E-mail, Miller to Loomis, Oyster Creek Request to Extend 4th ISI Interval Acceptance Review
ML113250698
Person / Time
Site: Oyster Creek
Issue date: 11/21/2011
From: Geoffrey Miller
Plant Licensing Branch 1
To: Tom Loomis
Exelon Corp
Miller G, NRR/DORL/LPL1-2, 415-2481
References
Download: ML113250698 (1)


Text

From: Miller, Ed Sent: Monday, November 21, 2011 3:29 PM To: 'thomas.loomis@exeloncorp.com'

Subject:

Oyster Creek Request to Extend 4th ISI Interval Acceptance Review

Tom, By letter dated September 30, 2011, Exelon Generation Company, LLC submitted a relief request for the Oyster Creek Nuclear Generating Station. The request would extend the end date of the fourth 10-year ISI interval for Oyster Creek from October 14, 2012 to January 14, 2013.

The purpose of this e-mail is to provide you with the results of the Nuclear Regulatory Commission (NRC) staff's acceptance review of this submittal. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your submittal and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and protection of public health and safety and the environment.

If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence. If you have any questions, please contact me at (301) 415-2481.

G. Edward Miller Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation