ML12229A128
ML12229A128 | |
Person / Time | |
---|---|
Site: | Indian Point |
Issue date: | 08/16/2012 |
From: | Rogge J Engineering Region 1 Branch 3 |
To: | Ventosa J Entergy Nuclear Operations |
References | |
IR-12-008, IR-12-009 | |
Download: ML12229A128 (39) | |
See also: IR 05000247/2012009
Text
't"ffi UNITED STATES NUCLEAR REGULATORY
COMMISSION
REGION I 21OO RENAISSANCE
BOULEVARD, SUITE 1OO KING OF PRUSSIA, PENNSYLVANIA
1940S'2713
August L6, 20L2 Mr. John Ventosa, Site Vice President Entergy Nuclear Operations, lnc.Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 1051 1-0249 SUBJECT: INDIAN POINT NUCLEAR GENERATING
UNITS 2 AND 3 - NRC INSPECTION
REPORT 05000247t2012009
AND 0500028612012008
AND NOTICES OF VIOLATION Dear Mr. Ventosa: On April 26,2012, the U.S. Nuclear Regulatory
Commission (NRC) completed
an inspection
at lndian Point Units 2and 3. The enclosed inspection
report documents
the inspection
results which were discussed
on April 26, 2012, with Mr. Lawrence Coyle, and other members of your staff. Following
in-office
reviews, an additional
meeting was conducted
by telephone
with Mr. Patric Conroy, Director, Nuclear Safety Assurance, on June 8,2012, and an exit meeting was conducted
by telephone
with Mr. Patric Conroy and other members of your staff on July 20, 2012.The inspection
examined activities
conducted
under your license as they relate to safety and compliance
with the Commission's
rules and regulations, and with the conditions
of your license. The inspectors
reviewed the ongoing implementation
of your corrective
actions to restore full compliance
with Title 10 of the Code of Federal Regulations, Part 50, Appendix R, Section lll.G.2 regarding
denied exemptions
to implement
operator manual actions in lieu of meeting the aforesaid
fire protection
regulations.
Two violations
are cited in the enclosed Notices of Violation
and the circumstances
surrounding
them are described
in detail in the subject inspection
report. The violations
were evaluated
in accordance
with the NRC Enforcement
Policy. The current Enforcement
Policy is included on the NRC's Web site at http://www.nrc.gov/about-nrc/regulatory/enforcemenVenforce-pol.html.
The violations
involved the use of unapproved
operator manual actions to mitigate safe shutdown equipment
malfunctions
caused by a fire-induced
single spurious actuation
at Indian Point Units 2 and 3, in lieu of protecting
the equipment
in accordance
with 10 CFR Part 50 Appendix R, Section lll.G.2. Although determined
to be of very low safety significance (Green), these violations
are being cited in the Notices because not all of the criteria specified
in Section 2.3.2.a of the NRC Enforcement
Policy for a non-cited
violation
were satisfied.
Specifically, Entergy Nuclear Operations, Inc. (ENO) failed to restore compliance
within a reasonable
amount of time after the violations
were identified
to nuclear power plant licensees in Regulatory
lssue Summary 2006-10, Regulatory
Expectations
with Appendix R Paragraph lll.G.2 Operator ManualActions, on June 30, 2006. You are required to respond to this letter and should follow the instructions
specified
in the enclosed Notice when preparing
your response.
The NRC will use your response, in part, to determine
whether further enforcement
action is necessary
to ensure compliance
with regulatory
requirements.
J. Ventosa 2 One other finding of very low safety significance (Green) was also identified.
This finding was determined
to be a violation
of NRC requirements.
However, because of its very low safety significance, and because it was entered into your corrective
action program, the NRC is treating this finding as a non-cited
violation (NCV) consistent
with Section 2.3.2 of the NRC Enforcement
Policy. lf you contest the NCV in this report, you should provide a written response within 30 days of the date of this inspection
report with the basis for your denial, to the U.S. Nuclear Regulatory
Commission, ATTN: Document Control Desk, Washington
D.C.20555-0001;
with copies to the Regional Administrator, Region l; the Director, Office of Enforcement;
and the NRC Senior Resident Inspector
at Indian Point Unit 2 or 3. In addition, if you disagree with the cross-cutting
aspect assigned to any finding in this report, you should provide a response within 30 days of the date of this inspection
report, with the basis for your disagreement, to the Regional Administrator, Region l, and the Senior Resident Inspector
at f ndian Point Unit 2 or 3.ln accordance
with Title 10 of the Code of Federal Regulations
Part 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any)will be available electronically
for public inspection
in the NRC Public Document Room or from the Publicly Available
Records (PARS) component
of the NRC's document system (ADAMS). ADAMS is accessible
from the NRC Web Site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic
Reading Room).Sincerely, 4.' i ;,/dfr/--/ John F. Rogge, Chief Engineering
Branch 3 Division of Reactor Safety Docket Nos. 50-247, 50-286 License Nos. DPR-26, DPR-64 Enclosures:
1. Notice of Violation 2. I nspection
Report 05000247 l 20 1 2009 a nd 05000 286 l 20 1 2008 w/Attachment:
Supplemental
lnformation
cc Mencl: Distribution
via ListServ
J. Ventosa 2 One other finding of very low safety significance (Green) was also identified.
This finding was determined
to be a violation
of NRC requirements.
However, because of its very low safety significance, and because it was entered into your corrective
action program, the NRC is treating this finding as a non-cited
violation (NCV)consistent
with Section2.3.2
of the NRC Enforcement
Policy. lf you contest the NCV in this report, you should provide a written response within 30 days of the date of this inspection
report with the basis for your denial, to the U.S. Nuclear Regulatory
Commission, ATTN: Document Control Desk, Washington
D.C.20555-0001;
with copies to the Regional Administrator, Region l; the Director, Office of Enforcement;
and the NRC Senior Resident Inspector
at Indian Point Unit 2 or 3. In addition, if you disagree with the cross-cutting
aspect assigned to any finding in this report, you should provide a response within 30 days of the date of this inspection
report, with the basis for your disagreement, to the Regional Administrator, Region l, and the Senior Resident lnspector
at lndian Point Unit 2 or 3.ln accordance
with Title 10 of the Code of Federal Regulations
Part 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically
for public inspection
in the NRC Public Document Room or from the Publicly Available
Records (PARS) component
of the NRC's document system (ADAMS). ADAMS is accessible
from the NRC Web Site at http://www,nrc.gov/reading-rm/adams.html (the Public Electronic
Reading Room).Sincerely,/RN John F. Rogge, Chief Engineering
Branch 3 Division of Reactor Safety Docket Nos. 50-247, 50-286 License Nos. DPR-26, DPR-64 Enclosures:
1. Notice of Violation 2. I nspection
Report 05000247 l 201 2009 and 05000 2861201 2008 w/Attachment:
Supplemental
Information
cc w/encl: Distribution
via ListServ DOCUMENT NAME: GlDRS\Engineering
Branch 3\IPEC OMA Inspection\lP
OMA Inspection
Report.doc
ADAMS ACCESSION
NUMBER: ML12229A128
g suNstReview
V Non-Sensitive
n Sensitive g Publicly Available n Non-PubliclyAvailable
OFFICE RI/DRS RI/DRS RI/ORA RI/DRP NAME DOrr WSchmidt MMcLaughlin
via email MGray via email DATE 8t1t12 8t2t12 8t10t12 8t12t12 OFFICE RI/DRS RI/DRS NAME JRogge CMiller via email DATE 8116112 8t9t12 OFFICIAL
J. Ventosa Distribution
w/encl: W. Dean, RA D. Lew, DRA D. Roberts, DRP J. Clifford, DRP C. Miller, DRS P. Wilson, DRS S. Kennedy, Rl OEDO M. Gray, DRP B. Bickett, DRP S. McCarver, DRP M. Jennerich, DRP A. Ayegbusi, Acting SRI R. Montgomery, Acting Rl P. Cataldo, SRI N. Lafferty, Acting Rl D. Hochmuth, AA RidsNrrPM
lndianPoint
Resource RidsNrrDorlLpll
-1 Resource ROPreport
Resource J. Rogge, DRS D. Orr, DRS W. Schmidt, DRS J. Lilliendahl, DRS 3 via E-mail)RIoRAMATL
RESOURCE)RIORAMAlL
RESOURCE)RIDRPMAlL
RESOURCE)RIDRPMAlL
RESOURCE)RIDRSMAIL
RESOURCE)RIDRSMATL
RESOURCE)
ENCLOSURE
1 NOTICE OF VIOLATION - Indian Point Unit 2 Entergy Nuclear Operations, lnc.lndian Point Nuclear Generating
Unit 2 Docket No: 50-247 License No: DPR-26 During an NRC inspection
conducted
April 23 through April 26, 2012, a violation
of NRC requirements
was identified.
ln accordance
with the NRC Enforcement
Policy, the violation
is listed below: License Condition
2.K specifies, in part, that Entergy Nuclear Operations, lnc., (ENO) shall implement
and maintain in effect all provisions
of the NRC-approved
fire protection
program as described
in the Updated Final Safety Analysis Report.The Updated Final Safety Analysis Report, Section 9.6 specifies
that ENO will meet the requirements
of 10 CFR Part 50, Appendix R, Section lll.G.2, which requires, in part, except as provided for in paragraph
G.3 of this section, where cables or equipment, including associated
non-safety
circuits that could prevent operation
or cause maloperation
due to hot shorts, open circuits, or shorts to ground, of redundant
trains of systems necessary
to achieve and maintain hot shutdown conditions
are located within the same fire area, one of the means of ensuring that one of the redundant
trains is free of fire damage shall be provided, per the requirements
in G.2.a - G.2i .Contrary to the above, between June 30, 2006, and April 26,2012, ENO failed to implement all provisions
of the approved fire protection
program. Specifically, the safe shutdown strategy for Indian Point Unit 2 relied upon unapproved
operator manual actions to mitigate post-fire
safe shutdown equipment
malfunctions
caused by a single spurious actuation, in lieu of protecting
the equipment
in accordance
with 10 CFR Part 50 Appendix R, Section lll.G.2, per the requirements
in G.2.a - G.2.f . The specific operator manual actions and fire areas and fire zones that are in violation
of Appendix R, Section lll.G.2 are listed in the lndian Point Unit 2 Denied OMA Summary Table of NRC Inspection
Report 0500024712012009
and 0500028612012008.
The use of manual actions in lieu of providing the required protection
requires prior NRC approval.This violation
is associated
with a Green Significance
Determination
Finding.Pursuant to the provisions
of 10 CFR 2.201, ENO is hereby required to submit a written statement
or explanation
to the U.S. Nuclear Regulatory
Commission, ATTN: Document Control Desk, Washington, DC 20555-0001
with a copy to the RegionalAdministrator, Region l, and a copy to the NRC Resident Inspector
at the facility that is the subject of this Notice, within 30 days of the date of the letter transmitting
this Notice of Violation (Notice).
This reply should be clearly marked as a "Reply to a Notice of Violation" and should include for each violation:
(1) the reason for the violation, or, if contested, the basis for disputing
the violation
or severity level, (2) the corrective
steps that have been taken and the results achieved, (3) the corrective
steps that will be taken, and (4) the date when full compliance
will be achieved.
