|
---|
Category:Inspection Report
MONTHYEARIR 05000336/20244022024-10-0808 October 2024 Security Baseline Inspection Report 05000336/2024402 and 05000423/2024402 (Cover Letter Only) IR 05000336/20240052024-08-29029 August 2024 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Reports 05000336/2024005 and 05000423/2024005 IR 05000336/20240022024-08-13013 August 2024 Integrated Inspection Report 05000336/2024002 and 05000423/2024002 IR 05000336/20244412024-08-0606 August 2024 Supplemental Inspection Report 05000336/2024441 and 05000423/2024441 and Follow-Up Assessment Letter (Cover Letter Only) IR 05000336/20244032024-07-22022 July 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000336/2024403 and 05000423/2024403 IR 05000336/20245012024-07-0101 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000336/2024501 and 05000423/2024501 IR 05000336/20240102024-06-26026 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000336/2024010 and 05000423/2024010 IR 05000336/20244402024-06-24024 June 2024 Final Significance Determination for Security-Related Greater than Green Finding(S) with Assessment Follow-up; IR 05000336/2024440 and 05000423/2024440 and Notice of Violation(S), NRC Investigation Rpt 1-2024-001 (Cvr Ltr Only) ML24142A0952024-05-20020 May 2024 End of Cycle 22 Steam Generator Tube Inspection Report IR 05000336/20240012024-05-14014 May 2024 Integrated Inspection Report 05000336/2024001 and 05000423/2024001 and Apparent Violation IR 05000336/20244012024-04-30030 April 2024 Security Baseline Inspection Report 05000336/2024401 and 05000423/2024401 (Cover Letter Only) ML24116A0452024-04-25025 April 2024 Special Inspection Follow-Up Report 05000336/2024440 and 05000423/2024440 and Preliminary Finding(S) of Greater than Very Low Significance and NRC Investigation Report No. 1-2024-001 (Cover Letter Only) IR 05000336/20240112024-04-0101 April 2024 Comprehensive Engineering Team Inspection - Inspection Report 05000336/2024011 and 05000423/2024011 IR 05000336/20230062024-02-28028 February 2024 Annual Assessment Letter for Millstone Power Station, Units 2 and 3, (Reports 05000336/2023006 and 05000423/2023006) IR 05000336/20230042024-02-14014 February 2024 Integrated Inspection Report 05000336/2023004 and 05000423/2023004 IR 05000336/20234022024-01-30030 January 2024 Security Baseline Inspection Report 05000336/2023402 and 05000423/2023402 (Cover Letter Only) IR 05000336/20234402024-01-11011 January 2024 Special Inspection Report 05000336/2023440 and 05000423/2023440 (Cover Letter Only) IR 05000336/20230032023-11-0606 November 2023 Integrated Inspection Report 05000336/2023003 and 05000423/2023003 IR 05000336/20234202023-10-0404 October 2023 Security Inspection Report 05000336/2023420 and 05000423/2023420 IR 05000245/20230012023-09-19019 September 2023 Safstor Inspection Report 05000245/2023001 IR 05000336/20230102023-09-0808 September 2023 Commercial Grade Dedication Report 05000336/2023010 and 05000423/2023010 IR 05000336/20230052023-08-31031 August 2023 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Report 05000336/2023005 and 05000423/2023005) IR 05000336/20230022023-08-0909 August 2023 Integrated Inspection Report 05000336/2023002 and 05000423/2023002 IR 05000336/20234012023-07-17017 July 2023 Material Control and Accounting Program Inspection Report 05000336/2023401 and 05000423/2023401 - (Cover Letter Only) IR 07200047/20234012023-06-0808 June 2023 NRC Independent Spent Fuel Storage Installation Security Inspection Report No. 07200047/2023401 IR 05000336/20230012023-05-0808 May 2023 Integrated Inspection Report 05000336/2023001 and 05000423/2023001 IR 05000336/20234032023-05-0202 May 2023 Public - Millstone Power Station, Units 2 and 3 Final Significance Determination of Green Finding; Inspection Report 05000336/2023403 and 05000423/2023403 IR 05000336/20233022023-03-0707 March 2023 Operator Licensing Retake Examination Report 05000336/2023302 IR 05000336/20220062023-03-0101 March 2023 