MONTHYEARRS-24-098, Units 1 and 2 - Supplement to License Amendment Request to Revise Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel Assembly Storage, 4.3.1, Fuel Storage, Criticality2024-10-23023 October 2024 Units 1 and 2 - Supplement to License Amendment Request to Revise Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel Assembly Storage, 4.3.1, Fuel Storage, Criticality ML24291A0012024-10-17017 October 2024 Submittal of Core Operating Limits Report, Cycle 25 RS-24-095, Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals2024-10-10010 October 2024 Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary IR 05000456/20240112024-09-12012 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000456/2024011 and 05000457/2024011 ML24164A0032024-09-10010 September 2024 Issuance of Amendment Nos. 235 and 235 Revision of Technical Specifications for the Ultimate Heat Sink IR 05000456/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2024005 and 05000457/2024005) ML24227A0522024-08-29029 August 2024 Audit Plan for LAR to Remove ATWS Mtc Limit ML24225A1112024-08-13013 August 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000456/20240022024-08-0808 August 2024 Integrated Inspection Report 05000456/2024002 and 05000457/2024002 ML24172A1252024-07-26026 July 2024 Environmental Assessment and Finding of No Significant Impact Related to a Requested Increase in Ultimate Heat Sink Temperature (EPID L-2024-LLA-0075) - Transmittal Letter ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24163A3922024-06-25025 June 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, & Opportunity for a Hearing (EPID L-2024-LLA-0075)- Letter RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24164A2132024-06-13013 June 2024 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Braidwood Nuclear Plant RS-24-057, License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink2024-06-0404 June 2024 License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink IR 05000456/20240102024-05-31031 May 2024 License Renewal Phase 1 Report 05000456/2024010 RS-24-044, License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed2024-05-28028 May 2024 License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed RS-24-043, Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications2024-05-24024 May 2024 Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24136A0132024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report ML24136A2452024-05-15015 May 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000457/2024004 ML24128A1212024-05-0707 May 2024 Response to Braidwood and Dresden FOF Dates Change Request (2025) ML24122A6522024-05-0101 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests IR 05000456/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000456/2024301; 05000457/2024301 RS-24-026, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR)2024-04-25025 April 2024 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML24116A0052024-04-25025 April 2024 Transmittal of Braidwood Station, Unit 1, Core Operating Limits Report, Braidwood Unit 1 Cycle 25 IR 05000456/20240012024-04-24024 April 2024 Integrated Inspection Report 05000456/2024001 and 05000457/2024001 ML24113A1272024-04-22022 April 2024 Audit Plan in Support of Review of LAR Revision of TS 3.7.15, 3.7.16, and 4.3.1 (EPID: L-2023-LLA-0136) (Non-Proprietary) IR 05000457/20240902024-04-19019 April 2024 Final Significance Determination for 2b Auxiliary Feedwater Pump Diesel Engine Fuel Oil Dilution Issue - NRC Inspection Report 05000457/2024090 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-24-034, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-04-10010 April 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors ML24094A2692024-04-0303 April 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Report, WCAP-17451-P, Revision 2, Reactor Internals Guide Tube Wear Westinghouse Domestic Fleet Operational Projections RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24057A0372024-03-26026 March 2024 Proposed Alternative from Certain Requirements Contained in the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI RS-24-024, Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-03-22022 March 2024 Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML24067A3252024-03-0707 