IR 05000483/2016004
Download: ML17025A419
Text
January 25, 2017
Mr. Fadi Diya, Senior Vice President and Chief Nuclear Officer Ameren Missouri Callaway Plant P.O. 620 Fulton, MO 65251
SUBJECT: CALLAWAY PLANT - NRC INTEGRATED INSPECTION REPORT 05000483/2016004
Dear Mr. Diya,
On December 31, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Callaway Plant. On January 4, 2017, the NRC inspectors discussed the results of this inspection with you and other members of your staff. Inspectors documented the results of this inspection in the enclosed inspection report. No NRC-identified or self-revealing findings were identified during this inspection. However, inspectors documented a licensee-identified violation which was determined to be of very low safety significance in this report. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy. If you contest the violations or significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC resident inspector at the Callaway Plant. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," a copy of this letter, its enclosure, and your response (if any) will be made available electronically for public inspection in the NRC's Public Document Room or the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response, if any, should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the public without redaction.
Sincerely,/RA/ Nicholas H. Taylor, Branch Chief Project Branch B Division of Reactor Projects Docket No. 50-483 License No. NPF-30
Enclosure:
Inspection Report 05000483/2016004 w/ Attachment 1: Supplemental Information Attachment 2: Request for Information
SUMMARY
IR 05000483/2016004; 10/01/16 - 12/31/16; Callaway Plant, Integrated Inspection Report The inspection activities described in this report were performed between October 1 and December 31, 2016, by the resident inspectors at the Callaway Plant and inspectors from the NRC's Region IV office. The significance of inspection findings is indicated by their color (i.e., Green, greater than Green, White, Yellow, or Red), determined using Inspection Manual Chapter 0609, "Significance Determination Process," dated April 29, 2015. Their cross-cutting aspects are determined using Inspection Manual Chapter 0310, "Aspects within the Cross-Cutting Areas," dated December 4, 2014. Violations of NRC requirements are dispositioned in accordance with the NRC Enforcement Policy. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," dated July 2016. Licensee-Identified Violations A violation of very low safety significance was identified by the licensee and has been reviewed by the inspectors. Corrective actions taken or planned by the licensee have been entered into the licensee's corrective action program. This violation and associated corrective action tracking numbers are listed in Section 4OA7 of this report.
3
PLANT STATUS
Callaway operated at 100 percent power for the duration of the inspection period with the exception of planned power reductions for routine surveillances and post-maintenance testing.
REPORT DETAILS
REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
1R01 Adverse Weather Protection
Readiness for Seasonal Extreme Weather Conditions - Cold Weather Preparations
a. Inspection Scope
On December 12, 2016, the inspectors completed an inspection of the station's readiness for seasonal extreme weather conditions. The inspectors reviewed the licensee's adverse weather procedures for cold weather and evaluated the licensee's implementation of these procedures. The inspectors verified that prior to the onset of cold weather, the licensee had corrected or plans to correct weather-related equipment deficiencies identified during the previous cold weather season. The inspectors selected the condensate storage tank and hardened condensate storage tank as risk-significant systems that were required to be protected from cold weather.
The inspectors reviewed the licensee's procedures and design information to ensure the systems would remain functional when challenged by cold weather. The inspectors verified that operator actions described in the licensee's procedures were adequate to maintain readiness of these systems. The inspectors walked down portions of these systems to verify the physical condition of the cold weather protection features.
These activities constituted one sample of readiness for seasonal adverse weather, as defined in Inspection Procedure 71111.01.
b. Findings
No findings were identified.
1R04 Equipment Alignment
Partial Walk-Down
a. Inspection Scope
The inspectors performed partial system walk-downs of the following risk-significant systems: October 6, 2016, train B motor-driven auxiliary feed system October 26, 2016, train A class 1E switchgear December 4, 2016, train B emergency exhaust system December 23, 2016, train A component cooling water The inspectors reviewed the licensee's procedures and system design information to determine the correct lineup for the systems. They visually verified that critical portions of the trains were correctly aligned for the existing plant configuration. These activities constituted four partial system walk-down samples as defined in Inspection Procedure 71111.04.
b. Findings
No findings were identified.
1R05 Fire Protection
Quarterly Inspection
a. Inspection Scope
The inspectors evaluated the licensee's fire protection program for operational status and material condition. The inspectors focused their inspection on five plant areas important to safety: November 8, 2016, train A switchgear room, area C-9 November 8, 2016, train B switchgear room, area C-10 November 15, 2016, train A emergency core cooling rooms, area A-2 November 15, 2016, train B emergency core cooling rooms, area A-4 December 1, 2016, train A class 1E air conditioning equipment room, area C-14 For each area, the inspectors evaluated the fire plan against defined hazards and defense-in-depth features in the licensee's fire protection program. The inspectors evaluated control of transient combustibles and ignition sources, fire detection and suppression systems, manual firefighting equipment and capability, passive fire protection features, and compensatory measures for degraded conditions. These activities constituted five quarterly inspection samples, as defined in Inspection Procedure 71111.05.
b. Findings
No findings were identified.
1R11 Licensed Operator Requalification Program and Licensed Operator Performance
.1 Review of Licensed Operator Requalification
a. Inspection Scope
On October 17, 2016, the inspectors observed an evaluated simulator scenario performed by an operating crew. The inspectors assessed the performance of the operators and the evaluators' critique of their performance. The inspectors also assessed the modeling and performance of the simulator during the scenario. These activities constituted completion of one quarterly licensed operator requalification program sample, as defined in Inspection Procedure 71111.11.
b. Findings
No findings were identified.
.2 Review of Licensed Operator Performance
a. Inspection Scope
The inspectors observed the performance of on-shift licensed operators in the plant's main control room. At the time of the observations, the plant was in a period of heightened activity. The inspectors observed the operators' performance of the following activities: November 3, 2016, shift turnover and train B emergency diesel generator surveillance testing December 23, 2016, shift turnover In addition, the inspectors assessed the operators' adherence to plant procedures, including Procedure ODP-ZZ-00001, "Operations Department - Code of Conduct," and other operations department policies. These activities constituted completion of one quarterly licensed operator performance sample, as defined in Inspection Procedure 71111.11.
b. Findings
No findings were identified.
1R12 Maintenance Effectiveness
.1 Routine Maintenance Effectiveness
a. Inspection Scope
On October 27, 2016, the inspectors reviewed door DSK 31011 for instances of degraded performance or conditions on safety-related structures, systems, and components. The inspectors reviewed the extent of condition of possible common cause structure, system, or component failures and evaluated the adequacy of the licensee's corrective actions. The inspectors reviewed the licensee's work practices to evaluate whether these may have played a role in the degradation of the structures, systems, and components. The inspectors assessed the licensee's characterization of the degradation in accordance with 10 CFR 50.65 (the Maintenance Rule), and verified that the licensee was appropriately tracking degraded performance and conditions in accordance with the Maintenance Rule.
These activities constituted completion of one maintenance effectiveness sample as defined in Inspection Procedure 71111.12.
b. Findings
No findings were identified.
.2 Quality Control
a. Inspection Scope
On December 21, 2016, the inspectors reviewed the licensee's dedication of commercial grade snubbers for use in safety-related applications.
