ML13109A436: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 14: Line 14:
| page count = 5
| page count = 5
}}
}}
=Text=
{{#Wiki_filter:UNITED STATES                            NUCLEAR REGULATORY COMMISSION                                                      REGION I                      2100 RENAISSANCE BOULEVARD, SUITE 100                    KING OF PRUSSIA, PENNSYLVANIA 19406-2713 April 19, 2013 MEETING
==SUMMARY==
LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC. 
FACILITY: PILGRIM NUCLEAR POWER STATION 
==SUBJECT:==
==SUMMARY==
OF PUBLIC MEETING
On April 2, 2013, at 5:30 p.m., the U. S. Nuclear Regulatory Commission (NRC) conducted a public open house at the Plymouth Town Hall in Plymouth, Massachusetts. The NRC conducted the open house to discuss its assessment of the safety performance at Pilgrim
Nuclear Power Station for 2012.
A notice of the open house was issued on Ma rch 27, 2013, and was posted on the NRC's external (public) Web page. The meeting notice can be found in the NRC's Agencywide Documents Access and Management System (ADAMS) with Accession No. ML13086A590. ADAMS is accessible from the NRC Web page at:
http://www.nrc.gov/reading-rm/adams.html.
The NRC presented poster boards, fact sheets and reading material and was available to discuss its assessment of the safety performance of Pilgrim Nuclear Power Station for the period of January 1 through December 31, 2012, as documented in our letter dated March 4, 2013 (ADAMS Accession No. ML13060A340). The NRC poster boards, fact sheets and reading material presented included background on the Reactor Oversight Process (ROP). Additional information relative to the NRC's Annual Assessment Process and the safety performance of
Pilgrim Nuclear Power Station can be found on the NRC's web site at:  www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html. Members of the public, local officials, State officials, and members of the media attended the open house and were offered the opportunity to question the NRC regarding Pilgrim's performance and the role of the agency in ensuring safe plant operations.
      /RA/    Ronald R. Bellamy, Chief Projects Branch 5 Division of Reactor Projects
==Enclosures:==
Attendee List (ML)
ML13060A340). The NRC poster boards, fact sheets and reading material presented included background on the Reactor Oversight Process (ROP). Additional information relative to the NRC's Annual Assessment Process and the safety performance of
Pilgrim Nuclear Power Station can be found on the NRC's web site at:
www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html. Members of the public, local officials, State officials, and members of the media attended the open house and were offered the opportunity to question the NRC regarding Pilgrim's performance and the role of the agency in ensuring safe plant operations.
==Enclosures:==
Attendee List (ML)
      /RA/    Ronald R. Bellamy, PhD, Chief Projects Branch 5 Division of Reactor Projects Distribution: (via email) R. Bellamy, DRP S. Shaffer, DRP E. Keighley, DRP J. DeBoer, DRP M. Schneider, DRP, SRI B. Smith, DRP, RI S. Campbell, DRP, AA RidsNRRPMPilgrim Resource DOC NAME: G:\DRP\BRANCH5\ANNUAL ASSESSMENT MEETINGS\2012 EOC\ANNUAL ASSESSMENT MEETING
==SUMMARY==
PILGRIM.DOCX ADAMS Accession No.:  ML13109A436 SUNSI Review Non-Sensitive  Sensitive Publicly Available Non-Publicly Available OFFICE klm RI/DRP RI/DRP    NAME EKeighley/EMK RBellamy/RRB    DATE 4 /19 /13    4/19 /13   
Name April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Page __ of :2) Organization (if applicable)
Name April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Page Organization (if applicable)
Name April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Organization (if applicable)}}

Revision as of 00:23, 18 July 2018

4/2/2013 - Pilgrim - Annual Assessment Meeting Summary
ML13109A436
Person / Time
Site: Pilgrim
Issue date: 04/19/2013
From: Bellamy R R
NRC/RGN-I/DRP/PB5
To:
Entergy Nuclear Operations
Bellamy R R
References
MN 13-005
Download: ML13109A436 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 April 19, 2013 MEETING

SUMMARY

LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC.

FACILITY: PILGRIM NUCLEAR POWER STATION

SUBJECT:

SUMMARY

OF PUBLIC MEETING

On April 2, 2013, at 5:30 p.m., the U. S. Nuclear Regulatory Commission (NRC) conducted a public open house at the Plymouth Town Hall in Plymouth, Massachusetts. The NRC conducted the open house to discuss its assessment of the safety performance at Pilgrim

Nuclear Power Station for 2012.

A notice of the open house was issued on Ma rch 27, 2013, and was posted on the NRC's external (public) Web page. The meeting notice can be found in the NRC's Agencywide Documents Access and Management System (ADAMS) with Accession No. ML13086A590. ADAMS is accessible from the NRC Web page at:

http://www.nrc.gov/reading-rm/adams.html.

The NRC presented poster boards, fact sheets and reading material and was available to discuss its assessment of the safety performance of Pilgrim Nuclear Power Station for the period of January 1 through December 31, 2012, as documented in our letter dated March 4, 2013 (ADAMS Accession No. ML13060A340). The NRC poster boards, fact sheets and reading material presented included background on the Reactor Oversight Process (ROP). Additional information relative to the NRC's Annual Assessment Process and the safety performance of

Pilgrim Nuclear Power Station can be found on the NRC's web site at: www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html. Members of the public, local officials, State officials, and members of the media attended the open house and were offered the opportunity to question the NRC regarding Pilgrim's performance and the role of the agency in ensuring safe plant operations.

/RA/ Ronald R. Bellamy, Chief Projects Branch 5 Division of Reactor Projects

Enclosures:

Attendee List (ML)

ML13060A340). The NRC poster boards, fact sheets and reading material presented included background on the Reactor Oversight Process (ROP). Additional information relative to the NRC's Annual Assessment Process and the safety performance of

Pilgrim Nuclear Power Station can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html. Members of the public, local officials, State officials, and members of the media attended the open house and were offered the opportunity to question the NRC regarding Pilgrim's performance and the role of the agency in ensuring safe plant operations.

Enclosures:

Attendee List (ML)

/RA/ Ronald R. Bellamy, PhD, Chief Projects Branch 5 Division of Reactor Projects Distribution: (via email) R. Bellamy, DRP S. Shaffer, DRP E. Keighley, DRP J. DeBoer, DRP M. Schneider, DRP, SRI B. Smith, DRP, RI S. Campbell, DRP, AA RidsNRRPMPilgrim Resource DOC NAME: G:\DRP\BRANCH5\ANNUAL ASSESSMENT MEETINGS\2012 EOC\ANNUAL ASSESSMENT MEETING

SUMMARY

PILGRIM.DOCX ADAMS Accession No.: ML13109A436 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE klm RI/DRP RI/DRP NAME EKeighley/EMK RBellamy/RRB DATE 4 /19 /13 4/19 /13

Name April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Page __ of :2) Organization (if applicable)

Name April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Page Organization (if applicable)

Name April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Organization (if applicable)