ML17348A280: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 64: | Line 64: | ||
>)p REVISION 1 TURPSÃPOINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING 3.4 EDG SYSTEM AUXILIARIES TESTING The tests outlined in this Section are run to assure that the individual components (previously tested)are capable of performing as a total system.These tests are performed as prerequisites to the testing described in Section 5.0.3.4.1 Coolin Water/Lube Oil Kee Warm S stems With both the lube oil and cooling water system filled and vented, the AC circ lube oil and turbo lube oil pumps are checked (See 3.4.4)..The cooling water immersion heater is also checked for proper operation. | >)p REVISION 1 TURPSÃPOINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING 3.4 EDG SYSTEM AUXILIARIES TESTING The tests outlined in this Section are run to assure that the individual components (previously tested)are capable of performing as a total system.These tests are performed as prerequisites to the testing described in Section 5.0.3.4.1 Coolin Water/Lube Oil Kee Warm S stems With both the lube oil and cooling water system filled and vented, the AC circ lube oil and turbo lube oil pumps are checked (See 3.4.4)..The cooling water immersion heater is also checked for proper operation. | ||
The system is operated in this mode to check the lube oil and cooling water temperatures at the lube oil cooler outlet and internally to the engine.The system operation is tested with the DC pumps in service as 1 previously done with the AC pumps.The pump auto start functions are checked during the AC pump to DC pump changeovers. | The system is operated in this mode to check the lube oil and cooling water temperatures at the lube oil cooler outlet and internally to the engine.The system operation is tested with the DC pumps in service as 1 previously done with the AC pumps.The pump auto start functions are checked during the AC pump to DC pump changeovers. | ||
3.4.2 Startin Air S stem with Air Com ressors, ers and Alarms Startup of the air start system consists of checking the following four areas: a.The motor and diesel driven air compressors are run individually and checked for proper operation of the compressors and functional checks of the instrumentation. | |||
====3.4.2 Startin==== | |||
Air S stem with Air Com ressors, ers and Alarms Startup of the air start system consists of checking the following four areas: a.The motor and diesel driven air compressors are run individually and checked for proper operation of the compressors and functional checks of the instrumentation. | |||
b.The air dryer systems are run and checked for proper operation, and functional checks are performed of all alarms and control systems.The dryers are checked to verify that the air is at an acceptable dew point at the receivers. | b.The air dryer systems are run and checked for proper operation, and functional checks are performed of all alarms and control systems.The dryers are checked to verify that the air is at an acceptable dew point at the receivers. | ||
c.The air barring device is checked for proper operation by rotating the engine.The alarm and interlock is also checked.d.The air supply system is checked for proper operation, including testing of the starting air receivers and the associated instrumentation. | c.The air barring device is checked for proper operation by rotating the engine.The alarm and interlock is also checked.d.The air supply system is checked for proper operation, including testing of the starting air receivers and the associated instrumentation. | ||
Line 89: | Line 91: | ||
This is to assure that condensation does not take place in the lube oil sump and also to assure that the engine is at a temperature where a rapid start followed with fast loading will not be detrimental to the EDG.The lube oil flow as well as differential pressure across the lube oil filter is verified.3-8 1'i+,>t'A REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM EKQLNCEMENT REPORT SUPPLEMENT NO 1: TESTING 3.6.5 Lube Oil and Pre-lube S stem The AC and DC lube oil pumps (circulating and turbo)are operated and motor data are recorded.The temperature switches, level switches, pressure switches and differential pressure switches are shown to be functional. | This is to assure that condensation does not take place in the lube oil sump and also to assure that the engine is at a temperature where a rapid start followed with fast loading will not be detrimental to the EDG.The lube oil flow as well as differential pressure across the lube oil filter is verified.3-8 1'i+,>t'A REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM EKQLNCEMENT REPORT SUPPLEMENT NO 1: TESTING 3.6.5 Lube Oil and Pre-lube S stem The AC and DC lube oil pumps (circulating and turbo)are operated and motor data are recorded.The temperature switches, level switches, pressure switches and differential pressure switches are shown to be functional. | ||
Each annunciator is actuated and verified to annunciate at the local control panel.Lube oil flow to the turbocharger and engine bearings is verified to assure that the prelubrication system is working e f fee tively.The lube oil sump low level alarm is functionally tested.3.6.6 Radiator Fan S stem The operation of the radiators and fans, temperature regulation valve and expansion tank are observed when the EDG is in operation. | Each annunciator is actuated and verified to annunciate at the local control panel.Lube oil flow to the turbocharger and engine bearings is verified to assure that the prelubrication system is working e f fee tively.The lube oil sump low level alarm is functionally tested.3.6.6 Radiator Fan S stem The operation of the radiators and fans, temperature regulation valve and expansion tank are observed when the EDG is in operation. | ||
3.6.7 Genera tor The generator standby heater circuit is checked for operability and heater current is recorded.0233L/3-9 | |||
====3.6.7 Genera==== | |||
tor The generator standby heater circuit is checked for operability and heater current is recorded.0233L/3-9 | |||
'f II ll IJ E REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM ENHANCEMENT REPORT SUPPLEM1%T NO 1: TESTING 4.1.1 Cubicle S ace Heater Bus Each cubicle space heater is demonstrated to be operable when the space heater bus is energized. | 'f II ll IJ E REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM ENHANCEMENT REPORT SUPPLEM1%T NO 1: TESTING 4.1.1 Cubicle S ace Heater Bus Each cubicle space heater is demonstrated to be operable when the space heater bus is energized. | ||
4.1.2 125V DC Control Power The load side of each 125V DC fuse within each cubicle is demonstrated to be energized with the 125V DC control power distribution bus energized free of grounds, and all undervoltage alarms reset.4.1.3 Bus 3D (4D)Volta e Monitorin Voltmeter, voltmeter selector switch, bus undervoltage detection circuitry, annunciation and SPDS voltage input are tested to assure proper operation of the bus voltage monitoring equipment. | 4.1.2 125V DC Control Power The load side of each 125V DC fuse within each cubicle is demonstrated to be energized with the 125V DC control power distribution bus energized free of grounds, and all undervoltage alarms reset.4.1.3 Bus 3D (4D)Volta e Monitorin Voltmeter, voltmeter selector switch, bus undervoltage detection circuitry, annunciation and SPDS voltage input are tested to assure proper operation of the bus voltage monitoring equipment. | ||
Line 109: | Line 113: | ||
HCC 4C Some loads are moved to MCC 4D.No individual testing is required as a result of these modifications. | HCC 4C Some loads are moved to MCC 4D.No individual testing is required as a result of these modifications. | ||
4.6 4.6.1 125V DC SYSTEM MODIFICATIONS New DC Panels Six (6)125V DC panels are added.The load side of each 125V DC breaker or fuse for each branch circuit is demonstrated to be energized free of grounds, and all undervoltage alarms reset.0233L/4-6 I C>>Le 4' REVISION 1%HUG%POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEM19iT NO 1!TESTING 4.6.2 New Batte Char rs Two (2)new Battery Chargers are added.The battery charger remote bypass control switch is removed from the Unit 3/4 control consoles.The new battery chargers are permanently connected to their associated 480V MCC source, and tested to ensure proper operation and to ensure that they function in accordance with design.4.6.3 New DC Transfer Switches Two (2)new DC transfer switches are added at the 3D (4D)switch-gears.The new transfer switches are tested to ensure proper operation. | 4.6 4.6.1 125V DC SYSTEM MODIFICATIONS New DC Panels Six (6)125V DC panels are added.The load side of each 125V DC breaker or fuse for each branch circuit is demonstrated to be energized free of grounds, and all undervoltage alarms reset.0233L/4-6 I C>>Le 4' REVISION 1%HUG%POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEM19iT NO 1!TESTING 4.6.2 New Batte Char rs Two (2)new Battery Chargers are added.The battery charger remote bypass control switch is removed from the Unit 3/4 control consoles.The new battery chargers are permanently connected to their associated 480V MCC source, and tested to ensure proper operation and to ensure that they function in accordance with design.4.6.3 New DC Transfer Switches Two (2)new DC transfer switches are added at the 3D (4D)switch-gears.The new transfer switches are tested to ensure proper operation. | ||
4.7 EMERGENCY BUS LOADIM'EQUENCERS Testing commences upon completion of the necessary modifications to existing sequencers 3C23A, 4C23A, 3C23B,&4C23B.New sequencers 3C23A-1, 4C23A-1, 3C23B-1, 6 4C23B-1 are installed and wired as required to power supplies, annunciation and associated equipment to make each sequencer ready for testing.0 Existin (Modified) | |||
===4.7 EMERGENCY=== | |||
BUS LOADIM'EQUENCERS Testing commences upon completion of the necessary modifications to existing sequencers 3C23A, 4C23A, 3C23B,&4C23B.New sequencers 3C23A-1, 4C23A-1, 3C23B-1, 6 4C23B-1 are installed and wired as required to power supplies, annunciation and associated equipment to make each sequencer ready for testing.0 Existin (Modified) | |||