Your response may reference
or include previous docketed correspondence, if the correspondence
adequately
addresses
the required response.
lf an adequate reply is not received within the time specified in this Notice, an order or a Demand for Information
may be issued as to why the Enclosure
1
2 license should not be modified, suspended, or revoked, or why such other action as may be proper should not be taken. Where good cause is shown, consideration
will be given to extending
the response time.lf you contest this enforcement
action, you should also provide a copy of your response, with the basis for your denial, to the Director, Office of Enforcement, United States Nuclear Regulatory
Commission, Washington, DC 20555-0001.
Because your response will be made available
electronically
for public inspection
in the NRC Public Document Room or from the NRC's document system (ADAMS), accessible
from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not include any personal privacy, proprietary, or safeguards
information
so that it can be made available
to the public without redaction.
lf personal privacy or proprietary
information
is necessary
to provide an acceptable
response, then please provide a bracketed
copy of your response that identifies
the information
that should be protected
and a redacted copy of your response that deletes such information.
lf you request withholding
of such material, you must specifically
identify the portions of your response that you seek to have withheld and provide in detail the bases for your claim of withholding (e.9., explain why the disclosure
of information
will create an unwarranted
invasion of personal privacy or provide the information
required by 10 CFR 2.390(b) to support a request for withholding
confidential
commercial
or financial information).
lf safeguards
information
is necessary
to provide an acceptable
response, please provide the level of protection
described
in 10 CFR 73.21.f n accordance
with 10 CFR 19.11, you may be required to post this Notice within two working days of receipt.Dated this 16th day of August, 2012 Enclosure
1
NOTICE OF VIOLATION - Indian Point Unit 3 Entergy Nuclear Operations, lnc.Indian Point Nuclear Generating
Unit 3 Docket No: 50-286 License No: DPR-64 During an NRC inspection
conducted
April 23 through April 26, 2012, a violation
of NRC requirements
was identified.
In accordance
with the NRC Enforcement
Policy, the violation
is listed below: License Condition
2.H specifies, in part, that Entergy Nuclear Operations, Inc., (ENO) shall implement
and maintain in effect all provisions
of the approved Fire Protection
Program as described
in the Final Safety Analysis Report.The Final Safety Analysis Report, Section 9.6.2 specifies
that ENO will meet the requirements
of 10 CFR Part 50, Appendix R, Section lll.G.2, which requires, in part, except as provided for in paragraph
G.3 of this section, where cables or equipment, including associated
non-safety
circuits that could prevent operation
or cause maloperation
due to hot shorts, open circuits, or shorts to ground, of redundant
trains of systems necessary
to achieve and maintain hot shutdown conditions
are located within the same fire area, one of the means of ensuring that one of the redundant
trains is free of fire damage shall be provided, per the requirements
in G.2.a - G.z.t.Contrary to the above, between June 30, 2006 and April 26, 2012, ENO failed to implement all provisions
of the approved fire protection
program. Specifically, the safe shutdown strategy for Indian Point Unit 3 relied upon unapproved
manual operator actions to mitigate post-fire
safe shutdown equipment
malfunctions
caused by a single spurious actuation, in lieu of protecting
the equipment
in accordance
with 10 CFR Part 50 Appendix R, Section lll.G.2, per the requirements
in G.2.a - G.z.f . The specific operator manual actions and fire areas and fire zones that are in violation
of Appendix R, Section lll.G.2 are listed in the Indian Point Unit 3 Denied OMA Summary Table of NRC lnspection
Report 0500024712012009
AND 0500028612012008.
The use of manual actions in lieu of providing the required protection
requires prior NRC approval.This violation
is associated
with a Green Significance
Determination
Finding.Pursuant to the provisions
of 10 CFR 2.201, ENO is hereby required to submit a written statement
or explanation
to the U.S. Nuclear Regulatory
Commission, ATTN: Document Control Desk, Washington, DC 20555-0001
with a copy to the Regional Administrator, Region l, and a copy to the NRC Resident Inspector
at the facility that is the subject of this Notice, within 30 days of the date of the letter transmitting
this Notice of Violation (Notice).
This reply should be clearly marked as a "Reply to a Notice of Violation" and should include for each violation:
(1) the reason for the violation, or, if contested, the basis for disputing
the violation
or severity level, (2) the corrective
steps that have been taken and the results achieved, (3) the corrective
steps that will be taken, and (4) the date when full compliance
will be achieved.
Your response may reference
or include previous docketed correspondence, if the correspondence
adequately
addresses
the required response.
lf an adequate reply is not received within the time specified Enclosure
1
2 in this Notice, an order or a Demand for lnformation
may be issued as to why the license should not be modified, suspended, or revoked, or why such other action as may be proper should not be taken. Where good cause is shown, consideration
will be given to extending
the response time.lf you contest this enforcement
action, you should also provide a copy of your response, with the basis for your denial, to the Director, Office of Enforcement, United States Nuclear Regulatory
Commission, Washington, DC 20555-0001.
Because your response will be made available
electronically
for public inspection
in the NRC Public Document Room or from the NRC's document system (ADAMS), accessible
from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not include any personal privacy, proprietary, or safeguards
information
so that it can be made available
to the public without redaction.
lf personal privacy or proprietary
information
is necessary
to provide an acceptable
response, then please provide a bracketed
copy of your response that identifies
the information
that should be protected
and a redacted copy of your response that deletes such information.
lf you request withholding
of such material, you must specifically
identify the portions of your response that you seek to have withheld and provide in detail the bases for your claim of withholding (e.9., explain why the disclosure
of information
will create an unwarranted
invasion of personal privacy or provide the information
required by 10 CFR 2.390(b) to support a request for withholding
confidential
commercial
or financial information).
lf safeguards
information
is necessary
to provide an acceptable
response, please provide the level of protection
described
in 10 CFR 73.21.ln accordance
with 10 CFR 19.11 , you may be required to post this Notice within two working days of receipt.Dated this 16th day of August, 2012 Enclosure
1
ENCLOSURE
2 U.S. NUCLEAR REGULATORY
COMMISSION
REGION I Docket Nos.: 50-247,50-286
License Nos,: DPR-26, DPR-64 ReportNos.:
0500024712012009,05000286/2012008
Licensee:
Entergy Nuclear Operations, Inc. (ENO)Facility: lndian Point Nuclear Generating
Units 2 and 3 Location:
450 Broadway, GSB Buchanan, NY 1051 1-0249 Dates: April 23 - April 26,2012 Inspectors:
D. Orr, Senior Reactor Inspector W. Schmidt, Senior Reactor Analyst J. Lilliendahl, Reactor Inspector Approved by: John F. Rogge, Chief Engineering
Branch 3 Division of Reactor Safety Enclosure
2
SUMMARY OF FINDINGS lR 0500024712012009, 0500028612012008;
412312012 - 412612012;
Indian Point Nuclear Generating
Units 2 and 3; Annual Follow-up
of Selected lssues Inspection.
The report covered a one-week annual follow-up
of selected issues inspection
by specialist
inspectors, Three findings of very low significance
were identified.
Two of these findings were determined
to be cited violations
and one of these findings was determined
to be a non-cited violation.
The significance
of most findings is indicated
by their color (Green, White, Yellow, Red) using Inspection
Manual Chapter (lMC) 0609, Significance
Determination
Process. Cross-cutting aspects associated
with findings are determined
using IMC 0310, Components
Within The Cross-Cutting
Areas. Findings for which the significance
determination
process (SDP)does not apply may be Green or be assigned a severity level after NRC management
review.The NRC's program for overseeing
the safe operation
of commercial
nuclear power reactors is described
in NUREG-1649, Reactor Oversight
Process, Revision 4, dated December 2006.Cornerstone:
Mitigating
Systems. Green. The inspectors
identified
a finding of very low safety significance (Green), involving
a cited violation
of lndian Point Unit 2 Operating
License Condition
2.Kto implement
and maintain all aspects of the approved fire protection
program.Specifically, ENO failed to protect required post-fire
safe shutdown components
and cabling to ensure one of the redundant
trains of equipment
remained free from fire damage as required by 10 CFR Part 50, Appendix R, Section lll.G.2. In lieu of protecting
a redundant
safe shutdown train, ENO utilized unapproved
operator manual actions to mitigate component
malfunctions
or spurious operations
caused by postulated
single fire-induced
circuit faults. ENO submitted
an exemption
request (M1090770151)
on March 6, 2009, in which it sought exemption
from requirements
of Paragraph
lll.G.2, to permit the use of OMAs upon which it had been relying for safe-shutdown
in a number of fire areas. However, several OMAs within the exemption
request were denied because ENO failed to demonstrate
that the OMAs were feasible and reliable, or to appropriately
evaluate fire protection
defense-in-depth.
ENO's performance
deficiency
delayed achieving
full compliance
with fire protection
regulations
and adversely
affected post-fire
ENO has entered this issue into the corrective
program for resolution.
The inspectors
found the manual actions in addition to roving fire watches in all affected areas to be reasonable
interim compensatory
measures pending final resolution
by ENO.ENO's failure to protect components
credited for post-fire
safe shutdown from fire damage caused by single spurious actuation
is considered
a performance
deficiency.
The performance
deficiency
was more than minor because it affected the Mitigating
Systems cornerstone
objective
to ensure the availability, reliability, and capability
of systems that respond to an external event to prevent undesirable
consequences
in the event of a fire. Specifically, the use of operator manual actions during post-fire
safe shutdown is not as reliable as normal systems operation
which could be utilized had the requirements
of 10 CFR Part 50, Appendix R, Section lll.G.2 been met and, therefore, prevented
fire damage to credited components
and/or cables. The inspectors
used IMC 0609, Appendix F, Fire Protection
Significance
Determination
Process, Phase 1 and" =nclosure
2
a Senior Reactor Analyst conducted
a Phase 3 evaluation, to determine
that this finding was of very low safety significance (Green). This finding does not have a cross cutting aspect because the performance
deficiency
occurred greater than three years ago when the exemption
request was submitted
to the NRC on March 6, 2009, and is not indicative
of current licensee performance. (Section 4OA2.1)Green. The inspectors
identified
a finding of very low safety significance (Green), involving
a cited violation
of Indian Point Unit 3 Operating
License Condition
2.H to implement
and maintain all aspects of the approved fire protection
program.Specifically, ENO failed to protect required post-fire
safe shutdown components
and cabling to ensure one of the redundant
trains of equipment
remained free from fire damage as required by 10 CFR Part 50, Appendix R, Section lll.G.2. In lieu of protecting
a redundant
safe shutdown train, ENO utilized unapproved
operator manual actions to mitigate component
malfunctions
or spurious operations
caused by postulated
single fire-induced
circuit faults. ENO submitted
an exemption
request (M1090760993)
on March 6, 2009, in which it sought exemption
from requirements
of Paragraph
lll.G.2, to permit the use of OMAs upon which it had been relying for safe-shutdown
in a number of fire areas. However, several OMAs within the exemption
request were denied because ENO failed to demonstrate
that the OMAs were feasible and reliable, or to appropriately
evaluate fire protection
defense-in-depth.
ENO's performance
deficiency
delayed achieving
full compliance
with fire protection
regulations
and adversely
affected post-fire
ENO has entered this issue into the corrective
program for resolution.
