Line 1: |
Line 1: |
| {{Adams | | {{Adams |
| | number = ML18207A942 | | | number = ML18309A350 |
| | issue date = 08/01/2018 | | | issue date = 11/05/2018 |
| | title = NRC Examination Report 05000445/2018301, 05000446/2018301 | | | title = Notification of NRC Initial Operator Licensing Examination 05000445/2018301 and 05000446/2019301 |
| | author name = Gaddy V | | | author name = Gaddy V |
| | author affiliation = NRC/RGN-IV/DRS/OB | | | author affiliation = NRC/RGN-IV/DRS/OB |
Line 10: |
Line 10: |
| | license number = NPF-087, NPF-089 | | | license number = NPF-087, NPF-089 |
| | contact person = | | | contact person = |
| | document report number = 50-445/18-301, 50-446/18-301
| | | document type = Letter, License-Operator, Part 55 Examination Related Material |
| | document type = Letter, License-Operator Examination Report | | | page count = 4 |
| | page count = 13 | |
| }} | | }} |
|
| |
|
Line 18: |
Line 17: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:August 1, 2018 | | {{#Wiki_filter:November 5, 201 8 Ken J. Peters, Senior Vice President and Chief Nuclear Officer Attention: Regulatory Affairs Vistra Operations Company LLC P.O. Box 1002 Glen Rose, TX 76043 SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT |
| | | - NOTIFICATION OF NRC INITIAL OPERATOR LICENSING EXAMINATION 05000445/201 9 301 AND 05000446/201 9 301 |
| ==SUBJECT:==
| |
| COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 - NRC EXAMINATION REPORT 05000 445/2018301; 05000 446/2018301 | |
|
| |
|
| ==Dear Mr. Peters:== | | ==Dear Mr. Peters:== |
| On July 19, 20 18, the U.S. Nuclear Regulatory Commission (NRC) completed an initial operator license examination at Comanche Peak Nuclear Power Plant, Units 1 and 2. The enclosed report documents the examination results and licensing decisions. The preliminary examination results were discussed on June 15, 2018 , with members of your staff.
| | In a telephone conversation on October 24, 201 8, between Messrs. J. Ruby , Examination and Simulator Supervisor, and B. Lars on, Chief Examiner, arrangements were made for the administration of licensing examinations at Comanche Peak Nuclear Power Plant during the week of June 10, 201 9. As agreed during the telephone conversation, your staff will prepare the examinations based on the guidelines in Revision 11 to NUREG-1021, "Operator Licensing Examination Standards for Power Reactors |
| | ." The NRC's regional office will discuss with your staff any changes that might be necessary before the examinations are administered. |
|
| |
|
| A telephonic exit meeting was conduct ed on July 19, 2018 , with M s. Donna Christiansen, Training Director
| | To meet the above schedule, it will be necessary for your staff to furnish the operating test outlines by January 7, 2019. The written examination outlines were provided to your staff on September 18, 2018. |
| , who was provided the NRC licensing decisions.
| |
|
| |
|
| The examination included the evaluation of six applicants for reactor operator licenses, six applicants for instant senior reactor operator licenses, and three applicant s for upgrade senior reactor operator license s. The license examiners determined that fourteen of the fifteen applicants satisfied the requirements of Title 10 of the Code of Federal Regulations (CFR) Part 55, and the appropriate licenses have been issued. | | The written examinations, operating tests, and supporting reference materials identified in Attachment 3 to ES-201 will be due by March 25, 2019. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (CFR), an authorized representative of the facility licensee shall approve the examinations and tests before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use. We request that any personal, proprietary, sensitive unclassified, or Safeguards Information in your response be contained in a separate enclosure and appropriately marked. Delays in receiving the required materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be cancelled or rescheduled. In addition, your support for onsite validation of the examinations is required during the week of May 6, 2019. |
|
| |
|
| There was one post examination comment submitted by your staff.