Emer nc Bus Zoadin Se uencers Sequencers'C23A (Train A), 3C23B (Train B), 4C23A (Train A)and 4C23B (Train B)These existing sequencers no longer play an active role in the bus stripping and sequencing of load, however they are tested in conjunction with the new sequencers, as described in Subsection 4.7.2 below.4.7.2 New Emer nc Bus Loadin Se uencers Sequencers 3C23A-1 (Train 3A), 3C23B-1 (Train B)>4C34A-1 (Train A)and 4C23B-1 (Train B)Auto, or continuous, testing as well as manual testing via test selector switches demonstrate proper functions. | Emer nc Bus Zoadin Se uencers Sequencers'C23A (Train A), 3C23B (Train B), 4C23A (Train A)and 4C23B (Train B)These existing sequencers no longer play an active role in the bus stripping and sequencing of load, however they are tested in conjunction with the new sequencers, as described in Subsection 4.7.2 below.4.7.2 New Emer nc Bus Loadin Se uencers Sequencers 3C23A-1 (Train 3A), 3C23B-1 (Train B)>4C34A-1 (Train A)and 4C23B-1 (Train B)Auto, or continuous, testing as well as manual testing via test selector switches demonstrate proper functions. | ||
Bus stripping logic is demonstrated to respond to real or test inputs placing the.sequencer in the correct mode of operation. | Bus stripping logic is demonstrated to respond to real or test inputs placing the.sequencer in the correct mode of operation. | ||
Line 119: | Line 125: | ||
Existing bus clearing relays located at the 4kV switchgear are actuated and demonstrated to be tested via the new sequencer test selector switches and monitoring pilot lights.The existing remaining sequencer equipment, including power supplies,'uses, relays, etc., is tested and demonstrated to function as part of the integrated bus stripping/loading scheme.The Reactor Coolant Pump backup underfrequency relaying scheme, including annunciation, is demonstrated to function as intended.4.8 ASSIGNMENT OP EXISTINQ EDGs 19 UNIT 3 Preoperational testing begins after completion of the necessary prerequisites as applicable to per-train testing.Some examples of the prerequisites are: o Main control room control console and vertical panel modifica-tions, including relabeling, new metering, new meter scales, controls, indication and annunciation. | Existing bus clearing relays located at the 4kV switchgear are actuated and demonstrated to be tested via the new sequencer test selector switches and monitoring pilot lights.The existing remaining sequencer equipment, including power supplies,'uses, relays, etc., is tested and demonstrated to function as part of the integrated bus stripping/loading scheme.The Reactor Coolant Pump backup underfrequency relaying scheme, including annunciation, is demonstrated to function as intended.4.8 ASSIGNMENT OP EXISTINQ EDGs 19 UNIT 3 Preoperational testing begins after completion of the necessary prerequisites as applicable to per-train testing.Some examples of the prerequisites are: o Main control room control console and vertical panel modifica-tions, including relabeling, new metering, new meter scales, controls, indication and annunciation. | ||
o Modifications to EDG 4.16kV circuit breaker controls.o Modifications to EDG protective and lockout relaying.o MCC Telemand transfer schemes removed.o New 480V swing load center installed and tested.o New MCCs installed and tested, including new and relocated 480V loads.o Existing bus loading sequencers modified.o New bus loading sequencers connected and ready to operate.o Proper starting, operation and loading of the EDGs from their respective sequencers is demonstrated. | o Modifications to EDG 4.16kV circuit breaker controls.o Modifications to EDG protective and lockout relaying.o MCC Telemand transfer schemes removed.o New 480V swing load center installed and tested.o New MCCs installed and tested, including new and relocated 480V loads.o Existing bus loading sequencers modified.o New bus loading sequencers connected and ready to operate.o Proper starting, operation and loading of the EDGs from their respective sequencers is demonstrated. | ||
4.8.1 Train 3A Modifications Existing EDG A is assigned and relabeled as EDG"3A" and all power, controls, indication and metering associated with the existing"A" machine at Unit 4 are removed and/or disconnected (to be reutilized I.for new EDG 4A per Section 4.9).0233L/4-8 tp'p h Cl REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM ENELNCEMENT REPORT SUPPLEMENT NO 1: TESTING Additional testing to verify proper functional separation of the EDG and Tra'in alignment is performed as part of the'integrated enhanced Emergency Power System testing, per Sections 6.0 and 7.0.4.8.2 Train 4A modifications are discussed in Subsection 4.9.1, below.Train 3B Modifications Existing EDG B is assigned and relabeled as EDG"3B" and all power, controls, indication and metering associated with the existing"B" machine at Unit 4 is removed and/or disconnected. | |||
====4.8.1 Train==== | |||
3A Modifications Existing EDG A is assigned and relabeled as EDG"3A" and all power, controls, indication and metering associated with the existing"A" machine at Unit 4 are removed and/or disconnected (to be reutilized I.for new EDG 4A per Section 4.9).0233L/4-8 tp'p h Cl REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM ENELNCEMENT REPORT SUPPLEMENT NO 1: TESTING Additional testing to verify proper functional separation of the EDG and Tra'in alignment is performed as part of the'integrated enhanced Emergency Power System testing, per Sections 6.0 and 7.0.4.8.2 Train 4A modifications are discussed in Subsection 4.9.1, below.Train 3B Modifications Existing EDG B is assigned and relabeled as EDG"3B" and all power, controls, indication and metering associated with the existing"B" machine at Unit 4 is removed and/or disconnected. | |||
This also includes any alternate shutdown panel modifications and testing.Additional testing is performed to verify proper separation. | This also includes any alternate shutdown panel modifications and testing.Additional testing is performed to verify proper separation. | ||
Verification is performed as part of the Enhanced Emergency Power System testing, per Sections 6.0 and 7.0.4.9 Train 4B modifications are discussed in Subsections 4.9.1 and 4.9.2.ASSIGNMENT OF NEW EDGs 10 UNIT 4 Preoperational testing, on a per-train basis, begins after completion of the necessary prerequisites as applicable to per-train testing.Some examples of the prerequisites are: 0 0 Hain control room control console and vertical panel modifications, including relabeling, new metering, new meter scales, controls, indication and annunciation. | Verification is performed as part of the Enhanced Emergency Power System testing, per Sections 6.0 and 7.0.4.9 Train 4B modifications are discussed in Subsections 4.9.1 and 4.9.2.ASSIGNMENT OF NEW EDGs 10 UNIT 4 Preoperational testing, on a per-train basis, begins after completion of the necessary prerequisites as applicable to per-train testing.Some examples of the prerequisites are: 0 0 Hain control room control console and vertical panel modifications, including relabeling, new metering, new meter scales, controls, indication and annunciation. |
Revision as of 10:32, 18 October 2018
ML17348A280 | |
Person / Time | |
---|---|
Site: | Turkey Point |
Issue date: | 05/31/1990 |
From: | FLORIDA POWER & LIGHT CO. |
To: | |
Shared Package | |
ML17348A279 | List: |
References | |
PROC-900531, NUDOCS 9006120231 | |
Download: ML17348A280 (78) | |
Text
-'0 FLORIDA POWER 5 LIGHT COMPANY TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT PROJECT TESTING REPORT REVISION 1 MAY 1990 9006i202'3i 900604 PDR ADOCK 050002 0 F PDC kv'E k'5 1p,~l TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANC199$
T REPORT SUPPLEMENT NO 1: TESTING REVISION 1 TABLE OF CONTENTS SECTION TITIE PAGE COVER SHEET 1.0 2.0 2.1 2.2 TABLE OP CONTENTS INTRODUCTION PURPOSE AND SCOPE OP TESTING PURPOSE OF TESTING SCOPE OF TESTING 2-1 2-1 2-1 3.0 3.1 3.2 3.3 3.4 3.5 3.6~.o 4.2 4.3 4'4.5 4.6 4.7 4.8 4.9 5.0 5.1 5.2~6.0 7.0 7.1 7.2 7.3 STARTUP TESTING MECHANICAL COMPONENTS TESTING ELECTRICAL COMPONENTS TESTING INSTRUMENTATION AND CONTROL COMPONENTS TESTING EDG SYSTEM AUXILIARIES TESTING EDG SUPPORT SYSTEM TESTING INITIAL EDGs OPERATION AND CHECKOUT ELECTRICAL SYSTEM STARTUP/PREOPERATIONAL TESTING~16 kV SWING SWITCHGEAR D D 480V SWING LOAD CENTER 3H (4H)MODIFICATION OF EXISTING 480V LOAD CENTERS NEW 480V MCCs AND RELOCATED LOADS MODIFICATION OP EXISTING 480V MCCs 125V DC SYSTEM MODIFICATIONS EMERGENCY BUS LOADING SEQUENCERS ASSIGNMENT OF EXISTING EDGs TO UNIT 3 ASSIGNMENT OP NEW EDGs TO UNIT 4 EDG PREOPERATIONAL TESTING PART 1-LOCAL EDG OPERATIONS PART 2-REMOTE EDG OPERATIONS VERIPICATION OP PROPER LO~ROUP ASSIGNMENTS INTEGRATED ACCEPTANCE TESTING INCLUDING SAFEGUARDS TESTING UNITS 3 AND TRAIN"A" AND"B" MODIFICATIONS INTEGRATED PREOPERATION TEST=ACCEPTANCE CRITERIA 3-1 3-1 3-3 3-3 3-4 3-7 4-1 4-1 4-3 4-4 4-5 4-5 4-6 4-7 4-8 4-9 5-1 5-1 5-2 6-1 7-1 7-1 7-1 7-4
REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING TABLE OF CONTENTS Continued SECTION 8.0 9.0 TITLE CONFORMANCE TO NRC REGULATORY GUIDES RELATED TO TESTING'EFERENCES PAGE 8-1 9-1 PIGURE LIST OF FIGURE AC ONE-LINE DIAGRAM I~<I~Et n<
REVISION 1 TURKEY POINT UNITS 3 AND 4 EM1RGENCY POWER SYSTEM EQQLNCEMENT REPORT SUPPIB9KNT NO 1 TESTING INTRODUCTION Florida.Power&Light (FPL)is installing two new Emergency Diesel Generators (EDGs)and associated electrical and mechanical equipment at the Turkey Point Nuclear site, as documented in the report enclosed with FPL letter L-88-269 dated June 23, 1988 and as revised by FPL letter submitted under separate cover.This Supplement 81 initially transmitted by FPL letter~9-124 dated April 3, 1989, provided additional information regarding the testing to be performed on the various components and systems during turnover and startup, during preoperational testing and the.testing performed to return to service.Normal inservice testing is governed by the Turkey Point In-Service Test (IST)Program and the Plant Technical Specifications.