Annual Assessment Letter for Millstone Power Station, Units 2 and 3 (Reports 05000336/2022006 and 05000423/2022006) IR 05000336/20220042023-02-13013 February 2023 Integrated Inspection Report 05000336/2022004 and 05000423/2022004 IR 05000336/20224012023-01-26026 January 2023 Security Baseline Inspection Report 05000336/2022401 and 05000423/2022401 and Preliminary Finding(S) of Greater than Very Low Significance and Apparent Violation(S) (Cover Letter Only) IR 05000245/20220012023-01-0909 January 2023 Safstor Inspection Report 05000245/2022001 IR 05000336/20224032023-01-0505 January 2023 Cyber Security Inspection Report 05000336/2022403 and 05000423/2022403 IR 05000336/20225012022-12-14014 December 2022 Reissued Emergency Preparedness Biennial Exercise Inspection Report 05000336/2022501 and 05000423/2022501 IR 05000336/20223012022-11-22022 November 2022 Initial Operator Licensing Examination Report 05000336/2022301 ML22325A1042022-11-21021 November 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000336/2022501 and 05000423/2022501 IR 05000336/20220032022-11-14014 November 2022 Integrated Inspection Report 05000336/2022003 and 05000423/2022003 IR 05000336/20220102022-11-0101 November 2022 Biennial Problem Identification and Resolution Inspection Report 05000336/2022010 and 05000423/2022010 IR 05000336/20220112022-09-0808 September 2022 Triennial Fire Protection Inspection Report 05000336/2022011 and 05000423/2022011 IR 05000336/20220052022-08-31031 August 2022 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Report 05000336/2022005 and 05000423/2022005) IR 05000336/20220022022-08-11011 August 2022 Integrated Inspection Report 05000336/2022002 and 05000423/2022002 IR 05000336/20224022022-05-23023 May 2022 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000336/2022402 and 05000423/2022402 IR 05000336/20220012022-05-10010 May 2022 Integrated Inspection Report 05000336/2022001 and 05000423/2022001 IR 05000423/20223022022-03-0707 March 2022 Operator Licensing Retake Examination Report 05000423/2022302 IR 05000336/20210062022-03-0202 March 2022 Annual Assessment Letter for Millstone Power Station, Units 2 and 3 (Reports 05000336/2021006 and 05000423/2021006) IR 05000336/20210042022-02-10010 February 2022 Integrated Inspection Report 05000336/2021004 and 05000423/2021004 IR 05000336/20210112022-01-20020 January 2022 Post-Approval Site Inspection for License Renewal - Phase 4 Inspection Report 05000336/2021011 IR 05000336/20210032021-11-12012 November 2021 Integrated Inspection Report 05000336/2021003 and 05000423/2021003 IR 05000423/20213012021-11-10010 November 2021 Initial Operator Licensing Examination Report 05000423/2021301 IR 05000336/20210052021-09-0101 September 2021 Updated Inspection Plan for the Millstone Power Station, Units 2 and 3 (Report 05000336/2021005 and 05000423/2021005) 2024-08-06
[Table view] Category:Letter
MONTHYEAR05000423/LER-2024-001, Loss of Safety Function and Condition Prohibited by Technical Specifications for Loss of Secondary Containment Boundary2024-10-14014 October 2024 Loss of Safety Function and Condition Prohibited by Technical Specifications for Loss of Secondary Containment Boundary IR 05000336/20244022024-10-0808 October 2024 Security Baseline Inspection Report 05000336/2024402 and 05000423/2024402 (Cover Letter Only) ML24281A1102024-10-0707 October 2024 Requalification Program Inspection 05000423/LER-2023-006-02, Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications2024-09-26026 September 2024 Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24260A2192024-09-16016 September 2024 Decommissioning Trust Fund Disbursement - Revision to Previous Thirty-Day Written Notification ML24260A1952024-09-16016 September 2024 Response to Request for Additional Information Regarding Proposed Amendment to Support Implementation of Framatome Gaia Fuel ML24248A2272024-09-0404 September 2024 Operator Licensing Examination Approval ML24240A1532024-09-0303 September 