Waterford Unit 3 - Request for Additional Information, Request to Revise Updated Final Safety Analysis Report to Clarify Pressurizer Heaters Function for Natural Circulation at the Onsite of a Loss of Offsite Power (TAC No. MF3058)
ML14171A263
Person / Time
Site: Waterford Entergy icon.png
Issue date: 08/22/2014
From: Wang A B
Plant Licensing Branch IV
To:
Entergy Operations
Wang A B
References
TAC MF3058
Download: ML14171A263 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Vice President, Operations Entergy Operations, Inc. Waterford Steam Electric Station, Unit 3 17265 River Road Killona, LA 70057-3093 August 22, 2014

SUBJECT:

WATERFORD STEAM ELECTRIC STATION, UNIT 3-REQUEST FOR ADDITIONAL INFORMATION REGARDING A CHANGE TO THE UPDATED FINAL SAFETY ANALYSIS REPORT CLARIFYING PRESSURIZER HEATERS FUNCTION FOR NATURAL CIRCULATION (TAC NO. MF3058)

Dear Sir or Madam:

By letter dated November 11, 2013, Entergy Operations, Inc., proposed changes to the Waterford Steam Electric Station, Unit 3 Updated Final Safety Analysis Report, which would clarify how the Pressurizer Heaters function is met for natural circulation at the onset of a loss of offsite power concurrent with the specific single point vulnerability. After reviewing your request, the U.S. Nuclear Regulatory Commission staff has determined that additional information is required to complete the review. Please provide additional information requested in the enclosure within 45 days of receipt of this letter. If you have any questions, please contact me at 301-415-1445 or via e-mail at alan.wang@nrc.gov. Docket No. 50-382

Enclosure:

Request for Additional Information cc w/encl: Distribution via Listserv Sincerely, Alan B. Wang, Project Manager Plant Licensing IV-2 and Decommissioning Transition Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST TO CLARIFY THE UPDATED FINAL SAFETY ANALYSIS REPORT PRESSURIZER HEATERS FUNCTION ENTERGY OPERATIONS, INC. WATERFORD STEAM ELECTRIC STATION, UNIT 3 DOCKET NO. 50-382 By letter dated November 11, 2013 (Agencywide Documents Access and Management System Accession No. ML 13316C052), Entergy Operations, Inc. (the licensee), submitted a license amendment request (LAR) in which it requested a revision to the Updated Final Safety Analysis Report (l)FSAR) for the Waterford Steam Electric Station, Unit 3. The proposed change would modify UFSAR Sections 1.9.26 and 5.4.1 0.2, to clarify how the Pressurizer Heaters function is met for natural circulation at the onset of a loss of offsite power concurrent with the specific single point vulnerability. The following questions were developed as a result of the U.S. Nuclear Regulatory Commission (NRC) staff's review of the licensee's LAR. 1. Please identify and provide an explanation for which criteria of paragraph 50.59(c)(2) of Title 10 of the Code of Federal Regulations (1 0 CFR) necessitated a license amendment under 10 CFR 50.90. 2. *Please provide electrical schematic drawings that show how the common control circuit breaker, CVCEBKR014AB-13, affects the control power close circuitry of the Supply Circuit Breakers to Switchgears 32A and 32B. 3. In Insert 1 of Attachment 2 of the LAR, the licensee proposed to add the following clarification to the UFSAR 1.9.26: Part of the closing circuitry to these safety-grade circuit breakers share a specific common circuit breaker, CVCEBKR014AB-13. If CVCEBKR014AB-13 is Open at the onset ofa loss of offsite power, local manual operator action in the respective train switchgear room is necessary to reenergize the Pressurizer Heaters of that train. Please explain which alarm in the control room will help a control room operator identify whether the common circuit breaker, CVCEBKR014AB-13 is open. Provide a markup copy of the operating procedure which will then identify the need for the local manual operator action in the respective train switchgear room to reenergize the necessary Pressurizer Heaters. Enclosure

ML 14171A263 OFFICE NRR!DORULPL4-2/PM NRR!DORULPL4-2/PM NAME MOrenak A Wang DATE 06/23/14 06/29/14 Sincerely, IRA/ Alan B. Wang, Project Manager Plant Licensing IV-2 and Decommissioning Transition Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsNrrDorllpl4-2 Resource RidsNrrPMWaterford Resource RidsNrrLAJBurkhardt Resource RidsRgn4MaiiCenter Resource NRRIDORULPL4-2/LA NRR/DORLILPL4-2/BC JBurkhardt DBroaddus 6/23/14 08/20/14 NRRIDORULPL4-2/PM A Wang 08/22/14