The inspectors
found the manual actions in addition to roving fire watches in all affected areas to be reasonable
interim compensatory
measures pending final resolution
by ENO.ENO's failure to protect components
credited for post-fire
safe shutdown from fire damage caused by single spurious actuation
is considered
a performance
deficiency, The performance
deficiency
was more than minor because it affected the Mitigating
Systems cornerstone
objective
to ensure the availability, reliability, and capability
of systems that respond to an external event to prevent undesirable
consequences
in the event of a fire. Specifically, the use of operator manual actions during postfire safe shutdown is not as reliable as normal systems operation
which could be utilized had the requirements
of 10 CFR 50, Appendix R, Section lll.G.2 been met and, therefore, prevented
fire damage to credited components
and/or cables. The inspectors
used IMC 0609, Appendix F, Fire Protection
Significance
Determination
Process, Phase 1 and a Senior Reactor Analyst conducted
a Phase 3 evaluation, to determine
that this finding was of very low safety significance (Green). This finding does not have a cross cutting aspect because the performance
deficiency
occurred greater than three years ago when the exemption
request was submitted
to the NRC on March 6, 2009, and is not indicative
of current licensee performance. (Section 4OA2.2)Green. The inspectors
identified
a Green, Non-Cited
Violation
of the lndian Point Nuclear Generating
Unit No. 2 Amended Facility Operating
License, Condition
2.K, in that ENO failed to implement
and maintain in effect all provisions
of the NRC-approved
fire protection
program as described
in the Updated Final Safety Analysis Report.Specifically, ENO failed to minimize transient
combustible
materials
within the primary auxiliary
building (PAB) and stored a compressed
gas cylinder containing
hydrogen gas lll Enclosure
2
B.under cable trays. The hydrogen gas cylinder was inappropriately
left in its storage location after a calibration
gas cylinder change-out
occurred for the waste gas analyzer, ENO promptly entered this issue into its corrective
action program and removed the hydrogen cylinder from the PAB. ENO initiated
a corrective
action to evaluate the identified
condition
and ensure actions to prevent its recurrence.
ENO's failure to remove the compressed
hydrogen gas cylinder from the PAB after its intended use as a calibration
gas for the waste gas analyzer was a performance
deficiency.
This finding was more than minor because it was associated
with the External Factors attribute (fire) of the Mitigating
Systems Cornerstone
and adversely affects the cornerstone
objective
to ensure the availability, reliability, and capability
of systems that respond to initiating
events to prevent undesirable
consequences (i.e., core damage). Specifically, the hydrogen gas cylinder was stored below cable trays in an area that includes safe shutdown circuits and the associated
cables were at increased risk to fire damage. The inspectors
used IMC 0609, Appendix F, Fire Protection
Significance
Determination
Process, Phase 1 and a Senior Reactor Analyst conducted
a Phase 3 evaluation, to determine
that this finding was of very low safety significance (Green). The inspectors
determined
that this finding had a cross-cutting
aspect in the area of Human Performance
associated
with the work practice attribute
because ENO personnel
did not follow procedure, Control of Combustibles, EN-DC-161, Rev. 6, as written and did not remove the hydrogen gas cylinder from the PAB after it was disconnected
from the waste gas analyzer contrary to Control of Combustibles, EN-DC-161, Rev. 6. (H.4(b) per IMC 0310). (Section 4OA2.3)Licensee-ldentified
Violations
None.iv Enclosure
2
REPORT DETAILS Backqround
The NRC requirements
related to fire protection
are provided in Title 10 of the Code of Federal Regulations (CFR) Section 50.48. In accordance
with 10 CFR 50.48(b), nuclear power plants licensed to operate before January 1,1979 are required to meet Section lll.G, of 10 CFR Part 50, Appendix R. The underlying
purpose of Section lll.G of 10 CFR Part 50, Appendix R, is to ensure that the ability to achieve and maintain safe-shutdown
is preserved
following
a fire event.Paragraph
lll.G.2 of Appendix R requires one of the following
means to ensure that a redundant train of safe-shutdown
cables and equipment
is free of fire damage, where redundant
trains are located in the same fire area outside containment:
a. Separation
of cables and equipment
by a fire barrier having a three-hour
rating;b. Separation
of cables and equipment
by a horizontal
distance of more than 20 feet with no intervening
combustibles
or fire hazards and with fire detectors
and an automatic
fire suppression
system installed
in the fire area; or, c. Enclosure
of cables and equipment
of one redundant
train in a fire barrier having a one-hour rating and with fire detectors
and an automatic
fire suppression
system installed
in the fire area.lnside containments
one of the fire protection
means specified
above or one of the following fire protection
means shall be provided: d. Separation
of cables and equipment
and associated
non-safety
circuits of redundant trains by a horizontal
distance of more than 20 feet with no intervening
combustibles
or fire hazards;e. Installation
of fire detectors
and an automatic
fire suppression
system in the fire area; or f. Separation
of cables and equipment
and associated
non-safety
circuits of redundant trains by a noncombustible
radiant energy shield.However, as a result of safe-shutdown
focused inspections
conducted
in 2000, the NRC identified
that, in lieu of the methods specified
in Paragraph
lll.G.2, some licensees, including ENO, were crediting
operator manual actions (OMAs) to achieve and maintain safe shutdown in the event of a fire impacting
areas in which both trains of a safe-shutdown
system or component are co-located.
ln 2006, the NRC issued Regulatory
lssue Summary 2006-10, Regulatory
Expectations
with Appendix R, Paragraph
lll.G.2, Operator ManualActions, which clarified
Appendix R and that OMAs are not permitted, unless they have been specifically
approved by the NRC as part of a licensee's
request for exemption
from the requirements
of Paragraph
lll.G.2. The NRC also issued EGM 07-004 (ML071830345), which granted enforcement
discretion
for licensees
relying on OMAs and provided until March 6, 2009 for licensees
to complete corrective
actions.Corrective
actions included establishing
compliance
with fire protection
regulations
or, as appropriate, submitting
an exemption
request to the NRC to implement
OMAs in lieu of fire protection
regulations.
Enclosure
2
2 ln response to this issue, on March 6, 2009, ENO submitted
exemption
requests for Indian Point Nuclear Generating
Units 2 and 3 (M1090770151
and M1090760993)
in which it sought exemption
from certain requirements
of Paragraph
lll.G.2, to permit the use of OMAs upon which it had been relying for safe-shutdown
in a number of fire areas. Because the acceptability
of the OMAs was being considered
under this exemption
request, enforcement
discretion
continued
for the duration of the NRC review. The NRC considered
ENO's exemption
requests, as supplemented
by information
provided by ENO in response to NRC requests for additional
information.
The period of enforcement
discretion
for noncompliance
with NRC fire protection
requirements
at lndian Point Nuclear Generation
Units 2 and 3 ended with the NRC issuance of the February 1,2012,letters (ML112140509
and ML112200442)
documenting
completion
of the NRC review. The NRC recognized
that ENO implemented
additional
compensatory
measures (fire watches in all affected fire areas) to enhance the fire protection
response in the areas. In a triennial
fire protection
inspection
in June 2011 (ML111920339), NRC inspectors
assessed the feasibility
of these compensatory
measures.
In addition, NRC fire protection
inspections
have verified that Indian Point Nuclear Generating
Units 2 and 3 have implemented
a defense-in-
depth fire protection
program, including
a site fire brigade, that is trained and equipped to respond to and fight fires.In order to determine
how the denied OMAs affected ENO's compliance
with Appendix R requirements, the NRC requested
information
from ENO about the schedule and plans for bringing Indian Point Nuclear Generating
Units 2 and 3 into full compliance (M112031A176).
ENO responded
on March 1,2012 (Mt12074A028)
with a proposed schedule that showed full restoration
of compliance
for all but two of the OMAs by the fourth quarter of 2012, and for the finaltwo OMAs by the Unit 2 refueling
outage in Spring 2014.This report presents the results of a problem identification
and resolution
annual follow-up
of selected issues inspection
conducted
in accordance
with NRC Inspection
Procedure (lP) 71152, Problem ldentification
and Resolution
to review ENO's implementation
of corrective
actions to restore full compliance
regarding
the use of OMAs.The objectives
of this inspection
were to: a. Assess the adequacy of compensatory
measures for unapproved
OMAs;b. Verify commitments
to resolve all unapproved
OMAs were appropriately
entered into the corrective
action program (CAP);c. Review updates to procedures, OMA feasibility
and reliability
studies, and safe-shutdown analyses;
and, d. Review progress to date and the proposed schedule for restoring
compliance.
Specific documents
reviewed by the inspectors
are listed in the attachment.
Enclosure
2
4. OTHER ACTTVTTIES
[OAl 4OA2 Problem ldentification
and Resolution
(71152- 1 sample)a. Inspection
Scope b.1.The inspectors
assessed ENO's problem identification
threshold, extent of condition reviews, compensatory
actions, and timeliness
of corrective
actions to determine whether ENO was appropriately
identifying, evaluating, and correcting
problems associated
with unapproved
OMAs.The inspectors
reviewed the fire hazard analysis, safe shutdown analysis and supporting
licensing
and design basis documents
to understand
the structures, systems, and components
required for fire safe shutdown.
The inspectors
reviewed the fire safe shutdown operating
procedures
to verify that all OMAs were either granted an exemption or were being addressed
by the corrective
action program. The inspectors
reviewed condition
reports to evaluate the adequacy of evaluations
and corrective
actions with respect to the denied OMAs. The fire protection
engineer and safe shutdown engineer were interviewed
to evaluate the feasibility
of the proposed plan to restore compliance
and to assess corrective
actions taken to date.The inspectors
previously
walked down all denied OMAs as part of the 2011 triennial
fire protection
inspection
to assess the feasibility
of the OMAs. The inspectors
walked down portions of the OMAs to re-validate
the feasibility
of the actions. The inspectors
walked down all fire zones that credited denied OMAs to assess the fire risk significance
which can be affected by ignition sources, transient
and fixed combustibles, or absence of train separation, detection, and automatic
suppression.
The inspectors
reviewed condition
reports, fire watch logs, and fire protection
program impairment
requirements
to verify that compensatory
measures in the form of fire watches were being adequately
performed
as required by the fire protection
program.Findinos Failure to Protect Safe Shutdown Eouipment
from the Effects of Fire (Unit 2)lntroduction.
The inspectors
identified
a finding of very low safety significance (Green), involving
a cited violation
of Indian Point Unit2 Operating
License Condition
2.Kto implement
and maintain all aspects of the approved fire protection
program.Specifically, ENO failed to protect required post-fire
safe shutdown components
and cabling to ensure one of the redundant
trains of equipment
remained free from fire damage as required by 10 CFR Part 50, Appendix R, Section lll.G.2. In lieu of protecting
a redundant
safe shutdown train, ENO utilized unapproved
operator manual actions to mitigate component
malfunctions
or spurious operations
caused by postulated
single fire-induced
circuit faults. ENO submitted
an exemption
request (M1090770151)
on March 6, 2009, in which it sought exemption
from requirements
of Paragraph
lll.G.2, to permit the use of OMAs upon which it had been relying for safe-shutdown
in a number of fire areas. However, several OMAs within the exemption
request were denied Enclosure
2
4 because ENO failed to demonstrate
that the OMAs were feasible and reliable, or to appropriately
evaluate fire protection
defense-in-depth.
