|
---|
Category:Inspection Plan
MONTHYEARIR 05000483/20240052024-08-14014 August 2024 Updated Inspection Plan for Callaway Plant (Report 05000483/2024005) ML24088A3212024-04-0101 April 2024 Notification of Commercial Grade Dedication Inspection (05000483/2024013) and Request for Information ML24066A1932024-03-0707 March 2024 2024 Callaway Plant Notification of Biennial Problem Identification and Resolution Inspection and Request for Information IR 05000483/20230062024-02-28028 February 2024 Annual Assessment Letter for Callaway Plant Report 05000483/2023006 ML24011A1492024-01-11011 January 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information (05000483/2024011) IR 05000483/20240122023-10-24024 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (05000483/2024012) IR 05000483/20230052023-08-23023 August 2023 Updated Inspection Plan for Callaway Nuclear Power Plant, Unit 1 (Report 05000483/2023005) - Mid Cycle Letter 2023 ML23158A1462023-06-13013 June 2023 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000483/2023010) ML23163A1572023-06-0606 June 2023 In-service Inspection Request for Information ML23080A1382023-03-21021 March 2023 Notification of Inspection (NRC Inspection Report 05000483/2023003) and Request for Information IR 05000483/20220062023-03-0101 March 2023 Annual Assessment Letter for Callaway Plant (Report 05000483/2022006) ML23027A0362023-01-27027 January 2023 Information Request, Security IR 2023402 IR 05000483/20220052022-08-23023 August 2022 Updated Inspection Plan for Callaway Plant (Report 05000483/2022005) ML22173A0562022-06-22022 June 2022 Information Request, Security IR 2022402 IR 05000483/20210062022-03-0202 March 2022 Annual Assessment Letter for Callaway Plant (Report 05000483/2021006) ML21336A6392021-12-0202 December 2021 .05 Sec Doc Request IR 05000483/20224022021-11-30030 November 2021 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000483/2022402 IR 05000483/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Callaway Plant (Report 05000483/2021005) ML21195A0252021-07-13013 July 2021 Email 7-13-21 Request for Information - Callaway EP Exercise Inspection - Sept 2021 ML21088A3872021-03-30030 March 2021 Notification of Evaluations of Changes, Tests, and Experiments Inspection (Inspection Report 05000483/2021002) and Request for Information ML21069A3422021-03-11011 March 2021 Notification of Inspection (NRC Inspection Report 05000483/2021003) and Request for Information ML21055A0062021-03-0303 March 2021 Annual Assessment Letter for Callaway Plant (Report 05000483/2020006) ML20245E4402020-09-0101 September 2020 Cwy Inspection Schedule Mc 2020 IR 05000483/20200052020-09-0101 September 2020 Updated Inspection Plan for Callaway Plant (Report 05000483/2020005) IR 05000483/20190062020-03-0303 March 2020 Annual Assessment Letter for Callaway Plant (Report 05000483/2019006) ML19347D1482019-12-11011 December 2019 Cwy Security Inspection Information Request 2020410 IR 05000483/20190052019-08-30030 August 2019 Updated Inspection Plan for Callaway Plant Unit 1, Report No. 05000483/2019005 ML19199A1812019-07-18018 July 2019 Notification of NRC Design Base Assurance Inspection (Programs) (05000483/2019011) and Initial Request for Information IR 05000483/20180062019-03-0404 March 2019 Annual Assessment Letter for Callaway Plant (Report 05000483/2018006) ML19023A2032019-01-22022 January 2019 Notification of NRC Triennial Heat Sink Performance Inspection (05000483/2019001) and Request for Information IR 05000483/20170062018-03-0101 March 2018 Annual Assessment Letter for Callaway Plant (Report 05000483/2017006) IR 05000483/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000483/2017005) IR 05000483/20160062017-03-0101 March 2017 Annual Assessment Letter for Callaway Plant (Report 05000483/2016006) IR 05000483/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2016005) ML16237A0332016-08-31031 August 2016 Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2016005) IR 05000483/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Callaway Plant (NRC Physical Security Inspection Report Number 05000483/2016401) IR 05000483/20150062016-03-0202 March 2016 Annual Assessment Letter for Callaway Plant (Report 05000483/2015006) IR 05000483/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2015005) ML15244B0922015-09-0101 September 2015 Non-Public Security Inspection Plan for Callaway Plant (NRC Physical Security Inspection Report Number 05000483/2015401) ML15023A0962015-01-23023 January 2015 Notification of Conduct of a Triennial Fire Protection Baseline IR 05000483/2015007 and Request for Information IR 05000483/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Callaway Plant (NRC Physical Security Inspection Report Number 05000483/2014402) IR 05000483/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2014006) IR 05000483/20130012014-03-0404 March 2014 Annual Assessment Letter for Callaway Plant (Report 05000483/2013001) ML14027A2792014-01-27027 January 2014 Information Request for NRC Triennial Baseline Component Design Bases Inspection NRC Inspection Report 05000483-14-007 IR 05000483/20134052013-09-26026 September 2013 Callaway Plant - Notification of TI-186 Inspection (NRC Inspection Report 05000483-13-405) and Request for Information ML13269A4372013-09-26026 September 2013 Notification of TI-186 Inspection (NRC Inspection Report 05000483-13-405) and Request for Information ML13246A2822013-09-0303 September 2013 Mid-Cycle Assessment Letter 2013 IR 05000483/20128012013-03-0404 March 2013 Annual Assessment Letter for Callaway Plant (Report 05000483/2012801) IR 05000483/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - Callaway Plant (05000483/2012006) IR 05000483/20120012012-03-0505 March 2012 Annual Assessment Letter for Callaway Plant (Report 05000483/2012001) 2024-08-14
[Table view] Category:Letter