2024 Summary of Regulatory Audit Supporting the Review of License Amendment Request for Implementation of Framatome Gaia Fuel IR 05000336/20240052024-08-29029 August 2024 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Reports 05000336/2024005 and 05000423/2024005 IR 05000336/20240022024-08-13013 August 2024 Integrated Inspection Report 05000336/2024002 and 05000423/2024002 ML24221A2872024-08-0808 August 2024 Independent Spent Fuel Storage Installation (ISFSI) - Submittal of Cask Registration for Spent Fuel Storage IR 05000336/20244412024-08-0606 August 2024 Supplemental Inspection Report 05000336/2024441 and 05000423/2024441 and Follow-Up Assessment Letter (Cover Letter Only) ML24212A0742024-08-0505 August 2024 Request for Withholding Information from Public Disclosure - Millstone Power Station, Unit No. 3, Proposed Alternative Request IR-4-13 to Support Steam Generator Channel Head Drain Modification ML24211A1712024-07-25025 July 2024 Associated Independent Spent Fuels Storage Installation, Revision to Emergency Plan - Report of Change IR 05000336/20244032024-07-22022 July 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000336/2024403 and 05000423/2024403 IR 05000336/20245012024-07-0101 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000336/2024501 and 05000423/2024501 ML24180A0932024-06-28028 June 2024 Readiness for Additional Inspection: EA-23-144 IR 05000336/20240102024-06-26026 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000336/2024010 and 05000423/2024010 ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 IR 05000336/20244402024-06-24024 June 2024 Final Significance Determination for Security-Related Greater than Green Finding(S) with Assessment Follow-up; IR 05000336/2024440 and 05000423/2024440 and Notice of Violation(S), NRC Investigation Rpt 1-2024-001 (Cvr Ltr Only) ML24281A2072024-06-20020 June 2024 Update to the Final Safety Analysis Report, Revision 37 (Redacted Version) ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24280A0012024-06-20020 June 2024 Update to the Final Safety Analysis Report (Redacted Version) ML24162A0882024-06-10010 June 2024 Control Room Air Conditioning Unit Inoperable Due to Refrigerant Overcharge Resulting in a Condition Prohibited by Technical Specifications ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code ML24165A1292024-06-0505 June 2024 ISFSI, 10 CFR 50.59 Annual Change Report for 2023 Annual Regulatory Commitment Change Report for 2023 ML24128A2772024-06-0404 June 2024 Issuance of Amendment No. 290 to Revise TSs for Reactor Core Safety Limits, Fuel Assemblies, and Core Operating Limits Report for Use of Framatome Gaia Fuel (EPID L-2023-LLA-0074) (Non-Proprietary) ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24110A0562024-05-21021 May 2024 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material (EPID L-2023-LLE-0013) (Letter) ML24109A0032024-05-21021 May 2024 Issuance of Amendment No. 289 to Revise Technical Specifications to Use Framatome Loss of Coolant Accident Evaluation Methodologies for Establishing Core Operating Limit (EPID L-2023-LLA-0065) (Non-Proprietary) ML24141A1502024-05-20020 May 2024 Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications ML24141A2432024-05-20020 May 2024 Response to Request for Additional Information Regarding Alloy 600 Aging Management Program Submittal Related to License Renewal Commitment No. 15 ML24142A0952024-05-20020 May 2024 End of Cycle 22 Steam Generator Tube Inspection Report IR 05000336/20240012024-05-14014 May 2024 Integrated Inspection Report 05000336/2024001 and 05000423/2024001 and Apparent Violation ML24123A2042024-05-0202 May 2024 Pre-Decisional Replay to EA-23-144 ML24123A2272024-05-0202 May 2024 Pressurizer Power Operated Relief Valve Failed to Stroke Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications ML24123A1222024-04-30030 April 2024 Inservice Inspection Program - Owners Activity Report, Refueling Outage 22 IR 05000336/20244012024-04-30030 