing and badging, dosimetry issuance, pre-job brief for walk-downs 9:30a.m. Plant walk-down tours were conducted.

1:30 p.m. Post walk-down discussion and debrief 2:00p.m. Main control room (MCR) abandonment presentation 4:30p.m. Licensee wrap-up meeting 5:00p.m. Adjourn for the day Wednesday. July 17. 2013 8:00a.m. Morning breakout sessions 10:00 a.m. Programmatic breakout 12:30 p.m. Presentation on plant modifications Reviews and breakouts continued from morning sessions 1:00 p.m. Control room ceiling modification discussion, combined fire modeling/PRA breakout 2:00p.m. Discussion with licensee on request for additional information (RAI) process 4:30p.m. Licensee wrap-up meeting 5:00p.m. Adjourn for the day Enclosure 1

Thursday, July 18, 2013 8:00a.m. Morning breakout sessions and interviews 8:30a.m. Review areas: fire modeling, Appendix Revaluation, SSD, defense-in-depth, safety margin, breaker control, fire PRA 4:15p.m. Audit exit meeting 4:30p.m. Adjourn

List of Participants U.S. Nuclear Regulatory Commission (NRC) Team

  • Alex Klein NRC Branch Chief
  • Hossein Hamzehee NRC Branch Chief
  • Paul Lain NRC QA
  • Jonathan DeJesus NRC PRA Pacific Northwest National Laboratory (PNNL) Team
  • Karl Bohlander PNNL FPE
  • Garill Coles PNNL FPRA
  • Peter Lowry PNNL FPRA Center for Nuclear Waste Regulatory Analyses (CNWRA) Team
  • Marc Janssen Fire Modeling/Lead
  • Debashis Basu Fire Modeling
  • Robert Fosdick Programmatic/Lead Arkansas Nuclear One, Unit 2 (AN0-2) Nuclear Plant Team
  • Bill Greeson ANO Management Sponsor
  • Bob Beaird ANO FP Supervisor
  • Richard Nance Entergy NFPA 805 Fleet Project Director
  • Larry Young Consultants Engineering Lead
  • Chris Little Consultants Electrical/Circuit Analysis Safe Shutdown
  • Dennis Barton Consultants Electrical/Circuit Analysis Safe Shutdown
  • Walter Hill Consultants Penetration Seals and Barriers
  • Hayden Collins Consultants Fire Protection
  • Stephen Lynn Consultants Modifications
  • David Robinson Consultants Modifications
  • Vern Kinsey ICE Scheduling
  • Justin Franco Kaly Tech Student Intern
  • Matt Dossett Entergy Fleet FP Engineering
  • Sean Hunt Hughes Fire Modeling
  • Justin Williamson Hughes Fire Modeling Enclosure 2
  • Lori Potts ICE PRA
  • Jessica Walker Hughes Engineering Support
  • Paul Amico Hughes PRA
  • Steve Hardy Hughes PRA
  • Robert Burrell Entergy PRA
  • Usama Farradj ERIN PRA
  • Joe Renner ERIN PRA
  • Kiang Zee ERIN PRA
  • Stephenie Pyle ANO Manager Licensing
  • Dana Miller Kaly Tech Licensing Support Industry Observers
  • Dan Kearnaghan Browns Ferry
  • Todd Stafford Browns Ferry
  • Michael Lilley Ginna

List of Documents Reviewed Reports:

ANO-C-FP-07-001, Thermal Analysis of Concrete Embedded Conduit AN02-FP-09-00013, Control Room Abandonment Study EC494, Justification of Barrier Protection Provided for Concrete Embedded Conduit ER-AN0-2003-0450-000, Review of Cable Procurements to Determine Extent of Non-Thermoset Cables PRA-A2-05-003RO, Fire Scenario Report PRA-A2-05-004, PRA Summary Report PRA-A2-05-011, Evaluation of Development and Timings of HGL Conditions in Selected AN0-2 Fire Zones Generic Fire Modeling Treatments Supplements used at AN0-2 0247-07-0005.01, ERIN Report, Fire Risk Quantification and Summary SNC-1, Quality Assurance Topical Report, Version 11.0 Drawings/PhotographsNideo:

1. Fire pre-plans, which show fire area/zone boundaries, credited fire protection systems, etc.,

for the fire zones that were walked down

2. Drawings and photographs of sheet metal plenum space separation above the louvers and glass doors between Unit 1 and Unit 2 control rooms. These drawings and photographs were requested since it was not possible during the walk-downs to look above the false ceiling.
3. Videos and photographs of fire zones 2007-LL and 2014-LL to avoid having to walk down areas in the RCA.

Training/Procedure/Program Documents:

FCBT-GET-PATSS, Entergy Fleet Specific Plant Access Training EN-DC-203, Maintenance Rule Program EN-DC-204, Maintenance Rule Scope and Basis EN-DC-205, Maintenance Rule Monitoring EN-DC-207, Maintenance Rule Periodic Assessment OP-1003-014, ANO Fire Protection Program EN-AD-103, Document Control and Records Management EN-TQ-125, Fire Brigade Training Program OP-11 04.032, Fire Protection Systems EN-DC-127, Control of Hot Work and Ignition Sources EN-DC-143-02, ENO Procedure, Program and Component Health Report Supplemental Guidance EN-LI-1 02, ENO Procedure, Corrective Action Process ENO-DC-115, ENO Procedure, Engineering Change Process ENO-DC-128, ENO Procedure, Fire Protection Impact Review HP 2.8, Response to Unusual Radiological Occurrences EN-DC-161, ENO Procedure Control of Combustibles Enclosure 3

ML15007A478 *via memo OFFICE NRR/DORLILPL4-1/PM NRR/DORLILPL4-1/LA NRR/DRA/AFPB/BC(A)*

NAME A George JBurkhardt AKiein (DFrumkin for)

DATE 1/13/15 1/9/15 12/22/14 OFFICE NRR/DRA/APRA/BC(A)* NRR/DORL/LPL4-1/BC(A) NRR/DORL/LPL4-1/PM NAME HHamzehee (SDinsmore for) EOesterle A George DATE 12/22/14 1/14/15 1/15/15