ENO's performance
deficiency
delayed achieving
full compliance
with fire protection
regulations
and adversely
affected post-fire
safe shutdown.Description.
On June 30, 2006, the NRC issued Regulatory
lssue Summary (RlS)2006-10, Regulatory
Expectations
with Appendix R, Paragraph
lll.G.2, Operator Manual Actions, which clarified
Appendix R and that OMAs are not permitted, unless they have been specifically
approved by the NRC as part of a licensees
request for exemption
from the requirements
of Paragraph
lll.G.2. In addition to information
provided to the licensees
in RIS 2006-10, the NRC issued enforcement
guidance memorandum (EGM)07-004, which granted enforcement
discretion
for licensees
relying on noncompliant
OMAs to bring themselves
back into compliance
with the existing regulations, The enforcement
discretion
provided licensees
until March 6, 2009, to complete their corrective
actions.ENO submitted
exemption
requests on March 6, 2009 for OMAs in several non-compliant
fire areas. The NRC considered
ENO's exemption
requests, as supplemented
by information
provided by ENO in response to NRC requests for additional
information.
On February 1,2012, the NRC denied many of the requested
exemptions
based on lack of fire protection
defense-in-depth, such as detection
or automatic
suppression, or lack of time margin available
to complete the OMA. The NRC's denial of several OMAs within the exemption
requests was based on guidance to the NRC staff and available
to the industry.
NUREG 1852, Demonstrating
the Feasibility
and Reliability
of OMAs in Response to Fire, published
October 2007, page 1-2, states that additional
considerations
to ensure that adequate defense-in-depth
such as fire detection
and suppression
is maintained
are addressed
in Regulatory
Guide (RG) 1 .189 and should be considered
when applying for an exemption
or license amendment.
RG 1 .189, Fire Protection
Program for Nuclear Power Plants, Rev. 1, March 2007, (in effect when NUREG 1852 was issued) Section 5.3.3 similarly
states that allfire-related
operator manual actions must be feasible and reliable.
RG 1 .189 further states that the use of operator manual actions does not obviate the detection
and suppression
capabilities
that are required by the regulations
and in addition, the omission or elimination
of these capabilities
in an area containing
systems, structures, or components (including
circuits)important
to safety would generally
be considered
an adverse effect on safe shutdown since it would reduce, at a minimum, fire protection
defense-in-depth.
ENO's failure to demonstrate
that several OMAs were feasible and reliable, and to appropriately
evaluate fire protection
defense-in-depth
delayed achieving
full compliance
with fire protection
regulations
and adversely
affected post-fire
ENO entered this issue into its CAP for long term resolution
as CR-lP2-2012-00654.
Interim compensatory
measures for the fire protection
non-compliances
included roving fire watches in all affected fire areas and were initiated
in June 2011. The inspectors
considered
the interim compensatory
measures reasonable
pending final resolution.
ENO responded
to the NRC in a letter dated March 1,2012 (ML120744028)
with a proposed schedule to resolve all Unit 2 non-compliances
for all but two of the OMAs by the fourth quarter o12012, and for the remaining
two OMAs by the Unit 2 refueling outage in Spring 2014.Enclosure
2
5 Additionally, the inspectors
identified
that ENO failed to identify two OMAs that were being relied upon to achieve and maintain safe shutdown in the event of a fire impacting FZFlTA. During plant walkdowns, the inspectors
noted an emergency
control station within the 480V switchgear
room that provided an isolation
function and start and stop controls for the 21 charging pump. Entergy engineers
informed the inspectors
that the emergency
control station was installed
as a plant modification
under ER-lP2-03-21959
in 2003 to address a previously
identified
Appendix R cable separation
concern in fire zone (FZ) F/7A. The emergency
control station isolates control circuits that terminate
at a local control panel for the charging pumps. The 21 charging pump can be isolated from the effects of a fire in FZFITA and started in the 480V switchgear
room from the emergency
control station. Entergy failed to include this unapproved
operator manual action in its exemption
request submitted
on March 6,2009 (M1090770151).
During interviews
with Entergy engineers
regarding
the charging pump local control panel and its impact on charging pump operation
for a fire in FZ F 17 A, the inspectors
also identified
that an additional
OMA was necessary
to operate the 21 charging pump. The additional
OMA required local operation
of the 21 charging pump scoop tube positioner
to control the 2l charging pump speed. Entergy promptly entered these missed OMAs into its corrective
action program as CR-lP2-2012-03024
and verified the OMAs were feasible and reliable and noted that fire watches as compensatory
measures for other OMAs within this fire zone remained in place. The inspectors
considered
Entergy's compensatory
measures and immediate
corrective
actions adequate for the missed OMAs. Similar to the denied OMAs, Entergy planned to resolve the missed OMAs and establish
compliance
with 10 CFR Part 50, Appendix R, Section lll.G.2.Analvsis.
The inspectors
identified
a performance
deficiency
in that ENO failed to protect components
credited for post-fire
safe shutdown from fire-induced
damage. The denied OMAs, as well as the missed OMAs, were considered
a single performance
deficiency
as the apparent causalfactors
were related, an inadequate
review and evaluation
of operator manual actions, and also occurred when the exemption
request was submitted
to the NRC on March 6, 2009. The performance
deficiency
was more than minor because it was associated
with the Protection
against External Events (Fire)attribute
of the Mitigating
Systems Cornerstone
and negatively
affected the objective
to ensure the availability, reliability, and capability
of systems that respond to initiating
events to prevent undesirable
consequences
in the event of a fire. Specifically, the use of OMAs during post-fire
shutdown is not as reliable as normal system operation
from the main control room which would be utilized had the requirements
of 10 CFR Part 50, Appendix R, Section 11,,.G2 been met. The inspectors
used IMC 0609, Appendix F, Fire Protection
Significance
Determination
Process, Phase 1 and a Senior Reactor Analyst conducted
a Phase 3 evaluation, to determine
that this finding was of very low safety significance (Green). This finding does not have a cross cutting aspect because the performance
deficiency
occurred greater than three years ago when the exemption request was submitted
to the NRC on March 6, 2009, and is not indicative
of current licensee performance.
The inspectors
determined
the issue did not screen to Green with a Phase 1 SDP because the finding category was post-fire
safe shutdown and involved operator manual actions. A Phase 3 SDP was performed
by a Senior Reactor Analyst (SRA) because the Fire Protection
Phase 2 SDP is intended to support the assessment
of known issues Enclosure
2
6 only in the context of an individual
fire area and this issue involved multiple fire areas and fire zones. However, the SRA determined
the Phase 2 SDP tools could be used on an area by area basis to inform the Phase 3 SDP and screen fire zones if a sufficient
basis was developed
for each fire zone and justified
an absence of credible fire scenarios
such that mitigating
equipment
or its associated
cables would not be damaged or a plant transient
would not occur. Guidance in each attachment
of IMC 0609, Appendix F was applied in addition to the following
assumptions
specific for lndian Point Nuclear Generating
Unit 2 cable construction
and detail: All cables are treated as thermoplastic
with damage potential
described
in Tables A7.2 and 47.3: All cables are jacketed with an asbestos braid and do not act as intervening
combustibles
or contribute
to fire spread; and, Asbestos cable jacket is not credited as a thermal or radiant heat shield.The inspectors
walked down each of the individual
fire zones to identify potential
fire damage scenarios
to circuits that were not protected
to the requirements
of 10 CFR Part 50, Appendix R, Paragraph
lll.G.2. For the vapor containment
fire area and its associated
operator manual actions, the inspectors
reviewed a video that was recorded by the licensee in the previous Unit 2 refueling
outage specifically
for this inspection
purpose and at the request of the NRC inspectors.
A summary of the risk evaluation
for each OMA and its associated
denied or missed OMAs is in a table at the end of this Analysis section. In general, all of the fire zones except FZFI6 screened out because: Detailed circuit and cable analysis demonstrated
that cable damage could not cause spurious operations
to credited safe shutdown equipment.
The safe shutdown analysis that was used by ENO to formulate
conclusions
on the protection
of safe shutdown capability
in their exemption
request was overly conservative.
Because damage to these cables would not cause a malfunction
of safe shutdown equipment, the associated
OMAs were unnecessary
and were not violations
of 10 CFR Part 50, Appendix R, lll.G.2.;An ignition source did not exist that could credibly cause cable damage. The cables were sufficiently
separated
from all fixed ignition sources to not be damaged from thermal or radiant heat and a transient
fire with an assumed origin two feet above the floor would also not generate sufficient
thermal or radiant heat to damage cables at their high elevations;
or, The only credible ignition source was a transient
combustible
fire and the associated
weighting
factor was very low, i.e., the critical floor area was much smaller than the plausible
floor area for the assumed transient
combustible
fire.For fire zone FG and its associated
denied OMA, OMA 6, the postulated
fire resulted from an oil leak of the 22 charging pump fluid drive causing damage to the pump itself and the cabling associated
with the operation
and controls for the charging pump suction valves. There are two suction paths available
to the charging pumps: 1) the volume control tank (VCT) from a normally open motor operated valve (MOV) 112C which is physically
located in the VCT room, and 2) the refueling
water storage tank (RWST) from Enclosure
2
7 a normally closed air operated valve (AOV) 1128, which is located in the 22 charging pump cellor FZFl6. Valve 112B is designed to open automatically
in the event of a low VCT level through 1 128 valve position monitoring
circuitry.
Under these conditions, 1 12C would also close. The fire was conservatively
assumed to render 1128 failed closed and close 1 12C due to cable damage to the 1 128 position monitoring
circuit. The denied OMA 6 included actions within FZ Fl6 to locally open the 1128 bypass valve 288 and in the VCT room to verify closed 112C. These actions were necessary
to align the RWST as a suction source before starting the credited 21 charging pump from the main control room.Due to uncertainties
involved in fire induced core damage assessment, the SRA conducted
two bounding analyses:
1) a fire model case based on fire modeling which assumed that only equipment
in the subject fire area was potentially
damaged and all other equipment
failed probabilistically, and 2) an Appendix R case where only equipment
credited in the safe shutdown analysis was available.
For the Phase 3 SDP results, the SRA chose the fire model case as it represented
the more realistic
plant and operator response to a potential
fire in FZFl6.Both analyses were conducted
for FZ F/6 using the lP2 SPAR model version 8.20 to estimate the increase in conditional
core damage probability
if the denied OMAs were needed vice not needed and Appendix R requirements
were met such that all mitigating
operations
were available
from the control room. The lP2 SPAR model credits the charging pumps as an emergency
boration source during an anticipated
transient without scram (ATWS) and as a source of reactor coolant pump (RCP) seal injection.
RCP seal injection
along with the RCP thermal barrier cooling from the closed cooling water system (CCW) provides RCP seal cooling and precludes
a RCP sealfailure
loss of coolant accident.
This core damage analysis differed from the Appendix R guidelines
to maintain or restore RCS pressurizer
level. An independent
Region I SRA reviewed and found acceptable
the SPAR model changes made to conduct these analyses.
