Environ Event Rept 81-01:on 810604,daily Chlorination Cycle Extended for 126 Minutes.Caused by Malfunction of Timer. New Timer W/More Precise Time Control Installed W/Setting of 110 Minutes Per Day
ML20009A010
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 07/02/1981
From: Ward E
NORTHERN STATES POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
NUDOCS 8107070360
Download: ML20009A010 (1)


Text

Northern States Power Company 414 ' hco!!et Mall Minneapohs. Minnesota 55401 Telephone 1612) 330-5500 July 2, 1981 s

< grr n ,$

_ NLN Ch Mr J G Keppler, Director, Region III , 9-JR0 Ob T

Of fice of Inspection & Enforcement C *12 U S Nuclear Regulatory Commission g D '

799 Roosevelt Road Glen Ellyn, IL 60137 PRAIRIE ISLAND INCLEAR GENERATING PLANT

\ c' Docket No. 50-282 License No. DPR-42 50-306 DPR-60 Environmental Event Report 81-01 Under TS B-5.4.2.A, we are required to report as an Environmental Event, when a protection condition is exceeded. TS B-2.4.1 specifies that during chlorination periods, the total residual chlorine concentration at the outf all of the circulating water system shall not cxceed 0.05 ppm for a chlorination cycle of not more than two hours per day.

The daily chlorination cycle on June 4, 1981 extended for i duration of 126 minutes due to a malfunction of the timer.

As correction cccion a new electronic timer with more precise time

~ control has been installed with a setting of 110 minutes per day.

W E C Ward, PE Manager-Nuclear Environmental Services ECW/jh cc Director, NRR c/o DSB (17)

Resident Inspector MPCA Attn: J W Ferman 8107070360 010702~'