MONTHYEARIR 05000483/20240032024-10-23023 October 2024 Integrated Inspection Report 05000483/2024003 IR 05000483/20240132024-10-21021 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000483/2024013 IR 05000483/20244012024-10-0909 October 2024 Material Control and Accounting Program Inspection Report 05000483/2024401 Public ULNRC-06901, Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter)2024-10-0101 October 2024 Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter) ML24247A3042024-09-11011 September 2024 Regulatory Audit Questions for License Renewal Commitments 34 and 35 (EPID L-2024-LRO-0009) - Non-Proprietary IR 05000483/20244032024-08-28028 August 2024 Security Baseline Inspection 05000483-2024-403 IR 05000483/20240052024-08-14014 August 2024 Updated Inspection Plan for Callaway Plant (Report 05000483/2024005) IR 05000483/20253012024-08-0505 August 2024 Notification of NRC Initial Operator Licensing Examination 05000483/2025301 ML24212A2822024-08-0202 August 2024 Regulatory Audit Summary Concerning Review of Request No. C3R-01 for Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections IR 05000483/20240022024-07-18018 July 2024 And Independent Spent Fuel Storage Installation Integrated Inspection Report 05000483/2024002 and 07201045/2024001 ML24185A1032024-07-16016 July 2024 2024 Biennial Problem Identification and Resolution Inspection Report ULNRC-06892, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00062024-06-26026 June 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0006 ULNRC-06891, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00052024-06-26026 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0005 ULNRC-06884, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00022024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0002 ULNRC-06886, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00042024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0004 ULNRC-06885, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00032024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0003 ML24144A0492024-06-11011 June 2024 Requests for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML24158A5222024-06-0606 June 2024 Application to Revise Technical Specifications to Adopt Tstf-569, Rev. 2, Revise Response Time Testing Definition (LDCN 24-0008) ML24178A1132024-06-0606 June 2024 Ameren Missouris Intent to Adopt Revision 1 to Amendment 0 of Certificate of Compliance No. 1040 as Applicable to the ISFSI at the Callaway Plant Site ML24143A1632024-05-23023 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Storage Canister HGMPC0001 ULNRC-06882, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00122024-05-16016 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0012 ML24137A2342024-05-16016 May 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Canister HGMPC0011 ML24122A1502024-05-0707 May 2024 Audit Plan to Support Review of Steam Generator License Renewal Response to Commitment Nos 34 and 35 ULNRC-06877, Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 252024-05-0606 May 2024 Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 25 IR 05000483/20244022024-05-0606 May 2024 Security Baseline Inspection Report 05000483/2024402 (Full Report) IR 05000483/20240112024-05-0101 May 2024 NRC Post-Approval Site Inspection for License Renewal (Phase 2) Report 05000483/2024011 ULNRC-06856, CFR 50.59 and 10 CFR 72.48 Summary Report2024-05-0101 May 2024 CFR 50.59 and 10 CFR 72.48 Summary Report ULNRC-06869, Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report ML24122A1132024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radioactive Effluent Release Report ULNRC-06876, Registration of Dry Spent Fuel Storage Canister HGMPC00102024-04-25025 April 2024 Registration of Dry Spent Fuel Storage Canister HGMPC0010 ML24108A1082024-04-17017 April 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0009 ULNRC-06871, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00072024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0007 ULNRC-06872, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00082024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0008 ULNRC-06866, Submittal of Cycle 26 Commitment Change Summary Report2024-04-17017 April 2024 Submittal of Cycle 26 Commitment Change Summary Report IR 05000483/20240012024-04-16016 April 2024 Integrated Inspection Report 05000483/2024001 IR 05000483/20244042024-04-0909 April 2024 Cyber Security Inspection Report 05000483/2024404 ML24088A3212024-04-0101 April 2024 Notification of Commercial Grade Dedication Inspection (05000483/2024013) and Request for Information ML24086A5132024-03-26026 March 2024 CFR 50.46 Annual Report Regarding ECCS Evaluation Model Revisions ULNRC-06863, Submittal of Annual Exposure Report for 20232024-03-20020 March 2024 Submittal of Annual Exposure Report for 2023 ML24079A1622024-03-19019 March 2024 Re Nuclear Property Insurance Reporting ML24066A1932024-03-0707 March 2024 2024 Callaway Plant Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ULNRC-06852, Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 262024-03-0505 March 2024 Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 26 IR 05000483/20230062024-02-28028 February 2024 Annual Assessment Letter for Callaway Plant Report 05000483/2023006 ML24052A3662024-02-26026 February 2024 Regulatory Audit Plan in Support of Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections ULNRC-06858, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-02-21021 February 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation ML24036A1712024-02-20020 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0079 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) IR 05000483/20230042024-01-19019 January 2024 – Integrated Inspection Report 05000483/2023004 ML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 2024-09-11
[Table view] |
Text
ust 30, 2019
SUBJECT:
UPDATED INSPECTION PLAN FOR CALLAWAY PLANT UNIT 1, REPORT 05000483/2019005
Dear Mr. Diya:
The enclosed inspection plan lists the inspections scheduled through June 30, 2021, for the Callaway Plant. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP), including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In accordance with Title 10 of the Code of Federal Regulations (CFR) 2.390 of the NRCs, Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (817) 200-1141 with any questions you have regarding this letter.