Both analyses assumed that a fire in FZFI6 would: a a a a Occur at a frequency
of 5.0E-5 per year consistent
with Attachment
4 of the Fire Protection
SDP for a pump oilfire;Only occur if the 22 charging pump was running;Fail the 22 charging pump;Fail1128 closed; and, Result in operator responses
in accordance
with procedures;
o A manually initiated
reactor trip, which was reflected
as a transient initiation
event; and, o Removing pressurizer
power operated relief valve (PORV) control power fuses in the control room to prevent spurious PORV operation.
This action was assumed always successful.
For ATWS sequences, it was assumed that all PORVs and RCS safety valves would be open and that operators
would not remove fuses to close the PORVS, but would continue to recover a charging pump and establish
emergency
boration.Enclosure
2
I The fire model analysis estimated
an increase in the core damage frequency
less than 1E-9, if the OMAs were not successful, given the estimated22
charging pump lube oil fire occurred at a frequency
of 5E-5 per year and the very limited credit afforded the charging pumps in core damage mitigation.
The dominating
core damage sequence involving
the OMAs was an ATWS following
the manual reactor trip caused by mechanical
binding of all the control rods, and a failure of operators
to manually open 288 to establish
emergency
boration with the 21 charging pump. The negligible
increase in core damage frequency
was also due to the extremely
low probability
of an ATWS where emergency
boration would be necessary
or a common cause failure of the service water system which would lead to a RCP seal failure. This analysis allowed normal plant equipment
to remain functional
provided it was not damaged as a result of the fire scenario based on fire modeling.
The fire model analysis assumed that a fire in FZFI6 would:. Fail 112C closed with the probability
of an intra-conduit
hot short of 0.05, based on NUREG/CR-6850.
Fail112C open with a 0.95 probability.
lf 112C failed open, it must be closed to restore the RWST suction to the 21 charging pump.. Not generate a damaging hot gas layer nor damage any equipment
in the adjacent primary auxiliary
building corridor, FZFlTA. This assumption
was based on fire modeling.. Result in control room operators
in accordance
with procedure
promptly disabling the 21 charging pump from automatic
operation.
This action is required by procedure
to preclude damage to the 21 charging pump should it operate without a water source aligned to its suction as the result of spurious^valve
operations.
A failure probability
of 1.1E-2 was assumed based on SPAR-H', assuming diagnosis
and allfactors
in their nominal state.. Result in operators
implementing
the denied OMAs in accordance
with procedures
and specifically
aligning the RWST to the charging pumps suction after the fire is extinguished
and includes: o Manually opening valve 288 with a failure probability
of 2.3E-l assumed based on SPAR-H with all factors in their nominal state except for high stress and conservatively
assuming barely sufficient
time.o Verify or close 1 12C with a failure probability
o'f 2.3E-1 assumed based on SPAR-H with all factors in their nominal state except for high stress and conservatively
assuming barely sufficient
time.. Result in control room operators, starting the 21 charging pump, in accordance
with procedure, once suction to the RWST was aligned by the OMAs. A failure probability
of 1.1E-2 was assumed based on SPAR-H assuming diagnosis
and all factors in their nominal state.The Appendix R analysis estimated
an increase in the core damage frequency
in the mid-E-7 range. The Appendix R analysis assumed no credit afforded the charging pumps in the dominating
core damage sequence.
In the Appendix R analysis, the OMAs did not impact the core damage frequency
results. The dominating
core damage sequence involved a RCP loss of seal cooling event leading to a small loss of coolant accident due to RCP sealfailure
at a leak rate of 182 gpm per RCP and successful
operation
of the 21 AFW train. Although 21 AFW was successful, core damage occurs because the reactor cannot be depressurized
because PORV fuses are removed by Enclosure
2
9 procedure
failing the PORVs closed, and high pressure coolant injection
is assumed to have failed in the Appendix R analysis.
lf a loss of RCP seal cooling does not occur, the dominant core damage sequence included failure of the 21 AFW train (in the range of 1 in 125) and the inability, using high pressure coolant injection
and the PORVs (feed and bleed), to remove decay heat. The Appendix R analysis assumed that a fire in the FZF16 would:. Cause a loss of RCP seal cooling and subsequent
RCP sealfailure.
A loss of RCP seal cooling occurred due to the fire induced closures of 112C and a CCW system MOV in the RCP thermal barrier cooling flow path. In this case, with a fire in the 22 charging pump cell, operators
would not be able to open valve 288 to establish
a suction path to the 21 charging pump in sufficient
time to prevent the assumed RCP sealfailure.. Cause a failure of all equipment
within fire area F including:
o Both trains of high pressure injection.
o 22train of low pressure injection.
o Motor control centers 264 and 268.o Cause failure of the 22 motor driven and 23 turbine driven AFW pumps.The table below summarizes
the results for each OMA with its respective
fire zone: Indian Point Unit 2 Denied OMA Summary Table Fire OMA No.'Area/Zone Violation
of lll.G.2 Comments Risk lncrease Results F/5A FITA No Based on circuit reviews, cables of interest within this No increase FZ do not result in a spurious operation
that necessitates
this OMA.Yes This area required a detailed phase 3 SDP analysis.
Negligible
The inspectors
assumed a 5200kW fire from 54 increase gallons of oil leaked from the 22 charging pump fluid based on drive within a 40 sqft skid 15.5ft directly below cable detailed YZ1-J85. Details of the phase 3 SDP analysis are Phase 3 described
in the analysis section prior to this table. SDP analysis No Based on circuit reviews, cables of interest within this No increase FZ do not result in a spurious operation
that necessitates
this OMA.Yes There were no fixed or assumed transient combustible
ignition sources that could credibly damage cable YZ1-JB1 which is located 14ft above the floor.Ft6 Screened based on Phase 2 SDP tasks Enclosure
2
10 Ft27A 5 F/33A 6 5 Yes Based on circuit reviews, cables of interest within this FZ do not result in a spurious operation
that necessitates
this OMA.The only credible ignition source was a transient combustible
fire and the associated
transient weighting
factor was very low, i.e. an 8sqft critical floor area compared to 6000sqft plausible
floor area equals a 2.3E-7 area weighting
factor.See above, same as FlTA for OMA 20.No Based on circuit reviews, cables of interest within this FZ do not result in a spurious operation
that necessitates
this OMA, Yes This OMA involves opening a manual valve, 227, to align a charging path to the reactor coolant system if the normally open air operated valve, HCY-l42, were to close from a loss of instrument
air (lA). Circuits to HCV-142 do not route through the associated
FZs.Therefore
this OMA is only necessary
for a fire induced loss of lA. The inspectors
walked down each FZ and did not identify any lA lines near ignition sources. Additionally, a loss of lA resulting
from the spurious operation
of several lA loads and a subsequent
high demand on the lA system would require multiple spurious operations.
Yes The only credible ignition source to cable CK1-YP3, power supply cable to 112C, is the motor control center where CK1-YP3 terminates.
This is a fire damage state zero scenario (FDSO). FDSO scenarios
are not analyzed in the SDP as a risk contributor.
See step 2.2 of IMC 0609, Appendix F.Yes See above, same as Fl27A for OMA 5.No increase Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks No increase Screened based on Phase 2 SDP tasks No increase Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks F/594 5 Yes See above, same as Fl27 A for OMA 5.Enclosure
2
11 Ht72A I Hl75A 8,9, 10 Hl77 A 8, 9, 10 Yes See above, same as Hl72A for OMA 8.H/84A 8 Yes See above, same as Hl72A for OMA 8.H/85A 8 Yes See above, same as Hl72A for OMA 8.Hl87 A 8, 9, 10 Yes See above, same as Hl72A for OMA 8.Yes This FZ is in the vapor containment (VC) and was not accessible
to the inspectors
for walkdown, NRC inspectors
walkdown the VC as part of the baseline inspection
program following
plant outages and just prior to plant startup in part to verify the licensee has thoroughly
removed all outage materials
and combustibles.
The licensee performs similar inspections
prior to startup. The inspectors
observed the FZ using a video recording
taken by the licensee during the most recent refuel outage. Additionally, the inspectors
reviewed the spatial separation
between ignition sources and cables of concern as described
in ENO's September
29,2010 response to the NRC's request for additional
information
on August 1 1, 2010 (ML1 02930237).
Yes See above, same as Hl72A for OMA 8.Screened based on Phase 2 SDP tasks Jt19 11 Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks No increase Jt25 12 J/39A 11,12 No Based on circuit reviews, cables of interest within this FZ do not result in a spurious operation
that necessitates
this OMA.No See above, same as J/19 for OMA 11.No See above, same as J/19 for OMA 11.No increase No increase Enclosure
2
12 Jl43A 11, 12, Jt45A 11 Jl46A 11, 12, Jl47A 11 J/50A 11,12 J1270 12 K60A 14,15, 13 13 No See above, same as J/19 for OMA 11.No See above, same as J/19 for OMA 11.No See above, same as J/19 for OMA 1 1.No See above, same as J/19 for OMA 11.No See above, same as J/19 for OMA 11.No See above, same as J/19 for OMA 11.Yes Based on circuit reviews there are no cables within these FZs that also result in a loss of main feedwater with the assumed fire-induced
loss of auxiliary feedwater
from cable damage. Therefore
a fire within this fire zone will not result in a plant transient from spurious operations.
Yes Based on circuit reviews there are no cables within these FZs that also result in a loss of main feedwater with the assumed fire-induced
loss of auxiliary feedwater
from cable damage. Therefore
a fire within this fire zone will not result in a plant transient from spurious operations.
No increase No increase No increase No increase No increase No increase Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks 19 5.l(654 14,15,19 1As identified
in table on pages 1 through 4 of Attachment
1 to ENO response letter to the NRC dated March 1,2012 (M112074A028).
OMAs 20 and 21 were NRC identified
during plant walkdowns
and are described
in the following
list.Description
of Indian Point Unit 2 Denied OMAs Open HCV-142 bypass valve 227 to align charging pump makeup path to the reactor coolant system (RCS).Align charging pump suction source to the refueling
water storage tank (RWST).Transfer instrument
buses 23 and 23A to alternate
power.Fail open valves 2044 (charging
flow to the RCS loop 2 hot leg) and 2Q4B (charging
flow to RCS loop 1 cold leg) to align charging pump makeup path to the RCS.Activate or enable alternate
safe shutdown system (ASSS) pneumatic
instruments (steam generator
level, pressurizer
pressure and pressurizer
level) at the fan house local control panel.Enable ASSS source-range
channel and RCS loop 21 and 22 hot leg and cold leg temperature
channels.Enclosure
2 6.7.8.9.10.
11.13 Trip breakers 52l5A and 52-SAC on Bus 5A and 5216A and 52ffAO at Bus 64 and remove control power fuses.Transfer instrument
buses 23 and 23A to emergency
power source.Align charging pump suction to the RWST.Operate transfer switch EDCS and close supply breaker at substation
12FD3 to transfer the 2l auxiliary
pump (AFW) to the ASSS power source.Open the 21AFW pump recirculation
bypass valve BFD-77.Operate the 21AFW pump flow control valves to control AFW flow to steam generators
21 and 22.Locally operate the 21 charging pump scoop tube positioner.
OMA 20 was NRC identified
during plant walkdowns
and its use in lieu of meeting 10 CFR Part 50, Appendix R, Section lll.G.2 requirements
was not included in the exemption
request submitted
to the NRC on March 6, 2009 (M1090770151).