| | To conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests, along with any video and audio recordings of the dynamic operating tests |
| | , until the NRC takes licensing action on all the applications and any adjudicatory actions on any hearing demands are complete. |
|
| |
|
| Enclosure 1 contains details of this report and Enclosure 2 summarizes post examination comment resolution
| | Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered. |
| . No violations were identified during this examination
| |
| . In accordance with 10 CFR 2.390 of the NRC's "Agency Rules of Practice and Procedure," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
| |
|
| |
|
| Sincerely,
| | To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver or excusal requests (if any) (Office of Management and Budget (OMB) approval number 3150-0090) at least 60 days before the first examination date (if able). Mr. Larson should be contacted to determine the method for submission of the waiver and/or excusal requests. |
| /RA/ Vincent G. Gaddy, Chief Operations Branch Division of Reactor Safety Docket Nos.
| |
|
| |
|
| 50-445, 50-446 License Nos.
| | Preliminary reactor operator and senior reactor operator license applications (OMB approval number 3150-0090) and medical certifications (OMB approval number 3150-0024) should be submitted at least 30 days before the first examination date. |
|
| |
|
| NPF-87, NPF-89 Enclosure s: 1. Examination Report 05000445/2018301; 05000446
| | If the preliminary applications are not received at least 30 days before the examination date, a postponement may be necessary. Final signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date. |
| /2018301
| |
|
| |
|
| ===w/Attachment:===
| | Although the minimum guidelines for receiving waiver or excusal requests is 30 days before the first examination date (preliminary) and 14 days before the first examination date (final), the requests should be submitted as early in the process as possible (see the 60-day guideline above). Resolutions resulting from verbal inquiries by the licensee to the NRC are not binding. Submittals addressing waivers and/or excusals should be in writing (i.e., on NRC Form 398, or as directed by Mr. Lars on when contacted to determine the method for submission). The NRC's final decision on whether to grant a waiver or excusal will be documented on the final (not preliminary) NRC Form 398 submitted for the applicant and will not be provided until the final application is submitted to the NRC. |
| Supplemental Information 2. NRC Post Examination Comment Resolution COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2
| |
| - NRC EXAMINATION REPORT 05000445/2018301; 05000 446/2018301 DATED AUGUST 1, 2018 DISTRIBUTION: | |
| KKennedy, RA SMorris, DRA AVegel, DRP MShaffer, DRS JClark, DRS RLantz, DRP DCylkowski, RC JJosey, DRP RKumana, DRP MHaire, DRP RAlexander, DRP AAthar, DRP LNewman, DRP LReyna, DRP JBowen, RIV/OEDO VDricks, ORA JWeil, OCA MO'Banion, NRR AMoreno, RIV/CAO BMaier, RSLO JBridges, OB GGeorge, IPAT PJayroe, DRP/IPAT MHerrera, DRMA R4Enforcement
| |
|
| |
|
| REGION IV Docket Nos.: 50-445, 50-446 License Nos.: NPF-87, NPF-89 Report No s.: 05000445/2018301; 0500044 6/2018301 Licensee: Vistra Operations Company LLC Facility: Comanche Peak Nuclear Power Plant, Units 1 and 2 Location: Glen Rose, Texas Dates: June 11 - July 19 , 201 8 Inspectors:
| | Paperwork Reduction Act Statement This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). |
| K. Clayton, Chief Examiner, Senior Operations Engineer J. Kirkland , Senior Operations Engineer C. Osterholtz, Senior Operations Engineer M. Hayes, Operations Engineer Approved By:
| | These information collections were approved by the Office of Management and Budget, approval number 3150-0018. The burden to the public for these mandatory information collections is estimated to average 400 hours per examination or response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collection. |
| Vincent G. Gaddy, Chief Operations Branch Division of Reactor Safety
| |
|
| |
|
| 2
| | You may submit comments on any aspect of the information collection, including suggestions for reducing the burden, to FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington , DC 20555-0001, or by electronic mail to INFOCOLLECTS.RESOURCE@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503. |
|
| |
|
| =SUMMARY=
| | Public Protection Notification The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid OMB control number. In accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Agency Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC's Agencywide Documents Access and Management System (ADAMS). |
| ER 05000 445/2018301; 05000 446/2018301; June 11 - July 19 , 2018; Comanche Peak Nuclear Power Plant, Units 1 and 2; Initial Operator Licensing Examination Report.
