MONTHYEARML25022A2962025-01-23023 January 2025 Technical Specification Bases Pages ML25023A0392025-01-23023 January 2025 Senior Reactor and Reactor Operator Initial License Examinations L-25-001, Endorsement of Framatomes Requested Review Schedule for Topical Report ANP-10358P, Revision O Increased Burnup for PWRs2025-01-23023 January 2025 Endorsement of Framatomes Requested Review Schedule for Topical Report ANP-10358P, Revision O Increased Burnup for PWRs ML25014A2862025-01-21021 January 2025 Alternative Request to Defer ASME Code Section XI Inservice Inspection Examinations for Pressurizer and Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles IR 05000336/20244032025-01-13013 January 2025 Cyber Security Inspection Report 05000336/2024403 and 05000423/2024403 (Cover Letter Only) ML24365A2032024-12-30030 December 2024 ISFSI - 10 CFR 72.30 Decommissioning Funding Plan ML24351A2422024-12-19019 December 2024 Reactor Coolant System Alloy 600 Inspection Program for License Renewal Commitment No. 15 ML24351A2412024-12-19019 December 2024 Reactor Vessel Internals Inspections Aging Management Program Submittal Related to License Renewal Commitment No. 13 ML24346A2532024-12-12012 December 2024 Correction to Implementation Date for License Amendment No. 291 Regarding Framatome Gaia Fuel IR 05000336/20243012024-12-0606 December 2024 Initial Operator Licensing Examination Report 05000336/2024301 ML24324A0442024-12-0303 December 2024 Issuance of Amendment No. 292 Regarding Adoption of Technical Specification Task Force Traveler TSTF-421 05000336/LER-2024-002, Two Main Steam Safety Valves Failed to Lift within the Acceptance Criteria Resulting in a Condition Prohibited by Technical Specifications2024-11-26026 November 2024 Two Main Steam Safety Valves Failed to Lift within the Acceptance Criteria Resulting in a Condition Prohibited by Technical Specifications 05000423/LER-2024-002, Door Latch Failure Resulted in Loss of Safety Function for Secondary Containment Boundary2024-11-26026 November 2024 Door Latch Failure Resulted in Loss of Safety Function for Secondary Containment Boundary ML24296B2352024-11-19019 November 2024 Issuance of Amendment No. 291 License Amendment to Support the Implementation of Framatome Gaia Fuel (EPID L-2023-LLA-0150) (Non-Proprietary) IR 05000245/20240012024-11-12012 November 2024 Safstor Inspection Report 05000245/2024001 ML24317A2562024-11-12012 November 2024 Core Operating Limits Report, Gycle 30 IR 05000336/20240032024-11-0707 November 2024 Integrated Inspection Report 05000336/2024003 and 05000423/2024003 and Apparent Violation and Independent Spent Fuel Storage Installation Inspection Report 07200008/2024001 ML24289A0152024-10-21021 October 2024 Review of the Fall 2023 Steam Generator Tube Inspection Report 05000423/LER-2024-001, Loss of Safety Function and Condition Prohibited by Technical Specifications for Loss of Secondary Containment Boundary2024-10-14014 October 2024 Loss of Safety Function and Condition Prohibited by Technical Specifications for Loss of Secondary Containment Boundary IR 05000336/20244022024-10-0808 October 2024 Security Baseline Inspection Report 05000336/2024402 and 05000423/2024402 (Cover Letter Only) ML24281A1102024-10-0707 October 2024 Requalification Program Inspection 05000423/LER-2023-006-02, Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications2024-09-26026 September 2024 Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24260A1952024-09-16016 September 2024 Response to Request for Additional Information Regarding Proposed Amendment to Support Implementation of Framatome Gaia Fuel ML24260A2192024-09-16016 September 2024 Decommissioning Trust Fund Disbursement - Revision to Previous Thirty-Day Written Notification ML24248A2272024-09-0404 September 2024 Operator Licensing Examination Approval ML24240A1532024-09-0303 September 2024 Summary of Regulatory Audit Supporting the Review of License Amendment Request for Implementation of Framatome Gaia Fuel IR 05000336/20240052024-08-29029 August 2024 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Reports 05000336/2024005 and 05000423/2024005 IR 05000336/20240022024-08-13013 August 2024 Integrated Inspection Report 05000336/2024002 and 05000423/2024002 ML24221A2872024-08-0808 August 2024 Independent Spent Fuel Storage Installation (ISFSI) - Submittal of Cask Registration for Spent Fuel Storage IR 05000336/20244412024-08-0606 August 2024 Supplemental Inspection Report 05000336/2024441 and 05000423/2024441 and Follow-Up Assessment Letter (Cover Letter Only) ML24212A0742024-08-0505 August 2024 Request for Withholding Information from Public Disclosure - Millstone Power Station, Unit No. 3, Proposed Alternative Request IR-4-13 to Support Steam Generator Channel Head Drain Modification ML24211A1712024-07-25025 July 2024 Associated Independent Spent Fuels Storage Installation, Revision to Emergency Plan - Report of Change ML24200A1062024-07-22022 July 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000336/2024403 and 05000423/2024403 IR 05000336/20245012024-07-0101 