These activities constituted completion of one quality control sample, as defined in Inspection Procedure 71111.12.
b. Findings
No findings were identified.
1R13 Maintenance Risk Assessments and Emergent Work Control
a. Inspection Scope
The inspectors reviewed three risk assessments performed by the licensee prior to changes in plant configuration and the risk management actions taken by the licensee in response to elevated risk: October 10, 2016, planned maintenance on train A residual heat removal pump room cooler and train A safety injection pump October 20, 2016, red light socket replacement for BGHIS8149CA, Job 13007136 November 28, 2016, train B spent fuel pool pump room cooler replacement while being the protected train The inspectors verified that these risk assessment were performed timely and in accordance with the requirements of 10 CFR 50.65 (the Maintenance Rule) and plant procedures. The inspectors reviewed the accuracy and completeness of the licensee's risk assessments and verified that the licensee implemented appropriate risk management actions based on the result of the assessments. These activities constituted completion of three maintenance risk assessments and emergent work control inspection samples, as defined in Inspection Procedure 71111.13.
b. Findings
No findings were identified.
1R15 Operability Determinations and Functionality Assessments
a. Inspection Scope
The inspectors reviewed five operability determinations that the licensee performed for degraded or nonconforming structures, systems, or components: July 27, 2016, train B emergency diesel generator #14 fuel injector pump stuck full open October 11, 2016, functionality assessment of door to train B safety injection pump room impaired for train B safety injection pump room cooler replacement November 17, 2016, train B cooling tower bypass valve did not fully close December 19, 2016, train A control room pressurization system ducting missing a plug December 22, 2016, steam generator C main feedwater regulating valve bypass valve hunting while in the full open position The inspectors reviewed the timeliness and technical adequacy of the licensee's evaluations. Where the licensee determined the degraded structures, systems, or components to be operable, the inspectors verified that the licensee's compensatory measures were appropriate to provide reasonable assurance of operability. The inspectors verified that the licensee had considered the effect of other degraded conditions on the operability of the degraded structures, systems, or components. These activities constituted completion of five operability and functionality review sample as defined in Inspection Procedure 71111.15.
b. Findings
No findings were identified.
1R19 Post-Maintenance Testing
a. Inspection Scope
The inspectors reviewed five post-maintenance testing activities that affected risk-significant structures, systems, or components: October 5, 2016, SLG10A, train A residual heat removal pump room cooler November 9, 2016, PKJ01B, train B emergency diesel jacket water keep warm pump November 15, 2016, train B emergency diesel generator supply fan November 17, 2016, train B cooling tower bypass valve November 29, 2016, C atmospheric steam dump The inspectors reviewed licensing- and design-basis documents for the structures, systems, or components and the maintenance and post-maintenance test procedures. The inspectors observed the performance of the post-maintenance tests to verify that the licensee performed the tests in accordance with approved procedures, satisfied the established acceptance criteria, and restored the operability of the affected structures, systems, or components. These activities constituted completion of five post-maintenance testing inspection samples, as defined in Inspection Procedure 71111.19.
b. Findings
One licensee-identified violation is documented in Section
==4OA7 .
1R22 Surveillance Testing
==
a. Inspection Scope
The inspectors observed four risk-significant surveillance tests and reviewed test results to verify that these tests adequately demonstrated that the structures, systems, and components were capable of performing their safety functions: In-service tests: December 20, 2016, train A safety injection pump in-service test Containment isolation valve surveillance tests: December 23, 2016, containment isolation signal phase A slave relay test Other surveillance tests: December 22, 2016, train A load shed and emergency load sequencing test December 27, 2016, train A safety injection signal slave relay test The inspectors verified that these tests met technical specification requirements, that the licensee performed the tests in accordance with their procedures, and that the results of the tests satisfied appropriate acceptance criteria. The inspectors verified that the licensee restored the operability of the affected structures, systems, or components following testing. These activities constituted completion of four surveillance testing inspection samples, as defined in Inspection Procedure 71111.22.
b. Findings
No findings were identified.
Cornerstone:
1EP2 Alert and Notification System Evaluation
a. Inspection Scope
The inspectors verified the adequacy of the licensee's methods for testing the primary and backup alert and notification system, and reviewed siren maintenance records for calendar years 2014, 2015, and 2016. The inspectors also reviewed the licensee's program for identifying emergency planning zone locations requiring tone alert radios and for distributing the radios, and reviewed audits of distribution records. The inspectors interviewed licensee personnel responsible for the maintenance of the primary and backup alert and notification system and reviewed a sample of corrective action system reports written for alert and notification system problems. The inspectors compared the licensee's alert and notification system testing program with criteria in NUREG-0654, "Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants," Revision 1; FEMA Report REP-10, "Guide for the Evaluation of Alert and Notification Systems for Nuclear Power Plants," and the licensee's current FEMA-approved alert and notification system design report, "Callaway Plant Alert and Notification System Design Report," dated October 2014.
These activities constituted completion of one alert and notification system evaluation sample as defined in Inspection Procedure 71114.02.
b. Findings
No findings were identified.
1EP3 Emergency Response Organization Staffing and Augmentation System
a. Inspection Scope
The inspectors verified the licensee's emergency response organization on-shift and augmentation staffing levels were in accordance with the licensee's emergency plan commitments. The inspectors reviewed documentation and discussed with licensee staff the operability of primary and backup systems for augmenting the on-shift emergency response staff to verify the adequacy of the licensee's methods for staffing emergency response facilities, including the licensee's ability to staff pre-planned alternate facilities. The inspectors also reviewed records of emergency response organization augmentation tests and events to determine whether the licensee had maintained a capability to staff emergency response facilities within emergency plan timeliness commitments. These activities constitute completion of one emergency response organization staffing and augmentation testing sample as defined in Inspection Procedure 71114.03.
b. Findings
No findings were identified.
1EP4 Emergency Action Level and Emergency Plan Changes
a. Inspection Scope
The inspectors performed an in-office review of Emergency Plan Implementing Procedure EIP-ZZ-00101, Addendum 2, "Emergency Action Level Technical Basis Document," Revision 11, implemented October 17, 2016. This revision added references to Technical Specification 3.4.16 to the basis description for emergency action level SU4.1, "Sample Analysis indicates RCS activity > Technical Specifications Section 3.4.16 Limits," and corrected minor spelling errors. This revision was compared to its previous revision, to the criteria of NUREG-0654, "Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants," Revision 1, to Nuclear Energy Institute Report 99-01, "Emergency Action Level Methodology," Revision 5, and to the standards in 10 CFR 50.47(b) to determine if the revision adequately implemented the requirements of 10 CFR 50.54(q)(3) and 50.54(q)(4). The inspectors verified that the revision did not decrease the effectiveness of the emergency plan. This review was not documented in a safety evaluation report and did not constitute approval of licensee-generated changes; therefore, this revision is subject to future inspection.
These activities constitute completion of one emergency action level and emergency plan changes sample as defined in Inspection Procedure 71114.04.
b. Findings
No findings were identified.