| |
|
| |
|
| NRC examiners evaluated the competency of six applicants for reactor operator licenses, six applicants for instant senior reactor operator licenses and three applicant s for upgrade senior reactor operator license at Comanche Peak Nuclear Power Plant, Units 1 and 2
| | ADAMS is accessible from the Electronic Reading Room page of the NRC's public Web Site at http://www.nrc.gov/reading-rm/adams.html |
| . The NRC developed the examinations using NUREG | | . Thank you for your cooperation in this matter. Mr. Ruby has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Lars on at 817-200-1 1 72 or myself at 817-200-1159. |
| -1021, "Operator Licensing Examination Standards for Power Reactors," Revision 11. The written examination was administered by the licensee on June 20, 2018. NRC examiners administered the operating tests on June 11 - 17, 2018. The examiners determined that fourteen of the fifteen applicants satisfied the requirements of 10 CFR Part 55, and the appropriate licenses have been issued.
| |
|
| |
|
| ===A. NRC-Identified and Self-Revealing Findings===
| | Sincerely, |
| | | /RA/ Vincent G. Gaddy, Chief Operations Branch Division of Reactor Safety Dockets: 50-445; 50-446 Licenses: NPF-87; NPF-89 cc: Electronic Distribution |
| None.
| |
| | |
| ===B. Licensee-Identified Violations===
| |
| | |
| None.
| |
| | |
| 3
| |
| | |
| =REPORT DETAILS=
| |
| | |
| ==OTHER ACTIVITIES (OA)==
| |
| {{a|4OA5}}
| |
| ==4OA5 Other Activities (Initial Operator License Examination)==
| |
| | |
| ===.1 License Applications===
| |
| | |
| ====a. Scope====
| |
| NRC examiners reviewed all license application s submitted to ensure each applicant satisfied relevant license eligibility requirements.
| |
| | |
| Examiners also audited three of the license applications in detail to confirm that they accurately reflected the subject applicant's qualifications. This audit focused on the applicant's experience and on
| |
| -the-job training, including control manipulations that provided significant reactivity changes.
| |
| | |
| ====b. Findings====
| |
| No findings were identifie d.
| |
| | |
| ===.2 Examination Development===
| |
| | |
| ====a. Scope====
| |
| The NRC developed the written exam and operating tests in accordance the requirements of NUREG
| |
| -1021. The NRC examination team conducted an on
| |
| -site validation of the operating tests.
| |
| | |
| ====b. Findings====
| |
| No findings were identified.
| |
| | |
| ===.3 Operator Knowledge and Performance===
| |
| | |
| ====a. Scope====
| |
| On June 20, 2018, the licensee proctored the administration of the written examinations to all applicants. The licensee staff graded the written examinations, analyzed the results, and presented their analysis and post examination comments to the NRC on June 25, 2018
| |
| . The NRC examination team administered the various portions of the operating test s to all applicants on June 11 - 17, 2018.
| |
| | |
| ====b. Findings====
| |
| No findings were identified.
| |
| | |
| All applicants passed the written examination and fourteen of fifteen applicants passed all portions of the operating test. The final written examination s and post examination analysis and comments may be accessed in the ADAMS system under the accession numbers noted in the attachment.
| |
| | |
| The examination team note d five generic weaknesses associated with applicant performance on the operating tests. All of the weaknesses were attributed to knowledge weaknesses on the topic and included the following items:
| |
| 1. Several crews (2/4) could not adequately determine a fuel failure event was in progress during a scenario
| |
| . 2. Several applicants (3/4) could not adequately operate the control room ventilation system. 3. Applicants had difficulty with anti-pump features of handswitches and their associated breakers
| |
| . 4. Several crews (3/4) had difficulty diagnosing a faulted a nd ruptured steam generator during a scenario.
| |
| | |
| 5. Several crews struggled with proper communications during the scenario s.
| |
| | |
| The licensee identified five generic weaknesses associated with applicant performance on the written examinations. All of the weaknesses were attributed to knowledge weaknesses on the topic and included the following items:
| |
| 1. Applicants were unfamiliar with design features of the containment sump
| |
| . 2. Applicants were unfamiliar with Abnormal Procedure ABN
| |
| -901, Fire Protection System Alarms or Malfunctions | |
| . 3. Applicants had difficulty recalling safety-related battery capacities.