This submittal is Revision 1 to Supplement 81 of the Turkey Point EPS Enhancement Report.It provides updated information for various aspects of the EPS Enhancement Prospect test program requirements.
This Supplement is divided into nine sections.Following this introductory section, Section 2.0 outlines the purpose and scope of the testing described herein.Section 3.0 discusses the Startup testing required to make the EDGs ready for preoperational testing and power operation.
Section 4.0 describes the Preoperational Testing of the enhanced Emergency Power System components (AC and DC)such as switchgear, load centers, etc.Section 5.0 discusses the Preoperational Testing of the new EDGs and their auxiliaries.
Section 6.0 describes the testing performed to verify proper load-group assignments.
Section 7.0 discusses the Integrated Testing to be performed to bring both Units back to power operation from the dual-Unit outage condition.
Section 8.0 outlines the conformance to various Regulatory Guides related to testing, then Section 9.0 provides a list of references used in the preceeding discussions.
1-1 i4 e REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING 2.0 PURPOSE AND SCOPE OF TESTING 2.1 PURPOSE OF TESTING The test program outlined in this Supplement describes the engineering
~requirements to provide additional assurance (f ollowing factory testing of the components) that the EPS Enhancement modifications have been properly designed as well as verification that the installation of associated systems and components has been accomplished in accordance with the design.Successful completion of this testing program provides the necessary assurance that the enhanced EPS will operate in accordance with the applicable design and licensing requirements.
2 02 SCOPE OF TESTING The Emergency Power System Enhancement testing covers the entire range of testing of equipment, components and systems, as outlined in this Supplement.
New equipment (Emergency Diesel Generators (EDGs), 4.16 kV switchgear, 480V load centers, 480V motor control centexs, 125V DC panels, bat tery charge ra, sequencers, etc.)is being designed, fabricated and installed at the Turkey Point site to interface with existing equipment and systems, and the existing equipnent and systems are being modified as required to result in an enhanced onsite Emergency Power System.The installation of new equipment, and the modification of existing equipment, is accomplished under FPL's controlled Plant Change/Modification (PC/M)process'he test program requirements, outlined herein, encompass the scope of events that begins with completion of system/component construction and installation, and ends with completion of integrated acceptance testing.This testing submittal defines the engineering requirements to fully demonstrate the operability of the enhanced EPS.It is not intended to necessarily specify the required sequence or order of test implementation at Turkey Point.The end result, an enhanced onsite AC Emergency Power System, therefore focuses the discussions contained herein to the testing of the new EDGs and the enhanced onsite electrical, distribution system.Equal importance and attention is given by FPL to testing of the other equipment and systems being installed as a part of this prospect, particuLarly as part of the erection of a new EDG Building and new Diesel Oil Storage Tank Enclosure, but is not detailed in this supplement.
Such additional testing includes the extensions of the Fire Protection, Lighting, HVAC, and Communications Systems in the new EDG buildings, testing of the idle start modifications to the existing EDGs, and testing of the new spare battery.These systems are tested using additional testing procedures which supplement the existing testing and surveillance procedures for the existing equi'pnent and systems.2-1"
\'t I$~'t I*ifJf, REVISION 1 TURKEY POINT UNITS 3 AND 4 EM1KGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING A description of the shop qualification testing performed on the new EDGs was provided in FPL letter L-88&54, dated October 19, 1988~Based on that letter and additional in f ormation, the NRC provided FPL an SER enclosed with NRC letter dated August 10, 1989, whereby the Staff found the 30 Start and Load Test acceptable.
In addition, FPL provided respons'es to the NRC's Requests for Additional Information (RAIs), related to the new EDGs and the enhanced EPS.The NRC RAIs were transmitted in letters dated January 6, 1989 and March 16, 1990.FPL's responses were provided in letters L&9-54, L&9-107, and L-90-140.The above information supplements the information pxovided in this Testing Submittal.
The testing described in this Supplement covers the following tests of the EDGs and the EPS: Onsite Startup (Installation)
Testing, including testing performed under the direction/cognizance of the Factory Service Representative (Section 3.0)Onsite Startup Testing of Initial Operation of the New EDGs and Their Auxiliaries (Section 3.0)Onsite Preoperational Testing for the New EDGe and the Enhanced EPS (Sections 4.0 and 5.0)Onsite Integrated Testing of the EDGs and EPS (Section 6.0)including performance of the Integrated Safeguards Testing prior to bringing one or both Units back on line (Section 7.0)2-2
'44Iy C l'1p REVISION 1 0 3.0 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPl226MP NO 1: TESTING STARTUP TESTING The testa described in Sections 3.1, 3.2 and 3.3 below are performed on individual components and systems as prerequisites for startup and preoperational testing of the systems as a whole.Startup Testing is conducted under the direction of the Turkey Point Startup Superintendent.
A Morrison~udsen field service representative is on site for this portion of the testing and acts as a consultant reporting to the Startup Superintendent.
The Startup Superintendent is assisted by Mechanical, Electrical and I&C engineering disciplines and crafts.3.1 MECHANICAL COMPONENTS TESTING This section includes the checkout of individual pieces of equipment.
This equipment is tested as a system as discussed in Section 3.4 below.3.1.1 EDG Cooling Water S stem The EDG Cooling Water System is shipped dry without any preservative in the piping.The engine portion of the Cooling Water System is protected with a rust inhibitor.
The system is flushed per a startup flush procedure and is then filled with an appropriate coolant pez the manufacturer's recommendation for normal operation.
The fan and motors on the radiators are checked for proper operation.
3.1.2 EDG Startin Air S stem The EDG Starting Air System consists of two air compxessors, one electric driven and one diesel driven, one air dryer, four air receivers, four air start motors and the associated valves,.instrumentation and piping.These components are tested for proper opexation.
3.1.2.1 En ne Air Barri Device The engine air barring device is operated.The barring device limit switches are checked for proper operation and indication.
3.1.3 EDG Fuel Oil Transfer S stem The new Fuel Oil Transfer System consists of two new fuel oil storage tanks and two new fuel oil transfer pumps and the associated piping.3-1 f,p REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM EKGLNCEMENT REPORT SUPPLEMENT NO 1 TESTING The quality of the fuel oil is tested and verified per existing plant procedures prior to being put into the storage tanks from'a fuel oil tanker.The'two transfer pumps are run to supply fuel oil to the day tanks.The pressure drop across the fuel oil transfer pump suction strainers is monitored while pumps are in operation.
The Diesel Oil Storage Tanks are checked for cleanliness.
Flow is established from the Diesel Oil Storage Tanks through all new piping to ensure adequate flushing.The new fuel oil transfer pumps and motors are checked for proper operation.
.Each pump is checked for pressure and flow.Biseline data, for future In-Service Testing, is documented.
The level instrumentation of the storage and day tanks is functionally checked.EDG Fuel Oil S stems The suction piping to the DC priming pump is filled and vented, and proper operation of the DC fuel priming pump is verified.EDG Lube Oil S stems The engine skid and the lube oil sump are checked f or cleanliness.
The lube oil, turbo oil and auxiliary turbo oil filters are checked for proper operation.
The lube oil pump motors are bumped for rotation and then checked for proper operation.
The engine box oil strainers are inspected for cleanliness and correct installation.
The lube oil system is operated using the two AC and two DC pumps.I Each motor driven pump is operated individually to verify acceptable system pressure.All instrumentation is checked for proper operation.
Cl V'-II'l)I H y5 4f 4 REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING 3.1.6 EDG Governor H draulic S stem The governor casing is inspected for cleanliness and filled with manufacturer's recommended fluid.3.1.7 EDG En ine Combustion and Exhaust Air The combustion air piping is checked for cleanliness from the air filter to the turbocharger.
The exhaust air piping is checked for cleanliness at the exhaust air line and the outlet of the turbocharger.
3.1.8 EDG Building Ventilation S stem Motors are bumped for rotation and checked for proper lubrication and proper operation.
Fans are checked for operating speed, differential pressure across the fan and total air flow.Motor data and air flow data are taken to evaluate the performance of the fans.3.2 ELEC%ICAL COMPONENTS TESTING The major system or component electrical testing is completed as discussed in Sect1on 4.0 below.As a prerequisite to Section 4.0 preoperational testing, the following items are checked as appropriate:
a.Continuity check the wiring for motors, electrical power distribution equipment such as switchgears and panels, MCCs and control circuits.b.Megger generators, motors and power distribution equipment.
c.Phase check generators and motors.d.Trace protective device and control circuits, check terminations and calibrate instrumentation.
e.Check of all loop circuits and components for proper function.3.3 INSTRUMENTATION AND CONTROL COMPONENTS TESTING I&C testing is integrated into system testing in Section 3.4 below.As a prerequisite to the EDG System Auxiliaries testing, the fo1lowing items are checked as appropriate:
a.Calibrate pressure switches, temperature switches, level switches and pressure, temperature and level gauges.b.Check control cabinet instruments and logic.napery/3-3
>)p REVISION 1 TURPSÃPOINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING 3.4 EDG SYSTEM AUXILIARIES TESTING The tests outlined in this Section are run to assure that the individual components (previously tested)are capable of performing as a total system.These tests are performed as prerequisites to the testing described in Section 5.0.3.4.1 Coolin Water/Lube Oil Kee Warm S stems With both the lube oil and cooling water system filled and vented, the AC circ lube oil and turbo lube oil pumps are checked (See 3.4.4)..The cooling water immersion heater is also checked for proper operation.