1EP5 Maintenance of Emergency Preparedness
a. Inspection Scope
The inspectors reviewed the following for the period May 2014 through October 2016: After-action evaluation reports for licensee drills and exercises Independent audits and surveillances of the licensee's emergency preparedness program Self-assessments of the emergency preparedness program conducted by the licensee Licensee evaluations of changes made to the emergency plan and emergency plan implementing procedures Drill and exercise performance issues entered into the licensee's corrective action program Emergency preparedness program issues entered into the licensee's corrective action program Maintenance records for equipment supporting the emergency preparedness program Emergency response organization and emergency planner training records The inspectors reviewed summaries of 344 corrective action program reports associated with emergency preparedness and selected 22 to review against program requirements, to determine the licensee's ability to identify, evaluate, and correct problems in accordance with planning standard 10 CFR 50.47(b)(14) and 10 CFR Part 50, Appendix E, IV.F. The inspectors verified that the licensee accurately and appropriately identified and corrected emergency preparedness weaknesses during critiques and assessments. The inspectors reviewed summaries of 241 evaluations of the impact of changes to the emergency plan and implementing procedures and selected 12 to review against program requirements to determine the licensee's ability to identify reductions in the effectiveness of the emergency plan in accordance with the requirements of 10 CFR 50.54(q)(3) and 50.54(q)(4). The inspectors verified that evaluations of proposed changes to the licensee emergency plan appropriately identified the impact of the changes prior to being implemented. The inspectors reviewed summaries of 235 records of preventative or periodic maintenance for equipment and facilities used to implement the emergency plan, and 190 records of emergent maintenance. The inspectors verified that equipment and facilities were maintained in accordance with the commitments of the licensee's emergency plan. These activities constitute completion of one sample of the maintenance of the licensee's emergency preparedness program as defined in Inspection Procedure 71114.05.
b. Findings
No findings were identified.
1EP6 Drill Evaluation
Training Evolution Observation
a. Inspection Scope
On October 17, 2016, the inspectors observed simulator-based licensed operator requalification training that included implementation of the licensee's emergency plan. The inspectors verified that the licensee's emergency classifications, off-site notifications, and protective action recommendations were appropriate and timely. The inspectors verified that any emergency preparedness weaknesses were appropriately identified by the evaluators and entered into the corrective action program for resolution.
These activities constituted completion of one training observation sample, as defined in Inspection Procedure 71114.06.
b. Findings
No findings were identified.
RADIATION SAFETY
Cornerstones: Public Radiation Safety and Occupational Radiation Safety
2RS2 Occupational ALARA Planning and Controls
a. Inspection Scope
The inspectors assessed licensee performance with respect to maintaining individual and collective radiation exposures as low as is reasonably achievable (ALARA). The inspectors performed this portion of the attachment as a post-outage review. During the inspection the inspectors interviewed licensee personnel, reviewed licensee documents, and evaluated licensee performance in the following areas: Radiological work planning, including work activities of exposure significance, and radiological work planning ALARA evaluations, initial and revised exposure estimates, and exposure mitigation requirements. The inspectors also verified that the licensee's planning identified appropriate dose reduction techniques, reviewed any inconsistencies between intended and actual work activity doses, and determined if post-job (work activity) reviews were conducted to identify lessons learned.
Verification of dose estimates and exposure tracking systems, including the basis for exposure estimates, and measures to track, trend, and if necessary reduce occupational doses for ongoing work activities. The inspectors evaluated the licensee's method for adjusting exposure estimates and reviewed the licensee's evaluations of inconsistent or incongruent results from the licensee's intended radiological outcomes.
Problem identification and resolution for ALARA planning. The inspectors reviewed audits, self-assessments, and corrective action program documents to verify problems were being identified and properly addressed for resolution.
These activities constitute completion of two of the five required samples of occupational ALARA planning and controls program, as defined in Inspection Procedure 71124.02.
b. Findings
No findings were identified.
2RS4 Occupational Dose Assessment
a. Inspection Scope
The inspectors evaluated the accuracy and operability of the licensee's personnel monitoring equipment, verified the accuracy and effectiveness of the licensee's methods for determining total effective dose equivalent, and verified that the licensee was appropriately monitoring occupational dose. The inspectors interviewed licensee personnel, walked down various portions of the plant, and reviewed licensee performance in the following areas: Source term characterization, including characterization of radiation types and energies, hard-to-detect isotopes, and scaling factors External dosimetry including National Voluntary Laboratory Accreditation Program (NVLAP) accreditation, storage, issue, use, and processing of active and passive dosimeters Internal dosimetry, including the licensee's use of whole body counting, use of in vitro bioassay methods, dose assessments based on airborne monitoring, and the adequacy of internal dose assessments Special dosimetric situations, including declared pregnant workers, dosimeter placement and assessment of effective dose equivalent for external exposures, shallow dose equivalent, and neutron dose assessment Problem identification and resolution for occupational dose assessment, the inspectors reviewed audits, self-assessments, and corrective action program documents to verify problems were being identified and properly addressed for resolution These activities constitute completion of the five required samples of occupational dose assessment program, as defined in Inspection Procedure 71124.04.
b. Findings
No findings were identified.
OTHER ACTIVITIES
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Security
4OA1 Performance Indicator Verification
.1 Mitigating Systems Performance Index:
High Pressure Injection Systems (MS07) and Mitigating Systems Performance Index: Residual Heat Removal Systems (MS09)
a. Inspection Scope
The inspectors reviewed the licensee's mitigating system performance index data for the period of fourth quarter 2015 through third quarter 2016 to verify the accuracy and completeness of the reported data. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 7, to determine the accuracy of the reported data. These activities constituted verification of the mitigating system performance index for high pressure injection systems and residual heat removal systems, as defined in Inspection Procedure 71151.
b. Findings
No findings were identified.
.2 Drill/Exercise Performance (EP01)
a. Inspection Scope
The inspectors reviewed the licensee's evaluated exercises and selected drills and exercises conducted between April 2014 and September 2016 to verify the accuracy of the licensee's data for classification, notification, and protective action recommendation opportunities. The inspectors reviewed a sample of the licensee's completed classifications, notifications, and protective action recommendations to verify their timeliness and accuracy. The inspectors used Nuclear Energy Institute Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 7, to determine the accuracy of the reported data.
These activities constituted verification of the drill/exercise performance performance indicator as defined in Inspection Procedure 71151.
b. Findings
No findings were identified.
.3 Emergency Response Organization Drill Participation (EP02)
a. Inspection Scope
The inspectors reviewed the licensee's records for participation in drill and training evolutions between April 2014 and September 2016 to verify the accuracy of the licensee's data for drill participation opportunities. The inspectors verified that all members of the licensee's emergency response organization in the identified key positions had been counted in the reported performance indicator data. The inspectors reviewed the licensee's basis for reporting the percentage of emergency response organization members who participated in a drill. The inspectors reviewed drill attendance records and verified a sample of those reported as participating. The inspectors used Nuclear Energy Institute Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 7, to determine the accuracy of the reported data.
These activities constituted verification of the emergency response organization drill participation performance indicator as defined in Inspection Procedure 71151.
b. Findings
No findings were identified.