| |
| | |
| 4. Applicants were unfamiliar with the immediate operability requirements regarding fuel oil for the emergency diesel generators and their Technical Specification requirements (day tank requirements).
| |
| | |
| 5. Applicants had difficulty determining what system to use during emergency procedures to lower containment hydrogen during a Loss of Coolant Accident
| |
| . Copies of all individual examination reports were sent to the facility Training Manager for evaluation and determination of appropriate remedial training.
| |
| | |
| The licensee generated Issue Report IR-2018-004425 for resolution of all operating test and written examination generic weaknesses.
| |
| | |
| ===.4 Simulation Facility Performance===
| |
| | |
| ====a. Scope====
| |
| The NRC examiners observed simulator performance with regard to plant fidelity during examination validation and administration.
| |
| | |
| ====b. Findings====
| |
| No findings were identified.
| |
| | |
| ===.5 Examination Security===
| |
| | |
| ====a. Scope====
| |
| The NRC examiners reviewed examination security for examination development during both the onsite preparation week and examination administration week for compliance with 10 CFR 55.49 and NUREG-1021. Plans for simulator security and applicant control were reviewed and discussed with licensee personnel.
| |
| | |
| ====b. Findings====
| |
| No findings were identified.
| |
| | |
| 4OA 6 Meetings, Including Exit
| |
| | |
| ===Exit Meeting Summary===
| |
| | |
| The chief examiner presented the preliminary examination results to M r. Thomas McCool, Site Vice President, and other members of the staff on June 15, 2018. A telephonic exit was conducted on July 19, 2018 between Mr. K. Clayton, Chief Examiner, and M s. Donna Christiansen, Training Director
| |
| . The licensee did not identify any information or materials used during the examination as proprietary.
| |
| | |
| =SUPPLEMENTAL INFORMATION=
| |
| | |
| ==KEY POINTS OF CONTACT==
| |
| | |
| ===Licensee Personnel===
| |
| : [[contact::T. McCool]], Site Vice President
| |
| : [[contact::D. Christiansen]], Training Director
| |
| : [[contact::J. Lloyd]], Operations Support Manager
| |
| : [[contact::J. Ruby]], Exam Developer
| |
| | |
| ===NRC Personnel===
| |
| : [[contact::J. Josey]], Senior Resident Inspector
| |
| | |
| ==ADAMS DOCUMENTS REFERENCED==
| |
|
| |
|
| | ML18309A350 SUNSI Review: |
| | ADAMS: Non-Publicly Available Non-Sensitive Keyword: By: VGaddy Yes No Publicly Available Sensitive NRC-002 OFFICE SOE:OB C:OB NAME BLarson VGaddy SIGNATURE /RA/ /RA/ DATE 11/05/18 11/05/18 |
| }} | | }} |
|
---|
Category:Letter
MONTHYEARCP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 IR 05000445/20230042024-01-29029 January 2024 Integrated Inspection Report 05000445/2023004 and 05000446/2023004 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) ML24024A2102024-01-29029 January 2024 Summary of Regulatory Audit Regarding a License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML24025A0052024-01-25025 January 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report ML24023A0242024-01-24024 January 2024 Correction to Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident Methodology ML24018A1072024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000445/2024012 and 05000446/2024012) and Request for Information ML23159A2082023-12-20020 December 2023 Request for Withholding Information from Public Disclosure ML23319A3872023-12-20020 December 2023 Issuance of Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident (Fsloca) Methodology ML23348A2392023-12-19019 December 2023 Nonacceptance of License Amendment Request to Relocate Technical Specification 3.9.3, Nuclear Instrumentation, to the Technical Requirements Manual CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 ML23333A0872023-12-13013 December 2023 Transmittal of Dam Safety Inspection Report - Public CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 ML23313A0732023-12-0606 December 2023 Issuance of Amendment Nos. 184 and 184 Regarding Revision to Technical Specifications to Implement WCAP-17661-P-A, Rev. 1, Improved Roac and CAOC Fq Surveillance Technical