IR 05000336/2022011

From kanterella
Jump to navigation Jump to search
Triennial Fire Protection Inspection Report 05000336/2022011 and 05000423/2022011
ML22251A051
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 09/08/2022
From: Glenn Dentel
Division of Operating Reactors
To: Stoddard D
Dominion Energy
Dentel G
References
IR 2022011
Download: ML22251A051 (9)


Text

September 8, 2022

SUBJECT:

MILLSTONE POWER STATION, UNITS 2 AND 3 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000336/2022011 AND 05000423/2022011

Dear Daniel Stoddard:

On August 19, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Millstone Power Station, Units 2 and 3 and discussed the results of this inspection with Michael O'Connor, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Glenn T. Dentel, Chief Engineering Branch 2 Division of Operating Reactor Safety

Docket Nos. 05000336 and 05000423 License Nos. DPR-65 and NPF-49

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000336 and 05000423

License Numbers:

DPR-65 and NPF-49

Report Numbers:

05000336/2022011 and 05000423/2022011

Enterprise Identifier: I-2022-011-0014

Licensee:

Dominion Energy Nuclear Connecticut, Inc.

Facility:

Millstone Power Station, Units 2 and 3

Location:

Waterford, CT 06385

Inspection Dates:

August 1, 2022 to August 19, 2022

Inspectors:

L. Dumont, Senior Reactor Inspector

C. Hobbs, Reactor Inspector

S. Makor, Reactor Inspector

E. Miller, Reactor Inspector

M. Patel, Senior Reactor Inspector

Approved By:

Glenn T. Dentel, Chief

Engineering Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Millstone Power Station,

Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21N.05 - Fire Protection Team Inspection (FPTI)

Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)===

The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).

(1) Unit 2 - Auxiliary Feed Water System (TDAFW pump)
(2) Unit 2 - Chemical and Volume Control System (CVCS)
(3) Unit 2 - Electrical Distribution System - AC Power Cross-Tie from Unit 3
(4) Unit 3 - Auxiliary Feed Water System (TDAFW pump)
(5) Unit 3 - Chemical and Volume Control System (CVCS), RCS Letdown
(6) Unit 3 - Residual Heat Removal System
(7) Unit 3 - Fire Protection Water Supply System, including Fire Pumps and Tanks and Underground Buried Piping

Fire Protection Program Administrative Controls (IP Section 03.02) (4 Samples)

The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees fire protection program (FPP) contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.

(1) Unit 2 - Combustible Control Program
(2) Unit 2 - Fire Brigade Training, Drills, and Qualifications
(3) Unit 3 - Combustible Control Program
(4) Unit 3 - Fire Brigade Training, Drills, and Qualifications

Fire Protection Program Changes/Modifications (IP Section 03.03) (3 Samples)

The inspectors verified the following:

a. Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown; b. The adequacy of the design modification, if applicable; c. Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications; d. The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, FHA, and SSA were updated consistent with the FPP or design change; and e. Post-fire SSD operating procedures, such as abnormal operating procedures, affected by the modification were updated.

(1) Unit 2 - Battery Charger Replacement (201A/DC1)
(2) Unit 3 - Fire Detection System Upgrade - Zone Panel 5
(3) Unit 3 - Fire Detection System Upgrade - Main

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On August 19, 2022, the inspectors presented the triennial fire protection inspection results to Michael O'Connor, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.05 Corrective Action

Documents

1096430

1096886

29375

1154762

1170024

1174033

1176172

1192162

1199085

203569

203703

204234

204287

204295

204449

Corrective Action

Documents

Resulting from

Inspection

204812

204841

204885

205026

205334

205672

205713

205739

205739

205758

205762

205762

205861

205940

205951

249200

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Changes

DM3-00-0055-05

Replacement of Electric Fire Pump M7-8

2/09/2005

MP3-17-00149

MP3 Fire Detection System Upgrade

Revision 3

MPS-18-00188

MP3 Fire Detection System Upgrade -- Zone Panel 5

Revision 0

Engineering

Evaluations

203-SP-M2-

SU-1046

Millstone Unit 2 Appendix R Compliance Report

Revision 1

ETE-MP-2014-

214

Millstone Unit 3 Branch Technical Position 9.5-1

Compliance Report

Revision 4

ETE-MP-2021-

1035

Millstone Power Station Fire Protection Program Manual

Revision 0

Miscellaneous

Zone Panel 5 System Upgrade Factory Acceptance Test

Procedure

09/24/2019

21 Bravo Shift UBSD

09/29/2021

Live fire training Bravo Shift with EB fire dept. offsite

07/15/2022

212-652-

005VTM

Vendor Technical Manual - Simplex 4020 Panel

Revision 2

BKG EOP 3509.1

Basis - Control Room, Cable Spreading Area, or

Instrument Rack Room Fire

Revision 27

TR-MP-TPG-

2300

Fire Protection Programs Training Program Guide

Revision 6

Procedures

AOP 2579A

Fire Procedure for Hot Standby Appendix R Fire Area R-1

Revision 13

AOP 2579C

Fire Procedure for Hot Standby Appendix R Fire Area R-3

Revision 06

AOP 2579L

Fire Procedure for Hot Standby Appendix R Fire Area R-

Revision 08

AOP 2579P

Fire Procedure for Hot Standby Appendix R Fire Area R-

Revision 09

C OP 200.18

Time Critical Action Verification and Validation

Revision 13

C SP 600.24

Fire Brigade Equipment Inspection

Revision 2

C SP 600.7

Electric Fire Pump M7-8 Annual Operability

Demonstration

Completed

09/04/2021

C SP 600.9

Diesel Fire Pump M7-7 Annual Operability Demonstration

Completed

07/11/2020

CM-AA-FPA-100

Fire Protection/Appendix R (Fire Safe Shutdown) Program

Revision 19

CM-AA-FPA-101

Control of Combustible and Flammable Materials

Revision 15

CM-AA-FPA-102

Fire Protection and Fire Safe Shutdown Review and

Revision 11

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Preparation Process and Design Change Process

EOP 2541

Appendix 7

TDAFW Pump Abnormal Startup

Revision 1

EOP 3509

Fire Emergency

Revision 30

EOP 3509.1

Control Room, Cable Spreading Area, or Instrument Rack

Room Fire

Revision 27

EOP 3509.2

Aux Building Elevation 24'6", South Floor Area, 43'6" &

66'6" Fire

Revision 8

MP-PROC-OPS-

SFP 10

Fire Prevention Inspections

Revision 09

RPM 2.3.13

Inspection and Inventory of Self Contained Breathing

Apparatus

Revision 2

SA-AA-115

Conduct of Fire Drills

Revision 6

Work Orders

53103046471

53103117263

203236598

203255322

203255324

203308271

203319891

203336288

203344045

203359004

203359683

203359684

203359726