{{#Wiki_filter:September 12, 2016 Mr. Fadi Diya, Senior Vice President and Chief Nuclear Officer Union Electric Company P.O. Box 620 Fulton, MO 65251 SUBJECT: ERRATA FOR MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2016005
{{#Wiki_filter:ber 12, 2016
)
 
==SUBJECT:==
ERRATA FOR MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2016005)


==Dear Mr. Diya:==
==Dear Mr. Diya:==
It was identified that the enclosed inspection plan in a letter to you dated August 31, 2016 (ML16237A033) was improperly marked. The inspection plan contained the markings of "Official Use Only  
It was identified that the enclosed inspection plan in a letter to you dated August 31, 2016 (ML16237A033) was improperly marked. The inspection plan contained the markings of Official Use Only - Sensitive Internal Information/Security-Related Information, however, the inspection plan did not contain information under that category. The inspection plan that was originally placed into ADAMS has been corrected by striking through the markings. The original Mid-Cycle Assessment Letter and the corrected inspection plan are enclosed. Please note that neither the content of the assessment letter, nor the inspection plan has changed.
- Sensitive Internal Information/Security-Related Information", however, the inspection plan did not contain information under that category. The inspection plan that was originally placed into ADAMS has been corrected by striking through the markings. The original Mid-Cycle Assessment Letter and the corrected inspection plan are enclosed. Please note that neither the content of the assessment letter, nor the inspection plan has changed.


In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agency wide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agency wide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).


Sincerely,
Sincerely,
/RA/ Thomas R. Hipschman, Team Leader Inspection Program and Assessment Team Division of Reactor Safety Docket No.: 50-483 License No.: NPF-30 Enclosure s: 1. Callaway Plant Inspection/Activity Plan 2. 2016 Mid-Cycle Assessment Letter (ML16237A033
/RA/
) UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E LAMAR BLVD ARLINGTON, TX 76011-4511 Page 1 of 2 08/30/2016 09:32:44 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteCallawayInspection / Activity Plan 07/01/2016-06/30/2018BASELINE-PLANT MODS 1 1 IP A dverse Weather (Site/Imminent)7111101-Imminent 01/01/2016 12/31/2016 EB1-07T-CWY HEAT SINK PERFORMANCE 1 1 IP Heat Sink Performance7111107T 09/26/2016 09/30/2016 RS 24-RADIATION SAFETY 3 1 IP Occupational ALARA Planning and Controls71124.0211/07/201611/11/2016 1 IP Occupational Dose Assessment71124.0411/07/201611/11/2016 EP-1-EP PERFORMANCE INDICATORS 1 1 IP Drill/Exercise Performance71151-EP0111/14/201611/18/2016 1 IP ERO Readiness71151-EP0211/14/201611/18/2016 1 IP A lert & Notification System Reliability71151-EP0311/14/201611/18/2016 EP-2-BIENNIAL EP PROGRAM INSPECTION 1 1 IP A lert and Notification System Testing711140211/14/201611/18/2016 1 IP Emergency Preparedness Organization Staffing and Augmentation System711140311/14/201611/18/2016 1 IP Emergency Action Level and Emergency Plan Changes711140411/14/201611/18/2016 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies711140511/14/201611/18/2016 ISFSI-ROUTINE INSPECTION (ONE WEEK IN MONTH)
Thomas R. Hipschman, Team Leader Inspection Program and Assessment Team Division of Reactor Safety Docket No.: 50-483 License No.: NPF-30 Enclosures:
1 1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 02/01/2017 02/28/2017EXAM-INIT EXAM 4 1 INITIAL EXAM CALLAWAY (09/2017)
1. Callaway Plant Inspection/Activity Plan 2. 2016 Mid-Cycle Assessment Letter (ML16237A033)
X02591 08/14/2017 08/18/2017 1 INITIAL EXAM CALLAWAY (09/2017)
 
