2008 Mid-Cycle Performance Review and Inspection Plan - Beaver Valley
ML082470472
Person / Time
Site: Beaver Valley
Issue date: 09/02/2008
From: Bellamy R
NRC/RGN-I/DRP/PB6
To: Sena P
FirstEnergy Nuclear Operating Co
BELLAMY RR
References
Download: ML082470472 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 September 2, 2008

Mr. Peter P. Sena, III Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P. O. Box 4 Shippingport, PA 15077

SUBJECT:

MID CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

BEAVER VALLEY, UNITS 1 AND 2

Dear Mr. Sena:

On August 11, 2008, the NRC staff completed its performance review of the Beaver Valley Units 1 and 2 for the first half of calendar year 2008 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security Information" will include the security cornerstone review and resultant inspection plan.

Plant performance for the most recent quarter of 2008 at Beaver Valley Units 1 and 2 was within the Licensee Response column of the NRC's Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.

The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

P. Sena 2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5200 with any questions you may have regarding this letter or the inspection plan.

Sincerely, /RA by Raymond J. Powell Acting for/

Ronald R. Bellamy, Ph.D., Chief Division of Reactor Projects Projects Branch 6

Docket Nos.: 50-334, 50-412 License Nos: DPR-66, NPF-73

Enclosure:

Beaver Valley Units 1 and 2 Inspection/ Activity Plan

cc w/encl: J. Hagan, President and Chief Nuclear Officer J. Lash, Senior Vice President of Operations and Chief Operating Officer D. Pace, Senior Vice President, Fleet Engineering J. Rinckel, Vice President, Fleet Oversight P. Harden, Vice President, Nuclear Support G. Halnon, Director, Fleet Regulatory Affairs Manager, Fleet Licensing Company K. Ostrowski, Director, Site Operations E. Hubley, Director, Maintenance M. Manoleras, Director, Engineering L. Freeland, Director, Site Performance Improvement C. Keller, Manager, Site Regulatory Compliance D. Jenkins, Attorney, FirstEnergy Corporation M. Clancy, Mayor, Shippingport, PA D. Allard, Director, PADEP C. O'Claire, State Liaison to the NRC, State of Ohio Z. Clayton, EPA-DERR, State of Ohio Director, Utilities Department, Public Utilities Commission, State of Ohio D. Hill, Chief, Radiological Health Program, State of West Virginia J. Lewis, Commissioner, Division of Labor, State of West Virginia W. Hill, Beaver County Emergency Management Agency J. Johnsrud, National Energy Committee, Sierra Club J. Powers, Director, PA Office of Homeland Security R. French, Director, PA Emergency Management Agency