The system is operated in this mode to check the lube oil and cooling water temperatures at the lube oil cooler outlet and internally to the engine.The system operation is tested with the DC pumps in service as 1 previously done with the AC pumps.The pump auto start functions are checked during the AC pump to DC pump changeovers.
3.4.2 Startin
Air S stem with Air Com ressors, ers and Alarms Startup of the air start system consists of checking the following four areas: a.The motor and diesel driven air compressors are run individually and checked for proper operation of the compressors and functional checks of the instrumentation.
b.The air dryer systems are run and checked for proper operation, and functional checks are performed of all alarms and control systems.The dryers are checked to verify that the air is at an acceptable dew point at the receivers.
c.The air barring device is checked for proper operation by rotating the engine.The alarm and interlock is also checked.d.The air supply system is checked for proper operation, including testing of the starting air receivers and the associated instrumentation.
t~g r~ii REVISION 1 TUR1UK POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING 3.4.3 Fuel Oil Transfer S stem 3.4.3.1 Fuel Oil Transfer Pum The pump f or each new diesel oil storage tank is.operated on recirculation through the bypass line.Fuel oil is transferred from storage tank 4A to storage tank 4B.The tank indicators and alarms are checked for proper operation.
In addition, all flow meters are verified operational.
The storage tank 4B transfer pump is operated and verification tests similar to those of the 4A tank are performed.
During each pump operation, the suction duplex strainers are operated to verify that they can be changed in service.Each individual pump is operated to check proper transfer function from the other storage tank.When operability of the existing EDGs will permit, the cross-connect capability between the new fuel storage system and the existing fuel storage system is demonstrated.
3.4.4 Fuel Oil Da Tank The day tank is filled using a fuel oil transfer pump.All tank level indicators, alarms and auto fill functions are checked for proper oper'ation.
3.4.5 Lube Oil and Prelube S stem Operation and startup testing of the lube oil system consists of two portions: the motor driven pumps and systems and the shaft driven pumps and systems.The initial testing is the operation of the.four motor driven pumps I and the functional testing of their alarms and control interlocks.
The pumps are checked for proper operation.
0233L/3-5 f'I 1 K 4 REVISION 1 TUR1KY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENQLNCEMENT REPORT SUPPLENQFZ NO 1: TESTING The shaf t-driven pumps and lube system are tes ted f or proper operation when the diesel engine is operated and tested.3.4.6.EDG Buildin Ventilation S stem System function testing consists of operation of the fans to verify their proper operation.
This test ensures that building heat can be removed while the diesel engine is shut down.Building and engine heat is removed by the radiator fan system during EDG operation and is tested in section 3.6.3.5 3.5.1 NEW EDGs CONTROL SYSTEMS TESTING Simulated EDG 0 ration Without running the engine, EDG operation is simulated at the local I control panel so all EDG start and trip functions can be tested.3.5.1.1 Emergency Start Signals The emergency diesel generator starts are tested for proper operation via simulated emergency start signals for various plant conditions, with each possible position of the normal/isolate, local/remote, and auto-start bypass switch positions.
The following signals are simulated:
i-Station loss of power signal (LOOP)ii-Engineered Safeguards Actuation Signal (SI)3.5.1.2 Emergency Stop/Trip Signals I The following emergency trips are verified to opexate in the normal (test)mode as well as in the emergency mode (LOOP and SI).Overspeed Generator Differential, Phase A Generator Differential, Phase B Generator Differential, Phase C Emergency Stop Pushbuttons
'k~'I 4\Oy l~e+~lp Cg~
REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ESDLNCEMENT REPORT SUPPLEMENT NO 1: TESTING 3.5.1.3 EDG Equipment Protection Trip Signals The following signals will shut down the EDG in the normal (test)mode of operation.
These trips are verified to be bypassed in an emergency mode.Ttd.s testing is simulated at the local control panel.Crankcase High Pressure Cooling Water Low Pressure Lube Oil Temperature High Exhaust Temperature High Cooling Water Temperature High Generator Overcurrent Phase A Generator Overcurrent Phase B Generator Overcurrent Phase C Generator Reverse Power Generator Loss of Excitation Generator Underfrequency Engine High Vibration Main Manifold Lube Oil Low Pressure Piston Cooling Oil Low Pressure 3.6 INITIAL EDGs OPERATION AND CHECKOUTThe EDGs are run to check proper operation, and the automatic operation of the system auxiliaries, such as, AC lube oil pump, cooling water fans, ventilation fans, etc., are verified to be functional.
Vibration levels of aU.new EDG support systems piping are observed at different load levels of the diesel generator.
Any excessive vibration levels are analyzed to determine the cause of vibration and effective means of.eliminating it (e.g., additional supports).
The acceptance criteria for vibration testing is per ASME OM-1987, Part 3, including addenda OMa-1988.4 The temperatures of the cylinder exhaust gases are recorded to assure that the theraocouples aud their circuits are operatioasl acd that the diesel engine is operating properly.3.6.1 Starti Air S stem 3.6.1.1 Air Compressor Performance Test The motor driven air compressors are operated to verify that the auto"one f f" f unctions properly to maintain required ai r receiver pressure.Motor data is recorded.The diesel driven air compressor is also tested to verify that the auto"loadmnload" function of the aachanical unloader also maintains the air receivers within the proper pressure range.0233L/3-7
, 4'I I+II H r,7 REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPU96PZ NO 1: TESTING During compressor operation, vibration data and operating speed (RPM), are recorded as baseline data.Capacity testing of the electric compressor will be performed as described in Section 5.1.2.3.6.1.2 Air Dryer Performance Test~The air dryer dewpoint is measured to determine maximum moisture content of the air in the air receivers.
3.6.1.3 Barring Device The barring device is checked for operability along with its interlocks.
3.6.1.4 Instrumentation All water detectors, pressure switches and alarms and their annunciation are checked at the local control panel.3.6.2 Fuel Oil Transfer S stem~~The fuel oil transfer pumps and their associated motors are checked to obtain operational characteristics such as flow.The auto"start-stop" function based on day tank level is also verified.The suction strainer is shifted to the duplex side while the pump is in operation and the pressure drop across the strainer is recorded.All annunciators are checked at the local control panel 3.6.3 DC Fuel Oil Primin The startmtop function of the DC fuel oil priming pump is checked and the engine pressures are recorded.I 3.6.4 Lube Oil/Coolin Water Kee-Warm S stem The keep-warm system is operated to assure that the lube oil, cooling water and engine are generally maintained at temperatures above their surroundings.
This is to assure that condensation does not take place in the lube oil sump and also to assure that the engine is at a temperature where a rapid start followed with fast loading will not be detrimental to the EDG.The lube oil flow as well as differential pressure across the lube oil filter is verified.3-8 1'i+,>t'A REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM EKQLNCEMENT REPORT SUPPLEMENT NO 1: TESTING 3.6.5 Lube Oil and Pre-lube S stem The AC and DC lube oil pumps (circulating and turbo)are operated and motor data are recorded.The temperature switches, level switches, pressure switches and differential pressure switches are shown to be functional.
Each annunciator is actuated and verified to annunciate at the local control panel.Lube oil flow to the turbocharger and engine bearings is verified to assure that the prelubrication system is working e f fee tively.The lube oil sump low level alarm is functionally tested.3.6.6 Radiator Fan S stem The operation of the radiators and fans, temperature regulation valve and expansion tank are observed when the EDG is in operation.
3.6.7 Genera
tor The generator standby heater circuit is checked for operability and heater current is recorded.0233L/3-9
'f II ll IJ E REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM ENHANCEMENT REPORT SUPPLEM1%T NO 1: TESTING 4.1.1 Cubicle S ace Heater Bus Each cubicle space heater is demonstrated to be operable when the space heater bus is energized.
4.1.2 125V DC Control Power The load side of each 125V DC fuse within each cubicle is demonstrated to be energized with the 125V DC control power distribution bus energized free of grounds, and all undervoltage alarms reset.4.1.3 Bus 3D (4D)Volta e Monitorin Voltmeter, voltmeter selector switch, bus undervoltage detection circuitry, annunciation and SPDS voltage input are tested to assure proper operation of the bus voltage monitoring equipment.
4.1.4 Bus 3D (4D)Lockout Rela Features The new lockout relays 186/3D (186/4D)are functionally tested for proper operation, including indications and alarms, for the various combinations of the normal/isolate selector switches.~~4.1.5 Functional Testin of Associated Circuit Breakers The circui t breakers no ted below are tested f or intended f unc tions and proper operation of interlocks; refer to Figure 1 for a depiction of the ties.As appropriate, new phase overcurrent relays, current transformers, ammeter and ammeter selector switches are demonstrated to be correctly calibrated and operable.The following are functionally checked: annunciation, breaker indication, closing and tripping circuits with the circuit breaker racked-in, rackedmut in test, locally, remote, etc.4.1.5.1 Bus 3D (4D)Tie Circuit Breakers at Existing Buses A and B: Bus A Circuit Breakers Bus B Circuit Breakers 4.1.5.2 Bus 3D (4D)Tie Circuit Breakers: Train A Tie Circuit Breakers Train B Tie Circuit Breakersnoser./4-2 l IP t~, a t'7'g I REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING 4.1.5.3 Bus 3D/4D Station Blackout (SBO)Tie Circuit Breakers.The EPS enhancement prospect intends to provide a design which complies with 10CFR50.63 and meets the provisions of Regulatory Guide 1.155, by providing a crosstie between Unit 3 and Unit 4 such that one of the four EDGs serves as an Alternate AC power source for a Unit which is encountering a station blackout event.This topic is described in FPL letter L-89-144 dated April 17, 1989 which addressed the schedular and information requirements of 10CFR50~63.Testing of these circuit breakers is performed similarly to the tie breaker testing above.4.1.5.4 Motor Feeder Circuit Breakers: CCW Pump 3C (4C)Circuit Breakers ICW Pump 3C (4C)-Circuit Breakers Spare Circuit Breakers 4.2 480V SWIlC LOAD CENT&.3H AND 4H 0 The new 480V load centers 3H (4H)are installed in the new Electrical Equipment Room.Startup testing commences as outlined below upon completion of the appropriate interfaces required to support the tests.4.2.1 Cubicle S ace Heater Bus Each cubicle space heater is demonstrated to be operable when the space heater bus is energized.