Locally start the 21 charging pump using the emergency
control station located in the 480V switchgear
room. OMA 21 was NRC identified
during plant walkdowns
and its use in lieu of meeting 10 CFR 50, Appendix R, Section lll.G.2 requirements
was not included in the exemption
request submitted
to the NRC on March 6, 2009 (M1090770151
).Enforcement.
Indian Point Unit 2 Operating
License Condition
2.K specifies, in part, that Entergy Nuclear Operations, lnc., shall implement
and maintain in effect all provisions
of the approved Fire Protection
Program as described
in the Updated Final Safety Analysis Report. The Updated Final Safety Analysis Report, Section 9.6 specifies
that ENO will meet the requirements
of 10 CFR Part 50, Appendix R, Section lll.G.2 which identifies
the means of protecting
post-fire
safe shutdown equipment
from fire damage. Contrary to the above, between June 30, 2006 and April 26, 2012, ENO failed to implement
their fire protection
program by using one of the means described
in Appendix R, Section lll.G.2 to protect circuits required for post-fire
safe shutdown from fire-induced
circuit damage. Specifically, ENO used unapproved
operator manual actions to mitigate post-fire
safe shutdown equipment
malfunctions
without having obtained NRC approval.The specific operator manual actions and fire areas and fire zones that are in violation
of Appendix R, Section lll.G.2 are listed in the Indian Point Unit 2 Denied OMA Summary Table of this inspection
report. This finding is being cited because not all of the criteria specified
in Section 2.3.2.a of the NRC Enforcement
Policy for a non-cited
violation
were satisfied.
Specifically, ENO failed to restore compliance
within a reasonable
amount of time after the violation
was identified
in RIS 2006-10 on June 30, 2006.VfO 0500024712012009-01, Failure to Protect Safe Shutdown Equipment
from the Effects of Fire.12.13.14.15.19.20.21.Enclosure
2
2.14 Failure to Protect Safe Shutdown Equipment
from the Effects of Fire (Unit 3)Introduction.
The inspectors
identified
a finding of very low safety significance (Green), involving
a cited violation
of lndian Point Unit 3 Operating
License Condition
2.H to implement
and maintain all aspects of the approved fire protection
program.Specifically, ENO failed to protect required post-fire
safe shutdown components
and cabling to ensure one of the redundant
trains of equipment
remained free from fire damage as required by 10 CFR Part 50, Appendix R, Section lll.G.2. In lieu of protecting
a redundant
safe shutdown train, ENO utilized unapproved
operator manual actions to mitigate component
malfunctions
or spurious operations
caused by postulated
single fire-induced
circuit faults. ENO submitted
an exemption
request (M1090760993)
on March 6, 2009, in which it sought exemption
from requirements
of Paragraph
lll.G.2, to permit the use of OMAs upon which it had been relying for safe-shutdown
in a number of fire areas. However, several OMAs within the exemption
request were denied because ENO failed to demonstrate
that the OMAs were feasible and reliable, or to appropriately
evaluate fire protection
defense-in-depth.
ENO's performance
deficiency
delayed achieving
full compliance
with fire protection
regulations
and adversely
affected post-fire
safe shutdown.Descriotion.
On June 30, 2006, the NRC issued Regulatory
lssue Summary (RlS)2006-10, Regulatory
Expectations
with Appendix R, Paragraph
lll.G.2, Operator Manual Actions, which clarified
Appendix R and that OMAs are not permitted, unless they have been specifically
approved by the NRC as part of a licensees
request for exemption
from the requirements
of Paragraph
lll.G.2. In addition to information
provided to the licensees
in RIS 2006-10, the NRC issued enforcement
guidance memorandum (EGM)07-004, which granted enforcement
discretion
for licensees
relying on noncompliant
OMAs to bring the facility back into compliance
with the existing regulations.
The enforcement
discretion
provided licensees
until March 6, 2009, to complete corrective
actions, ENO submitted
exemption
requests on March 6, 2009 for OMAs in several non-compliant
fire areas. The NRC considered
ENO's exemption
requests, as supplemented
by information
provided by ENO in response to NRC requests for additional
information
and on February 1,2012, the NRC denied many of the requested
exemptions
based on lack of fire protection
defense-in-depth, such as detection
or automatic
suppression, or lack of time margin available
to complete the OMA. The NRC's denial of several OMAs within the exemption
requests was based on guidance to the NRC staff and available
to the industry.
NUREG 1852, Demonstrating
the Feasibility
and Reliability
of OMAs in Response to Fire, published
October 2007 , page 1-2, states that additional
considerations
to ensure that adequate defense-in-depth
such as fire detection
and suppression
is maintained
are addressed
in Regulatory
Guide 1.189 and should be considered
when applying for an exemption
or license amendment.
RG 1.189, Fire Protection
Program for Nuclear Power Plants, Rev. 1, March 2007, (in effect when NUREG 1852 was issued) Section 5.3.3 similarly
states that allfire-related
operator manual actions must be feasible and reliable.
RG 1 .189 further states that the use of operator manual actions does not obviate the detection
and suppression
capabilities
that are required by the regulations
and in addition, the omission or elimination
of these capabilities
in an area containing
systems, structures, or components (including
circuits)Enclosure
2
15 important
to safety would generally
be considered
an adverse effect on safe shutdown since it would reduce, at a minimum, fire protection
defense-in-depth.
ENO's failure to demonstrate
that several OMAs were feasible and reliable, and to appropriately
evaluate fire protection
defense-in-depth
delayed achieving
full compliance
with fire protection
regulations
and adversely
affected post-fire
ENO entered this issue into its CAP for long term resolution
as CR-lP3-2012-00369.
lnterim compensatory
measures for the fire protection
non-compliances
included roving fire watches in all affected fire areas and were initiated
in June 2011. The inspectors
considered
the interim compensatory
measures reasonable
pending final resolution.
ENO responded
to the NRC in a letter dated March 1,2012, (M112074A028)
with a proposed schedule to resolve all Unit 3 non-compliances
by the fourth quarter of 2012.Analvsis.
The inspectors
identified
a performance
deficiency
in that ENO failed to protect components
credited for post-fire
safe shutdown from fire-induced
damage. The performance
deficiency
was more than minor because it was associated
with the Protection
against External Events (Fire) attribute
of the Mitigating
Systems Cornerstone
and negatively
affected the objective
to ensure the availability, reliability, and capability
of systems that respond to initiating
events to prevent undesirable
consequences
in the event of a fire. Specifically, the use of OMAs during post-fire
shutdown is not as reliable as normal system operation
from the main control room which would be utilized had the requirements
of 10 CFR Part 50, Appendix R, Section lfl.G.2 been met. The inspectors
used IMC 0609, Appendix F, Fire Protection
Significance
Determination
Process, Phase 1 and an SRA conducted
a Phase 3 evaluation, to determine
that this finding was of very low safety significance (Green). This finding did not have a cross cutting aspect because the performance
deficiency
occurred greater than three years ago when the exemption
request was submitted
to the NRC on March 6, 2009, and is not indicative
of current licensee performance.
The inspectors
determined
the issue did not screen with a Phase 1 SDP because the finding category was post-fire
safe shutdown and involved operator manual actions. A Phase 3 SDP was performed
by a Senior Reactor Analyst (SRA) because the Fire Protection
Phase 2 SDP is intended to support the assessment
of known issues only in the context of an individual
fire area and this issue involved multiple fire areas and fire zones. However, the SRA determined
the Phase 2 SDP tools could be used on an area by area basis to inform the Phase 3 SDP and screen firg zones if a sufficient
basis was developed
for each fire zone and justified
an absence of credible fire scenarios, such that mitigating
equipment
or its associated
cables would not be damaged or a plant transient
would not occur. Guidance in each attachment
of IMC 0609, Appendix F was applied in addition to the following
assumptions
specific for lndian Point Nuclear Generating
Unit 3 cable construction
and detail:. All cables are treated as thermoplastic
with damage potential
described
in Tables 47.2 and 47.3;. All cables are jacketed with an asbestos braid and do not act as intervening
combustibles
or contribute
to fire spread; and, o Asbestos cable jacket is not credited as a thermal or radiant heat shield.Enclosure
2
16 The inspectors
walked down each of the individual
fire zone to identify potentialfire
damage scenarios
to circuits that were not protected
to the requirements
of 10 CFR Part 50, Appendix R, Paragraph
lll.G.2.One of the unapproved
OMAs which was associated
with several fire zones was local manual operation
of the service water pump strainer backwash.
This OMA was determined
to be beyond the scope of an OMA and was documented
in a Green non-cited violation
in 201 1 (lnspection
Report 05000286/201
1008, ML1 1 1920339), The very low risk for this OMA was related to the very low likelihood
of ever needing the strainer backwash to operate during a post-fire
With the exception
of FZPAB 2{3}/6, all remaining
fire zones and associated
OMAs screened because there were no fixed or assumed transient
combustible
ignition sources that could credibly damage the cable of concern within the fire zones.For FZ PAB-2{3/6, the 32 charging pump cubicle, the SRA assumed a lube oil fire while the 32 charging pump was in operation
damages cables to the volume control tank (VCT) motor operated outlet valve (112C). The SRA compared differences
between Unit 2 and Unit 3 for the 22 and 32 charging pump cubicle fire scenarios.
The only noted differences
between plant configurations
or operating
procedures
was the 1128 valve design and the fire zone configurations.
The 1 128 valve at Unit 2 was a normally closed air operated valve, and at Unit 3 the 1 128 valve was a normally closed motor operated valve. At Unit 3, the 31 and 32 charging pumps were in the same fire zone (PAB-2{3yO), but an exemption
was previously
granted that found the fire barriers between the charging pump cubicles acceptable
and the 31 charging pump was credited in the event of a fire in the 32 charging pump cubicle. Both differences
between the Unit22 and 32 charging pump fire scenario would not change the fire damage or risk analysis assumptions.
Because there was no applicable
difference
between the Unit 2 and Unit 3 charging pump fire scenario, the results of the Unit 2 detailed Phase 3 SDP analysis can be used to determine
that the increased
risk from this fire scenario is negligible.