.4 Alert and Notification System Reliability (EP03)
a. Inspection Scope
The inspectors reviewed the licensee's records of Alert and Notification System tests conducted between April 2014 and September 2016 to verify the accuracy of the licensee's data for siren system testing opportunities. The inspectors reviewed procedural guidance on assessing Alert and Notification System opportunities and the results of periodic alert and notification system operability tests. The inspectors used Nuclear Energy Institute Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 7, to determine the accuracy of the reported data.
These activities constituted verification of the alert and notification system reliability performance indicator as defined in Inspection Procedure 71151.
b. Findings
No findings were identified.
4OA2 Problem Identification and Resolution
.1 Routine Review
a. Inspection Scope
Throughout the inspection period, the inspectors performed daily reviews of items entered into the licensee's corrective action program and periodically attended the licensee's condition report screening meetings. The inspectors verified that licensee personnel were identifying problems at an appropriate threshold and entering these problems into the corrective action program for resolution. The inspectors verified that the licensee developed and implemented corrective actions commensurate with the significance of the problems identified. The inspectors also reviewed the licensee's problem identification and resolution activities during the performance of the other inspection activities documented in this report.
b. Findings
No findings were identified.
.2 Semiannual Trend Review
a. Inspection Scope
The inspectors reviewed the licensee's corrective action program, performance indicators, system health reports, and other documentation to identify trends that might indicate the existence of a more significant safety issue. The inspectors verified that the licensee was taking corrective actions to address the following identified adverse trends: Increase in safety and human performance issues across the station Increase in equipment failures at the emergency operations facility These activities constituted completion of one semiannual trend review sample, as defined in Inspection Procedure 71152.
b. Observations and Assessments The inspectors evaluated a sample of issues and events that occurred over the course of the past two quarters to determine whether issues were appropriately considered as emerging or adverse trends. The inspectors verified that these issues were addressed within the scope of the corrective action program or through department review and documentation in the quarterly trend presentation for overall assessment. The inspectors' review of the trend related to safety and human performance issues produced the following observation and assessment: During the period of November 14-16, 2016, the licensee had nine safety and human performance issues identified in their corrective action program. The licensee considered this a negative trend, verified the corrective actions for each issue were appropriate, and initiated adverse trend Condition Report 201609248 to determine the causes for the negative trend.
To address the issue the licensee performed the following immediate actions: they designated a safety/nuclear professional advocate for all work activities performed on December 14, 2016; they increased supervisor contact at job sites; and they performed a half-day site-wide stand-down at the department level on December 15, 2016. The licensee is also performing a structured cause analysis to determine why this occurred and identify additional necessary actions. The inspectors evaluated the licensee's response to the negative trend and determined the immediate actions taken were appropriate.
The inspectors' review of the trend related to the increase in equipment failures at the emergency operations facility produced the following observation and assessment: Throughout 2016, several condition reports were written regarding issues on equipment that would support the functionality of the emergency operations facility. Some of the issues involved the HVAC and fire detection systems and were either repeat issues or very similar in nature to previous issues. The licensee evaluated this trend, verified the corrective actions for each issue were appropriate, and initiated trend Condition Report 201605531. The licensees' planned corrective actions are to replace the air conditioning unit to restore reliability of the ventilation system, and they have initiated a job [work order] to troubleshoot and evaluate the fire alarm system to determine the cause of the issues. Additional actions will be planned based on the results of the troubleshooting activities. The inspectors evaluated the licensee's response to the trend and determined the planned actions taken were appropriate.
c. Findings
No findings were identified.
.3 Annual Follow-up of Selected Issues
a. Inspection Scope
During an in-office inspection from October 26 through November 1, 2016, the inspectors reviewed the seven cyber security-related findings documented in Inspection Report 05000483/2014405, ADAMS accession number ML14304A195, for in-depth follow-up review. The inspectors reviewed updated procedures, updated critical digital asset listings, and corrective action documents. The inspectors assessed the licensee's extent of condition reviews, compensatory actions, and pending and completed corrective actions. The inspectors verified that the licensee appropriately prioritized the corrective actions and that these actions were appropriate.
These activities constitute completion of one annual follow-up sample as defined in Inspection Procedure 71152.
b. Findings
No findings were identified.
4OA3 Follow-up of Events and Notices of Enforcement Discretion
.1 (Closed) Licensee Event Report 2015-001-01, Completion of a Shutdown Required by the Technical Specifications
a. Inspection Scope
On July 23, 2015, plant operators became aware of indications of an increase in the reactor coolant system unidentified leak rate. Indications included containment radiation alarms as well as increasing containment humidity and sump levels. A reactor coolant inventory balance indicated an unidentified leak rate of 1.2 gallons per minute, which exceeded the technical specification limit of 1.0 gallons per minute for unidentified leakage. The licensee shut down the plant as required by technical specifications.
The licensee determined the leak was due to seat leakage through the pressurizer auxiliary spray supply drain valve BBV0400 and then through the non-safety related pipe flange immediately downstream of the valve. The licensee tightened the valve, which reduced the leakage to 60 drops per minute, and replaced the flange gasket. The licensee determined the root cause of the leak was that valve BBV0400 was not fully closed using normal closing force in November 2014 during Refueling Outage 20. The valve was replaced in April 2016 during Refuel Outage 21. Additionally, the licensee revised their procedures to require that selected valves (including BBV0400) be closed in Mode 3 using normal force or additional force if leakage is identified.
The inspectors reviewed the licensee's submittal along with corrective action documents. All findings were documented in NRC Inspection Report 05000483/2015004, ADAMS accession number ML16043A051. This licensee event report is closed.
b. Findings
No findings were identified.
.2 (Closed) Licensee Event Report 2015-002-01, Manual Auxiliary Feedwater System Actuation
a. Inspection Scope
On July 23, 2015, during a forced plant outage, the licensee tripped the only running main feedwater pump due to issues with the pump's speed control. Operators manually placed the auxiliary feedwater system in service in accordance with plant procedures. These procedures direct the operators to manually close the motor-driven auxiliary feedwater pump flow control valves (ALHV0005, ALHV0007, ALHV0009 and ALHV0011) and start the pumps. Once the pumps were started, the flow control valves were opened with the exception of ALHV0011 which did not open as demanded. The control room crew sent an operator to investigate and open this valve. The operator locally opened ALHV0011 and, after the valve was off its closed seat, the valve operated as expected from the main control room. The manual actuation of the auxiliary feedwater system was a result of tripping the running main feedwater pump. The licensee determined the cause of the main feed pump speed control issue was a software malfunction in the main feedwater digital control system. This malfunction has only occurred once and the licensee could not recreate the malfunction.
The licensee took corrective actions to revise their procedures to allow the startup feedwater pump to remain in a ready state or be rapidly started if the main feedwater pump has to be tripped. This will help prevent the need to manually actuate the auxiliary feedwater system during a routine plant shutdown. The inspectors reviewed the licensee's submittal along with corrective action documents. All findings were documented in NRC Inspection Reports 05000483/2015003, ADAMS accession number ML15306A580, and 05000483/2015009, ADAMS accession number ML16013A021. This licensee event report is closed.
b. Findings
No findings were identified.
4OA6 Meetings, Including Exit Exit Meeting Summary On November 2, 2016, the inspectors presented the cybersecurity inspection results to Mr. B. Cox, Senior Director, Nuclear Operations, and other members of the licensee staff.
The licensee acknowledged the issues presented. The inspectors did not review any proprietary information. On November 10, 2016, the inspectors presented the radiation safety inspection results to Mr. B. Cox, Senior Director, Nuclear Operations, and other members of the licensee staff. The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed. On November 18, 2016, the inspectors presented the results of the onsite inspection of the licensee's emergency preparedness program to Mr. B. Cox, Senior Director, Nuclear Operations, and other members of the licensee staff. The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed. On January 4, 2017, the inspectors presented the inspection results to Mr. F. Diya, Senior Vice President and Chief Nuclear Officer, and other members of the licensee staff. The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.
4OA7 Licensee-Identified Violations The following violation of very low safety significance (Green) was identified by the licensee and is a violation of NRC requirements which meets the criteria of the NRC Enforcement Policy for being dispositioned as a non-cited violation.
Technical Specification 5.4.1.a requires, in part, that written procedures shall be established, implemented and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Regulatory Guide 1.33, Revision 2, Appendix A, Section 9.a, requires, in part, that maintenance should be properly pre-planned and performed in accordance with documented instructions appropriate to the circumstances. Contrary to the above, on October 19, 2016, the licensee failed to properly pre-plan and perform a post-maintenance test in accordance with documented instructions appropriate to the circumstances. Specifically, the post-maintenance test for work performed on valve EFHV0066, the essential service water to ultimate heat sink cooling tower train B bypass valve, did not include a seat leak test, which would be necessary for the work performed. As a result, on November 17, 2016, operators discovered this valve leaking by at approximately 3900 gallons per minute. The licensee subsequently determined that the safety function of the ultimate heat sink would not be adversely affected with leakage up to 4100 gallons per minute. The inspectors evaluated the significance of the issue under the Significance Determination Process, as defined in Inspection Manual Chapter 0609.04, "Initial Characterization of Findings," and 0609 Appendix A, "The Significance Determination Process (SDP) for Findings at-Power," dated June 19, 2012. The inspectors concluded the finding was of very low safety significance (Green) because all questions in Exhibit 2 could be answered no. The licensee entered this issue into their corrective action program as Condition Report 201608791.
1
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
- S. Banker, Senior Director, Engineering
- T. Becker, Supervising Engineer, Performance Engineering
- F. Bianco, Director, Nuclear Operations
- J. Cortez, Manager, Site Recovery
- B. Cox, Senior Director, Nuclear Operations
- J. Geyer, Radiation Protection Manager
- C. Graham, Consulting Health Physicist
- B. Jungmann, Director, Maintenance
- L. Kanuckel, Director, Nuclear Oversight
- S. Kovaleski, Director, Engineering Design
- J. Kovar, Licensing Engineer
- T. Lowry, Manager, Cyber Security Program
- D. Mangold, Health Physicist
- K. March, Security Analyst, Cyber Security
- V. Miller, Supervising Health Physicist
- S. Petzel, Engineer, Regulatory Affairs
- G. Rauch, Manager, Emergency Preparedness
- J. Small, Manager, Chemistry
- K. Tipton, Supervisor, Engineering Systems
- M. Waller, Manager, Employee Concerns
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Closed
- 05000483/LER-2015-001-01 LER Completion of a Shutdown Required by the Technical Specifications (Section 4OA3.1)
- 05000483/LER-2015-002-01 LER Manual Auxiliary Feedwater System Actuation (Section 4OA3.2)
LIST OF DOCUMENTS REVIEWED
Section 1R01: Adverse Weather Protection Procedures Number Title Revision
- OTN-AP-00001 Condensate Transfer and Storage System 14
- OTN-AP-00003 Hardened Condensate Storage Tank Operations 3
Procedures
- Number Title Revision
- OTN-QJ-00003, Checklist 2 Condensate Storage Tank Heat Tracing Lineup 2
- OTS-ZZ-00007 Plant Cold Weather 32
Condition Reports
- 201000461
- 201608861
- 201609090
- 201609162
- Jobs
- 11002828
- 15004690
- 15511371
- 15511625
- 15512059
- 15512064
- 15512449
- 16001483
- 16005416
- 16005478
- 16005713
- 16005716
- 16005763
- 16005799
- 16005802
- 16005979
- 16005980
- 16005981
- 16005982
- 16005983 16502162
Section 1R04: Equipment Alignment Procedures Number Title Revision
- OTN-AL-00001, Checklist 1 Auxiliary Feedwater Valve Alignment 22
- OTN-AL-00001, Checklist 2 Motor-driven Auxiliary Feedwater Pump A and B Switch Alignment 18
- OTN-AL-00001, Checklist 4 Auxiliary Feedwater Breaker Alignment 18
- OTN-GG-00001 Fuel Building HVAC System 30
- OTN-GG-00001, Checklist 2 Fuel Handling Building HVAC System Breaker Lineup 13
- OTN-GG-00001, Checklist 3 Fuel Handling HVAC System Switch Lineup 13
- OTN-EG-00001 Component Cooling Water System 60
- OTN-EG-00001, Checklist 1 Component Cooling Water System Normal Power Supply Lineup 21
Procedures
- Number Title Revision
- OTN-EG-00001, Checklist 2 Component Cooling Water System Normal Valve Lineup 21
- OTN-EG-00001, Checklist 5 Component Cooling Water System Main Control Board Lineup 21
Drawings
- Number Title Revision M-22AL01(Q) Auxiliary Feedwater System Piping & Instrumentation Diagram 46 M-22EF01(Q) Essential Service Water System Piping & Instrumentation Diagram 79 M-22GG01(Q) Fuel Building HVAC Piping & Instrumentation Diagram 16 M-22GG02(Q) Fuel Building HVAC Piping & Instrumentation Diagram 13 M-22EG01(Q) Component Cooling Water System Piping & Instrumentation Diagram 11 M-22EG02(Q) Component Cooling Water System Piping & Instrumentation Diagram 22 M-22-EG03(Q) Component Cooling Water System Piping & Instrumentation Diagram 24
Condition Reports
- 201602658
- 201608571
- 201605765
- 201607267
- 201608376
- 201609284
- 201608440
- 201607831
- Jobs
- 08003471
- 16003536
- 16004820
- 16005725
Miscellaneous
- Number Title Revision/Date
- LP-06 Systems, Safeguards Power - NB/NG/NK/NN August 20, 2014
- NB-05 System NB Protective Relay Setpoints Calculation 4
Section 1R05: Fire Protection Miscellaneous Number Title Revision
- Fire Preplan Manual 39
- KC-60 C-9 Detailed Fire Modeling Report 0
- KC-61 C-10 Detailed Fire Modeling Report 1
- KC-82 Fire Safety Analysis for Fire Area A-2 1
- KC-84 Fire Safety Analysis for Fire Area A-4 1
- KC-120 Fire Safety Analysis for Fire Area C-9 1
- KC-121 Fire Safety Analysis for Fire Area C-10 1
- KC-125 Fire Safety Analysis for Fire Area C-14 1
Section 1R11: Licensed Operator Requalification Program Procedures Number Title Revision
- APA-ZZ-0100B Job Briefs 18
- ODP-ZZ-00001 Operations Department - Code of Conduct 99
- ODP-ZZ-00001, Addendum 2 Briefs 13
- ODP-ZZ-00003 Shift Relief and Turnover 36
- OSP-NE-0001B Standby Diesel Generator B Periodic Tests 65
Miscellaneous
- Number Title Date
- DS-Cycle 16-4A Dynamic Simulator Exam Scenario August 22, 2016
Section 1R12: Maintenance Effectiveness Procedures Number Title Revision
- MPM-SK-QW001, Addendum 5 Service and Inspection of "Pressure Doors" 0
- OSP-KC-00015 Fire Door Inspections 15
- WEP-ZZ-00001 Commercial Grade Evaluation 14
Condition Reports
- 201104612
- 201302289
- 201608195
- Jobs
- 13001647
- 14508647
- 15509712
- 15512266
Miscellaneous
- Number Title Date CG90006-6 Commercial Grade Evaluation for Gauge Snubbers May 6, 2016 PM0900141 Annual Winter Tamper Testing
- PM1008215 Service Infrequent Use Pressure Doors (A&B)
- PM0907014 FPP Fire Door 12M Inspection
- RFR008750A Install Snubbers on Various AFW Indicators December 18, 1990 RFR008750B Install Snubbers on Various AFW Indicators April 12, 1999 RFR018037C Supplemented - Add Piston Snubber for CCW Suction Pressure Gauges April 14, 1999 RFR020560A Supplemented - Allow Use of Pulsation Dampers on KJ Pressure Transmitters July 21, 2000 RFR020560B Correct Typographical Error to
- RFR 20560A September 22, 2000 RFR020560C Allow Use of Equivalent Piston-Type Snubbers September 27, 2002
Section 1R13: Maintenance Risk Assessment and Emergent Work Controls Procedures Number Title Revision
- EDP-ZZ-01129 Callaway Energy Center Risk Assessment 46
- OTN-BG-00001, Addendum 4 Operation of CVCS Letdown 21
- ODP-ZZ-00002 Equipment Status Control 85
- ODP-ZZ-00002, Appendix 1 Protected Equipment Program 24
- ODP-ZZ-00002, Appendix 2 Risk Management Actions for Planned Risk Significant Activities 11
Drawings
- Number Title Revision M-22EJ01 (Q) Residual Heat Removal System Piping and Instrumentation Diagram 62 M-22EM01 (Q) High Pressure Coolant Injection System Piping and Instrumentation Diagram 38 M-22GL01 (Q) Auxiliary Building HVAC Piping and Instrumentation Diagram 34 M-22GL02 (Q) Auxiliary Building HVAC Piping and Instrumentation Diagram 27
- Jobs
- 08003471
- 13007136
Miscellaneous
- Number Title Date
- Trend Data for Chemical & Volume Control System During Transient on October 20, 2016 December 14, 2016
Section 1R15: Operability Evaluations Procedures Number Title Revision
- APA-ZZ-00220 Records Management 40
- APA-ZZ-00605 Temporary System Modifications 33
- APA-ZZ-00750 Hazard Barrier Program 37
- OTN-NE-0001B, Addendum 3 Diesel Generator B Post Maintenance Run for Fuel System Priming 1
- MSM-KJ-QK001 Emergency Diesel Generator Inspection 35
Drawings
- Number Title Revision M-23FB05 Piping Isometric Auxiliary Steam System Supply Auxiliary Building 2
Condition Reports
- 201603929
- 201603960
- 201606547
- 201606579
- 201606595
Condition Reports
- 201606598
- 201607352
- 201607607
- 201607825
- 201608446
- 201608447
- 201608791
- 201609291
- 201609335
- Jobs
- 11007814
- 14512670
- 15000075
Miscellaneous
- Number Title Revision Date
- DNA History Plot of B Emergency Diesel Generator Power, Current, Amps, and Frequency July 27, 2016
- Fairbanks Morris Engineering Report of
- PC2.5 Fuel Injection Pump August 25, 2016
- Night Order -
- APA-ZZ-00750 Hazard Barrier Program, Identified Discrepancies 3 M-YY-49 Penetrant Test Profiles for Each Room in the Auxiliary Building Resulting from High Energy Line Break 1C M-YY-49, Revision 1, Addendum 4 Additional HELB Scenarios 0
- RFR 201201033 Request for Resolution - Provide Basis for HELB Program 0
Section 1R19: Post-Maintenance Testing Procedures Number Title Revision
- EDP-ZZ-01128 Maintenance Rule Program 24
- EDP-ZZ-01128, Appendix 1 SSCS in the Scope of the Maintenance Rule at Callaway 11
- EDP-ZZ-01128 Appendix 2 Summary of SSC Performance Criteria 31
- EDP-ZZ-01128, Appendix 4 Maintenance Rule System Function 16
- MTE-ZZ-QA015 MOVATS UDS Testing of Limitorque Motor Operated Butterfly Valves 18
- MTM-ZZ-QA006 Limitorque Actuator Electrical Rework and Adjustment 58
- OSP-EF-0002A Essential Service Water Train A Flow Verification 6
Procedures
- Number Title Revision
- OSP-EF-V001B Essential Service Water Train B Valve Operability 53
- OSP-NE-0001B Standby Diesel Generator B Periodic Tests 65
- OTN-NE-0001B Standby Diesel Generation System - Train B 53
- QCP-ZZ-05041 Visual Examination to ASME
- VT-2 29
Condition Reports
- 201608795
- 201608883
- 201609008
- 201609021
- 201609022
- Jobs
- 13006121
- 15004653
- 15004983
- 16005647
- 16005795
- 16512958
- 11503951
- 13000681
- 15510786
- 10502326
- 15511073
- 12002436
- 15001732
- 16006092
Miscellaneous
- Number Title Date
- Vibration Results for CGM01B November 15, 2016
Section 1R22: Surveillance Testing Procedures Number Title Revision
- ISL-NF-NB01A NB01 Degraded & UV to LSELS Channel I 29
- ISL-NF-NB01B NB01 Degraded & UV to LSELS Channel
- II 28
- ISL-NF-NB01C NB01 Degraded & UV to LSELS Channel
- III 27
- ISL-NF-NB01D NB01 Degraded & UV to LSELS Channel
- IV 27
- OSP-EM-P001A Safety Injection Train A Inservice Test - Group B 52
- OSP-SA-0009A Train A CISA Slave Relay Test 19
- OSP-SA-0012A Train A SIS Slave Relay Test 29
Condition Reports
- 201609345
- 201609365
- 201609388
- Jobs
- 16511465
- 16513719
- 16513723
- 16513725
- 16513726
- 16511654 16512085
Section 1EP2: Alert and Notification System Testing Procedures and Documents Number Title Revision
- KSP-ZZ-00008 Tone Alert Radios 7
- KSP-ZZ-00110 Siren Alerting System Testing 14
Condition Reports
- 201404446
- 201406861
- 201501559
- 201504153
- 201504922
- Jobs
- 13503075
- 14502659
- 15500540
Miscellaneous
- Number Title Date
- Preventative Maintenance Records, Sirens 01 through 62 2014
- Preventative Maintenance Records, Sirens 01 through 62 2015
- Preventative Maintenance Records, Sirens 01 through 62 2016
Section 1EP3: Emergency Response Organization Staffing and Augmentation System Procedures and Documents Number Title Revision
- EIP-ZZ-00200 Augmentation of the Emergency Response Organization 21
- KOA-ZZ-00200 Activation of the Callaway Plant Emergency Callout System 17
- KSP-ZZ-00102 Monthly Emergency Communications Testing 14
- KSP-ZZ-00103 Quarterly Emergency Communications Testing 5
- KSP-ZZ-00201 Emergency Augmentation Drill/Test 8
Condition Reports
- 201506484
- 201507987
- 201601334
Miscellaneous
- Number Title Date
- After Action Report for the Off Hours and Augmentation Drill conducted October 29, 2015
- 14500586 ERO Augmentation Testing Results May 17, 2014
- 14505035 ERO Augmentation Testing Results July 25, 2014
- 14508093 ERO Augmentation Testing Results October 7, 2014
- 14510722 ERO Augmentation Testing Results January 17, 2015
- 15500632 ERO Augmentation Testing Results April 20, 2015
- 15504072 ERO Augmentation Testing Results September 2, 2015
- 15511285 ERO Augmentation Testing Results February 15, 2016
- 16501826 ERO Augmentation Testing Results May 25, 2016
- 16506957 ERO Augmentation Testing Results September 8, 2016
- 1EP4:
- Emergency Action Level and Emergency Plan Changes Procedures Number Title Revision
- APA-ZZ-00004 Emergency Preparedness Department Responsibilities 22
- APA-ZZ-00500 Corrective Action Program 65
- APA-ZZ-00500, Appendix 12 Significant Adverse Condition 26
- APA-ZZ-00500, Appendix 13 Adverse Condition 27
- APA-ZZ-00500, Appendix 17 Screening Process Guidelines 29
- APA-ZZ-00500, Appendix 22 Corrective Action Program Definitions 13
- EIP-ZZ-00260 Event Closeout/Plant Recovery 27
- EIP-ZZ-A0001 Emergency Response Organization 18
- EIP-ZZ-A0020 Maintaining Emergency Preparedness 30
Procedures
- Number Title Revision
- EIP-ZZ-A0066 RERP Training Program 24
- KDP-ZZ-00013 Emergency Response Facility and Equipment Evaluation 13, 14
- KDP-ZZ-00013, Appendix 1 Equipment Important to Emergency Response Matrix 3
- KDP-ZZ-00300 Maintaining Emergency Preparedness Supplemental Documents 17
- KDP-ZZ-00400 RERP Impact Evaluations and Changes 23, 24
- KDP-ZZ-02001 Drill and Exercise Program 21, 22
- KSP-ZZ-00004 Emergency Response Facilities 7
- KSP-ZZ-00007 Offsite Effectiveness of the Emergency Preparedness Program 13
- KDP-ZZ-00013 Emergency Response Facility and Equipment Evaluation 14
Condition Reports
- 201404689
- 201405054
- 201404717
- 201404752
- 201404902
- 201502111
- 201504922
- 201505183
- 201505228
- 201505398
- 201505406
- 201505409
- 201507442
- 201507633
- 201507635
- 201507637
- 201507639
- 201507640
- 201600391
- 201606250
- 201606496
- 201606500
- 201606501
- 201605702
- 201608771
- Jobs
- 13512566
- 14504304
- 14508579
- 14511476
- 15502209
- 155022634
- 15505557
- 15508413
- 15508920
- 16500262
- 16501351
- 16504550
- 16502589
- 16505861
Miscellaneous Documents
- Number Title Revision/ Date
- After Action Report for the Exercise conducted May 8, 2014
- After Action Report for the Exercise conducted July 10, 2014
- After Action Report for the Field Monitoring Drill conducted July 10, 2014
Miscellaneous Documents
- Number Title Revision/ Date
- After Action Report for the Contaminated Injured Worker Drill conducted July 10, 2014
- After Action Report for the Exercise conducted August 28, 2014
- After Action Report for the Exercise conducted September 4, 2014
- After Action Report for the Exercise conducted September 11, 2014
- After Action Report for the Exercise conducted September 18, 2014
- After Action Report for the Exercise conducted September 25, 2014
- After Action Report for the Health Physics Drill conducted September 30, 2014
- After Action Report for the Exercise conducted January 8, 2015
- After Action Report for the Exercise conducted January 15, 2015
- After Action Report for the Exercise conducted January 22, 2015
- After Action Report for the Exercise conducted January 29, 2015
- After Action Report for the Exercise conducted February 5, 2015
- After Action Report for the Exercise conducted February 12, 2015
- After Action Report for the Exercise conducted March 10, 2015
- After Action Report for the Exercise conducted May 5, 2015
- After Action Report for the Health Physics Drill conducted June 10, 2015
- After Action Report for the Health Physics Drill conducted September 17, 2015
- After Action Report for the Exercise conducted September 16, 2015
- After Action Report for the Exercise conducted September 23, 2015
Miscellaneous Documents
- Number Title Revision/ Date
- After Action Report for the Exercise conducted September 30, 2015
- After Action Report for the Exercise conducted October 7, 2015
- After Action Report for the Exercise conducted October 14, 2015
- After Action Report for the Exercise conducted October 21, 2015
- After Action Report for the Exercise conducted December 10, 2015
- After Action Report for the Radiological Monitoring Drill conducted December 10, 2015
- After Action Report for the Exercise conducted January 14, 2016
- After Action Report for the Exercise conducted January 21, 2016
- After Action Report for the Exercise conducted January 28, 2016
- After Action Report for the Exercise conducted February 4, 2016
- After Action Report for the Exercise conducted February 11, 2016
- After Action Report for the Exercise conducted February 18, 2016
- After Action Report for the Exercise conducted June 16, 2016
- After Action Report for the Health Physics Drill conducted June16, 2016
- After Action Report for the Environmental Monitoring Drill conducted September 1, 2016
- After Action Report for the Health Physics Drill conducted September 8, 2016
- After Action Report for the Contaminated Injured Worker Drill conducted November 8, 2016
- Benchmark
- 201600062-04, ERO Improvement February 15, 2016
- Callaway Plant Radiological Emergency Response Plan 47
Miscellaneous Documents
- Number Title Revision/ Date
- Simple Self Assessment
- 201308863-24, Effectiveness Review Emergency Preparedness Standards March 3, 2014
- Student Critique Comments for Session
- Emergency Preparedness Equipment Repair Status, Second Quarter 2014
- Emergency Preparedness Equipment Repair Status, Third Quarter 2014
- Emergency Preparedness Equipment Repair Status, Fourth Quarter 2014 PM0912068 November 3, 2014, Media Day Package