March 2024 U.S. Department of Energy, Office of Legacy Management, 2023 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites ML24066A0122024-03-0606 March 2024 Operator Licensing Examination Approval Braidwood Station, Units 1 and 2, March 2024 IR 05000456/20244012024-03-0505 March 2024 Cyber Security Inspection Report 05000456/2024401 and 05000457/2024401 (Public) IR 05000456/20230062024-02-28028 February 2024 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2023006 and 05000457/2023006) ML24057A3022024-02-26026 February 2024 Regulatory Conference Supplemental Information ML24047A2382024-02-20020 February 2024 Regulatory Conference to Discuss Risk Associated with 2b Auxiliary Feedwater Pump Diesel Engine Fuel Oil Leak RS-24-013, Response to Request for Additional Information Regarding Proposed Alternative to Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators2024-02-13013 February 2024 Response to Request for Additional Information Regarding Proposed Alternative to Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators IR 05000456/20230042024-02-0202 February 2024 Integrated Inspection Report 05000456/2023004 and 05000457/2023004 2024-09-23
[Table view] Category:Meeting Summary
MONTHYEARML24164A0182024-06-12012 June 2024 May 29, 2024, Summary of the Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2 ML24152A1852024-06-0404 June 2024 Summary of March 28, 2024, Closed Hybrid Pre-Submittal Meeting Between Constellation Energy Generation, LLC and the U.S. Nuclear Regulatory Commission Regarding a Future Amendment Request for Fuel Transition ML24128A2512024-05-14014 May 2024 Summary of April 11, 2024, Public Meeting with Constellation Energy Generation, LLC Regarding Proposed Alternative to Implement American Society of Mechanical Engineers Operation and Maintenance Code Case OMN-32 ML24113A2872024-04-25025 April 2024 Summary of Public Meeting with Constellation Energy Generation, LLC Regarding Hooded Masks ML24079A2382024-03-19019 March 2024 Summary of March 7, 2024 Regulatory Conference with Constellation Nuclear Regarding Braidwood Station, Unit 2 ML24009A0552024-01-24024 January 2024 Summary of January 8, 2024, Presubmittal Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Removal of the Power Distribution Monitoring System from Technical Specifications ML23363A0942024-01-0303 January 2024 Summary of October 4, 2023, Pre Submittal Meeting Between the U.S. NRC and Constellation Energy Generation, LLC, Regarding Revising Technical Specification 3.7.9. Ultimate Heat Sink (UHS) ML23352A3822023-12-19019 December 2023 Summary of December 11, 2023, Presubmittal Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Deletion of Technical Specification 5.6.5.b.5 ML23320A2472023-11-17017 November 2023 Constellation - Summary of November 14, 2023, Public Pre-Application Meeting with Constellation Energy Generation, LLC on Adoption of TSTF-591 ML23263B1062023-09-22022 September 2023 R. E. Ginna Nuclear Power Plant - Constellation - Pre-Application Amse 9/18/2023 Meeting Summary ML23164A2112023-06-14014 June 2023 Summary of the June 1, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2; and Byron Station, Units 1 and 2 ML23129A0202023-05-30030 May 2023 Summary of March 22, 2023, Closed Meeting with Constellation Energy Generation, LLC, to Discuss a Future License Amendment Request That Allows Byron Station and Braidwood Station to Utilize a New Citicality Analysis for the Spent Fuel Pools ML23055A0352023-03-24024 March 2023 Summary of February 23, 2023, with Constellation Energy Generation, LLC on Proposed Changes to Emergency Plans to Revise Emergency Action Levels ML23033A6662023-02-0909 February 2023 Summary of Public Meeting with Constellation Energy Generation, LLC (Constellation) to Discuss Its Request for Alternatives for Certain Steam Generator Weld Inspections for Calvert Cliffs 1 & 2, Byron 1 & 2, Braidwood 1 & 2, and Ginna ML22264A1992022-11-14014 November 2022 Summary of August 22, 2022, Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Performance Monitoring of Steam Generator Welds (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and ML22305A5992022-11-10010 November 2022 Summary of Closed Presubmittal Meeting Between the U. S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Transition