Specifications ML23291A4382023-11-30030 November 2023 Notice of Availability of the Draft Plant-Specific Supplement 60, to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Comanche Peak Nuclear Power Plant, Unit Numbers 1 and 2, License Renewal Applica ML23325A0182023-11-30030 November 2023 Schedule Revision for the License Renewal Application Review IR 05000445/20234022023-11-30030 November 2023 NRC Security Inspection Report 05000445/2023402 and 05000446/2023402 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation ML23308A0032023-11-17017 November 2023 Letter to R. Nelson, Executive Director; Achp; Re., Comanche Peak Draft Environmental Impact Statement ML23308A0022023-11-17017 November 2023 Letter to M. Wolfe, Executive Director; Shpo; Re., Comanche Peak Draft Environmental Impact Statement ML23317A3002023-11-13013 November 2023 Letter to R. Sylestine, Chairman, Alabama-Coushatta Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2972023-11-13013 November 2023 Letter to R. Martin, President, Tonkawa Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2872023-11-13013 November 2023 Letter to J. Garza, Chairman, Kickapoo Traditional Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2832023-11-13013 November 2023 Letter to D. Dotson, President, Delaware Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2852023-11-13013 November 2023 Letter to E. Martinez, President, Mescalero Apache Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23306A0302023-11-13013 November 2023 Letter to J. Cernek, Chairman; Coushatta Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2902023-11-13013 November 2023 Letter to M. Pierite, Chairman, Tunica Biloxi Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2982023-11-13013 November 2023 Letter to R. Morrow, Town King, Thlopthlocco Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2842023-11-13013 November 2023 Letter to D. Kaskaske, Chairman, Kickapoo Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2822023-11-13013 November 2023 Letter to D. Cooper, Chairman, Apache Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2962023-11-13013 November 2023 Letter to M. Woommavovah, Chairman, Comanche Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2812023-11-13013 November 2023 Letter to C. Hoskin, Principal Chief, Cherokee Nation; Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2862023-11-13013 November 2023 Letter to J. Bunch, Chief, United Keetoowah Band of Cherokee Indians Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3032023-11-13013 November 2023 Letter to W. Yargee, Chief, Alabama-Quassarte Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2882023-11-13013 November 2023 Letter to L. Johnson, Chief, Seminole Nation of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3012023-11-13013 November 2023 Letter to S. Yahola, Mekko, Kialegee Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2792023-11-13013 November 2023 Letter to B. Gonzalez, Chairman, Caddo Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3022023-11-13013 November 2023 Letter to T. Parton, President, Wichita and Affiliated Tribes Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2892023-11-13013 November 2023 Letter to L. Spottedbird, Chairman, Kiowa Indian Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23360A6312023-10-26026 October 2023 FEMA, Submittal of Radiological Emergency Preparedness Final Report for the Comanche Peak Nuclear Power Plant Medical Services Drill Evaluated on August 23, 2023 CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23263A0242023-09-21021 September 2023 Revision of Schedule for the Environmental Review of the Comanche Peak Nuclear Power Plant Units 1 and 2 License Renewal Application 2024-01-31
[Table view] Category:License-Operator
