Summary of Meeting with Dominion Nuclear Connecticut, Inc.,Surry and North Anna, Units 1 & 2, and Millstone, Units 2 & 3, Discuss Current Licensing Issues with Dominion
ML051470186
Person / Time
Site: Millstone, Surry, North Anna  Dominion icon.png
Issue date: 05/20/2005
From: Stephen Monarque
NRC/NRR/DLPM/LPD2
To:
Dominion Nuclear Connecticut, Virginia Electric & Power Co (VEPCO)
Monarque, S R, NRR/DLPM, 415-1544
References
Download: ML051470186 (6)


Text

May 20, 2005 LICENSEE: Dominion Nuclear Connecticut, Inc. and Virginia Electric and Power Company FACILITY: Surry and North Anna Power Station, Units 1 and 2 and Millstone Nuclear Power Station, Units 2 and 3

SUBJECT:

SUMMARY

OF APRIL 26, 2005, MEETING WITH DOMINION NUCLEAR CONNECTICUT, INC. AND VIRGINIA ELECTRIC AND POWER COMPANY TO DISCUSS CURRENT LICENSING ISSUES On April 26, 2005, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Dominion Nuclear Connecticut, Inc. and Virginia Electric and Power Company (the licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the status of licensing actions that are under NRC staff review and exchange information on the quality of licensing submittals. A list of attendees is provided as Enclosure 1.

The licensee presented prioritized lists of licensing actions for North Anna, Surry, and Millstone.

Refer to Enclosures 2 and 3. The licensee and the NRC staff discussed the status of licensing actions that were under NRC staff review and whether the NRC staff could support the licensees expected completion dates. The licensee and the NRC staff addressed the continuation of cross-regional submittals, including the NRC staffs expectations on the quality of these submittals.

Regarding the issuance of letters, the NRC staff agreed to improve its process for sending correspondence. This will ensure that the licensee is able to respond to the NRC staffs requests for additional information in a timely manner. Both parties provided feedback on the quality of licensing submittals and safety evaluations.

Members of the public were not in attendance. Public Meeting Feedback forms were provided, but the NRC staff did not receive any comments. Please direct any inquiries to Stephen R.

Monarque at 301-415-1544, or srm2@nrc.gov.

/RA/

Stephen R. Monarque, Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-280, 50-281, 50-338, 50-339, 50-336, and 50-423

Enclosures:

1. List of Attendees
2. Priority of North Anna and Surry Licensing Tasks at the NRC
3. Top Ten Millstone Licensing Tasks cc w/encls: See next page

May 20, 2005 LICENSEE: Dominion Nuclear Connecticut, Inc. and Virginia Electric and Power Company FACILITY: Surry and North Anna Power Station, Units 1 and 2 and Millstone Nuclear Power Station, Units 2 and 3

SUBJECT:

SUMMARY

OF APRIL 26, 2005, MEETING WITH DOMINION NUCLEAR CONNECTICUT, INC. AND VIRGINIA ELECTRIC AND POWER COMPANY TO DISCUSS CURRENT LICENSING ISSUES On April 26, 2005, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Dominion Nuclear Connecticut, Inc. and Virginia Electric and Power Company (the licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the status of licensing actions that are under NRC staff review and exchange information on the quality of licensing submittals. A list of attendees is provided as Enclosure 1.

The licensee presented prioritized lists of licensing actions for North Anna, Surry, and Millstone.

Refer to Enclosures 2 and 3. The licensee and the NRC staff discussed the status of licensing actions that were under NRC staff review and whether the NRC staff could support the licensees expected completion dates. The licensee and the NRC staff addressed the continuation of cross-regional submittals, including the NRC staffs expectations on the quality of these submittals.

Regarding the issuance of letters, the NRC staff agreed to improve its process for sending correspondence. This will ensure that the licensee is able to respond to the NRC staffs requests for additional information in a timely manner. Both parties provided feedback on the quality of licensing submittals and safety evaluations.

Members of the public were not in attendance. Public Meeting Feedback forms were provided, but the NRC staff did not receive any comments. Please direct any inquiries to Stephen R.

Monarque at 301-415-1544, or srm2@nrc.gov.

/RA/

Stephen R. Monarque, Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-280, 50-281, 50-338, 50-339, 50-336, and 50-423

Enclosures:

1. List of Attendees
2. Priority of North Anna and Surry Licensing Tasks at the NRC
3. Top Ten Millstone Licensing Tasks cc w/encls: See next page Distribution: See next page Package No.: ML051530511 Enclosure 1: ML051540091 ADAMS Accession No.: ML051470186 Enclosure 2: ML051240093 NRC-001 OFFICE PDII-1/PM PDII-2/LA PDII-1/SC NAME SMonarque EDunnington SPeters for AMarinos DATE 5/16/05 5/18/05 5/20/05 OFFICIAL RECORD

SUBJECT:

SUMMARY

OF APRIL 26, 2005, MEETING WITH DOMINION NUCLEAR CONNECTICUT, INC. AND VIRGINIA ELECTRIC AND POWER COMPANY TO DISCUSS CURRENT LICENSING ISSUES Date: May 20, 2005 Distribution:

PUBLIC PDII-1 R/F RidsNrrPMSMonarque RidsOgcRp RidsAcrsAcnwMailCenter RidsNrrDlpm RidsNrrDlpmLpdii RidsNrrDlpmLpdii1 EDunnington TMensah RMartin CHolden VNerses JNakoski CCasto PWilloughby DSommers TShaub CFunderburk RidsRgn2MailCenter

LIST OF ATTENDEES APRIL 26, 2005 NAME ORGANIZATION Stephen Monarque NRC/NRR/DLPM Robert Martin NRC/NRR/DLPM Ed Hackett NRC/NRR/DLPM Cornelius Holden NRC/NRR/DLPM Victor Nerses NRC/NRR/DLPM John Nakoski NRC/NRR/DLPM Chuck Casto NRC/Region II Paul Willoughby Dominion Resources Services David Sommers Dominion Resources Services Thomas Shaub Dominion Resources Services Chris Funderburk Dominion Resources Services

Virginia Electric and Power Company Office of the Attorney General Commonwealth of Virginia cc: 900 East Main Street Ms. Lillian M. Cuoco, Esq. Richmond, Virginia 23219 Senior Counsel Dominion Resources Services, Inc. Mr. Chris L. Funderburk, Director Building 475, 5th Floor Nuclear Licensing & Operations Rope Ferry Road Support Waterford, Connecticut 06385 Innsbrook Technical Center Dominion Resources Services, Inc.

Mr. Donald E. Jernigan 5000 Dominion Blvd.

Site Vice President Glen Allen, Virginia 23060-6711 Surry Power Station Virginia Electric and Power Company Mr. Jack M. Davis 5570 Hog Island Road Site Vice President Surry, Virginia 23883-0315 North Anna Power Station Virginia Electric and Power Company Senior Resident Inspector P. O. Box 402 Surry Power Station Mineral, Virginia 23117-0402 U. S. Nuclear Regulatory Commission 5850 Hog Island Road Mr. C. Lee Lintecum Surry, Virginia 23883 County Administrator Louisa County Chairman P.O. Box 160 Board of Supervisors of Surry County Louisa, Virginia 23093 Surry County Courthouse Surry, Virginia 23683 Old Dominion Electric Cooperative 4201 Dominion Blvd.

Dr. W. T. Lough Glen Allen, Virginia 23060 Virginia State Corporation Commission Senior Resident Inspector Division of Energy Regulation North Anna Power Station P. O. Box 1197 U.S. Nuclear Regulatory Commission Richmond, Virginia 23218 1024 Haley Drive Mineral, Virginia 23117 Robert B. Stroube, MD, MPH State Health Commissioner Mr. David A. Christian Office of the Commissioner Sr. Vice President and Chief Nuclear Officer Virginia Department of Health Virginia Electric and Power Company P.O. Box 2448 Innsbrook Technical Center Richmond, Virginia 23218 5000 Dominion Boulevard Glen Allen, Virginia 23060-6711

Millstone Power Station, Unit Nos. 2 and 3 cc:

Lillian M. Cuoco, Esquire Mr. Evan W. Woollacott Senior Counsel Co-Chair Dominion Resources Services, Inc. Nuclear Energy Advisory Council Building 475, 5th Floor 128 Terrys Plain Road Rope Ferry Road Simsbury, CT 06070 Waterford, CT 06385 Mr. William D. Meinert Edward L. Wilds, Jr., Ph.D. Nuclear Engineer Director, Division of Radiation Massachusetts Municipal Wholesale Department of Environmental Electric Company Protection P.O. Box 426 79 Elm Street Ludlow, MA 01056 Hartford, CT 06106-5127 Mr. David W. Dodson Regional Administrator, Region I Licensing Supervisor U.S. Nuclear Regulatory Commission Dominion Nuclear Connecticut, Inc.

475 Allendale Road Building 475, 5th Floor King of Prussia, PA 19406 Roper Ferry Road Waterford, CT 06385 First Selectmen Town of Waterford Mr. J. Alan Price 15 Rope Ferry Road Site Vice President Waterford, CT 06385 Dominion Nuclear Connecticut, Inc.

Building 475, 5th Floor Charles Brinkman, Director Rope Ferry Road Washington Operations Nuclear Services Waterford, CT 06385 Westinghouse Electric Company 12300 Twinbrook Pkwy, Suite 330 Mr. Chris L. Funderburk Rockville, MD 20852 Director, Nuclear Licensing and Operations Support Senior Resident Inspector Innsbrook Technical Center Millstone Power Station 5000 Dominion Boulevard c/o U.S. Nuclear Regulatory Commission Glen Allen, VA 23060-6711 P. O. Box 513 Niantic, CT 06357 Mr. John Markowicz Co-Chair Nuclear Energy Advisory Council 9 Susan Terrace Waterford, CT 06385 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870