6/12-13/2012 Summary of Meeting at the Plant Site in Russellville, AR, to Discuss Entergy Operations, Inc.'S License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 at Arkansas Nuclear One, Unit 2
ML12171A366
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 07/16/2012
From: Kalyanam N
Plant Licensing Branch IV
To:
Entergy Operations
Kalyanam N
References
TAC ME8282
Download: ML12171A366 (6)


Text

~p.~ REGU( UNITED STATES

~.;:,(," "'1"'01> NUCLEAR REGULATORY COMMISSION

<l

. ~

0 WASHINGTON, D.C. 20555-0001 In  :

~ ~

~

"'o? ****i' ~o *' July 16, 2012 LICENSEE: Entergy Operations, Inc.

FACILITY: Arkansas Nuclear One, Unit 2

SUBJECT:

SUMMARY

OF JUNE 12 AND 13, 2012, MEETING WITH ENTERGY OPERATIONS, INC., ON NUCLEAR REGULATORY COMMISSION ACCEPTANCE REVIEW AND ENTERGY'S PLANS TO PROVIDE SUPPLEMENTAL INFORMATION TO THE ORIGINAL SUBMITTAL (TAC NO. ME8282)

On June 12 and 13,2012, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Entergy Operations, Inc. (Entergy), the licensee, for Arkansas Nuclear One, Unit 2 (ANO-2) at ANO offices, Reeves E. Ritchie Training Center (RERTC) Boardroom, 1448 SR 333, Russellville, Arkansas 72802. The meeting notice was issued on May 30, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML121460017). The licensee's slide presentations are available at ADAMS Accession Nos. ML12166A560 and ML12167A021.

By letter dated March 27, 2012 (ADAMS Accession No. ML12087A113), Entergy submitted a license amendment request (LAR) to adopt National Fire Protection Association (NFPA) 805 Performance Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants at AI\l0-2. By letter dated May 25, 2012 (ADAMS Accession No. IV1L 121380395), the NRC staff provided the results of its acceptance review of the LAR. In order to make the application complete and to enable the NRC staff to complete its acceptance review, the staff requested that Entergy supplement the application to address the information requested in the enclosure by July 11, 2012. The meeting was held at the request of Entergy to discuss the supplemental information requested on the four items in the NRC staff's letter dated May 25, 2012.

Item 1: The modifications for transition need to be described and modeled, as appropriate, in the probabilistic risk analysis (PRA) for estimating the risk changes.

Licensee Statement: The Entergy presentation described the modifications identified and final plant configurations after the proposed modifications. The licensee also stated that the modifications will be completed in a manner that supports the assumptions of the PRA NRC Staff Comments: The details provided appeared to be at about the right level. The NRC staff will make the final determination after the receipt of the licensee's supplement.

- 2 Item 2: Proper quantitative Recovery Action (RA) risk estimates need to demonstrate that the evaluations supporting the transitions have been completed satisfactorily.

Licensee Statement: Entergy stated the delta risk from RAs are being drafted and preliminary results are available for review. Examples of the information which will be in the supplement were provided.

NRC Staff Comments: The NRC staff stated that a) the sensitivity delta core damage frequency

(~CDF) will be needed for acceptance, b) the NRC staff would expect to see a positive delta risk in the licensee's calculations, and c) risk increases from the RAs to be provided.

Item 3: In Attachment G to the LAR, without a primary control station (besides the Main Control Room) and with only eight RAs identified for Fire Area G, the licensee reports the change in risk and the additional risk from RAs is bounded by a risk estimate of "0.0." This risk limit needs further explanation.

Licensee Statement: The licensee detailed the RAs credited for Control Room (CR) abandonment, proposed modifications, and recovery actions which are credited for CR abandonment.

NRC Staff Comments: The NRC suggested that the supplement should contain the delta risk numbers and a detailed explanation of the RAs and the modifications.

Item 4: The NRC staff expressed concern that two sensitivity studies compare the results based on one "unacceptable method" to results based on another "unacceptable method." The risk results were calculated using an unacceptable method.

Licensee Statement: The licensee stated the supplement will contain the calculated CDF and LERF and their deltas as requested in the sensitivity analyses.

NRC Staff Comments: The NRC staff suggested that the sensitivity studies compare the results obtained using the unacceptable method to those obtained using an acceptable method.

In summary, the licensee stated that it will be submitting the supplement on or before July 11, 2012. The NRC staff reiterated that while it expects that the application and the supplement may contain enough information to start the acceptance review, additional requests for information for the detailed review can be expected.

Visits inside the protected area by the NRC staff were carried out in order to get a better understanding of the issues and layouts.

No members of the public were in attendance. Public Meeting Feedback forms were not received.

- 3 Please direct any inquiries to me at 301-415-1480 or kaly.kalyanam@nrc.gov.

N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-368

Enclosure:

List of Attendees cc w/encl: Distribution via Listserv

LIST OF ATrENDEES JUNE 12-13, 2012, MEETING WITH ENTERGY OPERATIONS, INC.

