IR 05000336/2022011
| ML22251A051 | |
| Person / Time | |
|---|---|
| Site: | Millstone |
| Issue date: | 09/08/2022 |
| From: | Glenn Dentel Division of Operating Reactors |
| To: | Stoddard D Dominion Energy |
| Dentel G | |
| References | |
| IR 2022011 | |
| Download: ML22251A051 (9) | |
Text
September 8, 2022
SUBJECT:
MILLSTONE POWER STATION, UNITS 2 AND 3 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000336/2022011 AND 05000423/2022011
Dear Daniel Stoddard:
On August 19, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Millstone Power Station, Units 2 and 3 and discussed the results of this inspection with Michael O'Connor, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Glenn T. Dentel, Chief Engineering Branch 2 Division of Operating Reactor Safety
Docket Nos. 05000336 and 05000423 License Nos. DPR-65 and NPF-49
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000336 and 05000423
License Numbers:
Report Numbers:
05000336/2022011 and 05000423/2022011
Enterprise Identifier: I-2022-011-0014
Licensee:
Dominion Energy Nuclear Connecticut, Inc.
Facility:
Millstone Power Station, Units 2 and 3
Location:
Waterford, CT 06385
Inspection Dates:
August 1, 2022 to August 19, 2022
Inspectors:
L. Dumont, Senior Reactor Inspector
C. Hobbs, Reactor Inspector
S. Makor, Reactor Inspector
E. Miller, Reactor Inspector
M. Patel, Senior Reactor Inspector
Approved By:
Glenn T. Dentel, Chief
Engineering Branch 2
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Millstone Power Station,
Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
===71111.21N.05 - Fire Protection Team Inspection (FPTI)
Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)===
The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).
- (1) Unit 2 - Auxiliary Feed Water System (TDAFW pump)
- (2) Unit 2 - Chemical and Volume Control System (CVCS)
- (3) Unit 2 - Electrical Distribution System - AC Power Cross-Tie from Unit 3
- (4) Unit 3 - Auxiliary Feed Water System (TDAFW pump)
- (6) Unit 3 - Residual Heat Removal System
- (7) Unit 3 - Fire Protection Water Supply System, including Fire Pumps and Tanks and Underground Buried Piping
Fire Protection Program Administrative Controls (IP Section 03.02) (4 Samples)
The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees fire protection program (FPP) contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.
- (1) Unit 2 - Combustible Control Program
- (2) Unit 2 - Fire Brigade Training, Drills, and Qualifications
- (3) Unit 3 - Combustible Control Program
- (4) Unit 3 - Fire Brigade Training, Drills, and Qualifications
Fire Protection Program Changes/Modifications (IP Section 03.03) (3 Samples)
The inspectors verified the following:
a. Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown; b. The adequacy of the design modification, if applicable; c. Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications; d. The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, FHA, and SSA were updated consistent with the FPP or design change; and e. Post-fire SSD operating procedures, such as abnormal operating procedures, affected by the modification were updated.
- (1) Unit 2 - Battery Charger Replacement (201A/DC1)
- (2) Unit 3 - Fire Detection System Upgrade - Zone Panel 5
- (3) Unit 3 - Fire Detection System Upgrade - Main
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On August 19, 2022, the inspectors presented the triennial fire protection inspection results to Michael O'Connor, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21N.05 Corrective Action
Documents
1096430
1096886
29375
1154762
1170024
1174033
1176172
1192162
1199085
203569
203703
204234
204287
204295
204449
Corrective Action
Documents
Resulting from
Inspection
204812
204841
204885
205026
205334
205672
205713
205739
205739
205758
205762
205762
205861
205940
205951
249200
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Engineering
Changes
DM3-00-0055-05
Replacement of Electric Fire Pump M7-8
2/09/2005
MP3-17-00149
MP3 Fire Detection System Upgrade
Revision 3
MPS-18-00188
MP3 Fire Detection System Upgrade -- Zone Panel 5
Revision 0
Engineering
Evaluations
203-SP-M2-
SU-1046
Millstone Unit 2 Appendix R Compliance Report
Revision 1
ETE-MP-2014-
214
Millstone Unit 3 Branch Technical Position 9.5-1
Compliance Report
Revision 4
ETE-MP-2021-
1035
Millstone Power Station Fire Protection Program Manual
Revision 0
Miscellaneous
Zone Panel 5 System Upgrade Factory Acceptance Test
Procedure
09/24/2019
21 Bravo Shift UBSD
09/29/2021
Live fire training Bravo Shift with EB fire dept. offsite
07/15/2022
212-652-
005VTM
Vendor Technical Manual - Simplex 4020 Panel
Revision 2
BKG EOP 3509.1
Basis - Control Room, Cable Spreading Area, or
Instrument Rack Room Fire
Revision 27
TR-MP-TPG-
2300
Fire Protection Programs Training Program Guide
Revision 6
Procedures
AOP 2579A
Fire Procedure for Hot Standby Appendix R Fire Area R-1
Revision 13
AOP 2579C
Fire Procedure for Hot Standby Appendix R Fire Area R-3
Revision 06
AOP 2579L
Fire Procedure for Hot Standby Appendix R Fire Area R-
Revision 08
AOP 2579P
Fire Procedure for Hot Standby Appendix R Fire Area R-
Revision 09
Time Critical Action Verification and Validation
Revision 13
C SP 600.24
Fire Brigade Equipment Inspection
Revision 2
C SP 600.7
Electric Fire Pump M7-8 Annual Operability
Demonstration
Completed
09/04/2021
C SP 600.9
Diesel Fire Pump M7-7 Annual Operability Demonstration
Completed
07/11/2020
CM-AA-FPA-100
Fire Protection/Appendix R (Fire Safe Shutdown) Program
Revision 19
CM-AA-FPA-101
Control of Combustible and Flammable Materials
Revision 15
CM-AA-FPA-102
Fire Protection and Fire Safe Shutdown Review and
Revision 11
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Preparation Process and Design Change Process
EOP 2541
Appendix 7
TDAFW Pump Abnormal Startup
Revision 1
EOP 3509
Fire Emergency
Revision 30
EOP 3509.1
Control Room, Cable Spreading Area, or Instrument Rack
Room Fire
Revision 27
EOP 3509.2
Aux Building Elevation 24'6", South Floor Area, 43'6" &
66'6" Fire
Revision 8
MP-PROC-OPS-
SFP 10
Fire Prevention Inspections
Revision 09
RPM 2.3.13
Inspection and Inventory of Self Contained Breathing
Apparatus
Revision 2
Conduct of Fire Drills
Revision 6
Work Orders
53103046471
53103117263
203236598
203255322
203255324
203308271
203319891
203336288
203344045
203359004
203359683
203359684
203359726