4.2.2 125V DC Control Power The load side of each 125V DC fuse within each cubicle is demonstrated to be energized with the 125V DC control power distribution bus energized free of grounds, and all undervoltage alarms reset.4.2.3 LC 3H (4H)Volta e Monitorin Voltmeter, voltmeter selector switch, undervoltage relays, annunciation and SPDS voltage input via voltage transducer are tested to assure proper operation.
4-3 JI , 1'V a~CJ kc I 444 I N 1I' REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM E%QLNCEMENT REPORT SUPPLEMENT NO 1: TESTING 4.2.4 Functional Testin of Associated Circuit Breakers The circuit breakers noted below are tested for intended functions and proper operation of interlocks similar to the testing described in 4.1.5 above.4.2.4.1 Bus 3H (4H)Tie Circuit Breakers at Existing Load Centers: a.Circuit Breakers Located in the Existing Load Center 3C (4C)Train A Since the I C 3C (4C)compartment spaces have no breakers, the compartment is refurbished to accept new breaker(s).
b.Circui t Breakers Located in the Existing Load Center 3D (4D)Train B Since the LC 3D (4D)compartment spaces have no breakers, the compartment is refurbished to accept new breaker(s).
4 2.4.2 Bus 3H (4H)Tie Circuit Breakers a.Circuit Breakers Located in the New Load Center 3H (4H)providing the Train'A'ie b.Circuit Breakers Located in the New Load Center 3H (4H)providing the Train'B'ie 4.2.4.3 Circuit Breakers for Charging Pump 3C (4C)located in new Load Center 3H (4H)4.2.4.4 Circuit Breakers for MCC 3D (4D)Located in New Load Center 3H (4H)4.2.4.5 Spare Circuit Breakers: (Four spare cubic1es do not require any testing at this time since no breaker is installed.)
4.3 MODIFICATION
OF EXISTIlC 480V LOAD CENTERS 4.3.1 Load Centers 3A (4A)Circuit Breakers located in the Existing Load Center 3A (4A)The existing compartment is refurbished to accept a new breaker.The closing and tripping circuits are functionally checked with the circuit breaker racked-in and rackedmut in test.4.3.2 Load Centers 3B (4B)No changes are made to Load Center 3B (4B), thus no individual testing is required; g'I'I l I REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPUKENT NO 1: TESTING 4.3.3 Load Center 3C (4C)The feed to the charging pump is moved to new Load Center 3H (4H).Some loads are moved to MCC 3D (4D).Load Center undervoltage relaying is modified to replace certain relays associated with bus undervoltage annunciation and tripping of non-vital feeder breakers.These modifications are tested.'.3.4 Load Center 3D (4D)The"B" train Telemand transfer to MCC 3A (4A)is eliminated and the breakers are used for MCC 3K and MCC 4K.The closing and tripping circuits are functionally checked with the circuit breaker racked-in and rackedmut in test.Load Center undervoltage relaying is modified to replace certain relays associated with bus undervoltage annunciation and tripping of non-vital feeder breakers.These modifications are tested.4.4 NEW 480V MOTOR CONTROL CENTERS (MCCs)AND RELOCATED LOADS4.4.1 Each cubicle space heater is demonstrated to operate when the space heater bus is energized.
Incoming line breakers and lighting panel circuit breakers are molded case and are checked for function-ality.Each new MCC and its relocated load is tested to ensure proper operation.
The new MCCs are listed below;refer to Figure 1 as appropriate.
MCC 3K Located in existin EDG Building Ttd.s HCC feeds EDG 3B loads.4.4.2 MCC 4D This MCC is located in the new electrical room.4.4.3 MCC 4 J This MCC is located in the new EDG Building and feeds Diesel Generator 4A loads plus other miscellaneous loads.4.4'MCC 4K TM.s MCC is located in the new EDG Building and feeds Diesel Generator 4B loads plus other miscellaneous loads.4.5 MODIFICATION OF EXISTINQ 480 VOLT MCCs The modifications made to the existing MCCs are outlined below.Testing of the modifications on each MCC is performed as necessary to ensure proper operation.
Refer to Figure 1 as appropriate.
4-5 I+4 s REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEM1KT REPORT SUPPLEMENT NO 1: TESTING 4.5.1 HCC 3A Removal of Telemand transfer operators, control wiring and removal of tie from Load Center 3D.Some loads are moved to MCC 3D.No startup/preoperational testing is required at this stage;see Section 6.0.4.5.2 MCC 3B Some loads are moved to MCC 3D.No individual testing is required as a result of these modifications.
4.5.3 MCC 3C No individual testing is required.4.5.4 MCC 3D I 4.5.5 MCC D is relabeled MCC 3D and the Telemand operator is removed.The vital section feeders from Load Center 4C, and Load Center 3D, are removed and MCC 3D resupplied from Load Center 3H (see Section 4.2.4.1).All Unit 4 loads from vital section are moved to Unit 4 and these compartments are left as spares.Unit 3 loads from MCCs 3A and 3B are repowered from MCC 3D.MCC 4A Removal of Telemand transfer operators, control wiring and removal of tie from Load Center 4D.Some loads are moved to MCC 4D.No testing is required as a result of these modifications.
4.5.6 HCC 4B 4.5.7 Modification involves removal of EDG 3B auxiliary loads and transfer of these to MCC 3K (see Subsection 4.4.1).The motor starter compartments are left as spares.A transfer switch for Control Room AC"A" is added to this MCC and tested for operability.
HCC 4C Some loads are moved to MCC 4D.No individual testing is required as a result of these modifications.
4.6 4.6.1 125V DC SYSTEM MODIFICATIONS New DC Panels Six (6)125V DC panels are added.The load side of each 125V DC breaker or fuse for each branch circuit is demonstrated to be energized free of grounds, and all undervoltage alarms reset.0233L/4-6 I C>>Le 4' REVISION 1%HUG%POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEM19iT NO 1!TESTING 4.6.2 New Batte Char rs Two (2)new Battery Chargers are added.The battery charger remote bypass control switch is removed from the Unit 3/4 control consoles.The new battery chargers are permanently connected to their associated 480V MCC source, and tested to ensure proper operation and to ensure that they function in accordance with design.4.6.3 New DC Transfer Switches Two (2)new DC transfer switches are added at the 3D (4D)switch-gears.The new transfer switches are tested to ensure proper operation.
4.7 EMERGENCY
BUS LOADIM'EQUENCERS Testing commences upon completion of the necessary modifications to existing sequencers 3C23A, 4C23A, 3C23B,&4C23B.New sequencers 3C23A-1, 4C23A-1, 3C23B-1, 6 4C23B-1 are installed and wired as required to power supplies, annunciation and associated equipment to make each sequencer ready for testing.0 Existin (Modified)
Emer nc Bus Zoadin Se uencers Sequencers'C23A (Train A), 3C23B (Train B), 4C23A (Train A)and 4C23B (Train B)These existing sequencers no longer play an active role in the bus stripping and sequencing of load, however they are tested in conjunction with the new sequencers, as described in Subsection 4.7.2 below.4.7.2 New Emer nc Bus Loadin Se uencers Sequencers 3C23A-1 (Train 3A), 3C23B-1 (Train B)>4C34A-1 (Train A)and 4C23B-1 (Train B)Auto, or continuous, testing as well as manual testing via test selector switches demonstrate proper functions.
Bus stripping logic is demonstrated to respond to real or test inputs placing the.sequencer in the correct mode of operation.
All output/blocking relays are monitored at the connected 4kV and 480 V-control circuits to assure correct operation.
Bus lockout relay signals are similarily monitored.
0233L/4-7
'+I 41 V' REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER=-SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING Load sequencing logic is demonstrated to respond to real or test inputs.Particular time delays are verified by measuring and recording the output signals and their signal duration to assure correct operation and loading of equipment for each particular mode of operation.
Input signals to the sequencers are verified to meet design requirements.
Existing bus clearing relays located at the 4kV switchgear are actuated and demonstrated to be tested via the new sequencer test selector switches and monitoring pilot lights.The existing remaining sequencer equipment, including power supplies,'uses, relays, etc., is tested and demonstrated to function as part of the integrated bus stripping/loading scheme.The Reactor Coolant Pump backup underfrequency relaying scheme, including annunciation, is demonstrated to function as intended.4.8 ASSIGNMENT OP EXISTINQ EDGs 19 UNIT 3 Preoperational testing begins after completion of the necessary prerequisites as applicable to per-train testing.Some examples of the prerequisites are: o Main control room control console and vertical panel modifica-tions, including relabeling, new metering, new meter scales, controls, indication and annunciation.
o Modifications to EDG 4.16kV circuit breaker controls.o Modifications to EDG protective and lockout relaying.o MCC Telemand transfer schemes removed.o New 480V swing load center installed and tested.o New MCCs installed and tested, including new and relocated 480V loads.o Existing bus loading sequencers modified.o New bus loading sequencers connected and ready to operate.o Proper starting, operation and loading of the EDGs from their respective sequencers is demonstrated.