April 2024 Security Baseline Inspection Report 05000336/2024401 and 05000423/2024401 (Cover Letter Only) ML24116A0452024-04-25025 April 2024 Special Inspection Follow-Up Report 05000336/2024440 and 05000423/2024440 and Preliminary Finding(S) of Greater than Very Low Significance and NRC Investigation Report No. 1-2024-001 (Cover Letter Only) ML24114A2662024-04-24024 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report ML24116A1742024-04-24024 April 2024 Annual Radiological Environmental Operating Report ML24103A0202024-04-22022 April 2024 Summary of Regulatory Audit in Support of License Amendment Request to Use Framatome Small Break and Realistic Large Break Loss of Coolant Accident Evaluation Methodologies for Establishing Core Operating Limits ML24106A2032024-04-15015 April 2024 2023 Annual Environmental Operating Report ML24088A3302024-04-0404 April 2024 Regulatory Audit Plan in Support of License Amendment Request to Implement Framatome Gaia Fuel ML24093A2162024-04-0101 April 2024 Response to Request for Additional Information Regarding License Amendment Request to Use Framatome Small Break and Realistic Large Break Loss of Coolant Accident Evaluation Methodologies for Establishing Core Operating Limits ML24093A1022024-04-0101 April 2024 Alternative Request IR-4-13, Proposed Alternative Request to Support Steam Genera Tor Channel Head Drain Modification IR 05000336/20240112024-04-0101 April 2024 Comprehensive Engineering Team Inspection - Inspection Report 05000336/2024011 and 05000423/2024011 ML24092A0752024-03-28028 March 2024 3R22 Refueling Outage Inservice Inspection (ISI) Owners Activity Report Extension ML24088A2352024-03-26026 March 2024 Decommissioning Funding Status Report 2024-09-04
[Table view] |
Text
ber 29, 2016
SUBJECT:
MILLSTONE POWER STATION, UNITS 2 AND 3 - EVALUATED EMERGENCY PREPAREDNESS EXERCISE INSPECTION REPORT 05000336/2016502 AND 05000423/2016502
Dear Mr. Heacock:
On August 19, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection of the August 16, 2016, evaluated emergency preparedness exercise at the Millstone Power Station, Units 2 and 3. The enclosed inspection report documents the inspection results, which were discussed on August 19, 2016, with Mr. B. Stanley, Director of Safety and Licensing, and other members of your staff.
The inspection examined activities conducted under your licenses as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your licenses. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
The NRC inspectors did not identify any findings or violations of more than minor significance.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRCs Rules of Practice, a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS)
component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRCs Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Raymond R. McKinley, Chief Plant Support Branch 1 Division of Reactor Safety Docket Nos. 50-336 and 50-423 License Nos. DPR-65 and NPF-49
Enclosure:
Inspection Report 05000336/2016502 and 05000423/2016502 w/Attacment: Supplemental Information
REGION I==
Docket Nos. 50-336 and 50-423 License Nos. DPR-65 and NPF-49 Report Nos. 05000336/2016502 and 05000423/2016502 Licensee: Dominion Nuclear Connecticut, Inc. (Dominion)
Facility: Millstone Power Station, Units 2 and 3 Location: Waterford, CT 06385 Dates: August 15-19, 2016 Inspectors: S. Barr, Senior Emergency Preparedness Inspector, Division of Reactor Safety (DRS), Region I (Lead)
J. DeBoer, Emergency Preparedness Inspector, DRS E. Burket, Reactor Inspector, DRS B. Fuller, Senior Operations Inspector, DRS L. Cruz, Project Engineer, Division of Reactor Projects Approved By: Raymond R. McKinley, Chief Plant Support Branch 1 Division of Reactor Safety Enclosure
SUMMARY
IR 05000336/2016502 and 05000423/2016502; 08/15/2016 - 08/19/2016; Millstone Power
Station, Units 2 and 3; Exercise Evaluation - Scenario Review - Performance Indicator Verification.