X0259109/11/2017 09/15/2017 RS 5678-RS TEAM 5 1 IP Radiation Monitoring Instrumentation71124.05 02/27/2017 03/03/2017 1 IP Radioactive Gaseous and Liquid Effluent Treatment71124.06 02/27/2017 03/03/2017 1 IP Radiological Environmental Monitoring Program71124.07 02/27/2017 03/03/2017 1 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 02/27/2017 03/03/2017 EP-2-BIENNIAL EP EXERCISE INSPECTION 4 1 IP Exercise Evaluation7111401 04/24/2017 04/28/2017 1 IP Emergency Action Level and Emergency Plan Changes7111404 04/24/2017 04/28/2017 EP-3-EP PERFORMANCE INDICATOR VERIFICATION 1 1 IP Drill/Exercise Performance71151-EP01 04/24/2017 04/28/2017 1 IP ERO Readiness71151-EP02 04/24/2017 04/28/2017 1 IP A lert & Notification System Reliability71151-EP03 04/24/2017 04/28/2017 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
Attachment 2 - Proposed Inspection Plan        CWY Page 1 of 2     Callaway 08/30/2016 09:32:44     Inspection / Activity Plan Report 22 07/01/2016 - 06/30/2018 Unit Planned Dates        No. of Staff Number Start End Inspection Activity    Title  on Site BASELINE - PLANT MODS       1 1 01/01/2016 12/31/2016 IP 7111101-Imminent Adverse Weather (Site/Imminent)
EB1-07T - CWY HEAT SINK PERFORMANCE     1 1 09/26/2016 09/30/2016 IP 7111107T Heat Sink Performance RS 24 - RADIATION SAFETY       3 1 11/07/2016 11/11/2016 IP 71124.02 Occupational ALARA Planning and Controls 1 11/07/2016 11/11/2016 IP 71124.04 Occupational Dose Assessment EP-1 - EP PERFORMANCE INDICATORS     1 1 11/14/2016 11/18/2016 IP 71151-EP01 Drill/Exercise Performance 1 11/14/2016 11/18/2016 IP 71151-EP02 ERO Readiness 1 11/14/2016 11/18/2016 IP 71151-EP03 Alert & Notification System Reliability EP-2 - BIENNIAL EP PROGRAM INSPECTION     1 1 11/14/2016 11/18/2016 IP 7111402 Alert and Notification System Testing 1 11/14/2016 11/18/2016 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 11/14/2016 11/18/2016 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 11/14/2016 11/18/2016 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies ISFSI - ROUTINE INSPECTION (ONE WEEK IN MONTH)     1 1 02/01/2017 02/28/2017 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants EXAM - INIT EXAM       4 1 08/14/2017 08/18/2017 X02591 INITIAL EXAM CALLAWAY (09/2017)
1 09/11/2017 09/15/2017 X02591 INITIAL EXAM CALLAWAY (09/2017)
RS 5678 - RS TEAM       5 1 02/27/2017 03/03/2017 IP 71124.05 Radiation Monitoring Instrumentation 1 02/27/2017 03/03/2017 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 02/27/2017 03/03/2017 IP 71124.07 Radiological Environmental Monitoring Program 1 02/27/2017 03/03/2017 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation EP-2 - BIENNIAL EP EXERCISE INSPECTION     4 1 04/24/2017 04/28/2017 IP 7111401 Exercise Evaluation 1 04/24/2017 04/28/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes EP-3 - EP PERFORMANCE INDICATOR VERIFICATION     1 1 04/24/2017 04/28/2017 IP 71151-EP01 Drill/Exercise Performance 1 04/24/2017 04/28/2017 IP 71151-EP02 ERO Readiness 1 04/24/2017 04/28/2017 IP 71151-EP03 Alert & Notification System Reliability This report does not include INPO and OUTAGE activities.
 
This report shows only on-site and announced inspection procedures. Enclosure 1


Page 2 of 2 08/30/2016 09:32:44 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteCallawayInspection / Activity Plan 07/01/2016-06/30/2018 BRQ-BIENNIAL REQUAL INSPECTION 3 1 IP Licensed Operator Requalification Program7111111B 06/12/2017 06/16/2017 EB1-21M-CWY COMPONENT DESIGN BASES INSPECTION 6 1 IP Component Design Bases Inspection (Teams)7111121M 07/31/2017 09/01/2017 RS 12 PI-RADIATION SAFETY 3 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 10/16/2017 10/20/2017 1 IP Occupational ALARA Planning and Controls71124.02 10/16/2017 10/20/2017 1 IP Occupational Exposure Control Effectiveness71151-OR01 10/16/2017 10/20/2017 1 IP RETS/ODCM Radiological Effluent Occurrences71151-PR01 10/16/2017 10/20/201771111.08-INSERVICE INSPECTION RFO22 1 1 IP Inservice Inspection Activities - PWR7111108P 10/16/2017 10/27/2017 EP-1-EP PROGRAM INSPECTION 1 1 IP A lert and Notification System Testing7111402 04/23/2018 04/27/2018 1 IP Emergency Preparedness Organization Staffing and Augmentation System7111403 04/23/2018 04/27/2018 1 IP Emergency Action Level and Emergency Plan Changes7111404 04/23/2018 04/27/2018 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies7111405 04/23/2018 04/27/2018 1 IP Drill/Exercise Performance71151-EP01 04/23/2018 04/27/2018 1 IP ERO Readiness71151-EP02 04/23/2018 04/27/2018 1 IP A lert & Notification System Reliability71151-EP03 04/23/2018 04/27/2018 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
Attachment 2 - Proposed Inspection Plan      CWY Page 2 of 2     Callaway 08/30/2016 09:32:44     Inspection / Activity Plan Report 22 07/01/2016 - 06/30/2018 Unit Planned Dates        No. of Staff Number Start End Inspection Activity    Title on Site BRQ - BIENNIAL REQUAL INSPECTION   3 1 06/12/2017 06/16/2017 IP 7111111B Licensed Operator Requalification Program EB1-21M - CWY COMPONENT DESIGN BASES INSPECTION   6 1 07/31/2017 09/01/2017 IP 7111121M Component Design Bases Inspection (Teams)
RS 12 PI - RADIATION SAFETY     3 1 10/16/2017 10/20/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 10/16/2017 10/20/2017 IP 71124.02 Occupational ALARA Planning and Controls 1 10/16/2017 10/20/2017 IP 71151-OR01 Occupational Exposure Control Effectiveness 1 10/16/2017 10/20/2017 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71111.08 - INSERVICE INSPECTION RFO22   1 1 10/16/2017 10/27/2017 IP 7111108P Inservice Inspection Activities - PWR EP-1 - EP PROGRAM INSPECTION     1 1 04/23/2018 04/27/2018 IP 7111402 Alert and Notification System Testing 1 04/23/2018 04/27/2018 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 04/23/2018 04/27/2018 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 04/23/2018 04/27/2018 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 04/23/2018 04/27/2018 IP 71151-EP01 Drill/Exercise Performance 1 04/23/2018 04/27/2018 IP 71151-EP02 ERO Readiness 1 04/23/2018 04/27/2018 IP 71151-EP03 Alert & Notification System Reliability This report does not include INPO and OUTAGE activities.


UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E LAMAR BLVD ARLINGTON, TX 76011-4511 August 31, 2016 Mr. Fadi Diya, Senior Vice President and Chief Nuclear Officer Union Electric Company P.O. Box 620 Fulton, MO 65251 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2016005)
This report shows only on-site and announced inspection procedures. Enclosure 1
 
UNITED STATES ust 31, 2016
 
==SUBJECT:==
MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2016005)


==Dear Mr. Diya:==
==Dear Mr. Diya:==
On August 9, 2016, the U.S. Nuclear Regulatory Commission (NRC)
On August 9, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Callaway Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2015 through June 30, 2016. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
completed its mid-cycle performance review of Callaway Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2015 through June 30, 2016. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility.


The NRC determined that overall, Callaway Plant operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Callaway Plant during the most recent quarter was within the Licensee Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., Green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. The enclosed inspection plan lists the inspections scheduled through June 30 , 2018. Routine inspections performed by resident inspectors are not included in the inspection plan.
The NRC determined that overall, Callaway Plant operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Callaway Plant during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., Green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.


The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
The enclosed inspection plan lists the inspections scheduled through June 30, 2018. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.


In response to the accident at Fukushima, the Commission issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. The NRC conducted audits of licensee efforts towards compliance with these Orders, and the information gathered will aid staff in development of the ultimate Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Safety Evaluation will be issued. Then, the NRC staff Enclosure 2 will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction 191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.
," and Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation." The NRC conducted audits of licensee efforts towards compliance with these Orders, and the information gathered will aid staff in development of the ultimate Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction 191, "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans." In Staff Requirements Memorandum - SECY 16-0009, "Recommendations Resulting from the Integrated Prioritization and Re-Baselining of Agency Activities," the Commission approved the NRC staff recommendation to discontinue the formal mid-cycle assessment process beginning in calendar year 2017. This will be the final mid-cycle assessment letter. The staff will continue to conduct quarterly assessment meetings and communicate changes in the assessment of licensee performance in accordance with the guidance in Inspection Manual Chapter 0305, "Operating Reactor Assessment Program."


In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
In Staff Requirements Memorandum - SECY 16-0009, Recommendations Resulting from the Integrated Prioritization and Re-Baselining of Agency Activities, the Commission approved the NRC staff recommendation to discontinue the formal mid-cycle assessment process beginning in calendar year 2017. This will be the final mid-cycle assessment letter. The staff will continue to conduct quarterly assessment meetings and communicate changes in the assessment of licensee performance in accordance with the guidance in Inspection Manual Chapter 0305, Operating Reactor Assessment Program.
 
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).


Please contact me at 817-200-1141 with any questions you have regarding this letter.
Please contact me at 817-200-1141 with any questions you have regarding this letter.


Sincerely,
Sincerely,
/RA/ Nicholas H. Taylor, Chief Projects Branch B Division of Reactor Projects Docket No. 50-483 License No. NPF-30 Enclosure:
/RA/
Nicholas H. Taylor, Chief Projects Branch B Division of Reactor Projects Docket No. 50-483 License No. NPF-30 Enclosure:
Callaway Plant Inspection/Activity Plan
Callaway Plant Inspection/Activity Plan