4.8.1 Train
3A Modifications Existing EDG A is assigned and relabeled as EDG"3A" and all power, controls, indication and metering associated with the existing"A" machine at Unit 4 are removed and/or disconnected (to be reutilized I.for new EDG 4A per Section 4.9).0233L/4-8 tp'p h Cl REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM ENELNCEMENT REPORT SUPPLEMENT NO 1: TESTING Additional testing to verify proper functional separation of the EDG and Tra'in alignment is performed as part of the'integrated enhanced Emergency Power System testing, per Sections 6.0 and 7.0.4.8.2 Train 4A modifications are discussed in Subsection 4.9.1, below.Train 3B Modifications Existing EDG B is assigned and relabeled as EDG"3B" and all power, controls, indication and metering associated with the existing"B" machine at Unit 4 is removed and/or disconnected.
This also includes any alternate shutdown panel modifications and testing.Additional testing is performed to verify proper separation.
Verification is performed as part of the Enhanced Emergency Power System testing, per Sections 6.0 and 7.0.4.9 Train 4B modifications are discussed in Subsections 4.9.1 and 4.9.2.ASSIGNMENT OF NEW EDGs 10 UNIT 4 Preoperational testing, on a per-train basis, begins after completion of the necessary prerequisites as applicable to per-train testing.Some examples of the prerequisites are: 0 0 Hain control room control console and vertical panel modifications, including relabeling, new metering, new meter scales, controls, indication and annunciation.
Modifications to EDG 4.16kV circuit breaker controls.Modifications to EDG protective and lockout re1aying.MCC telemand transfer schemes removed.New 480V swing load center installed and tested.New MCCs installed and tested, including new and relocated 480V loads.Existing bus loading sequencers modified.New bus loading sequencers connected and ready to operate.Proper starting, operation and loading of the.EDGs from their respective seguencers is demonstrated.
4-9 P II jt,'
REVISION 1 TURREY POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM E%9LNC19KNT REPORT SUPPLEMENT NO 1: TESTING 4.9.1 Train 4A Modifications In addition to testing items specified in this Section and below, additional EDG tie-in testing includes the EDG differential current and overcurrent relaying, EDG lockout relaying, SPDS and annunciation, modification of existing EDG 4kV bus 4A circuit breaker controls including synchronizing and indication, safety injection and loss of offsite power auto-starting of the machine, remote governor control, remote voltage control and indication, battery charger remote bypass control removal per 4.6 and MCC telemand auto transfer removal per 4.5.Additional testing to verify proper separation of the EDG and Train assignment is performed as part of the EDG preoperational testing and the Enhanced Emergency Power System testing, as described in Sections 6.0 and 7.0.4.9.2 Train 4B modifications In addition to testing items similarly to those specified in Subsection 4.9.1 and below, EDG 4B/Train 4B testing includes testing of any modifications made to the alternate shutdown panel.I Verification is per f ormed as part of the Enhanced Emergency Power System testing, as described in Sections 6.0 and 7.0.0V33r,/4-,10 0 k P I II'pl REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPUBKNT NO 1: TESTING 5.0 NEW EDG PREOPERATIONAL TESTING The preoperational tests of the new EDGs are completed in two parts.Part 1 locally tests the operating engine without load, and with load (for example, via a temporary transformer).
Part 2 tests the EDG with permanent system buses from the control room, along with all ESF start'ests.
Most of the testing outlined in Section 5.1 can be performed following completion of the preoperational testing previously discussed in Section 3.0.The testing outlined in Section 5.2 can be performed following completion of the electrical components/system testing previo'usly discussed in Section 4.0.Successful completion of these testing requirements described in this Section results in each new EDG accepted as qualified to operate.5.1 PART 1-LOCAL EDG OPERATIONS The EDG is in the normal standby condition with the Master Control Switch in local for the following tests.5.1.1 Idle Start An EDG at standby conditions is idle started.After operating at idle speed for sufficient time for engine checks, the EDG is idle released to 900 rpn, then shut down via overspeed trip, recording standby engine overspeed trip setpoint data.5.1.2 Five-Start Test With the air compressor control switches to"off" and the four air receivers bled down to the pressure where the low pressure alarm actuates, the air capacity test for the air receivers is performed.
The EDG undergoes four start failures and then is started on the fifth attempt.Following the fifth start the time required to re-pressurize the two air receivers is demonstrated to be in accordance with design.This test demonstrates that the air start system meets design requirements.
5.1.3 Hot Overs ed Tri With the EDG loaded to greater than 50K load, engine temperatures are allowed to stabilize to the hot engine conditions.
The hot engine overspeed trip setpoint is verified after the above run.5.1.4 EDG Reliabilit Test These tests demonstrate the reliability of the EDG pursuant to R.G'.108 position C.2.(a)(9).
Since there are two identical new EDGs, each EDG is required to undergo at least 35 consecutive valid tests, with the total starts of both EDGs equal to 70 tests, with no failures.Voltage and frequency will be monitored for each start below.The EDG is started, synchronized to the grid, loaded to greater than 50X load and operated for greater than one hour.5-1
>pl rg f, R REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEM1%T NO 1: TESTING The above test is repeated such that each EDG has at least 35 successful tests without a failure.Each start must come to required frequency and voltage within acceptable limits and times.5.1.5 Start and Load Test An EDG is normal started (with a 60-second idle start period)and then auto-released to allow the EDG to go to 900 rpm.Speed and voltage values are verified to be within acceptable limits.The EDG is synchronized to grid and slowly loaded to 100X load.The engine parameters are allowed to stabilize.
5.1.6 Full Load Re ection Test The EDG is operated at a minimum of 100X load with stable engine parameters.
The EDG output breaker is opened, frequency and voltage transients are measured to assure the voltage requirements are met, and it is verified that the EDG does not trip on overspeed.
5.1.7 Twent-four Hour Run For the twenty-four hour run the EDG is normal started, synchronized and slowly loaded to 110%(approximately 3160 kW).After two hours at llOX, load is reduced to 100X.After one hour at 100X load a complete set of EDG data is recorded and repeated every hour.Twenty-two hours after load was adjusted to 100X, load is reduced slowly, the generator breaker is opened and the EDG is placed in a normal shutdown.This test also verifies that the cooling system functions within acceptable limits.Note: Revision 0 of this report stated that a fuel oil and lubrication oil consumption test would be performed during this twenty-four hour run.However, the current testing program provides for this testing at the vendor's facility.5.2 PART 2-REMOTE EDG OPERATION After the EDGe are permanently tied in to the plant buses, they are controlled and supervised by their respective main control room panels, local panels, etc.After the prerequisite testing in Section 4.0 above is completed, the following testing can proceed.5.2.1 0 ration from the Main Control Room The starts in this section are similar to the starts in Section 5.1 except all controls are from the Main Control Room.
l agk'k4,*~
REVISION 1 TlJRKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1 TESTING Idle Start with Normal Shutdown Emergency Start, Bypass of Non-Vital Trips Rapid Start with Normal Shutdown Emergency Stop 5.2.2 Isolation Switch Tests 0 With master control switch in"Local" position and two (2)isolation switches in"Isolate" positions on the local EDG control panel, it is verified that all control room EDG controls are disabled, and that the EDG control room alarms remain functional.
With master control switch in"local" position, and keylocked"auto-start" bypass switch in bypass, it is verified that Control Room EDG starts are disabled, including all emergency auto-start signals, and that the EDG Control Room alarms remain functional.
5.2.3 Emer nc Start, B ass of Non-Vital Tri An emergency start is performed and attempts made to trip the EDG with normal trips, to assure normal trips are bypassed.The EDG is then tripped by actuating a generator differential relay.5.2.4 EDG Surveillance Testin This completes the Startup and Preoperational Testing f or the new EDGs and the normal periodic testing is performed in accordance with existing plant procedures and Technical Specifications.
5-3 J~gL)C 4plt,IA REVISION 1 0 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING 6.0 VERIFICATION OF PROPER LO~ROUP ASSIGNMENTS In addition to the pre-operational testing described in Sections 4.0 and 5.0 above, plus the integrated acceptance testing outlined in Section 7.0 below which meets the recommendations of Regulatory Guide 1.108 (Rev 1, 08/77), the onsite testing program also meets the recommendations of Regulatory Guide 1.41 (Rev 0, 03/73), which indicates that: "...after major modifications...to a facility, those on-site electric power systems designed in accordance with Regulatory Guides 1.6 and 1.32 (Safety Guides 6 and 32)should be tested as follows to verify the existence of independence among redundant on-site power sources and their load groups." In accordance with Regulatory Guide 1.41 (Rev 0, 03/73), Positions C.l through C.3, the following tests are performed:
a.The plant electric power distribution system, not necessarily including the switchyard and the startup and auxiliary transformer, is isolated from the off-site transmission network.This isolation is effected by direct actuation of the undervoltage-sensing re1ays within the on-site system.b.Under the conditions above, the on-site electric power system is functionally tested in the various possible combinations of power sources and load groups (i.e., trains)available with all on-site AC power sources for three load groups (i.e., trains)at a time completely disconnected.
Each test includes in)ection of simulated accident signals, startup of the on"site power source(s)and load group(s)under test, sequencing of loads, and the functional performance of the loads.Each test is of sufficient duration to achieve stable operating conditions and thus permit the onset and detection of adverse conditions which could result from improper assignment of loads.c.During each test, the on-site AC buses and related loads under test are monitored to verify proper operation.
The above testing demonstrates conformance to Regulatory Guide 1.41 RO as it applies to the PTN enchanced EPS configuration.-The above load group verification testing is implemented as a part of the Integrated Safeguards testing described in Section 7.0.