MONTHYEARML23262A9942023-06-22022 June 2023 CP-2023-06 Public Forms ML23226A2342023-06-22022 June 2023 Post Exam Comments and Analysis with Letter CP-202200219, (Cpnpp), NRC Form 536, Operator Licensing Examination Data for Calendar Years 2023, 2024, 2025, and 20262022-05-18018 May 2022 (Cpnpp), NRC Form 536, Operator Licensing Examination Data for Calendar Years 2023, 2024, 2025, and 2026 ML21299A0192021-09-23023 September 2021 2021-08-DRAFT Outline Comments ML21285A0392021-09-23023 September 2021 CP-2021-08-Post Exam Comments ML21299A0452021-09-23023 September 2021 CP-2021-08-Public Forms ML21285A0372021-09-23023 September 2021 CP-2021-08-FINAL Operating Test ML21299A0252021-09-23023 September 2021 CP-2021-08-FINAL Outlines ML21299A0202021-09-23023 September 2021 CP-2021-08-DRAFT Outlines ML21299A0212021-09-23023 September 2021 CP-2021-08-DRAFT Written Exam Comments ML21299A0222021-09-23023 September 2021 CP-2021-08-DRAFT Written Exam ML21299A0232021-09-23023 September 2021 CP-2021-08-FINAL Make Up Op Test Outlines ML21299A0242021-09-23023 September 2021 CP-2021-08-FINAL Make Up Op Test ML21299A0182021-09-23023 September 2021 CP-2021-08-DRAFT Operating Test ML21299A0152021-09-23023 September 2021 CP-2021-08-DRAFT Make Up Op Test Outlines ML21299A0162021-09-23023 September 2021 CP-2021-08-DRAFT Make Up Op Test ML21299A0172021-09-23023 September 2021 CP-2021-08-DRAFT Operating Test Comments ML21299A0142021-09-23023 September 2021 CP-2021-08-DRAFT Make Up Op Test Outline Comments ML21285A0382021-09-23023 September 2021 CP-2021-08-FINAL Written Exam ML21299A0132021-09-23023 September 2021 CP-2021-08-DRAFT Make Up Op Test Comments CP-202100570, (CPNPP) - Initial Operator Licensing Examination2021-08-24024 August 2021 (CPNPP) - Initial Operator Licensing Examination CP-202100559, (CPNPP) - Initial Operator Licensing Examination2021-08-17017 August 2021 (CPNPP) - Initial Operator Licensing Examination ML20174A6052020-05-21021 May 2020 05 Draft Outline Comments ML20174A6072020-05-21021 May 2020 05 Draft Written Examination Comments.Pdf ML20174A6102020-05-21021 May 2020 05 Final Written Examination ML20174A6062020-05-21021 May 2020 05 Draft Outlines ML20174A6092020-05-21021 May 2020 05 Final Outlines ML20174A6082020-05-21021 May 2020 05 Draft Written Examination ML19011A3712019-01-10010 January 2019 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2019 ML18309A3502018-11-0505 November 2018 Notification of NRC Initial Operator Licensing Examination 05000445/2018301 and 05000446/2019301 IR 05000445/20183012018-11-0505 November 2018 Notification of NRC Initial Operator Licensing Examination 05000445/2018301 and 05000446/2019301 ML18157A0602018-06-0606 June 2018 NRC Initial Operator Licensing Examination Approval 05000445/2018301; 050000446/2018301 CP-201800217, Transmittal of NRC Form 536, Licensed Operator Examination Data2018-04-18018 April 2018 Transmittal of NRC Form 536, Licensed Operator Examination Data ML18086B0842018-02-16016 February 2018 Facility Cover Letter - Riv - March 2018 - GFE ML18009A9852018-01-0808 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17179A0032017-06-19019 June 2017 2017-06-DRAFT Operating Test Comments ML17179A0072017-06-19019 June 2017 2017-06-DRAFT Written Exam Comments ML17179A0062017-06-19019 June 2017 2017-06-DRAFT Outlines ML17179A0052017-06-19019 June 2017 2017-06-DRAFT Outline Comments ML17198B2822017-06-19019 June 2017 2017-06-Public Forms ML17179A3462017-06-19019 June 2017 2017-06-Post Examination Comments ML17179A0102017-06-19019 June 2017 2017-06-FINAL Outlines ML17179A0082017-06-19019 June 2017 2017-06-DRAFT Written Exam ML17179A0112017-06-19019 June 2017 2017-06-FINAL Written Exam CP-201700402, Response to RIS 2017-032017-04-28028 April 2017 Response to RIS 2017-03 ML17013A5482017-01-13013 January 2017 Generic Fundamentals Section of the Written Operator Licensing Examination Scheduled for 2017 ML16262A0372016-07-18018 July 2016 2016-07 Final Operating Test 2023-06-22
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML23226A2342023-06-22022 June 2023 Post Exam Comments and Analysis with Letter ML23262A9942023-06-22022 June 2023 CP-2023-06 Public Forms CP-202200219, (Cpnpp), NRC Form 536, Operator Licensing Examination Data for Calendar Years 2023, 2024, 2025, and 20262022-05-18018 May 2022 (Cpnpp), NRC Form 536, Operator Licensing Examination Data for Calendar Years 2023, 2024, 2025, and 2026 ML21299A0252021-09-23023 September 2021 CP-2021-08-FINAL Outlines ML21299A0212021-09-23023 September 2021 CP-2021-08-DRAFT Written Exam Comments ML21299A0192021-09-23023 September 2021 2021-08-DRAFT Outline