Attachment 6 OBDI 202 - IOLE Process Rev 3 PROPOSED OUTLINE COMMENTS Facility:

CPNPP First Exam Date:

9/23/2021 Written Exam Outline N/A Comment Resolution 1 N/A Administrative JPM Outline Sep 23, 2021 Comment Resolution 1

RA4: Determine escorted radiation worker allowable dose was on the June 2017 exam. Was it significantly modified? Was it randomly selected?

CPNPPs last two exams were in 2019 and 2018. The 2017 exam was three exams ago.

This JPM was randomly selected from the CPNPP bank and then checked to see if it was on the past two exams. It was not on the past two exams so it was treated as a direct from bank JPM and NOT modified.

2 SA2: Perform a Shutdown Margin Calculation was arguably two exams ago, on the June 2014 exam, was it significantly modified/randomly selected?

CPNPPs last two exams were in 2019 and 2018. The 2014 exam was six exams ago.

The JPM was randomly selected from the CPNPP bank and then checked to see if it was on the past two exams. It was not on the past two exams so it was treated as a direct from bank JPM and then modified to ensure the calculations are not the same as the bank version.

3 SA5: Classify an Emergency Plan event (SO1136) is on the Aug 2021 exam and the June 2017 exam, and the June 2014 exam - was it significantly modified for each exam or randomly selected?

Classify an Emergency Plan Event is just the title of the JPM. There are dozens of JPMs with that title in the CPNPP bank and they all fall under the same task SO1136.

This is a modified JPM that has the same title and task but a completely different EAL call than the other bank JPMs.

Control Room / In-Plant System JPM Outline Sep 23, 2021 Comment Resolution 1

S6 Respond to feedwater flow instrument failure was on the June 2014 exam (arguably 2 exams ago). Was it significantly modified or randomly selected?

CPNPPs last two exams were in 2019 and 2018. The 2014 exam was six exams ago.

The JPM was randomly selected from the CPNPP bank and then checked to see if it

OBDI 202 - IOLE Process Rev 3 was on the past two exams. It was not on the past two exams so it was treated as a direct from bank JPM and NOT modified.

Simulator Scenario Outline Comments (Date)