4' REVISION 1 TUR1G.Y POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM ENHANCEMENT REPORT SUPPLEMPNT NO 1 TESTING 7.0 7.1 INTEGRATED ACCEPTANCE TESTING INCLUDIM'AFEGUARDS TESTING UNITS 3 AND 4 RUIN"A" AND"B" MODIFICATIONS Refer to Section 4.0.e 7a2 INTEGRATED PREOPERATION TEST In order to meet the single failure criterion, each Unit must have its two EDGs (and associated safeguards equipment, including their individual HHSI pumps)OPERABLE, plus oaa EBO and its assooiatad HHSI pump on the other Unit OPERABLE as a Limiting Condition for Operation (LCO)in Modes 1-4.Thus, in order to bring one Unit out of the planned-dual-Unit outage, this test includes at least three of the four 4kV OZ33r,/7-1 zgf gt I f REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING buses (3A, 3B, 4A&4B)and their associated EDGs (3A, 3B, 4A&4B).If required, the remaining EDG and its buses are tested prior to bringing the second Unit up, from its outage configuration.
That Unit will require OPERABILITY of its two EDGs (and associated safeguards equipment) plus OPERABILITY of at least one other EDG and its associated HHSI pump on the other Unit.In addition, all four EDGs are demonstrated to start simultaneously as noted in Subsection 7.3.9.For a LOCA on one Unit, a Safety Infection Signal (SIS)is sent to all four sequencers which results in the starting of all four EDGs and all four HHSI pumps.If a safeguards actuation train fails, then three EDGs receive a start signal and three of the HHSI pumps receive a start signal (one HHSI/EDG on the unfailed train and both HHSI/EDGs on the other Unit).The starting circuits are demonstrated to function via relay dry contacts and/or an interposing relay at each associated EDG/pump sequencer.
All of the EDG starts discussed herein are fast starts and must meet the fifteen (15)second requirement to attain required frequency and voltage.Complete bus and EDG independence including that between interunit trains are demonstrated.
During each of the test sequencers, verification is made that design loads on the EDGs are not exceeded.The following sections present revised test objectives and the intended sequence of tests for the Integrated Safeguards Testing.These revisions provide for compliance with R.G.1.108 and R.G.1.41 requirements (Section 6.0), as they apply to the EPS Enhancement Project modifications.
The following test obgectives are accomplished in each section of the Integrated Preoperational Test;acceptance criteria for these tests are delineated in Section 7.3.7.2.1 LOOP Each EDG is automtarted with individual Unit LOOP.Bus feeder=breaker opening, bus stripping&clearing, EDG start, EDG frequency, voltage and current output, EDG breaker closure, and sequencer timing intervals with required load starting are monitored.
In short, the complete event sequence of LOOP initiation/detection, starting the EDG and picking up all required loads is recorded for later data processing and analysis.7.2.1.1 LOOP then LOCA After a successful LOOP start test but prior to synchronization of the EDG to the startup transformer, a subsequent LOCA signal is simulated.
Test data is gathered demonstrating the tripping of all loads connected to the bus and the sequential starting of safety related loads on the bus.During the sequencing, the design voltage conditions are monitored.
0233L/7-2 4 I REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO 1: TESTING 7.2.1.2 LOCA with EDG Loaded to Off-Site Power 7.2.2 After reset of the auto-start signal and synchronization of the EDG to the startup transformer and in parallel with the offsite source, a LOCA signal is simulated.
Connected recording equipment captures the tripping of the EDG breaker (with the machine continuing to operate)to allow the preferred source to power the connected loads and those emergency loads which start in response to the accident signal.LOCA Each EDG is auto-started by an individual Unit Safety Infection Signal and the affected HHSI pumps start.Sequencer start, HHSI pump breaker closure, EDG start, and EDG voltage and frequency output are all demonstrated.
Additional safetymelated loads are started for the affected Unit only.7.2.2.1 LOCA then LOOP Prior to resetting of the accident signal and with the EDG running at rated frequency and voltage, a LOOP is simulated.
The EDG output circuit breaker is closed and applicable parameters previously t mentioned in Subsection 7.2.1 are monitored.
7.2.3 Bus LOOP, LOCA and Hi-Hi Containment Pressure (HHCP)Each EDG is auto-started by individual bus LOOP with simultaneous LOCA and HHCP (associated train)signals.Applicable parameters previously mentioned in Subsection 7.2.1 are monitored.
In this mode, the containment spray pump sequencer loading relay reactuates after the sequencer is not timing.7.2.3.1 LOOP plus Other Unit LOCA During the above test in 7.2.3, the non-LOCA Unit's EDGs are started, and, the associated HHSI pumps and LOOP loads are correctly sequenced on the EDGs.7-3
'I II 0 P" 4 ,P Qa i C'gt g rt REVISION 1 TU1UGH'OINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM EMDLNCEMENT REPORT SUPPLEK9lT NO 1: TESTING 7.2.4 Bus Inde cadence Safety related AC buses are tested in various combinations to show that each bus is independent of every other safety related AC bus, considering swing loads as necessary.
In particular each EDG is made inoperable with a subsequent dual Unit LOOP initiated with a simultaneous Unit LOCA/HHCP signal.The remaining EDGs auto-start per 7.2.1 demonstrating no effect or interdependence to the failed train.7.2.5 Simultaneous EDG Startin Simultaneous starting of the EOGs is demonstrated as part of the testing specified above.7.2e6 Loss of Lar st Sin le Load The new EDGs are further tested by shutting down the largest single load, while maintaining voltage and frequency within acceptable limits.Subsequent restarting of this load shall be demonstrated to do so without experiencing unacceptable voltage and frequency degradation.
7.2.7~~Transfer from EDG to Off-Site Power These tests also demonstrate that each diesel generator can parallel its bus to the grid, transfer its emergency loads to the grid and be returned to a standby condition.
7.2.8 EDG 0 rabilit at Hot (0 ratin)Condition Capability of the EDG to respond to the design accident load conditions while the EDG engine is in a hot (full load temperature) condition will be demonstrated by performing step 5.1.7 prior to step 7.2.3.7.3 ACCEPTANCE CRITERIA The f ollowing acceptance criteria demonstrate that the onsi te electrical distribution systems adequate1y support the necessary systems during a simulated emergency condition.
Below are the acceptance criteria for both the existing and new diese1 generators.
Since there is approximately 20 years difference between the existing and new diesel generators, the criteria, codes and standards that pertain to the new diese1 generators may not pertain to the existing diesel generators.
02 3 7-4
>'l Yi i II 4 t REVISION 1 TUESDAY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANC19KNT REPORT SUPPLMST NO 1s TESTING Systems required to operate independently between diesel generators during a LOCA and/or LOOP condition operate withia time and load requirements of their design.(Sections 7.2.1, 7.2.2, 7.2.3 and 7.2.4)Regulatory Guide 1.9, C.4 Regulatory Guide 1.108, C.2.a.l, C.2.a.2 and C.l.c.l IEEE 387-1984, 5.1.2 Ia the event one diesel generator division beconee unavailable, the remaiaiag diese1s are capable of feeding the loads necessary for safe plant shutdown.(Section 7.2.4)Regulatory Guide 1.6, D.l Regulatory Guide 1.108, C.l.b;1 The failure of any one electrical division does not af feet the operation of the other or its LOCA functions.(Sectioa 7.2.4)Regulatory Guide 1.6, D.l The dieseL generators can start aad assume their LOCA and/or l.oss of off site power loads in the speci fied times and sequence while maintaining voltage and frequency within specified limits from hot (operating) temperature conditions.(Section 7.2.3)Regulatory Guide 1.108, C.2.a.5 On a loss of tbe largest siagle load, each diesel generator does not exceed nominal speed plus 75 percent of the difference between nceinal speed and the overspeed trip setpoint or 115 percent of-nominal speed whichever is lower.Also, on the addition of the largest single load or sequencing load, the voltage ie not reduced below 75 percent of normal and the frequency is not reduced below 95 percent of normal.(Section 7.2')Regulatory Guide 1.9, C.4 Regulatory Guide 1.108, C.2.a.4 ANSI/IEEE Std 387-1984 7-5
'\(l)1~g REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM EMGlNC13MENT REPORT SUPPU9KHT NO 1: TESTING The LOCA loads can be started, accelerated, and run while being supplied from standby AC power systems (Section 7.2.1, 7.2.2 and 7.2')I Regulatory Guide 1.108, C.2.a.2 Each diesel generator has the capability to assume and sustain its emergency loads during a LOOP with or without a LOCA signal present.(Sections 7.2.1, 7.2 2 and 7.2.3)ReguLatory Guide 1.108, C.2.a.2 Each diesel generator, while loaded with its emergency loads, can be synchronized and transfer its emergency loads to the offsite power source.Af ter trans fer of its load, the diesel generator can be returned to standby status.(Section 7.2.7)Reguletoxy Guide 1.108, C.2.a.6 Demonstrate that diesel generators 3A, 3B, 4A and 4B can be started simultaneously and that they accelerate to their nominal running speed, to 4160V+420V and to 60 Hz+1.2 Hz within 15 seconds after the start signal.(Section 7.2.5)Regulatory Guide 1.108, C.2.b Demonstrate the ability of the generator and excitation system to accept the most severe load without experiencing instability resulting in genexatox voltage collapse, or significant evidence of the inability of the voltage to recover.Also demonstrate that there is sufficient engine torque available to prevent engine stall, and to permit the engine speed to recover, when experiencing the most sevexe load requixements (Sections 7.2.1, 7.2.2 and 7.2.3)Regulatory Guide 1.9, C.4 Regulatory Guide 1.108, C.2.1.2 ANSI/IEEE Std 387-1984, 5.1.5 7-6 0l , I I I II If 0 REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM ENHANCEMENT REPORT SUPPLEKBFZ NO 1: TESTING CONFORMANCE TO NRC REGULATORY GUIDES REINED TO TESTING The design, installation, testing and operation of the new e1ectrical equipment provided f or the enhanced Emergency Power System conforms to the current NRC guidance contained in<the applicable Regulatory Guides (RGs)listed below.As indicated, these RGs in turn endorse (generally with some qualification) the industry standards noted.Some of the Regulatory Guides listed do not pertain, primarily, to testing requirements but are listed for completeness.