Comments ML21299A0182021-09-23023 September 2021 CP-2021-08-DRAFT Operating Test ML21299A0232021-09-23023 September 2021 CP-2021-08-FINAL Make Up Op Test Outlines ML21299A0172021-09-23023 September 2021 CP-2021-08-DRAFT Operating Test Comments ML21299A0152021-09-23023 September 2021 CP-2021-08-DRAFT Make Up Op Test Outlines ML21285A0392021-09-23023 September 2021 CP-2021-08-Post Exam Comments ML21299A0142021-09-23023 September 2021 CP-2021-08-DRAFT Make Up Op Test Outline Comments ML21299A0132021-09-23023 September 2021 CP-2021-08-DRAFT Make Up Op Test Comments ML21285A0372021-09-23023 September 2021 CP-2021-08-FINAL Operating Test ML21285A0382021-09-23023 September 2021 CP-2021-08-FINAL Written Exam ML21299A0222021-09-23023 September 2021 CP-2021-08-DRAFT Written Exam ML21299A0242021-09-23023 September 2021 CP-2021-08-FINAL Make Up Op Test ML21299A0452021-09-23023 September 2021 CP-2021-08-Public Forms ML21299A0162021-09-23023 September 2021 CP-2021-08-DRAFT Make Up Op Test ML21299A0202021-09-23023 September 2021 CP-2021-08-DRAFT Outlines CP-202100570, (CPNPP) - Initial Operator Licensing Examination2021-08-24024 August 2021 (CPNPP) - Initial Operator Licensing Examination ML20174A6062020-05-21021 May 2020 05 Draft Outlines ML20174A6052020-05-21021 May 2020 05 Draft Outline Comments ML20174A6072020-05-21021 May 2020 05 Draft Written Examination Comments.Pdf ML20174A6082020-05-21021 May 2020 05 Draft Written Examination ML20174A6092020-05-21021 May 2020 05 Final Outlines ML20174A6102020-05-21021 May 2020 05 Final Written Examination IR 05000445/20183012018-11-0505 November 2018 Notification of NRC Initial Operator Licensing Examination 05000445/2018301 and 05000446/2019301 ML18309A3502018-11-0505 November 2018 Notification of NRC Initial Operator Licensing Examination 05000445/2018301 and 05000446/2019301 ML18157A0602018-06-0606 June 2018 NRC Initial Operator Licensing Examination Approval 05000445/2018301; 050000446/2018301 CP-201800217, Transmittal of NRC Form 536, Licensed Operator Examination Data2018-04-18018 April 2018 Transmittal of NRC Form 536, Licensed Operator Examination Data ML18009A9852018-01-0808 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17179A0072017-06-19019 June 2017 2017-06-DRAFT Written Exam Comments ML17179A0112017-06-19019 June 2017 2017-06-FINAL Written Exam ML17198B2822017-06-19019 June 2017 2017-06-Public Forms ML17179A0082017-06-19019 June 2017 2017-06-DRAFT Written Exam ML17179A0062017-06-19019 June 2017 2017-06-DRAFT Outlines ML17179A3462017-06-19019 June 2017 2017-06-Post Examination Comments ML17179A0032017-06-19019 June 2017 2017-06-DRAFT Operating Test Comments ML17179A0052017-06-19019 June 2017 2017-06-DRAFT Outline Comments ML17179A0102017-06-19019 June 2017 2017-06-FINAL Outlines CP-201700402, Response to RIS 2017-032017-04-28028 April 2017 Response to RIS 2017-03 ML16262A0382016-07-18018 July 2016 2016-07 Final Written Exams ML16262A0372016-07-18018 July 2016 2016-07 Final Operating Test ML16262A0362016-07-18018 July 2016 2016-07 Post-Exam Comments and Analysis ML16293A9712016-07-11011 July 2016 2016-07 Proposed Outline Comments ML16293A9722016-07-11011 July 2016 2016-07 Proposed Written Exam 2023-06-22
[Table view] |
Text
November 5, 201 8 Ken J. Peters, Senior Vice President and Chief Nuclear Officer Attention: Regulatory Affairs Vistra Operations Company LLC P.O. Box 1002 Glen Rose, TX 76043 SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT
- NOTIFICATION OF NRC INITIAL OPERATOR LICENSING EXAMINATION 05000445/201 9 301 AND 05000446/201 9 301
Dear Mr. Peters:
In a telephone conversation on October 24, 201 8, between Messrs. J. Ruby , Examination and Simulator Supervisor, and B. Lars on, Chief Examiner, arrangements were made for the administration of licensing examinations at Comanche Peak Nuclear Power Plant during the week of June 10, 201 9. As agreed during the telephone conversation, your staff will prepare the examinations based on the guidelines in Revision 11 to NUREG-1021, "Operator Licensing Examination Standards for Power Reactors
." The NRC's regional office will discuss with your staff any changes that might be necessary before the examinations are administered.
