UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD, STE 102 KING OF PRUSSIA, PENNSLYVANIA 19406-2713 May 29, 2024 MEETING
SUMMARY
LICENSEE:
DOMINION ENERGY NUCLEAR CONNECTICUT, INC.
FACILITY:
MILLSTONE POWER STATION, UNITS 2 AND 3
SUBJECT:
SUMMARY
OF PUBLIC MEETING On May 16, 2024, at 7:00 p.m., the U.S. Nuclear Regulatory Commission (NRC) was part of a public meeting with the Connecticut Nuclear Energy Advisory Council (NEAC). During the first part of the meeting, the NRC staff presented the Agencys assessment of the safety performance at Millstone Power Station for the period of January 1, 2023 through December 31, 2023, as described in the annual assessment letter dated February 28, 2024.
A copy of the letter can be accessed through the NRCs Agencywide Documents Access and Management System (ADAMS), Accession Number ML24053A303. Following the presentation, an opportunity was provided to the members of the public and the Connecticut NEAC for questions. The following NRC staff provided presentations and answers to questions during the meeting: Matt Young (Branch Chief, Division of Operating Reactor Safety), Justin Fuller (Senior Resident Inspector, Millstone), Earl Bousquet (Resident Inspector, Millstone),
Dominic Antonangeli (Resident Inspector, Millstone), and Sarah Elkhiamy (Senior Project Engineer, Division of Operating Reactor Safety).
Copies of the slides used by the NRC staff during the meeting can be accessed through ADAMS, Accession Number ML24135A081. A notice of the NRC and NEAC meeting was issued on April 30, 2024, and was posted on the NRCs external (public) Web page (ADAMS Accession Number ML24113A183). ADAMS is accessible from the NRC Web page at:
http://www.nrc.gov/reading-rm/adams.html.
Additional information relative to the NRC's Annual Assessment Process and the safety performance of Millstone Power Station can be found on the NRC's website at:
https://www.nrc.gov/reactors/operating/oversight.html.
Matt R. Young, Chief Projects Branch 2 Division of Operating Reactor Safety MATTHEW YOUNG Digitally signed by MATTHEW YOUNG Date: 2024.05.29 13:47:24 -04'00'
ML24150A154 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DORS RI/DORS RI/DORS NAME AChristiano SElkhiamy MYoung DATE 5/29/2024 5/23/2024 5/23/2024