The table below summarizes
the results for each OMA with its respective
fire zone: Indian Point Unit 3 Denied OMA Summary Table Area/Zone Comments Risk Increase Results ETN- 6,8 4{11/7A Yes There were no fixed or assumed transient combustible
ignition sources that could credibly damage the cable of concern in this area.Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks ETN- 5,6,8,9,10, Yes There were no fixed or assumed transient 4{1ll 11,12 combustible
ignition sources that could credibly 60A damage the cable of concern in this area.Enclosure
2
17 ETN- 14,15,16, 4{3It 17 734 PAB- 18 2{3}l 6 Previously
evaluated as very low Screened based on Phase 2 SDP tasks Negligible
based on detailed Phase 3 SDP analysis Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks 13 Yes This OMA was previously
identified
as a violation during the last triennialfire
protection
inspection
and was documented
in that report as a very low safety significance (Green) NCV.Yes There were no fixed or assumed transient combustible
ignition sources that could credibly damage the cable of concern in this area.Yes This zone was described
in detail in the analysis section above this table.PAB- 22 2{5ll 174 PAB- 19,20 2{5}l 19A PAB- 22 2{5}l 204 PAB- 22 2{5ll 274 PAB- 22 2{5Il 304 PAB- 21 2{5}l 59A Yes There were no fixed or assumed transient combustible
ignition sources that could credibly damage the cable of concern in this area.Yes There were no fixed or assumed transient combustible
ignition sources that could credibly damage the cable of concern in this area.Yes There were no fixed or assumed transient combustible
ignition sources that could credibly damage the cable of concern in this area.Yes There were no fixed or assumed transient combustible
ignition sources that could credibly damage the cable of concern in this area.Yes There were no fixed or assumed transient combustible
ignition sources that could credibly damage the cable of concern in this area.Yes There were no fixed or assumed transient combustible
ignition sources that could credibly damage the cable of concern in this area.Enclosure
2
18 TBL- 25 5137A TBL- 25 5/38A TBL. 25 5t43A TBL- 25 5t44A TBL- 23,24 5t52A TBL- 24 5t54A YARD 26-71 222 Yes This OMA was previously
identified
as a violation during the last triennialfire
protection
inspection
and was documented
in that report as a very low safety significance (Green) NCV.Yes This OMA was previously
identified
as a violation during the last triennialfire
protection
inspection
and was documented
in that report as a very low safety significance (Green) NCV.Yes This OMA was previously
identified
as a violation during the last triennialfire
protection
inspection
and was documented
in that report as a very low safety significance (Green) NCV.Yes This OMA was previously
identified
as a violation during the last triennial
fire protection
inspection
and was documented
in that report as a very low safety significance (Green) NCV.Yes There were no fixed or assumed transient combustible
ignition sources that could credibly damage the cable of concern in this area.Yes There were no fixed or assumed transient combustible
ignition sources that could credibly damage the cable of concern in this area.Yes There were no fixed or assumed transient combustible
ignition sources that could credibly damage the cable of concern in this area.Yes This OMA was previously
identified
as a violation during the last triennialfire
protection
inspection
and was documented
in that report as a very low safety significance (Green) NCV.Previously
evaluated as very low Previously
evaluated as very low Previously
evaluated as very low Previously
evaluated as very low Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks Screened based on Phase 2 SDP tasks Previously
evaluated as very low 27 2As identified
in table on pages 1 through 5 of Attachment
2 to ENO response letter to the NRC dated March 1, 2Q12 (ML1207 4A028).Description
of Indian Point Unit 3 Denied OMAs 5, Operate HCV-1118 manually to control 32 AFW pump.6. Align Appendix R Diesel Generator (ARDG) to 480 V Buses 2A, 3,A, 5A, and 312.Enclosure
2
19 8. Locally operate FCV-405B, FCV-405D, or FCV-406B to control AFW flow to Steam Generators (SGs).9. Locally open valve 227 to establish
charging makeup flowpath to Reactor Coolant System (RCS).10. Locally close Level Control Valve (LCV)-1 12C and open valve 288 to align charging pump suction to the Refueling
Water Storage Tank (RWST).11. Locally operate Pressure Control Valve (PCV)-1 139 to ensure steam supply to 32 AFW pump.12. Locally operate PCV-13104
and PCV-13108
to ensure steam supply to 32 AFW pump.13. Locally manually perform Service Water (SW) pump strainer backwash as required.14. Operate HCV-1118 manually to control 32 AFW pump.15. Locally operate PCV-1 139 to ensure steam supply to 32 AFW pump.16. Locally operate 32 PCV-1310A, PCV-13108
to ensure steam supply to 32 AFW pump.17. Locally operate FCV-405C and FCV-405D to control AFW flow to SG.18. Locally close valve LCV-1 12C and open valve 228 to align charging pump suction path to RWST.19. Locally close supply breaker 'for 32 Charging Pump.2Q. Locally control 32 charging pump using scoop tube positioner.
21. Open bypass valve 227 to establish
charging flowpath to RCS around potentially
failed closed HCV-142.22. Locally close LCV-112C and open bypass valve 288 to establish
flowpath from RWST to charging pump suction.23. Locally operate [bypass valve for] FCV-1121 AFW pump recirculation
valve during pump startup.24. Locally operate FCV- 406A and FCV-406B to control AFW flow to SGs.25. Locally/manually
backwash SW pump strainer as required if power to strainer associated
with selected SW pump is lost.26. Locally start ARDG to supply Motor Control Center (MCC) 312A in support of the use of SW pump 38.Enclosure
2
27.20 Locally/manually
backwash SW Pump strainer as required if power to strainer associated
with selected SW pump is lost.Enforcement.
Indian Point Unit 3 Operating
License Condition
2.H specifies, in part, that Entergy Nuclear Operations, lnc., shall implement
and maintain in effect all provisions
of the approved Fire Protection
Program as described
in the Final Safety Analysis Report.The Final Safety Analysis Report, Section 9.6.2, specifies
that ENO will meet the requirements
of 10 CFR Part 50, Appendix R, Section lll.G.2, which identifies
the means of protecting
post-fire
safe shutdown equipment
from fire damage. Contrary to the above, between June 30, 2006 and April 26, 2012, ENO failed to implement
their fire protection
program by using one of the the means described
in Appendix R, Section lll.G.2, to protect circuits required for post-fire
safe shutdown from fire-induced
circuit damage. Specifically, ENO used unapproved
operator manual actions to mitigate post-fire
safe shutdown equipment
malfunctions
without having obtained NRC approval.The specific operator manual actions and fire areas and fire zones that are in violation
of Appendix R, Section lll.G.2, are listed in the Indian Point Unit 3 Denied OMA Summary Table of this inspection
report. This finding is being cited because not all of the criteria specified
in Section 2.3.2.a of the NRC Enforcement
Policy for a non-cited
violation
were satisfied.
Specifically, ENO failed to restore compliance
within a reasonable
amount of time after the violation
was identified
in RIS 2006-10 on June 30, 2006.VIO 0500028612012008-01, Failure to Protect Safe Shutdown Equipment
from the Effects of Fire.Violation
of Combustible
Controls Proqram lntroduction.
The inspectors
identified
a Green, Non-Cited
Violation (NCV) of the Indian Point Nuclear Generating
Unit No. 2 Amended Facility Operating
License, Condition
2.K, in that ENO failed to implement
and maintain in effect all provisions
of the NRC-approved FPP as described
in the Updated Final Safety Analysis Report (UFSAR).Specifically, ENO failed to minimize transient
combustible
materials
within the primary auxiliary
building (PAB) and stored a compressed
gas cylinder containing
hydrogen gas under cable trays.Description.
While walking down electrical
cables that were associated
with denied OMA exemptions, the inspectors
identified
a gas cylinder underneath
cable trays in fire zone (FZ) Fl7 A of the PAB. The gas cylinder was not in use, a valve protection
cap was installed, and the gas cylinder was chained to a corridor wall to prevent accidental
movement or tipping. The gas cylinder's
contents were unknown and without label other than a sticker indicating
the contents were flammable.
ENO removed the gas cylinder from the PAB and evaluated
its contents.
The gas cylinder was a mixture of 50 percent hydrogen and 50 percent nitrogen gasses and was previously
in service as a calibration
gas for the waste gas analyzer in FZ F/8A of the PAB. lt contained
about 150 psig of gas. FZ FlSA is an authorized
storage location for an in service hydrogen calibration
gas cylinder, and FZFITA is not an authorized
storage location for any hydrogen gas cylinders.
Enclosure
2
21 The storage of a hydrogen compressed
gas cylinder in FZFITA of the PAB was not in accordance
with ENO procedure, Control of Combustibles, EN-DC-161, Rev. 6, and a flammable
compressed
gas was not practically
minimized.
EN-DC-161, among other requirements, requires plant workers to: 1) limit transient
combustibles
to those materials
and quantities
necessary
to support work activities, 2) not place transient combustibles
directly under cable trays, and 3)determine
the need for a formal Transient
Combustible
Evaluation (TCE).ENO promptly entered this issue into its CAP as CR-lP2-2012-03036, and removed the hydrogen cylinder from the PAB. ENO initiated
a corrective
action to evaluate the identified
condition
and ensure actions to prevent its recurrence.
Analvsis.
ENO's failure to remove the compressed
hydrogen gas cylinder from the PAB after its intended use as a calibration
gas for the waste gas analyzer was a performance
deficiency.
This finding was more than minor because it was associated
with the External Factors attribute (fire) of the Mitigating
Systems Cornerstone
and adversely affected the cornerstone
objective
to ensure the availability, reliability, and capability
of systems that respond to initiating
events to prevent undesirable
consequences (i.e., core damage). Specifically, the hydrogen gas cylinder was stored below cable trays in an area that includes safe shutdown circuits and the associated
cables were at increased risk to fire damage. The inspectors
used IMC 0609, Appendix F, Fire Protection
Significance
Determination
Process, Phase 1 and a Senior Reactor Analyst conducted
a Phase 3 evaluation, to determine
that this finding was of very low safety significance (Green). The inspectors
determined
that this finding had a cross-cutting
aspect in the area of Human Performance
associated
with the work practice attribute
because ENO personnel
did not follow procedure, Control of Combustibles, EN-DC-161, Rev. 6, as written and did not remove the hydrogen gas cylinder from the PAB after it was disconnected
from the waste gas analyzer contrary to Control of Combustibles, EN-DC-161, Rev.6. (H.4(b) per IMC 0310).The inspectors
used Attachment
2 of IMC 0609, Appendix F, Fire Protection
Significance
Determination
Process (SDP), and assigned a high degradation
rating for this combustible
controls program finding. Accordingly, this finding did not screen to Green in Phase 1 of IMC 0609, Appendix F, and a Phase 3 analysis was performed
by a Senior Reactor Analyst (SRA) using similar assumptions
and methodologies
as the denied OMA findings.Conduct of the phase 3 SDP included identifying
the damage that could result based on detailed plant walkdowns, review of ENO provided circuit information, fire modeling evaluation
of potential
damage to plant equipment, and use of probabilistic
fire analysis methods documented
in NRC Inspection
Manual Chapter 0609, Appendix F, "Fire Protection
SDP" and NUREG/CR-6850, "EPRI/NRC-RES
Fire PRA Methodology
for Nuclear Power Facilities." The SRA analyzed the risk of a single hydrogen gas cylinder fire located directly below the cables in FZFITA that may cause the charging pumps to lose suction by closing the volume control tank (VCT) outlet valve (112C). Because the hydrogen compressed
gas cylinder was stored along a PAB corridor in FZFITA without controls or regards to its combustibility
or flammability, the SRA assumed for the purposes of analyzing
risk from fire, that the hydrogen gas cylinder was located directly Enclosure
2
22 beneath cables that if damaged may spuriously
close 112C. Closure of 112C causes the charging pumps to lose suction and OMAs are required to restore the VCT suction or align the refuel water storage tank (RWST) as an alternate
source by opening air operated valve 1128. The normally open 112C is physically
located in the VCT room, not in FZFlTA, and the normally closed 1128, is located in the 22 charging pump cell FZFl6. Valve 1128 is designed to open automatically
in the event of a low VCT level, which through 1128 valve position monitoring
circuitry
would cause the normal VCT suction valve 1 12C to close. The 1 128 valve position monitoring
circuit cable runs from FZFl6, where 1128 is located, through FZFITA. The fire is assumed to result in 1128 failing to open due to direct power supply cabling damage and 1 12C failing closed due to damage to the 1128 position monitoring
circuit wiring. The denied OMAs tor FZFITA were used in this analysis.
