5/26/11 Summary of Prelicensing Meeting with Omaha Public Power District to Discuss License Amendment Request to Adopt Risk-Informed National Fire Protection Association Standard NFPA 805 or Fort Calhoun Station, Unit 1 (TAC No. ME6242)
ML111680151
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 07/11/2011
From: Wilkins L E
Plant Licensing Branch IV
To:
Omaha Public Power District
Wilkins, L E, NRR/DORL/LPL4, 415-1377
References
TAC ME6242
Download: ML111680151 (4)


Text

",,.1\ UNITED STATES "1;. NUCLEAR REGULATORY COMMISSION t:! WASHINGTON, D.C. 20555-0001

<< 0 ... ;: '" """"", July 11,2011****..,

Omaha Public Power District Fort Calhoun Station, Unit 1

SUMMARY

OF PRE-LICENSING MEETING HELD ON MAY 26, 2011, WITH OMAHA PUBLIC POWER DISTRICT TO DISCUSS REQUEST TO ADOPT NATIONAL FIRE PROTECTION ASSOCIATION STANDARD NFPA-805 FOR FORT CALHOUN STATION, UNIT NO.1 (TAC NO. ME6242) On May 26, 2011, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Omaha Public Power District (OPPD, the licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland.

The purpose of the pre-licensing meeting was to discuss OPPD's planned submittal of an amendment request for Fort Calhoun Station (FCS), Unit NO.1. Specifically, the licensee discussed its intention to adopt the risk-informed, performance-based alternative described in "National Fire Protection Association Standard NFPA 805," as permitted by paragraph 50.48(c) of Title 10 of the Code of Federal Regulations.

The licensee's presentation slides are available in the Agencywide Documents Access and Management System (ADAMS) under ADAMS Accession No. ML 111570296.

The licensee discussed the project overview and schedule which includes plans to submit the NFPA-805 application to the NRC on June 9, 2011. The licensee presented information on the NFPA 805 transition project overview, current fire protection licensing basis, fire protection program transition, compliance with I\JFPA 805 and fire probabilistic risk assessment (PRA). The licensee stated that it planned to use analyses that were under review by the Industry New Methods Peer Review Panel for its fire PRA During a follow-up teleconference on May 27, 2011, the NRC staff informed the licensee that if it decided to use methodologies unreviewed by the industry panel, the application might not pass acceptance review since the methods review by the industry panel had not been initiated and thus the acceptability of the method would be an open item. The licensee informed the NRC staff that it would consider this information and inform the project manager, Lynnea Wilkins, of its decision.

The meeting notice and agenda are available under ADAMS Accession No. ML 111330643.

The public was invited to observe the meeting and was given an opportunity to communicate with the NRC after the business portion, but before the meeting was adjourned.

The meeting was attended by four members of the public. The individuals did not ask any questions or make any oral statements during the time allocated for public participation.

No Public Meeting Feedback forms were received.

-2 Please direct any inquiries to me at 301-415-1377 or Lynnea.Wilkins@nrc.gov.

P Ai /,' / /1/

C ,-:. Lynnea Wilkins, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285 List of cc w/encl: Distribution via Listserv LIST OF U.S. NUCLEAR REGULATORY MAY 26, 2011, PRE-LICENSING MEETING OMAHA PUBLIC POWER DISTRICT REGARDING TRANSITION TO NFPA FOR FORT CALHOUN STATION, UNIT DOCKET NO. Name Organization Lynnea Wilkins NRC/NRR/DORLlLPL4 Joe McManis Omaha Public Power District Tom Shudak Omaha Public Power District Gaston Riva Omaha Public Power District Bill Hansher Omaha Public Power District Donna Lippy Omaha Public Power District Francesco Pellizzari Engineering and Planning Management (EPM) Gerhard Samide Westinghouse Electric Company Clarence Worrell Westinghouse Electric Company Harry Barrett NRC/NRR/DRA/AFPB Alex Klein NRC/NRR/DRA/AFPB Paul Lain NRC/NRR/DRAlAFPB Jay Robinson NRC/NRR/DRA/AFPB Naeem Iqbal NRC/NRR/DRA/AFPB Daniel Frumkin NRC/NRR/DRA/AFPB Charles Moulten NRC/NRR/DRA/AFPB Donnie Harrison NRC/NRR/DRA/APLA Stephen Dinsmore NRC/NRR/DRA/APLA Ray Gallucci NRC/NRR/DRA/APLA Doug Pickett NRC/NRR/DORLlLPL 1-1 Gerry Gulla NRC/OE/EB Thomas Basso Nuclear Energy Institute Francy Mantine First Energy Corporation Kathy Stodola Iowa Homeland Security and Emergency Management Larry Young Arkansas Nuclear One Enclosure

-2 Please direct any inquiries to me at 301-415-1377 or Lynnea.Wilkins@nrc.gov.

I RAJ Docket No.

List of cc w/encl: Distribution via Listserv DISTRIBUTION:

PUBLIC LPLIV r/f RidsAcrsAcnw_MailCTR Resource RidsNrrDprPgcb Resource RidsNrrDraApla Resource RidsNrrDraAfpb Resource RidsNrrDorl Resource RidsNrrDorlLpl4 Resource RidsNrrPMFortCalhoun Resource RidsNrrLAJ Burkhardt Resource RidsOgcRp Resource RidsOpaMail Resource RidsRgn4MailCenter Resource Lynnea Wilkins, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation PLain, NRR/DRAJAFPB HBarrett, NRR/DRA/AFPB JRobinson, NRR/DRAJAFPB Nlqbal, NRRIDRAJAFPB DFrumpkin, NRR/DRA/AFPB CMoulton, NRRIDRAJAFPB SDinsmore, NRR/DRA/APLA RGallucci, NRRIDRA/APLA GGulla, NRR/OE/EB DPickett, NRR/DORLlLPL 1-1 CSteger, NRR SBush-Goddard, EDO RIV VDricks, OPA RIV ADAMS Accession Nos. Meeting Notice ML 110810695, Meeting Summary ML 111680151, Handouts ML 111570296

  • via email _. --,.. CE OORLlLPL4/PM OORLlLPL4/LA NRRIDRAIAPLAJBC NRR/DRA/AFPB/BC DORLlLPL4/BC MMarkley (BSingal NAME LWilkins JBurkhardt*

DHarrison AKlein for) DATE 6/27/11 6/23/11 7/11/11 7/11/11 7/11/11 .. DORLlLPL4/PM LWilkins 7/11/11 OFFICIAL RECORD