to Framatome Fuel ML22159A2232022-06-0909 June 2022 Summary of the June 2, 2022, Public Outreach to Discuss the NRC 2021 End of Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2 ML22111A2852022-05-0909 May 2022 Summary of April 4, 2022, Meeting Between the U.S. NRC and Constellation Energy Generation, LLC, Regarding Performance Monitoring of Pressurizer Welds (EPIDs L-2022-LLR-0035/36) ML22111A3362022-05-0909 May 2022 Summary of April 7, 2022, Meeting Between the NRC and Constellation Energy Generation, LLC, Regarding Performance Monitoring of Pressurizer Welds (Epids L-2022-LRR-0035 and 0036) ML21330A0722021-12-0303 December 2021 Summary of November 17, 2021, Meeting with Exelon Generation Company, LLC, Related to a Future License Amendment to Remove License Condition 2.C.(12)(d) for Braidwood Station, Unit 2 ML21333A1532021-11-30030 November 2021 Summary of November 16, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Extend the Inservice Inspection Interval ML21237A0412021-08-30030 August 2021 Summary of the July 27, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Use Case OMN-28, ML21176A0822021-07-0606 July 2021 June 15, 2021, Summary of Meeting with Exelon Generation Company, LLC Vessel Nozzle Repair Related to a Planned Request for an Alternative Related to Reactor Pressure ML21139A1852021-06-22022 June 2021 Summary of Meeting with Exelon Generation Company, LLC Regarding Its Requested Alternative to Eliminate Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting ML21167A2152021-06-16016 June 2021 June 8, 2021, Summary of the Public Outreach to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2; and Byron Station, Units 1 and 2 ML21147A4262021-06-0303 June 2021 Summary of May 12, 2021, Meeting with Exelon Generation Company, Llc, Related to a Planned License Amendment to Modify the Ultimate Heat Sink Technical Specifications ML21011A2822021-01-21021 January 2021 Summary of January 6, 2021, Presubmittal Meeting Between the NRC and Exelon Generation Company, LLC Regarding Licensing Activities to Support the Planned Early Closures of Byron, Unit Nos. 1 and 2 and Dresden, Units 2 and 3 ML20351A2832020-12-18018 December 2020 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Exemption to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs ML20342A3522020-12-10010 December 2020 Summary of November 13, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alterantive to Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting (EPID-L-2020-LRM-0102) ML20323A0332020-12-0101 December 2020 Summary of November 4, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs ML20218A5302020-08-0505 August 2020 July 14, 2020, Summary of the Public Webinar to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2; and Byron Station, Units 1 and 2 ML20181A0002020-06-29029 June 2020 Summary of 6/24/20 Meeting with Exelon Generation Company, LLC Regarding Planned Request for Alternative to Supplemental Valve Position Indication Testing Requirements for Braidwood, Calvert Cliffs, Clinton, Limerick, Nine Mile, Peach Botto ML19326C3582019-12-0303 December 2019 Summary of November 20, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Revise the Quality Assurance Program ML19326A3152019-12-0303 December 2019 Summary of November 18, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Supplemental Valve Position Indication Testing Requirements ML19162A0272019-06-21021 June 2019 Summary of June 4, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Extend the Test Interval for Safety Relief Valves ML20108F0902019-04-20020 April 2019 April 15, 2020, Meeting Summary with Exelon Generation Company, LLC Regarding Planned Request to Defer Submittal of Owner'S Activity Report (Braidwood 2,Byron 2,Calvert Cliffs 1, LaSalle 1, Limerick 1, Nine Mile Point 2, Quad 2, R. E. Ginna ML19036A8832019-02-0707 February 2019 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Use ASME Code Case N-879 ML18354B1712019-01-0202 January 2019 Summary of December 19, 2018, Meeting with Exelon Generation Company, LLC Regarding the Use of Boiling Water Reactor Vessel and Internals Project Guidelines ML18325A1712018-11-28028 November 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Planned Fleet License Amendment Request to Revise