Page 1 of 2 08/30/2016 09:32:44 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteCallawayInspection / Activity Plan 07/01/2016-06/30/2018BASELINE-PLANT MODS 1 1 IP A dverse Weather (Site/Imminent)7111101-Imminent 01/01/2016 12/31/2016 EB1-07T-CWY HEAT SINK PERFORMANCE 1 1 IP Heat Sink Performance7111107T 09/26/2016 09/30/2016 RS 24-RADIATION SAFETY 3 1 IP Occupational ALARA Planning and Controls71124.0211/07/201611/11/2016 1 IP Occupational Dose Assessment71124.0411/07/201611/11/2016 EP-1-EP PERFORMANCE INDICATORS 1 1 IP Drill/Exercise Performance71151-EP0111/14/201611/18/2016 1 IP ERO Readiness71151-EP0211/14/201611/18/2016 1 IP A lert & Notification System Reliability71151-EP0311/14/201611/18/2016 EP-2-BIENNIAL EP PROGRAM INSPECTION 1 1 IP A lert and Notification System Testing711140211/14/201611/18/2016 1 IP Emergency Preparedness Organization Staffing and Augmentation System711140311/14/201611/18/2016 1 IP Emergency Action Level and Emergency Plan Changes711140411/14/201611/18/2016 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies711140511/14/201611/18/2016 ISFSI-ROUTINE INSPECTION (ONE WEEK IN MONTH)
Attachment 2 - Proposed Inspection Plan Official Use Only - Sensitive Internal Information/Security-Related Information  CWY Page 1 of 2     Callaway 08/30/2016 09:32:44     Inspection / Activity Plan Report 22 07/01/2016 - 06/30/2018 Unit Planned Dates          No. of Staff Number Start End Inspection Activity    Title  on Site BASELINE - PLANT MODS       1 1 01/01/2016 12/31/2016 IP 7111101-Imminent Adverse Weather (Site/Imminent)
1 1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 02/01/2017 02/28/2017EXAM-INIT EXAM 4 1 INITIAL EXAM CALLAWAY (09/2017)
EB1-07T - CWY HEAT SINK PERFORMANCE       1 1 09/26/2016 09/30/2016 IP 7111107T Heat Sink Performance RS 24 - RADIATION SAFETY       3 1 11/07/2016 11/11/2016 IP 71124.02 Occupational ALARA Planning and Controls 1 11/07/2016 11/11/2016 IP 71124.04 Occupational Dose Assessment EP-1 - EP PERFORMANCE INDICATORS       1 1 11/14/2016 11/18/2016 IP 71151-EP01 Drill/Exercise Performance 1 11/14/2016 11/18/2016 IP 71151-EP02 ERO Readiness 1 11/14/2016 11/18/2016 IP 71151-EP03 Alert & Notification System Reliability EP-2 - BIENNIAL EP PROGRAM INSPECTION     1 1 11/14/2016 11/18/2016 IP 7111402 Alert and Notification System Testing 1 11/14/2016 11/18/2016 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 11/14/2016 11/18/2016 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 11/14/2016 11/18/2016 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies ISFSI - ROUTINE INSPECTION (ONE WEEK IN MONTH)     1 1 02/01/2017 02/28/2017 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants EXAM - INIT EXAM       4 1 08/14/2017 08/18/2017 X02591  INITIAL EXAM CALLAWAY (09/2017)
X02591 08/14/2017 08/18/2017 1 INITIAL EXAM CALLAWAY (09/2017)
1 09/11/2017 09/15/2017 X02591  INITIAL EXAM CALLAWAY (09/2017)
X0259109/11/2017 09/15/2017 RS 5678-RS TEAM 5 1 IP Radiation Monitoring Instrumentation71124.05 02/27/2017 03/03/2017 1 IP Radioactive Gaseous and Liquid Effluent Treatment71124.06 02/27/2017 03/03/2017 1 IP Radiological Environmental Monitoring Program71124.07 02/27/2017 03/03/2017 1 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 02/27/2017 03/03/2017 EP-2-BIENNIAL EP EXERCISE INSPECTION 4 1 IP Exercise Evaluation7111401 04/24/2017 04/28/2017 1 IP Emergency Action Level and Emergency Plan Changes7111404 04/24/2017 04/28/2017 EP-3-EP PERFORMANCE INDICATOR VERIFICATION 1 1 IP Drill/Exercise Performance71151-EP01 04/24/2017 04/28/2017 1 IP ERO Readiness71151-EP02 04/24/2017 04/28/2017 1 IP A lert & Notification System Reliability71151-EP03 04/24/2017 04/28/2017 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
RS 5678 - RS TEAM       5 1 02/27/2017 03/03/2017 IP 71124.05 Radiation Monitoring Instrumentation 1 02/27/2017 03/03/2017 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 02/27/2017 03/03/2017 IP 71124.07 Radiological Environmental Monitoring Program 1 02/27/2017 03/03/2017 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation EP-2 - BIENNIAL EP EXERCISE INSPECTION     4 1 04/24/2017 04/28/2017 IP 7111401 Exercise Evaluation 1 04/24/2017 04/28/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes EP-3 - EP PERFORMANCE INDICATOR VERIFICATION     1 1 04/24/2017 04/28/2017 IP 71151-EP01 Drill/Exercise Performance 1 04/24/2017 04/28/2017 IP 71151-EP02 ERO Readiness 1 04/24/2017 04/28/2017 IP 71151-EP03 Alert & Notification System Reliability This report does not include INPO and OUTAGE activities.
 
This report shows only on-site and announced inspection procedures. Enclosure Official Use Only - Sensitive Internal Information/Security-Related Information
 
Attachment 2 - Proposed Inspection Plan Official Use Only - Sensitive Internal Information/Security-Related Information CWY Page 2 of 2      Callaway 08/30/2016 09:32:44    Inspection / Activity Plan Report 22 07/01/2016 - 06/30/2018 Unit Planned Dates        No. of Staff Number Start End Inspection Activity    Title  on Site BRQ - BIENNIAL REQUAL INSPECTION    3 1 06/12/2017 06/16/2017 IP 7111111B Licensed Operator Requalification Program EB1-21M - CWY COMPONENT DESIGN BASES INSPECTION    6 1 07/31/2017 09/01/2017 IP 7111121M Component Design Bases Inspection (Teams)
RS 12 PI - RADIATION SAFETY      3 1 10/16/2017 10/20/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 10/16/2017 10/20/2017 IP 71124.02 Occupational ALARA Planning and Controls 1 10/16/2017 10/20/2017 IP 71151-OR01 Occupational Exposure Control Effectiveness 1 10/16/2017 10/20/2017 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71111.08 - INSERVICE INSPECTION RFO22    1 1 10/16/2017 10/27/2017 IP 7111108P Inservice Inspection Activities - PWR EP-1 - EP PROGRAM INSPECTION    1 1 04/23/2018 04/27/2018 IP 7111402 Alert and Notification System Testing 1 04/23/2018 04/27/2018 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 04/23/2018 04/27/2018 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 04/23/2018 04/27/2018 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 04/23/2018 04/27/2018 IP 71151-EP01 Drill/Exercise Performance 1 04/23/2018 04/27/2018 IP 71151-EP02 ERO Readiness 1 04/23/2018 04/27/2018 IP 71151-EP03 Alert & Notification System Reliability This report does not include INPO and OUTAGE activities.