Refer also to the FPL responses to NRC's January 1989 Request for Additional Information (FPL letters L-89-54 and L-89-107).
I RG 1,9 RG 1.41 RG 1.108"Selection, Design, and Qualification of Diesel Generator Units Used as Standby (Onsite)Electric Power Systems at Nuclear Power Plants", Revision 2 dated December 1979.RG 1.9 provides the NRC position on EDG capacity pursuant to GDC 17, and on testing pursuant to 10CFR50 Appendix B.The RG endorses, with comment, IEEE Standard 387-1977.Section 7.3 of this submittal describes the conformance of the enhanced EPS to RG 1.9, particularly for the new EDGs being provided."Preoperational Testing of Redundant On-Site Electric Power Systems to Verify Proper LoadWroup Assignments", Revision 0 dated March 1973.This RG provides the NRC position on testing of onsite emergency power systems which have been designed to RGs 1.6 and 1.9, to meet GDC 1 and 10CFR50 Appendix B.RG 1.41 clarifies a portion of IEEE Standard 308-1971.The conformance to RG 1.41 is described in Section 6.0 of this report."Periodic Testing of Diesel Generator Units Used as Onsite Electric Power Systems at Nuclear Power Plants", Revision 1, dated August 1977 (including Errata published September 1977).This RG provides the NRC positions for complying with GDCs 17 and 18, and with the testing provisions of 10CFR50 Appendix B.It encompasses preoperational and periodic testing of diesel electric power Units to ensure they will meet their availability requirements.
This submittal describes the construction, startup, preoperational and integrated testing performed on the EDGs and on the enhanced EPS.Periodic testing is conducted under'he applicable Turkey Point Technical Specifications.
8-1 l p k~A' REVISION 1 TURKEY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ENHANCEMENT REPORT SUPPLEMENT NO lo TESTING RG 1.137"Fuel Oil Systems f or Standby Diesel Generators", Revision 1 dated October 1979.This RG provides the NRC positions f or complying with GDC 17 and 10CPR50 Appendix B, and endorses, with comment, ANSI N 195-1976'regarding fuelmil systems f or standby diesel generators and assurance of adequate fuel~f1 quality.Puelmil quality is assured at Turkey Point by administrative procedures which follow ANSI N 195-1976, and the quality of fuelmil is tested in accordance with Technical Specifications which specify, as applicable, ASTM Standards (or equivalent)
D4057, D975&1, D1552-79, D2622-82, and D2276-78.(These Technical Specifications are currently under NRC review.)8-2 P ,)t~J~t REVISION 1 e 9'TURKEY POINT UNITS 3 AND 4 EMERGENCY PORK SYSTEM ENHANCEME2iT REPORT SUPPLEKST NO 1: TESTING REFERENCES IEEE 387-84-IEEE Standard Criteria for Diesel Generator Units Applied as Standby Power Supplies for Nuclear Power Generating Stations 2~NUREG CR-4440-A Review of Emergency Diesel Generator Performance at Nuclear Power Plants 3~4.5~6.7~8.9.10.Regulatory Guide 1.9-Selection, Design and Quali fi cation of Diesel~nerator Units used as Standby (On Site)Electric Power Systems at Nuclear Power Plants, Rev 2, December 1979 Regulatory Guide 1.41-Preoperational Testing of Redundant On-Site Electric Power Systems to Verify Proper Load Group Assignments, Rev 0, March 1973 Regulatory Guide 1.108-Periodic Testing of Diesel Generator Units used as On-Site Electric Power Systems at.Nuclear Power Plants, Rev 1, August 1977 Regulatory Guide 1.137-Fuel Oil Systems f or Standby Diese1 Generators, Rev 1, October 1979 Regulatory Guide 1.155-Station Blackout, Rev 0, August 1988 FPL Letter L&8-269 dated June 23, 1988 FPL Letter L-88-454 dated October 19, 1988 NRC Letter dated January 6, 1989, Request for Additional Inf ormation on Emergency Power System Enhancement Prospect (TAC Nos.69023 and 69024).12'3.14.15.FPL Letter L-89-54 dated February 24, 1989 FPL Letter~9>>107 dated March 20, 1989 FPL Letter L-89-124 dated April 3, 1989 FPL Letter Ir89-144 dated April 17, 1989.NRC Letter dated August 10, 1989, Qualification of New Emergency Diesel Generators.
16.NRC Letter dated March 16, 1990, Request f or Additional Information on Emergency Power System Enhancement Prospect (TAC Nos.69023 and 69024).17'8.FPL Letter L-90-140 dated April 16, 1990 ASME OM-1987, Operation and Maintenance of Nuclear Power Plants, Part 3-Requirements for Preoperational and Initial Startup Vibration Testing of Nuclear Power Plant Piping Systems.
h I 40 A, ff REVISION 1 TOEQXY POINT UNITS 3 AND 4 EMERGENCY POWER SYSTEM ESQLNCEMENT REPORT SUPPLEMENT NO 1: TESTING 4.0 ELECTRICAL SYSTEM STARTUP/PREOPERATIONAL TESTING A dual-Unit outage is planned for modifications and tie-in installation of the enhanced Emergency'Power System electrical componeats.
The outage activities include the tie-in of the new EDGs, modificatioa of the existing EDGs and the modification of the electrical traias, plus compoaent/system testing and safeguard testing.During a scheduled Unit refueling outage, both Uaits are planned to be shut down 1n order to implement the tie-in of the new EDGe, the modifications to the existing EDGs, and separation of the EDG sequencers to the electrical system.The tie-in of the EDG 4A to the Unit 4 Train A electrical auxiliary system also 1ncludes the tie-in of the 4.16kV Switchgear 4D, 480V Load Center 4H, the connection of MCC 4J to Load Center 4A, and the relocation of loads to Load Center 4H, MCC 4D and Switchgear 4D.Simultaneous to the tie-in of the EDG 4A, the EDG presently supplying power to Buses 3A and 4A will be disconnected aad Sequencers 3A and 4A replaced as described below.The Train 3A modifications w111 include the tie-in of the 4.16kV Switchgear 3D, 480V Load Center 3H, and the relocation of loads.The activities to modify Trains 3B and 4B are similar to those described for Trains 3A and 4A Details are prov1ded below.This section augments Section 3.2 startup testing, and includes a description of the startup/preoperational test requirements f or the enhanced power system relocated loads aad added loads, both.AC and DC, including the new 4.16 kV swing switchgear, 480V swing load centers, 480V MCCs, 125V DC buses, panelboarde and emergency bus stripping and loading sequencers.-
4.1 This secti.on discusses the electrical separation of the existing EDGs from the Unit 4 new EDGs.The preoperational testing requirements of the new EDGs are discussed i,n Sections 5.0 and 6.0, aad the integrated EPS testing requi.rements are discussed in Section 7.0.4.16 kV SWING SWITCHGEAR 3D (4D)The aew 4.16 kV switchgears 3D (4D)are ineta11ed in the aew EDG buildiag.Startup testiag commences upon completion of the l appropriate interfaces required to support the tests.4-1 j's
@as Was)))))))))))"-g)))>Wg))))))))~)g N~).):a@SYNOOIS'RGOCAIID EO)IPSGII (POWER QKVL'll)NOIE I SOO CIOSSIIE I.CMY SGECIKD SSIKIY RGAIB)ID)OS PRE QNWN 2.INKSKN NCR)4SIEY RSCKID Olf)'Ito~s t R~~)~~)ssss sf~s 4&ssL pP~ops)S KM'~ss$8 Iw C@sf')aas~)~a F)I&4 M~iTLC'X~S.I)C fOIIOWINC SEW O)JIPSGII IS 8ONC N)OID ISCN EPS OIIA)COSNI PRORCI)GCs 4A 0 48-4.16KV SWOR SO 0 40-4IKIV IOO COII95 3H 4 4H SCCs SK, 40, 4I 0 4K MINY IHA)tCNS SAI 0 3)2 4.1>C fOtEOWI)C EKISIINC EO)fief IS RGAI)GID tlCER EPS OSIA)COG)I PROKCI: OOSII)C REUOGID KDC A EDC SA EDC 0 B)C 38 IICC 0 ICC 20 MIERY CHARCN SA Mlle CH)RCN Sll MIKRY CH)RCER Se MIOtf CHSRCN Set MIKRf CHSRCOt SS MINY OISRCN 482 MINf CHARCN 4l MINf CHA)tCN 4AI MINf IIIA)CBt 48 MINY OIARCN 401 MINY CHSRCN 4S MIKRY CHSIICN 4)2 OQSIDsC MINY CHIRCO5 WIIE IC ROUCB)440 RGA)%llew AS QK)WN AOOIE.~)~))sefss DE)ICAIKS EO)IPSGII AOOID ef EPS OIIA>COGII PRODUCE~Q s~!j~QK W sS w'K KJ".'"~ss&Nf%8%~ss pQ~vasss~gl s~sss', ol ADIIIOA POWBI*UCHI CCSC'ANY IURKEY PODll PUflf tftlIS 0 4)4 FIGURE I-Nwss)~ENBICOCY POWN SSSIB4 OAINCKNENI SC OSE-UNE OUCSISN