Technical Specifications for High Radiation Areas ML18297A1722018-10-26026 October 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Planned License Amendment Request to Adopt TSTF-427 ML18225A3042018-08-16016 August 2018 Summary of August 8, 2018, Meeting with Exelon Generation Company, LLC, on a Future Relief Request to Extend the Post Peening Follow-Up Inspections for Certain Reactor Pressure Vessel Head Penetrations ML18135A0222018-05-14014 May 2018 Summary of the May 10th, 2018, Public Open House Regarding Braidwood Nuclear Power Station ML18120A1772018-05-0101 May 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Draft Guidance for Emergency Response Organization Staffing ML18065A8362018-03-0707 March 2018 Summary of February 27, 2018, Meeting with Exelon Generation Company, LLC Planned Fleet License Amendment Request to Relocate Staff Qualification Requirements from TSs to the Quality Assurance Topical Report ML18058A5232018-03-0101 March 2018 Summary of February 26, 2018, Meeting with Exelon Generation Company, LLC Regarding Proposed Alternative to the Main Steam Isolation Valve Testing Requirements ML18018B4432018-01-25025 January 2018 Summary of December 17, 2017, Closed Meeting with Exelon Generation Company, LLC, Regarding Tvel Lead Test Assemblies to Be Placed in the Braidwood Reactor (EPID 000976/05000456/L-2017-LRM and 000976/05000457/L-2017-LRM-0047 ML17347B1022017-12-14014 December 2017 Summary of Meeting with Exelon Generation Company, LLC on Its Planned Fleet License Amendment Request to Revise the Minimum Staffing Requirements for Emergency Response ML17184A0092017-07-10010 July 2017 Summary of June 29, 2017, Meeting with Exelon Generation Company, LLC, on Proposed Changes to Emergency Plans to Revise Emergency Action Levels (CAC Nos. MF9779-MF9801) ML17164A0512017-06-15015 June 2017 Summary of May 25, 2017, Meeting with Exelon Generation Company, LLC, on a Future License Amendment Request to Add Mitigating Actions to Technical Specifications with Two Control Room Ventilation Temperature Control System Trains Inoperable ML17132A3422017-05-12012 May 2017 Summary of the April 28, 2017, Open House to Discuss the 2016 End-of-Cycle Plant Performance Assessment of Braidwood Station 2024-06-04
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532
-4352 May 17, 2011 LICENSEE: Exelon Generation Company, LLC FACILITY: Braidwood Station, Units 1 and 2
SUBJECT:
SUMMARY
OF THE MAY 12 , 20 1 1 , PUBLIC MEETING TO DISCUSS THE BRAIDWOOD STATION, UNIT S 1 AND 2, END
-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On May 12 , 201 1, the Nuclear Regulatory Commission (NRC) held a public meeting at Braidwood City Hall. The meeting was between NRC Region III management and Exelon Generation Company management to discuss the NRC
=s assessment of the safety performance of Braidwood Station, Unit s 1 and 2, for the period from January 1 through December 31, 20 10. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML110871918 and ML111330667
, respectively. A list of principal NRC and licensee meeting participants can be found in the Enclosure.
The NRC began the meeting with an overview of the NRC
=s Reactor Oversight Process (ROP), the NRC's Action Matrix, and the national ROP results. This was followed by a discussion of the NRC
=s assessment of the performance of Braidwood Station, Units 1 an d 2 , in calendar year 20 10, which was documented in the March 4, 20 1 1 , end-of-cycle assessment letter as ML110620062
. As part of this regulatory performance meeting, Exelon responded to the NRC=s assessment. The licensee presentation can be found in ADAMS under ML111320194. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.
A list of principal meeting attendees can be found in the attached enclosure.
/RA/ Eric R. Duncan, Chief Branch 3 Division of Reactor Projects
Docket Nos. 50
-45 6; 50-45 7 License Nos. NPF
-72; NPF-77
Enclosure:
As Stated cc w/encl: Distribution via ListSer v