Page 2 of 2 08/30/2016 09:32:44 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteCallawayInspection / Activity Plan 07/01/2016-06/30/2018 BRQ-BIENNIAL REQUAL INSPECTION 3 1 IP Licensed Operator Requalification Program7111111B 06/12/2017 06/16/2017 EB1-21M-CWY COMPONENT DESIGN BASES INSPECTION 6 1 IP Component Design Bases Inspection (Teams)7111121M 07/31/2017 09/01/2017 RS 12 PI-RADIATION SAFETY 3 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 10/16/2017 10/20/2017 1 IP Occupational ALARA Planning and Controls71124.02 10/16/2017 10/20/2017 1 IP Occupational Exposure Control Effectiveness71151-OR01 10/16/2017 10/20/2017 1 IP RETS/ODCM Radiological Effluent Occurrences71151-PR01 10/16/2017 10/20/201771111.08-INSERVICE INSPECTION RFO22 1 1 IP Inservice Inspection Activities - PWR7111108P 10/16/2017 10/27/2017 EP-1-EP PROGRAM INSPECTION 1 1 IP A lert and Notification System Testing7111402 04/23/2018 04/27/2018 1 IP Emergency Preparedness Organization Staffing and Augmentation System7111403 04/23/2018 04/27/2018 1 IP Emergency Action Level and Emergency Plan Changes7111404 04/23/2018 04/27/2018 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies7111405 04/23/2018 04/27/2018 1 IP Drill/Exercise Performance71151-EP01 04/23/2018 04/27/2018 1 IP ERO Readiness71151-EP02 04/23/2018 04/27/2018 1 IP A lert & Notification System Reliability71151-EP03 04/23/2018 04/27/2018 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
This report shows only on-site and announced inspection procedures. Enclosure Official Use Only - Sensitive Internal Information/Security-Related Information


ML16237A033 SUNSI Review By: ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive Keyword: NRC-002 OFFICE: RIV SPE:DRP/B D: DRS D: DRP C: DRP/B NAME DProulx AVegel TWPruett NTaylor SIGNATURE /RA/ /RA Jeff Clark for/
ML16237A033 SUNSI Review ADAMS  Publicly Available Non-Sensitive Keyword:
/RA/ /RA/ DATE 8/22/16 8/22/16 8/23/16 8/23/16 Letter to Fadi Diya from Nicholas H. Taylor dated August 31, 2016 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2016005)
By: Yes No Non-Publicly Available Sensitive NRC-002 OFFICE: RIV SPE:DRP/B D: DRS D: DRP C: DRP/B NAME DProulx AVegel TWPruett NTaylor SIGNATURE /RA/ /RA Jeff Clark for/ /RA/ /RA/
DISTRIBUTION
DATE 8/22/16 8/22/16 8/23/16 8/23/16
: Regional Administrator (Kriss.Kennedy@nrc.gov)


Letter to Fadi Diya from Nicholas H. Taylor dated August 31, 2016 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2016005)
DISTRIBUTION:
Regional Administrator (Kriss.Kennedy@nrc.gov)
Deputy Regional Administrator (Scott.Morris@nrc.gov)
Deputy Regional Administrator (Scott.Morris@nrc.gov)
DRP Director (Troy.Pruett@nrc.gov)
DRP Director (Troy.Pruett@nrc.gov)
Line 80: Line 100:
Senior Project Engineer, DRP/B (David.Proulx@nrc.gov)
Senior Project Engineer, DRP/B (David.Proulx@nrc.gov)
Project Engineer, DRP/B (Steven.Janicki@nrc.gov)
Project Engineer, DRP/B (Steven.Janicki@nrc.gov)
Administrative Assistant (Dawn.Yancey@nrc.gov
Administrative Assistant (Dawn.Yancey@nrc.gov)
) Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Project Manager (John.Klos@nrc.gov)
Project Manager (John.Klos@nrc.gov)
Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)
Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)
Line 102: Line 122:
ROPreports.Resource@nrc.gov ROPassessment.Resource@nrc.gov
ROPreports.Resource@nrc.gov ROPassessment.Resource@nrc.gov


ML16256A288
ML16256A288 /PACKAGE: ML16256A277 SUNSI Review ADAMS Publicly Available Non-Sensitive Keyword:
/PACKAGE: ML16256A277 SUNSI Review By: EDU ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive Keyword: NRC-002 OFFICE TL: IPAT NAME THipschman SIGNATURE /RA/ DATE 9/12/16 Letter to Fadi Diya from Thomas R. Hipschman dated September 12, 2016 SUBJECT: ERRATA FOR MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2016005)
By: EDU Yes No Non-Publicly Available Sensitive NRC-002 OFFICE TL: IPAT NAME THipschman SIGNATURE /RA/
DISTRIBUTION
DATE 9/12/16
: Regional Administrator (Kriss.Kennedy@nrc.gov)
 