LICENSE AMENDMENT REQUEST TO ADOPT NATIONAL FIRE PROTECTION AGENCY (NFPA) 805 AT ARKANSAS NUCLEAR ONE, UNIT 2 DOCKET NO. 50-368 June 12, 2012 Entergy Operations, Inc. (Entergy)

Chris Schwarz - Site Vice President, Operations, Arkansas Nuclear One (ANO)

Dale James - Director, Nuclear Safety Assurance, ANO Jaime McCoy - Director, Engineering, ANO Deepak Rao - PRA Supervisor, Entergy Corporate Richard Harris - Lead PRA, ANO Chris Little - NFPA 805 Safe Shutdown, ANO Tom Malise - Operations Control Room Supervisor, ANO Lori Potts - NFPA 805 PRA Dennis Barton - NFPA 805 Safe Shutdown Jessica Walker - Fire Protection, Kleinsorg Risk Group Services Bill Rowlett - Mechanical Design Engineer, ANO Rick Nance - Entergy Fleet NFPA 805 Project Manager George Woerner III - Mechanical Design Engineer Supervisor, ANO Ronnie Hendrix - Lead Fire Protection, ANO Bill Greeson - Engineer Programs & Components Manager, ANO Glenn Dobbs - Electrical Design Engineer Supervisor, ANO Alfred Sanchez - Senior NRC Resident Inspector, ANO Larry Young - NFPA 805 Project Lead, ANO Grant Ehren - NFPA 805 Project Manager, ANO Bryan Daiber - Design Engineer Manager, ANO Stephenie Pyle - Licensing Manager, ANO Robert Beaird - Engineer Programs & Components Supervisor, ANO Mike Chisum - General Manager, ANO David Bice - Licensing NFPA 805 Lead ANO U.S. Nuclear Regulatory Commission (NRC)

Alex Klein - Branch Chief, NRR/DRAlAFPB Harry Barrett - Senior Fire Protection Engineer, NRR/DRAlAFPB Ray Gallucci - Senior Fire PRA Engineer, NRRIDRAIAPLA William Schaup - ANO Resident Inspector, Region IV Paul Lain, Senior Fire Protection Engineer, NRRlDRAlAFPB*

Chuck Moulton, Fire Protection Engineer, NRR/DRAlAFPB*

Leslie Fields, Senior Project Manager, NRRIDRAlAHPB*

Jonathan Evans, General Engineer, NRRIDRAIAPLA*

Kaly Kalyanam, Project Manager, NRR/DORLlLPL4*

  • via teleconference Enclosure

- 2 June 13, 2012 Entergy Operations, Inc. (Entergy)

Dale James - Director, Nuclear Safety Assurance, Arkansas Nuclear One (ANO)

Jaime McCoy - Director, Engineering, ANO Deepak Rao - PRA Supervisor, Entergy Corporate Richard Harris - Lead PRA, ANO Chris Little - NFPA 805 Safe Shutdown, ANO Lori Potts - NFPA 805 PRA Jessica Walker - Fire Protection, Kleinsorg Risk Group Services Rick Nance - Entergy Fleet NFPA 805 Project Manager George Woerner III - Mechanical Design Engineer Supervisor, ANO Ronnie Hendrix - Lead Fire Protection, ANO Bill Greeson - Engineer Programs & Components Manager, ANO Alfred Sanchez - Senior NRC Resident Inspector, ANO Larry Young - NFPA 805 Project Lead, ANO Grant Ehren - NFPA 805 Project Manager, ANO Stephenie Pyle - Licensing Manager, ANO David Bice - Licensing NFPA 805 Lead ANO U.S. Nuclear Regulatory Commission (NRC)

Alex Klein - Branch Chief, NRR/DRAlAFPB Harry Barrett - Senior Fire Protection Engineer, NRRIDRAlAFPB Ray Gallucci - Senior Fire PRA Engineer, NRRlDRAIAPLA William Schaup - ANO Resident Inspector, Region IV Paul Lain, Senior Fire Protection Engineer, NRR/DRAlAFPB*

Chuck Moulton, Fire Protection Engineer, NRRlDRAlAFPB*

Leslie Fields, Senior Project Manager, NRR/DRAlAHPB*

Mike Markley, Branch Chief, NRR/DORLlLPL4*

Kaly Kalyanam, Project Manager, NRRIDORLlLPL4*

  • via teleconference

Meeting Notice ML121460017, Meeting Summary ML12171A366, Handouts ML12166A560 and ML12167A021 OFFICE NRR/DORLlLPL4/PM N RR/DORLlLPL4/LA N RR/DRA/AFPB/BC NAME NKalyanam JBurkhardt AKlein DATE 6/22/12 6/21/12 17/10/12 OFFICE NRRIDRAIAPLA/BC NRRIDORLlLPL4/BC NRRIDORLlLPL4 NAME DHarrison (BBeasley for) MMarkley (BSingal for) NKalyanam DATE 7/9/12 7116/12 7/16/12