This report covers an announced inspection conducted by five Region I-based inspectors.
No findings were identified during the inspection. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 6.
Cornerstone: Emergency Preparedness
No findings were identified.
REPORT DETAILS
1.
REACTOR SAFETY
1EP1 Exercise Evaluation
Main article: IP 71114.01
a. Inspection Scope
On August 16, 2016, Dominion conducted a biennial Millstone emergency preparedness (EP) exercise. The inspectors evaluated the adequacy of Dominions conduct of the exercise, the performance of Millstones emergency response organization (ERO) to respond to the simulated emergency, and Dominions capability to assess their own staff performance via a formal critique process, as required by Title 10 of the Code of Federal Regulations (CFR) 50.47(b)(14). This overall exercise inspection activity represented the completion of one sample on a biennial cycle.
The exercise evaluation consisted of the following review and assessment:
The adequacy of Dominions performance in the biennial full-participation exercise regarding the implementation of the risk-significant planning standards described in 10 CFR 50.47(b)(4), (5), (9), and (10), which are: emergency classification; offsite notification; radiological assessment; and protective action recommendations, respectively.
The overall adequacy of Millstones emergency response facilities with regard to NUREG-0696, Functional Criteria for Emergency Response Facilities, and Emergency Plan commitments. The facilities assessed were the Control Room Simulator, Technical Support Center, and Emergency Operations Facility.
A review of other performance areas, such as: Dominion EROs recognition of abnormal plant conditions; command and control; intra- and inter-facility communications; prioritization of mitigating activities; utilization of repair and field monitoring teams; interface with offsite agencies; staffing and procedure adequacy; and the overall implementation of the Millstone emergency plan and its implementing procedures.
A review of past performance issues from the last NRC Millstone exercise inspection report and Dominions EP drill reports, to determine the effectiveness of Dominion corrective actions as demonstrated during the August 16, 2016, exercise and to ensure compliance with 10 CFR 50.47(b)(14).
Dominions post-exercise critiques, to evaluate Dominions self-assessment of its ERO performance during the August 16, 2016, exercise and to ensure compliance with 10 CFR Part 50, Appendix E, Section IV.F.2.g.
The inspectors reviewed the documents listed in the attachment to this report.
b. Findings
No findings were identified.
1EP8 Exercise Evaluation - Scenario Review
Main article: IP 71114.08
a. Inspection Scope
Prior to the August 16, 2016, EP exercise, Dominion had submitted the exercise objectives and scenario to the NRC. The NRC inspectors conducted an in-office review of the submittal to determine if the exercise would test major elements of the Millstone Emergency Plan as required by 10 CFR 50.47(b)(14). This overall exercise inspection activity represented the completion of one sample on a biennial cycle.
The inspectors reviewed the documents listed in the attachment to this report.
b. Findings
No findings were identified.
4.
OTHER ACTIVITIES (OA)
4OA1 Performance Indicator (PI) Verification
a. Inspection Scope
The inspectors reviewed data for the Millstone EP performance indicators (PIs), which are:
- (1) Drill and Exercise Performance;
- (2) ERO Drill Participation; and,
- (3) Alert and Notification System Reliability. The last NRC EP inspection at Millstone was conducted in the third calendar quarter of 2015, so the inspectors reviewed supporting documentation from EP drills, training records, and equipment tests, from the third calendar quarter of 2015 through the second quarter of 2016, to verify the accuracy of the reported PI data. The review of these PIs was conducted in accordance with NRC Inspection Procedure 71151, using the acceptance criteria documented in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guidelines, Revision 7.
This inspection activity represented the completion of three samples.
b. Findings
No findings were identified.
4OA6 Meetings, including Exit
On August 19, 2016, the inspectors presented the results of this inspection to Mr. B. Stanley, Director of Safety and Licensing, and other members of the Dominion staff. No proprietary information was provided to the inspectors during this inspection.
ATTACHMENT:
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
- B. Stanley, Director of Safety and Licensing
- D. Smith, Emergency Preparedness Manager
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
None.
LIST OF DOCUMENTS REVIEWED