Deputy Regional Administrator (Scott.Morris@nrc.gov) DRP Director (Troy.Pruett@nrc.gov)
Letter to Fadi Diya from Thomas R. Hipschman dated September 12, 2016 SUBJECT: ERRATA FOR MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2016005)
DISTRIBUTION:
Regional Administrator (Kriss.Kennedy@nrc.gov)
Deputy Regional Administrator (Scott.Morris@nrc.gov)
DRP Director (Troy.Pruett@nrc.gov)
DRP Deputy Director (Ryan.Lantz@nrc.gov)
DRP Deputy Director (Ryan.Lantz@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
Line 116: Line 140:
Project Engineer, DRP/B (Steven.Janicki@nrc.gov)
Project Engineer, DRP/B (Steven.Janicki@nrc.gov)
Administrative Assistant (Dawn.Yancey@nrc.gov)
Administrative Assistant (Dawn.Yancey@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov
Public Affairs Officer (Victor.Dricks@nrc.gov)
) Project Manager (John.Klos@nrc.gov) Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)
Project Manager (John.Klos@nrc.gov)
Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)
Project Engineer, DRS/IPAT (Eduardo.Uribe@nrc.gov)
Project Engineer, DRS/IPAT (Eduardo.Uribe@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)

Latest revision as of 15:18, 30 October 2019

Errata for Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2016005)
ML16256A288
Person / Time
Site: Callaway Ameren icon.png
Issue date: 09/12/2016
From: Thomas Hipschman
Division of Reactor Safety IV
To: Diya F
Union Electric Co
Hipschman T
Shared Package
ML16256A277 List:
References
IR 2016005
Download: ML16256A288 (11)


Text

ber 12, 2016

SUBJECT:

ERRATA FOR MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2016005)

Dear Mr. Diya:

It was identified that the enclosed inspection plan in a letter to you dated August 31, 2016 (ML16237A033) was improperly marked. The inspection plan contained the markings of Official Use Only - Sensitive Internal Information/Security-Related Information, however, the inspection plan did not contain information under that category. The inspection plan that was originally placed into ADAMS has been corrected by striking through the markings. The original Mid-Cycle Assessment Letter and the corrected inspection plan are enclosed. Please note that neither the content of the assessment letter, nor the inspection plan has changed.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agency wide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Thomas R. Hipschman, Team Leader Inspection Program and Assessment Team Division of Reactor Safety Docket No.: 50-483 License No.: NPF-30 Enclosures:

1. Callaway Plant Inspection/Activity Plan 2. 2016 Mid-Cycle Assessment Letter (ML16237A033)

Attachment 2 - Proposed Inspection Plan CWY Page 1 of 2 Callaway 08/30/2016 09:32:44 Inspection / Activity Plan Report 22 07/01/2016 - 06/30/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site BASELINE - PLANT MODS 1 1 01/01/2016 12/31/2016 IP 7111101-Imminent Adverse Weather (Site/Imminent)

EB1-07T - CWY HEAT SINK PERFORMANCE 1 1 09/26/2016 09/30/2016 IP 7111107T Heat Sink Performance RS 24 - RADIATION SAFETY 3 1 11/07/2016 11/11/2016 IP 71124.02 Occupational ALARA Planning and Controls 1 11/07/2016 11/11/2016 IP 71124.04 Occupational Dose Assessment EP-1 - EP PERFORMANCE INDICATORS 1 1 11/14/2016 11/18/2016 IP 71151-EP01 Drill/Exercise Performance 1 11/14/2016 11/18/2016 IP 71151-EP02 ERO Readiness 1 11/14/2016 11/18/2016 IP 71151-EP03 Alert & Notification System Reliability EP-2 - BIENNIAL EP PROGRAM INSPECTION 1 1 11/14/2016 11/18/2016 IP 7111402 Alert and Notification System Testing 1 11/14/2016 11/18/2016 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 11/14/2016 11/18/2016 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 11/14/2016 11/18/2016 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies ISFSI - ROUTINE INSPECTION (ONE WEEK IN MONTH) 1 1 02/01/2017 02/28/2017 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants EXAM - INIT EXAM 4 1 08/14/2017 08/18/2017 X02591 INITIAL EXAM CALLAWAY (09/2017)

1 09/11/2017 09/15/2017 X02591 INITIAL EXAM CALLAWAY (09/2017)

RS 5678 - RS TEAM 5 1 02/27/2017 03/03/2017 IP 71124.05 Radiation Monitoring Instrumentation 1 02/27/2017 03/03/2017 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 02/27/2017 03/03/2017 IP 71124.07 Radiological Environmental Monitoring Program 1 02/27/2017 03/03/2017 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation EP-2 - BIENNIAL EP EXERCISE INSPECTION 4 1 04/24/2017 04/28/2017 IP 7111401 Exercise Evaluation 1 04/24/2017 04/28/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes EP-3 - EP PERFORMANCE INDICATOR VERIFICATION 1 1 04/24/2017 04/28/2017 IP 71151-EP01 Drill/Exercise Performance 1 04/24/2017 04/28/2017 IP 71151-EP02 ERO Readiness 1 04/24/2017 04/28/2017 IP 71151-EP03 Alert & Notification System Reliability This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure 1

Attachment 2 - Proposed Inspection Plan CWY Page 2 of 2 Callaway 08/30/2016 09:32:44 Inspection / Activity Plan Report 22 07/01/2016 - 06/30/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site BRQ - BIENNIAL REQUAL INSPECTION 3 1 06/12/2017 06/16/2017 IP 7111111B Licensed Operator Requalification Program EB1-21M - CWY COMPONENT DESIGN BASES INSPECTION 6 1 07/31/2017 09/01/2017 IP 7111121M Component Design Bases Inspection (Teams)