Enclosure Meeting Participants NRC S. West, Director, Division of Reactor Projects, Region III E. Duncan, Chief, Branch 3, Division of Reactor Projects, Region III J. Benjamin, Senior Resident Inspector, Braidwood D. Betancourt-Roldan , Resident Inspector, Braidwood B. Dickson, Chief, Plant Support Team, Region III R. Edwards, Reactor Inspector, Division of Nuclear Materials Safety, Region III H. Logaras, Government Liaison Specialist, Region III V. Mitlyng, Public Affairs Officer, Region III P. Chandrathil, Public Affair Officer, Region III J. Nance, Reactor Engineer, Region III Exelon Generation Company - Braidwood Station D. Enright, Site Vice President M. Kanavos, Plant Manager Illinois Emergency Management Agency (IEMA) R. Zuffa, Supervisor, NFS M. Perry , IEMA Resident Inspector
- Braidwood Other Attendees C. Davis, Big Brothers Big Sisters D. deGroh, President, Braidwood Historical Society A. Hulton, President, Braidwood Chamber of Commerce W. Rulier, Braidwood Finance Commissioner, Braidwood Chamber of Commerce H. Damron, Will County Emergency Management Agency M. Grace, Principal, Reed
-Custer Middle School J. King, Director of Operations, Reed
-Custer Schools L. Blackburn, School Board Member, Reed
-Custer School District 255U J. Cosgrove, Godley Park District J. Krug, Godley Park District A. Gerstyne, Godley Park District T. Branum, Coordinator, ESDA J. Willis, Assistant Coordinator, ESDA D. Kraft, Director, NEIS J. Hustis, Morris Herald N. Simon, Braidwood Jour nal T. Zimmer, Member of the Public J. Zimmer, Member of the Public J. Odeen, Member of the Public S. Allison, Member of the Public J. Hutton, Member of the Public M. Mack, Member of the Public B. DeMarse, Member of the Public R. Scamen, Member of the Publ ic Enclosure (Other attendees continued)
N. Scamen, Member of the Public M. Sheck, Member of the Public R. Aschenbrener, Member of the Public J. Aschenbrener, Member of the Public D. Gudger, Regulatory Assurance Manager, Exelon/Byron R. Radulovich, Nuclear Oversight, Exelon/Braidwood J. Garrity, Regulatory Assurance, Exelon/Braidwood
P. Simpson, Licensing Manager, Exelon L. Schofield, Licensing Engineer, Exelon C. Vandenburgh, Regulatory Assurance Manager, Exelon K. Lopykinski, Exelon
T. Braun, Exelo n
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532
-4352 May 17, 2011 LICENSEE: Exelon Generation Company, LLC FACILITY: Braidwood Station, Units 1 and 2
SUBJECT:
SUMMARY
OF THE MAY 12, 2011, PUBLIC MEETING TO DISCUSS THE BRAIDWOOD STATION, UNITS 1 AND 2, END
-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On May 12, 2011, the Nuclear Regulatory Commission (NRC) held a public meeting at Braidwood City Hall. The meeting was between NRC Region III management and Exelon Generation Company management to discuss the NRC
=s assessment of the safety performance of Braidwood Station, Units 1 and 2, for the period from January 1 through December 31, 2010. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML110871918 and ML111330667
, respectively. A list of principal NRC and licensee meeting participants can be found in the Enclosure.
The NRC began the meeting with an overview of the NRC
=s Reactor Oversight Process (ROP), the NRC's Action Matrix, and the national ROP results. This was followed by a discussion of the NRC
=s assessment of the performance of Braidwood Station, Units 1 and 2, in calendar year 2010, which was documented in the March 4, 20 11 , end-of-cycle assessment letter as ML110620062. As part of this regulatory performance meeting, Exelon responded to the NRC=s assessment. The licensee presentation can be found in ADAMS under ML111320194. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. A list of principal meeting attendees can be found in the attached enclosure.
Eric R. Duncan, Chief
` /RA/ Branch 3 Division of Reactor Projects Docket Nos. 50
-456; 50-457 License Nos. NPF
-72; NPF-77
Enclosure:
As Stated cc w/encl:
Distribution via ListServ DOCUMENT NAME:
G:\DRPIII\1-Secy\1-Work In Progress
\EOC Mtg Summary
\Braidwood 2010 EOC Public Meeting Summary.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII NAME EDuncan:dtp DATE 05/17/11 OFFICIAL RECORD COPY
Letter to Exelon Generation Company, LLC from E. Duncan dated May 1 7, 2011.
SUBJECT:
SUMMARY
OF THE MAY 12, 2011, PUBLIC MEETING TO DISCUSS THE BRAIDWOOD STATION, UNITS 1 AND 2, END
-OF-CYCLE PLANT PERFORMANCE ASSESSMENT DISTRIBUTION
- RidsNrrDorlLpl3
-2 Resource Daniel Merzke RidsNrrPMBraidwood Resource RidsNrrDirsIrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker DRPIII DRSIII Carole Ariano Linda Linn Patricia Buckley Tammy Tomczak ROPreports Resource