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000336/2024501 and 05000423/2024501 ML24180A0932024-06-28028 June 2024 Readiness for Additional Inspection: EA-23-144 IR 05000336/20240102024-06-26026 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000336/2024010 and 05000423/2024010 ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 IR 05000336/20244402024-06-24024 June 2024 Final Significance Determination for Security-Related Greater than Green Finding(S) with Assessment Follow-up; IR 05000336/2024440 and 05000423/2024440 and Notice of Violation(S), NRC Investigation Rpt 1-2024-001 (Cvr Ltr Only) ML24281A2072024-06-20020 June 2024 Update to the Final Safety Analysis Report, Revision 37 (Redacted Version) ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24280A0012024-06-20020 June 2024 Update to the Final Safety Analysis Report (Redacted Version) ML24176A1782024-06-20020 June 2024 Update to the Final Safety Analysis Report ML24176A2622024-06-20020 June 2024 Update to the Final Safety Analysis Report, Revision 37 ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code 05000336/LER-2024-001, Control Room Air Conditioning Unit Inoperable Due to Refrigerant Overcharge Resulting in a Condition Prohibited by Technical Specifications2024-06-10010 June 2024 Control Room Air Conditioning Unit Inoperable Due to Refrigerant Overcharge Resulting in a Condition Prohibited by Technical Specifications ML24170A7832024-06-0606 June 2024 ISFSI, Virgil C. Summer, Unit 1, and ISFSI, North Anna, Units 1 & 2, and ISFSI, Surry, Units 1 & 2, and ISFSI - Submittal of Revision 36 of the Quality Assurance Topical Report ML24165A1292024-06-0505 June 2024 ISFSI, 10 CFR 50.59 Annual Change Report for 2023 Annual Regulatory Commitment Change Report for 2023 ML24128A2772024-06-0404 June 2024 Issuance of Amendment No. 290 to Revise TSs for Reactor Core Safety Limits, Fuel Assemblies, and Core Operating Limits Report for Use of Framatome Gaia Fuel (EPID L-2023-LLA-0074) (Non-Proprietary) ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities 2025-01-23
[Table view] Category:License-Operator Examination Report
MONTHYEARIR 05000336/20243012024-12-0606 December 2024 Initial Operator Licensing Examination Report 05000336/2024301 IR 05000336/20233022023-03-0707 March 2023 Operator Licensing Retake Examination Report 05000336/2023302 IR 05000336/20223012022-11-22022 November 2022 Initial Operator Licensing Examination Report 05000336/2022301 IR 05000423/20223022022-03-0707 March 2022 Operator Licensing Retake Examination Report 05000423/2022302 IR 05000423/20213012021-11-10010 November 2021 Initial Operator Licensing Examination Report 05000423/2021301 IR 05000336/20203012020-11-12012 November 2020 Initial Operator Licensing Examination Report 05000336/2020301 IR 05000423/20193012019-10-28028 October 2019 Initial Operator Licensing Examination Report 05000423/2019301 IR 05000336/20183012018-11-20020 November 2018 Initial Operator Licensing Examination Report 05000336/2018301 IR 05000423/20173012018-02-0606 February 2018 Initial Operator Licensing Examination Report 05000423/2017301 IR 05000336/20173022017-03-0808 March 2017 Initial Re-take Operator Licensing Examination Report 05000336/2017302 IR 05000336/20163012016-11-23023 November 2016 Initial Operator Licensing Examination Report 05000336/2016301 IR 05000423/20153012015-11-0202 November 2015 Er 05000423/2015301; September 14 to 18, 2015 and September 21, 2015; Millstone Power Station, Unit 3; Initial Operator Licensing Examination Report IR 05000336/20143012015-01-0808 January 2015 Er 05000336/2014301; September 29-October 31, 2014; Millstone Power Station, Unit 2; Initial Operator Licensing Examination Report IR 05000423/20133012014-01-16016 January 2014 Er 05000423/2013301; December 2-9, 2013; Millstone Power Station, Unit 3, Initial Operator Licensing Examination Report IR 05000336/20113012011-12-0606 December 2011 Er 05000336-11-301, on 10/ 3-11/2011, Millstone Power Station, Unit 2, Initial Operator Licensing Examination Report IR 05000423/20113022011-08-0404 August 2011 Er 05000423/11-302, on 7/11-7/18/2011, Millstone Power Station, Unit 3, Initial Operator Licensing Examination Report IR 05000423/20093022009-11-0202 November 2009 Er 05000423-09-302; September 14-22, 2009; Millstone Power Station, Unit 3; Initial Operator Licensing Examination Report IR 05000336/20093012009-05-18018 May 2009 Er 05000336/2009301, January 26 - February 24, 2009, Millstone Power Station, Unit 2, Initial Operator Licensing Examination Report ML0331604982003-11-12012 November 2003 Senior Reactor Operator Initial Examination Report No. 050000336/2003-302 2024-12-06
[Table view] |
Text
March 7, 2022
SUBJECT:
MILLSTONE POWER STATION, UNIT 3 - OPERATOR LICENSING RETAKE EXAMINATION REPORT 05000423/2022302
Dear Mr. Stoddard:
On January 20, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an examination at Millstone Power Station, Unit 3. The enclosed examination report documents the examination results, which were discussed on February 10, 2022, with Cristalle Walsh and other members of your staff.