RS 12 PI - RADIATION SAFETY 3 1 10/16/2017 10/20/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 10/16/2017 10/20/2017 IP 71124.02 Occupational ALARA Planning and Controls 1 10/16/2017 10/20/2017 IP 71151-OR01 Occupational Exposure Control Effectiveness 1 10/16/2017 10/20/2017 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71111.08 - INSERVICE INSPECTION RFO22 1 1 10/16/2017 10/27/2017 IP 7111108P Inservice Inspection Activities - PWR EP-1 - EP PROGRAM INSPECTION 1 1 04/23/2018 04/27/2018 IP 7111402 Alert and Notification System Testing 1 04/23/2018 04/27/2018 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 04/23/2018 04/27/2018 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 04/23/2018 04/27/2018 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 04/23/2018 04/27/2018 IP 71151-EP01 Drill/Exercise Performance 1 04/23/2018 04/27/2018 IP 71151-EP02 ERO Readiness 1 04/23/2018 04/27/2018 IP 71151-EP03 Alert & Notification System Reliability This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure 1

UNITED STATES ust 31, 2016

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2016005)

Dear Mr. Diya:

On August 9, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Callaway Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2015 through June 30, 2016. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined that overall, Callaway Plant operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Callaway Plant during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., Green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2018. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.

In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. The NRC conducted audits of licensee efforts towards compliance with these Orders, and the information gathered will aid staff in development of the ultimate Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Safety Evaluation will be issued. Then, the NRC staff Enclosure 2 will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction 191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.

In Staff Requirements Memorandum - SECY 16-0009, Recommendations Resulting from the Integrated Prioritization and Re-Baselining of Agency Activities, the Commission approved the NRC staff recommendation to discontinue the formal mid-cycle assessment process beginning in calendar year 2017. This will be the final mid-cycle assessment letter. The staff will continue to conduct quarterly assessment meetings and communicate changes in the assessment of licensee performance in accordance with the guidance in Inspection Manual Chapter 0305, Operating Reactor Assessment Program.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 817-200-1141 with any questions you have regarding this letter.

Sincerely,

/RA/

Nicholas H. Taylor, Chief Projects Branch B Division of Reactor Projects Docket No. 50-483 License No. NPF-30 Enclosure:

Callaway Plant Inspection/Activity Plan

Attachment 2 - Proposed Inspection Plan Official Use Only - Sensitive Internal Information/Security-Related Information CWY Page 1 of 2 Callaway 08/30/2016 09:32:44 Inspection / Activity Plan Report 22 07/01/2016 - 06/30/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site BASELINE - PLANT MODS 1 1 01/01/2016 12/31/2016 IP 7111101-Imminent Adverse Weather (Site/Imminent)

EB1-07T - CWY HEAT SINK PERFORMANCE 1 1 09/26/2016 09/30/2016 IP 7111107T Heat Sink Performance RS 24 - RADIATION SAFETY 3 1 11/07/2016 11/11/2016 IP 71124.02 Occupational ALARA Planning and Controls 1 11/07/2016 11/11/2016 IP 71124.04 Occupational Dose Assessment EP-1 - EP PERFORMANCE INDICATORS 1 1 11/14/2016 11/18/2016 IP 71151-EP01 Drill/Exercise Performance 1 11/14/2016 11/18/2016 IP 71151-EP02 ERO Readiness 1 11/14/2016 11/18/2016 IP 71151-EP03 Alert & Notification System Reliability EP-2 - BIENNIAL EP PROGRAM INSPECTION 1 1 11/14/2016 11/18/2016 IP 7111402 Alert and Notification System Testing 1 11/14/2016 11/18/2016 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 11/14/2016 11/18/2016 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 11/14/2016 11/18/2016 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies ISFSI - ROUTINE INSPECTION (ONE WEEK IN MONTH) 1 1 02/01/2017 02/28/2017 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants EXAM - INIT EXAM 4 1 08/14/2017 08/18/2017 X02591 INITIAL EXAM CALLAWAY (09/2017)

1 09/11/2017 09/15/2017 X02591 INITIAL EXAM CALLAWAY (09/2017)

RS 5678 - RS TEAM 5 1 02/27/2017 03/03/2017 IP 71124.05 Radiation Monitoring Instrumentation 1 02/27/2017 03/03/2017 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 02/27/2017 03/03/2017 IP 71124.07 Radiological Environmental Monitoring Program 1 02/27/2017 03/03/2017 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation EP-2 - BIENNIAL EP EXERCISE INSPECTION 4 1 04/24/2017 04/28/2017 IP 7111401 Exercise Evaluation 1 04/24/2017 04/28/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes EP-3 - EP PERFORMANCE INDICATOR VERIFICATION 1 1 04/24/2017 04/28/2017 IP 71151-EP01 Drill/Exercise Performance 1 04/24/2017 04/28/2017 IP 71151-EP02 ERO Readiness 1 04/24/2017 04/28/2017 IP 71151-EP03 Alert & Notification System Reliability This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure Official Use Only - Sensitive Internal Information/Security-Related Information