Sincerely,
/RA/
Neil F. O'Keefe, Chief Project Branch B Division of Reactor Projects Docket No. 50-483 License No. NPF-30 Enclosure:
Inspection Plan
ML19234A212 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: JFM Yes No Publicly Available Sensitive NRC-002 OFFICE PBB:PE PBB:SPE PBB:C NAME JMelfi BTharakan NOKeefe SIGNATURE /RA/ /RA/ /RA/
DATE 08/26/19 08/26/19 08/30/19
IP 22 Inspection Activity Plan Report Callaway 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count Fire Protection Inspection - CWY 0 1 07/14/2019 07/20/2019 IP 71111.05XT 000697 Fire Protection - NFPA 805 1 07/28/2019 08/03/2019 IP 71111.05XT 000697 Fire Protection - NFPA 805 CW 2019 BRQ 2 1 07/28/2019 08/03/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance EP EXERCISE AND PI INSPECTION 4 1 08/12/2019 08/16/2019 IP 71114.01 000716 Exercise Evaluation 1 08/12/2019 08/16/2019 IP 71151 001397 Performance Indicator Verification Cyber Security Inspection - CWY 4 1 09/22/2019 09/28/2019 IP 71130.10P 000741 Cyber Security 1 10/06/2019 10/12/2019 IP 71130.10P 000741 Cyber Security CALLAWAY DBA PROGRAMS EQ INSPECTION 3 1 10/21/2019 10/25/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)
1 11/04/2019 11/08/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)
Callaway - Design Bases Assurance Inspection (Teams) 6 1 03/02/2020 03/20/2020 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
Security Access Control .02 1 1 03/09/2020 03/13/2020 IP 71130.02 000734 Access Control 1 03/09/2020 03/13/2020 IP 71151 001338 Performance Indicator Verification BIENNIAL PI&R 4 1 04/20/2020 04/24/2020 IP 71152B 000747 Problem Identification and Resolution 1 05/04/2020 05/08/2020 IP 71152B 000747 Problem Identification and Resolution RS24 Radiation Safety 2 1 05/18/2020 05/22/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 1 05/18/2020 05/22/2020 IP 71124.04 000728 Occupational Dose Assessment CW 2020 INITIAL EXAM 4 1 07/26/2020 08/01/2020 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1 08/30/2020 09/05/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
This report does not include INPO and OUTAGE activities. Page 1 of 2 This report shows only on-site and announced inspection procedures.
8/23/2019 9:47:06 AM
IP 22 Inspection Activity Plan Report Callaway 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count CW 2020 INITIAL EXAM 4 1 09/06/2020 09/12/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
Security Equipment .04 and Training .07 2 1 09/21/2020 09/25/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1 09/21/2020 09/25/2020 IP 71130.07 000739 Security Training Inservice Inspection RF24 - CWY 1 1 10/12/2020 10/23/2020 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RS12PI Radiation Safety 2 1 10/19/2020 10/23/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 10/19/2020 10/23/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls Security FFD .08 1 1 05/03/2021 05/07/2021 IP 71130.08 000740 Fitness For Duty Program RP 5,6,7,8 PS Team 5 1 06/14/2021 06/18/2021 IP 71124.05 000729 Radiation Monitoring Instrumentation 1 06/14/2021 06/18/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1 06/14/2021 06/18/2021 IP 71124.07 000731 Radiological Environmental Monitoring Program 1 06/14/2021 06/18/2021 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation MCA - Material Control & Accounting 1 1 06/14/2021 06/18/2021 IP 71130.11 000742 Material Control and Accounting (MC&A)
CW 2021 BRQ 2 1 06/20/2021 06/26/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance 50.59 Inspection 17T - Callaway 3 1 06/21/2021 06/25/2021 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments This report does not include INPO and OUTAGE activities. Page 2 of 2 This report shows only on-site and announced inspection procedures.
8/23/2019 9:47:06 AM