These OMAs included the manual opening of the 1 128 bypass valve (288), the verification
or closure of 112C, and starting the 21 charging pump, after the RWST suction is aligned, using the emergency
control station in the 480V switchgear
room.The SRA conducted
a detailed probabilistic
analysis tor FZ F/7A, using the lP2 SPAR model version 8.20 to estimate the conditional
core damage probability
if the fire were to occur. This analysis represented
a fire model estimate that allowed normal plant equipment
to remain functional
if it would not be damaged based on fire modeling of the actual plant configuration.
The analysis determined
a negligible
increase in core damage frequency (less than 1 in one billion years), given an estimated
6.5E-4 per year fire frequency (consistent
with Attachment
4 of the Fire Protection
SDP for a hydrogen storage tank) and the conditional
core damage probability
calculated (if the performance
deficiency
had not occurred there was no credible ignition source). An independent
Region I SRA reviewed and found acceptable
the SPAR model changes made to conduct the analysis, which were based on following
assumptions
that a fire in FZFITA would: o Cause operators
to manually initiate a reactor trip from the control room, which was reflected
as a transient
initiation
event.. Failthe running charging pump.. Fail 1128 closed.o Fail 112C closed with a probability
of an intra-cable
hot short of 0.30, based on NUREG/CR-6850
or fail it open with a 0.70 probability.
lf MOV-112C fails open it must be manually closed as part of restoring
the RWST suction flowpath to the 21 charging pump.. Not generate a hot gas layer in the PAB corridor and not damage any cabling or equipment
outside of FZ F/7A based on fire modeling.r Result in control room operators
in accordance
with procedures:
o Removing control power fuses for both PORVs in the control room to prevent spurious opening which was assumed always successful.
For ATWS sequences, all PORVs and RCS safety valves would be open and operators
would not pull the fuses to close the PORVS, but would continue to recover charging to establish
emergency
boration.o Promptly disabling
the 21 charging pump from automatic
operation.
This action is required by procedure
to preclude damage to the 21 charging pump should it operate without a water source aligned to its suction as Enclosure
2
23 the result of spurious valve operations.
A failure probability
of 1.1E-2 was assumed based on SPAR-H1, assuming diagnosis
and allfactors
in their nominalstate.
o Result in operators
implementing
the denied OMAs in accordance
with procedures
and specifically
aligning the RWST to the charging pumps suction after the fire is extinguished
and includes: o Manually opening valve 288 with a failure probability
of 2.3E-1 assumed based on SPAR-H with all factors in their nominal state except for high stress and conservatively
assuming barely sufficient
time.o Verify or close 112C with a failure probability
of 2.3E-1 assumed based on SPAR-H with all factors in their nominal state except for high stress and conservatively
assuming barely sufficient
time.. Result in operators
implementing
the missed OMA to start the 21 charging pump from the emergency
control station in the 480 V switchgear
room after the RWST suction was aligned. This action was assigned a failure probability
of 2.9E-1 based on SPAR-H assuming diagnosis
and allfactors
in their nominal state except for incomplete
and poor procedures.
Incomplete
and poor procedures
was chosen because operators
knew of the emergency
control station in the switchgear
room, and because it was incorporated
in the post-fire
safe shutdown following
control room abandonment, however, use of the emergency
control station was not in the procedure
used for a PAB fire.The dominating
core damage sequence involving
the hydrogen calibration
gas cylinder fire scenario was an ATWS caused by mechanical
binding of all control rods and a failure of the operator to manually open 288 to establish
emergency
boration with the 21 charging pump. The negligible
increase in core damage frequency (less than 1 in one billion years) is due to the 6.5E-4 per year initiating
event frequency
and the extremely low chances of an ATWS situation
where emergency
boration would be necessary
or a common cause failure of the SW system would lead to a reactor coolant pump seal failure.Enforcement.
Entergy Nuclear Operations, Inc.(ENO), Operating
License, Condition
2.K, requires, in part, that ENO shall implement
and maintain in effect all provisions
of the NRC-approved
FPP as described
in the UFSAR. UFSAR Section 9.6,2 references
the FPP as described
in three ENO documents, one of these documents
is the lndian Point Energy Center (IPEC) Fire Protection
Program Plan, SEP-FPP-IP-001, Rev. 0. Control of Combustibles, EN-DC-161, Rev. 6, is referenced
in the IPEC FPP Plan and, in part, requires plant workers to: 1) limit transient
combustibles
to those materials
and quantities
necessary
to support work activities (Section 5.2[1]), 2) not place transient
combustibles
directly under cable trays, (Section 5.2141), (Section 5.5[1](d)), and 3) determine
the need for a formal Transient
Combustible
Evaluation (TCE) (Section 5.6t21). Contrary to the above, a compressed
gas cylinder containing
hydrogen gas was left in FZ 7 A of the PAB on an unknown date of the PAB.The unauthorized
storage of a hydrogen gas bottles was identified
by the NRC on April 25, 2012. Because this finding was of very low safety significance (Green) and has been entered into ENO's corrective
action program (CR-lP2-2012-03036), this violation is being treated as a NCV, consistent
with Section 2.3.2 of the NRC Enforcement
Policy.(NCV 0500024712012009-001, Violation
of Transient
Gombustible
Gontrol Program)Enclosure
2
24 40A6 Meetinos.
includinq
Exit Exit Meetinq Summarv The inspectors
presented
their preliminary
inspection
results to Mr. Lawrence Coyle, General Manager, Plant Operations, and other members of the site staff at an exit meeting on April 26,2012. Following
in-office
reviews, an additional
meeting was conducted
by telephone
with Mr. Patric Conroy, Director, Nuclear Safety Assurance, on June 8, 2012, and an exit meeting was conducted
by telephone
with Mr. Patric Conroy, and other members of the site staff on July 20,2012. No proprietary
information
was included in this inspection
report.ATTACHMENT:
SUPPLEMENTAL
INFORMATION
Enclosure
2
A-1 ATTACHMENT
SUPPLEMENTAL
INFORMATION
KEY POINTS OF CONTACT Licensee Personnel P. Conroy, Director, Nuclear Safety Assurance L. Coyle, General Manager, Plant Operations
J. Cottam, Fire Protection
Engineer G. Dahl, Licensing
Specialist
K. Elliot, Safe Shutdown Engineer M. Tesoriero, Manager, Programs and Components
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED Opened 05000247/2012009-01
VIO Failure to Protect Safe Shutdown Equipment
from the Effects of Fire (Section 4042.1)05000286/2012008-01
VIO Failure to Protect Safe Shutdown Equipment
from the Effects of Fire (Section 4042.2)Opened and Closed 0500024712012009-01
NCV Violation
of Transient
Combustible
Control Program (Section 4OA2.3)LIST OF DOCUMENTS
REVIEWED Fire Protection
Licensino
Documents Unit 3 Technical
Requirements
Manual 3.7.8, Appendix R Safe Shutdown Equipment, Rev. 9 Letter from J. Bayne to H. Denton, Appendix R Exemption
Request Information, Dated 11122182 Desiqn Basis DocumentslP-RPT-OS, ,P2 10 CFR 50, Appendix R Safe-Shutdown
Separation
Analysis, Rev. 1 lP2-RPT-03-00015,lP2
Fire Hazards Analysis, Rev. 4 lP3-ANAL-FP-02143, Fire Hazards Analysis Report, Rev. 5 lP3-ANAL-FP-01503, Safe Shutdown Analysis Report, Rev. 2 SEP-FPP-lP-001, IPEC Fire Protection
Program Plan, Rev.0 Attachment
A-2 Calcu lations/Enq
ineerinq Evaluation
Reports EO-6068, Fire and Heat Resistance
Tests on 600V Power and Control Cable and Switchboard
Wires, Dated 8120171lP-RPT-12-00008, lP3 OMAs 2 through 8 Evaluation, Draft Evaluation
of lP3 OMAs 18 through 22, Draft Evaluation
of lP3 OMA 26, Draft PGI-00433, Combustible
Loading Calculation, Rev. 6 Procedures
SAO-703, Fire Protection
lmpairment
Criteria and Surveillance, Rev, 28 SEP-FPP-lP-002,IPEC
Fire Watch Program, Rev. 0 EN-DC-161, Control of Combustibles, Rev. 6 EN-DC-127, Control of Hot Work and lgnition Sources, Rev. 11 EN-IS-109, Compressed
Gas Cylinder Handling and Storage, Rev. 7 Operations
Procedures
2-AOP-SSD-1, Control Room Inaccessibility
Safe Shutdown Control, Rev. 18 2-ONOP-FP-001, Plant Fires, Revs. 7 & I 2-SOP-ESP-0O1, Local Equipment
Operation
and Contingency
Actions, Rev. 6 3-ONOP-FP-1, Plant Fires, Rev. 28 3-SOP-EL-Q12, Operation
of the Alternative
Safe Shutdown Equipment, Rev. 18 3-SOP-ESP-001, Local Equipment
Operation
and Contingency
Actions, Rev. 21 Condition
Reports cR-lP2-2011-02417
CR-1P2-2012-01487
CR-lP3-2011-02325
cR-rP2-2011-03139
CR-lP3-2011-02853
cR-tP2-201
1-03695 CR-tP2-2012-03024
CR-lP3-2011-02951
cR-tP2-201
1-03889 CR-lP2-2012-03036
CR-IP3-201
1-02966 cR-lP2-201
1-04608 CR-lP2-2012-03410
CR-lP3-2011-03497
cR-rP2-2011-0631
CR-lP3-2011-03563
cR-lP2-2012-00643
CR-lP3-2011-00044
CR-lP3-2012-00369
Attachment
ADAMS AFW ASSS ATWS CAP ccw CFR DRS EGM ENO FDSO FSAR FZ GPM IA IMC IP IPEC KW MOV NCV NRC OMA PAB PAR PORV PSIG RCP RCS RIS RWST SDP SQFT SRA TCE VC UFSAR V VCT A_3 LIST OF ACRONYMS Agency,vide
Documents
Access and Management
System Auxiliary
Feedwater Alternate
Safe Shutdown System Anticipated
Without Scram Corrective
Action Program Closed Cooling Water Code of Federal Regulations
Division of Reactor Safety Enforcement
Guidance Memorandum
Entergy Nuclear Operations, Inc.Fire Damage State Zero Final Safety Analysis Report Fire Zone Gallon Per Minute lnstrument
Air Inspection
Manual Chapter Inspection
Procedure Indian Point Energy Center Kilowatt Motor Operated Valve Non-Cited
Violations
Nuclear Regulatory
commission
Operator ManualAction
Primary Auxiliary
Building Publicly Available
Records Power Operated Relief Valve Pounds Per Square Inch Gauge Reactor Coolant Pump Reactor Coolant System Regulatory
lssue Summary Refuel Water Storage Tank Significance
Determination
Process Square Feet Senior Reactor Analyst Transient
Combustible
Evaluation
Vapor Containment
Updated Final Safety Analysis Report Volt Volume ControlTank
Attachment