Attachment 2 - Proposed Inspection Plan Official Use Only - Sensitive Internal Information/Security-Related Information CWY Page 2 of 2 Callaway 08/30/2016 09:32:44 Inspection / Activity Plan Report 22 07/01/2016 - 06/30/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site BRQ - BIENNIAL REQUAL INSPECTION 3 1 06/12/2017 06/16/2017 IP 7111111B Licensed Operator Requalification Program EB1-21M - CWY COMPONENT DESIGN BASES INSPECTION 6 1 07/31/2017 09/01/2017 IP 7111121M Component Design Bases Inspection (Teams)

RS 12 PI - RADIATION SAFETY 3 1 10/16/2017 10/20/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 10/16/2017 10/20/2017 IP 71124.02 Occupational ALARA Planning and Controls 1 10/16/2017 10/20/2017 IP 71151-OR01 Occupational Exposure Control Effectiveness 1 10/16/2017 10/20/2017 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71111.08 - INSERVICE INSPECTION RFO22 1 1 10/16/2017 10/27/2017 IP 7111108P Inservice Inspection Activities - PWR EP-1 - EP PROGRAM INSPECTION 1 1 04/23/2018 04/27/2018 IP 7111402 Alert and Notification System Testing 1 04/23/2018 04/27/2018 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 04/23/2018 04/27/2018 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 04/23/2018 04/27/2018 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 04/23/2018 04/27/2018 IP 71151-EP01 Drill/Exercise Performance 1 04/23/2018 04/27/2018 IP 71151-EP02 ERO Readiness 1 04/23/2018 04/27/2018 IP 71151-EP03 Alert & Notification System Reliability This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure Official Use Only - Sensitive Internal Information/Security-Related Information

ML16237A033 SUNSI Review ADAMS Publicly Available Non-Sensitive Keyword:

By: Yes No Non-Publicly Available Sensitive NRC-002 OFFICE: RIV SPE:DRP/B D: DRS D: DRP C: DRP/B NAME DProulx AVegel TWPruett NTaylor SIGNATURE /RA/ /RA Jeff Clark for/ /RA/ /RA/

DATE 8/22/16 8/22/16 8/23/16 8/23/16

Letter to Fadi Diya from Nicholas H. Taylor dated August 31, 2016 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2016005)

DISTRIBUTION:

Regional Administrator (Kriss.Kennedy@nrc.gov)

Deputy Regional Administrator (Scott.Morris@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Thomas.Hartman@nrc.gov)

Resident Inspector (Michael.Langelier@nrc.gov)

Branch Chief, DRP/B (Nick.Taylor@nrc.gov)

Senior Project Engineer, DRP/B (David.Proulx@nrc.gov)

Project Engineer, DRP/B (Steven.Janicki@nrc.gov)

Administrative Assistant (Dawn.Yancey@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Project Manager (John.Klos@nrc.gov)

Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)

RIV RSLO (Bill.Maier@nrc.gov)

Director, DIRS, NRR (Chris.Miller@nrc.gov)

Deputy Director, DIRS, NRR (Shana.Helton@nrc.gov)

Director, DORL, NRR (Anne.Boland@nrc.gov)

Deputy Director, DORL, NRR (George.Wilson@nrc.gov)

Director, NSIR (Brian.Holian@nrc.gov)

Director, DPR, NSIR (Marissa.Bailey@nrc.gov)

DRP Branch Chiefs (R4DRPBC@nrc.gov)

DRS Branch Chiefs (R4DRSBC@nrc.gov)

ROPreports.Resource@nrc.gov ROPassessment.Resource@nrc.gov

ML16256A288 /PACKAGE: ML16256A277 SUNSI Review ADAMS Publicly Available Non-Sensitive Keyword:

By: EDU Yes No Non-Publicly Available Sensitive NRC-002 OFFICE TL: IPAT NAME THipschman SIGNATURE /RA/

DATE 9/12/16

Letter to Fadi Diya from Thomas R. Hipschman dated September 12, 2016 SUBJECT: ERRATA FOR MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2016005)

DISTRIBUTION:

Regional Administrator (Kriss.Kennedy@nrc.gov)

Deputy Regional Administrator (Scott.Morris@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Thomas.Hartman@nrc.gov)

Resident Inspector (Michael.Langelier@nrc.gov)

Branch Chief, DRP/B (Nick.Taylor@nrc.gov)

Senior Project Engineer, DRP/B (David.Proulx@nrc.gov)

Project Engineer, DRP/B (Steven.Janicki@nrc.gov)

Administrative Assistant (Dawn.Yancey@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Project Manager (John.Klos@nrc.gov)

Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)

Project Engineer, DRS/IPAT (Eduardo.Uribe@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)

RIV RSLO (Bill.Maier@nrc.gov)

Director, DIRS, NRR (Chris.Miller@nrc.gov)

Deputy Director, DIRS, NRR (Shana.Helton@nrc.gov)

Director, DORL, NRR (Anne.Boland@nrc.gov)

Deputy Director, DORL, NRR (George.Wilson@nrc.gov)

Director, NSIR (Brian.Holian@nrc.gov)

Director, DPR, NSIR (Marissa.Bailey@nrc.gov)

DRP Branch Chiefs (G-R4-DRP-BC@nrc.gov)

DRS Branch Chiefs (R4DRS-BC1@nrc.gov)

ROPreports.Resource@nrc.gov ROPassessment.Resource@nrc.gov