To meet the above schedule, it will be necessary for your staff to furnish the operating test outlines by January 7, 2019. The written examination outlines were provided to your staff on September 18, 2018.
The written examinations, operating tests, and supporting reference materials identified in Attachment 3 to ES-201 will be due by March 25, 2019. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (CFR), an authorized representative of the facility licensee shall approve the examinations and tests before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use. We request that any personal, proprietary, sensitive unclassified, or Safeguards Information in your response be contained in a separate enclosure and appropriately marked. Delays in receiving the required materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be cancelled or rescheduled. In addition, your support for onsite validation of the examinations is required during the week of May 6, 2019.
To conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests, along with any video and audio recordings of the dynamic operating tests
, until the NRC takes licensing action on all the applications and any adjudicatory actions on any hearing demands are complete.
Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver or excusal requests (if any) (Office of Management and Budget (OMB) approval number 3150-0090) at least 60 days before the first examination date (if able). Mr. Larson should be contacted to determine the method for submission of the waiver and/or excusal requests.
Preliminary reactor operator and senior reactor operator license applications (OMB approval number 3150-0090) and medical certifications (OMB approval number 3150-0024) should be submitted at least 30 days before the first examination date.
If the preliminary applications are not received at least 30 days before the examination date, a postponement may be necessary. Final signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date.
Although the minimum guidelines for receiving waiver or excusal requests is 30 days before the first examination date (preliminary) and 14 days before the first examination date (final), the requests should be submitted as early in the process as possible (see the 60-day guideline above). Resolutions resulting from verbal inquiries by the licensee to the NRC are not binding. Submittals addressing waivers and/or excusals should be in writing (i.e., on NRC Form 398, or as directed by Mr. Lars on when contacted to determine the method for submission). The NRC's final decision on whether to grant a waiver or excusal will be documented on the final (not preliminary) NRC Form 398 submitted for the applicant and will not be provided until the final application is submitted to the NRC.
Paperwork Reduction Act Statement This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).
These information collections were approved by the Office of Management and Budget, approval number 3150-0018. The burden to the public for these mandatory information collections is estimated to average 400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br /> per examination or response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collection.
You may submit comments on any aspect of the information collection, including suggestions for reducing the burden, to FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington , DC 20555-0001, or by electronic mail to INFOCOLLECTS.RESOURCE@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.
Public Protection Notification The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid OMB control number. In accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Agency Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the Electronic Reading Room page of the NRC's public Web Site at http://www.nrc.gov/reading-rm/adams.html
. Thank you for your cooperation in this matter. Mr. Ruby has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Lars on at 817-200-1 1 72 or myself at 817-200-1159.
Sincerely,
/RA/ Vincent G. Gaddy, Chief Operations Branch Division of Reactor Safety Dockets: 50-445; 50-446 Licenses: NPF-87; NPF-89 cc: Electronic Distribution
ML18309A350 SUNSI Review:
ADAMS: Non-Publicly Available Non-Sensitive Keyword: By: VGaddy Yes No Publicly Available Sensitive NRC-002 OFFICE SOE:OB C:OB NAME BLarson VGaddy SIGNATURE /RA/ /RA/ DATE 11/05/18 11/05/18