BV Inspection / Activity Plan 07/01/2008

-12/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/29/2008 15:39:23 Report 22 2 7111111B-L.O. REQUAL.PROG.(FOCUS U1)+P/F RVW Baseline Inspections Licensed Operator Requalification Program 08/04/2008 08/08/2008 1, 2 7111111B IP 7 71002-LICENSE RENEWAL License Renewal Inspe c License Renewal Inspection 07/14/2008 07/18/2008 1, 2 71002 IP 4 12/8 EXM-U2 INITIAL OPERATOR LICENSING EXAMS Not Applicable BEAVER VALLEY UNIT 2 INITIAL EXAM (FY09) 11/10/2008 11/14/2008 2 U01628 Not Applicable BEAVER VALLEY UNIT 2 INITIAL EXAM (FY09) 12/08/2008 12/12/2008 2 U01628 Not Applicable BEAVER VALLEY UNIT 2 INITIAL EXAM (FY09) 12/15/2008 12/19/2008 2 U01628 1 7112103-OCC RAD SAFETY - INSTRUMENTS Baseline Inspections Radiation Monitoring Instrumentation and Protective Equipment 08/25/2008 08/29/2008 1, 2 7112103 IP 7 7111121-CDBI Baseline Inspections Component Design Bases Inspection 09/15/2008 09/19/2008 1, 2 7111121 IP Baseline Inspections Component Design Bases Inspection 09/29/2008 10/03/2008 1, 2 7111121 IP Baseline Inspections Component Design Bases Inspection 10/06/2008 10/10/2008 1, 2 7111121 IP 3 TI 171-TI 171 Generic Safety Inspecti o Verification of Site Specific Implementation Of B.5.b Phase 2 & 3 Mitigating Strategies 10/20/2008 10/24/2008 1, 2 2515/171 IP 1 TI 176-TI 176 Generic Safety Inspecti o Emergency Diesel Generator Tech Spec Surveillance Requirements Re: Endurance & Margin Testing 11/03/2008 11/07/2008 1, 2 2515/176 IP 1 71121-OCC RAD SAFETY Baseline Inspections A ccess Control to Radiologically Significant Areas 02/09/2009 02/13/2009 1, 2 7112101 IP Baseline Inspections A LARA - Required 02/09/2009 02/13/2009 1, 2 7112102-7112102R IP 1 71122.01-PUB RAD SAFETY - RETS Baseline Inspections Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 03/23/2009 03/27/2009 1, 2 7112201 IP 1 7111108P-U1 INSERVICE INSPECTION Baseline Inspections Inservice Inspection Activities - PWR 04/20/2009 04/24/2009 1 7111108P IP Baseline Inspections Inservice Inspection Activities - PWR 04/27/2009 05/01/2009 1 7111108P IP 1 71121-OCC RAD SAFETY Baseline Inspections A ccess Control to Radiologically Significant Areas 04/27/2009 05/01/2009 1 7112101 IP Baseline Inspections A LARA - Required 04/27/2009 05/01/2009 1 7112102-7112102R IP 3 7111111B-REQUAL (FOCUS U2) W/ P/F RESULTS Baseline Inspections Licensed Operator Requalification Program 07/20/2009 07/24/2009 1, 2 7111111B IP 1 71122.03-PUB RAD SAFETY - REMP Baseline Inspections Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 07/13/2009 07/17/2009 1, 2 7112203 IP 5 TRI FIRE-TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections Fire Protection [Triennial]

07/20/2009 07/24/2009 1, 2 7111105T IP This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

BV Inspection / Activity Plan 07/01/2008

-12/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/29/2008 15:39:23 Report 22 5 TRI FIRE-TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections Fire Protection [Triennial]

08/03/2009 08/07/2009 1, 2 7111105T IP 1 EP PROG-EP PROGRAM INSPECTION EP Baseline Inspection A lert and Notification System Testing 08/31/2009 09/04/2009 1, 2 7111402 IP EP Baseline Inspection Emergency Response Organization Augmentation Testing 08/31/2009 09/04/2009 1, 2 7111403 IP EP Baseline Inspection Emergency Action Level and Emergency Plan Changes 08/31/2009 09/04/2009 1, 2 7111404 IP EP Baseline Inspection Correction of Emergency Preparedness Weaknesses and Deficiencies 08/31/2009 09/04/2009 1, 2 7111405 IP Baseline Inspections Drill/Exercise Performance 08/31/2009 09/04/2009 1, 2 71151-EP01 IP Baseline Inspections ERO Drill Participation 08/31/2009 09/04/2009 1, 2 71151-EP02 IP Baseline Inspections A lert & Notification System 08/31/2009 09/04/2009 1, 2 71151-EP03 IP 5 71152B-PI&R BIENNIAL TEAM Baseline Inspections Identification and Resolution of Problems 08/17/2009 08/21/2009 1, 2 71152B IP Baseline Inspections Identification and Resolution of Problems 08/31/2009 09/03/2009 1, 2 71152B IP 1 7111108P-U2 INSERVICE INSPECTION Baseline Inspections Inservice Inspection Activities - PWR 10/19/2009 10/30/2009 2 7111108P IP 1 71121-OCC RAD SAFETY Baseline Inspections A LARA Planning and Controls 10/26/2009 10/30/2009 2 7112102 IP This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.