The examination included the evaluation of one applicant for an upgrade senior reactor operator license. The operating examination was developed using NUREG-1021, "Operator Licensing Examination Stand ards for Power Reactors," Revision 11. The license examiner determined that the applicant satisfied the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 55, and the appropriate license was issued on February 10, 2022.
No findings were identified during this examination.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs Agencywide Documents Access Management System (ADAMS). ADAMS is accessible from the NRC website http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely, Donald E. Jackson, Chief Operations Branch
Division of Operating Reactor Safety
Docket No. 50-423 License No. NPF-49
Enclosure:
Examination Report 05000423/2022302 w/Attachment: Supplementary Information
cc w/encl: Distribution via ListServ
Donald E.
Jackson Digitally signed by Donald E.
Jackson Date: 2022.03.07 14:49:24-05'00'
SUMMARY
ER 05000423/2022302; January 20, 2022; Millstone Power Station, Unit 3; Operator Licensing
Retake Examination Report.
Two NRC examiners evaluated the competency of one applicant for an upgrade senior reactor operator license at Millstone Power Station, Unit 3. The facility licensee developed the examination using NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 11. NRC examiners administered the operating test on January 20, 2022.
The NRC examiners determined that the applicant satisfied the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 55, and the appropriate license has been issued.
NRC-Identified and Self-Revealing Findings
No findings were identified.
Licensee-Identified Violations
None.
REPORT DETAILS
OTHER ACTIVITIES (OA)
4OA5 Other Activities (Operator License Retake Examination)
.1 License Applications
a. Scope
The examiners reviewed the license application submitted by the licensee to ensure the application reflected that the applicant satisfied relevant license eligibility requirements.
The application was submitted on NRC Form 398, Personal Qualification Statement, and NRC Form 396, Certification of Medical Examination by Facility Licensee. The examiner also audited the license application in detail to confirm that it accurately reflected the subject applicants qualifications. This audit focused on the applicants experience and on-the-job training, including control manipulations that provided significant reactivity changes.
b. Findings
No findings were identified.
.2 Operator Knowledge and Performance
a. Examination Scope
The NRC examiners administered the simulator scenario portion of the operating examination to the applicant on January 20, 2022. The applicant for upgrade senior reactor operator license participated in one dynamic simulator scenario.
b. Findings
The applicant passed the operating test.
.3 Retake Licensing Examination Development
a. Examination Scope
The facility licensee developed the examination in accordance with NUREG-1021, Revision 11. All licensee facility training and operations staff involved in examination preparation and validation were listed on a security agreement. The facility licensee submitted the operating examination on December 12, 2021. The NRC conducted an onsite validation of the operating examination during the week of January 17, 2022.
b. Findings
No findings were identified.
.4 Simulation Facility Performance
a. Examination Scope
The examiners observed simulator performance with regard to plant fidelity during the examination validation and administration.
b. Findings
No findings were identified.
.5 Examination Security
a. Examination Scope
The examiners reviewed examination security for examination development and during both the onsite preparation week and examination administration week for compliance with NUREG-1021, Revision 11 requirements. Plans for simulator security and applicant control were reviewed and discussed with licensee personnel.
b. Findings
No findings were identified.
4OA6 Meetings, Including Exit
The chief examiner presented the examination results to Cristalle Walsh, Manager Nuclear Training (Plant), and other members of the licensee's management staff on February 10, 2022.
The licensee did not identify any information or materials used during the examination as proprietary.
SUPPLEMENTARY INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
- W. Forrestt, Exam Developer
ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
NONE
Closed
NONE
Discussed
NONE
ADAMS DOCUMENTS REFERENCED