- PM0912069 Annual EP Brochure Mailing and Follow-up, 2015
Section 1EP6: Drill Evaluation Procedures Number Title Revision
- EIP-ZZ-00101, Addendum 2 Emergency Action Level Technical Bases Document 11
Miscellaneous
- Number Title Date
- DS-Cycle 16-4A Dynamic Simulator Exam Scenario August 22, 2016
Section 2RS2: Occupational
- ALARA Planning and Controls Procedures Number Title Revision
- APA-ZZ-01001 Callaway Plant ALARA Program 26
- APA-ZZ-01004 Radiological Work Standards 28
- HDP-ZZ-01100 ALARA Planning and Review 19
- HDP-ZZ-01200 Radiation Work Permits 30
- HDP-ZZ-01500 Radiological Postings 44
Procedures
- Number Title Revision
- HTP-ZZ-06001 High Radiation/Locked High Radiation/Very High Radiation Area Access 50
- Audits and Self-Assessments Number Title Date AP15-002 Nuclear Oversight Audit of Radiation Protection February 23, 2015 20140632-6.2 Radiation Safety Self-Assessment October 12, 2015
Condition Reports
- 201500844
- 201507845
- 201508261
- 201508608
- 201600550
- 201601052
- 201602957
- 201603512
- 201604028
- 201607143
- 201600999
- 201605317
- 201604480
- 201603017
- 201507021
- 201603425
- 201607667
- 201607832
- 201608655
- 201600468
- 201604746
- 201602487
- 201506676
- Radiation Work Permits Number Title Revision
- 210813187 Install Stud Tensioner Hoists, Detension Reactor Vessel Studs 0 210917004MAN Steam Generator Manway Cover Removal, Re-installation and Bolt Hole Work 1 210917004PLUG Steam Generator Tube Plugging and Stabilizing, Including Setup 2
- 15004134 Load Legacy Waste drums into cask and Ship Legacy Waste Drums 0
- ALARA Planning, In-Progress Reviews, and Post-Job Reviews Number Title Revision
- 210813187 Install Stud Tensioner Hoists, Detension Reactor Vessel Studs 0 210917004MAN Steam Generator Manway Cover Removal, Re-installation and Bolt Hole Work 1
- ALARA Planning, In-Progress Reviews, and Post-Job Reviews Number Title Revision 210917004PLUG Steam Generator Tube Plugging and Stabilizing, Including Setup 2 21091700EC Steam Generator Tube Eddy Current Testing In All Four Steam Generators 2
Miscellaneous Documents
- Number Title Revision
- Callaway Energy Center Long Range Dose And Source Term Reduction Plan 6
- Refuel Outage 21 Outage ALARA Report
- Selected Log Entries from the Outage Control Center (OCC) Refuel Outage 21
Section 2RS4: Occupational Dose Assessment Procedures Number Title Revision
- APA-ZZ-00014 Conduct of Operations - Radiation Protection 22
- APA-ZZ-01000 Callaway Energy Center Radiation Protection Program 41
- APA-ZZ-01000, Appendix A Control of Radioactive Material 20
- APA-ZZ-01004 Radiological Work Standards 28
- APA-ZZ-01004, Appendix A General Instructions for Donning / Removing Protective Clothing 6
- APA-ZZ-01004, Appendix B General Instructions for Personnel Frisking Upon Exit from Satellite RCA or Contaminated Area 5
- APA-ZZ-01004, Appendix C General Instructions for Donning / Removing Respiratory Equipment
- 6
- APA-ZZ-01004, Appendix D General Instructions for Use of Primary Monitoring Device 2
- HDM-ZM-01300 Internal Dose Assessment Guidelines 0
- HDP-ZZ-1200 Radiation Work Permits 30
- HDP-ZZ-01300 Internal Dosimetry Program 34
- HDP-ZZ-01433 Personnel Exposure Records 56
- HDP-ZZ-01500 Radiological Postings 44
Procedures
- Number Title Revision
- HDP-ZZ-06001 High Radiation / Locked High Radiation / Very High Radiation Area Access 50
- HTP-HC-09002 10
- CFR 61 Sampling Program 4
- HTP-ZZ-1302-DTI-DPW Response to Positive In Vitro Count for Declared Pregnant Woman 6
- HTP-ZZ-1302-DTI-Entry/Return Response to Positive Entry or Return from Trip In Vitro Count
- 8
- HTP-ZZ-1302-DTI-Medical-Admin Response to a Medical Administration of Radioactive Nuclides 4
- HTP-ZZ-1302-DTI-Routine / Diag Response to Positive Routine or Diagnostic In Vitro Count 17
- HTP-ZZ-1302-DTI-Terminations Response to Positive Termination In Vitro Count 20
- HTP-ZZ-1320-DTI-Initial Dose Initial Assessment of Internal Dose Equivalent 13
- HTP-ZZ-01433 Personnel Exposure Records 57
- HTP-ZZ-04700 Count Room and Whole Body Counter Quality Control Program 19
- HTP-ZZ-06009 Personnel Contamination Assessment and Decontamination 49
- RP-DTI-Air Sample Dose
- Intake Assessment from Air Samples 6
- RP-DTI-Count Room Routines Count Room Routine Activities 23
- RP-DTI-In Vitro Bioassay In Vitro Bioassay Sample Collection 2
- RP-DTI-TRU Assessment Alpha Monitoring Facility Characterization 6
- Audits and Self-Assessments Number Title Date AP15-002 Nuclear Oversight Audit of Radiation Protection February 23, 2015 AP16-003 Nuclear Oversight Audit of the Radiological and Non-Radiological Environmental Monitoring Programs July 15, 2016
Condition Reports
- 201301109
- 201505336
- 201600999
- 201601787
- 201602487
- 201603733
- 201605807
- 201606446
- 201607143
Miscellaneous Documents
- Number Title Revision/Date
- Nuclide Distribution Report September 10, 2015
- NVLAP Certificate of Accreditation; Effective Dates 01/01/2016 through 12/31/2016 Reviewed November 7, 2016
- Calibration of the FastScan
- FS-5301-HP October 11, 2016
- Calibration of the Chair Whole Body Counter April 24, 2015
- Selected Dosimetry Records for Declared Pregnant Workers 2015 and 2016
- Selected Investigations of Potentially Discrepant Dosimetry Records 2015 and 2016 HPIC 0202 Electronic Dosimeter Calibration Adjustment Factor 2 PM0700003 Preventive Maintenance Surveillance to Perform 10
- CFR 61 Analysis
- August 11, 2016
Section 4OA1: Performance Indicator Verification Procedures Number Title Revision
- MSPI Basis Document 17
- APA-ZZ-01111 Mitigating Systems Performance Index (MSPI) Program Administration 4
- APA-ZZ-01111, App A MSPI/WANO Performance Indicators, Data Collection and Reporting 10
- RRA-ZZ-00001 NRC Performance Indicator Program 9
- KDP-ZZ-02000 NRC Performance Indicator Data Collection 17, 18
- KSP-ZZ-00110 Siren Alerting System Testing 14
- EIP-ZZ-00101 Classification of Emergencies 52, 53
- EIP-ZZ-00101, Addendum 2 Emergency Action Level Technical Bases Document 10, 11
Procedures
- Number Title Revision
- EIP-ZZ-00201 Notification 50
- EIP-ZZ-00201, Addendum 1 Control Room Notification Flowchart 26
- EIP-ZZ-00201, Addendum C EOF Notification Package 27
- EIP-ZZ-00212 Protective Action Recommendations 27, 28
- KOA-ZZ-04000 Completing the Offsite Notification Form 1
Condition Reports
- 201501539
- 201502626
- 201506160
- 201506748
- 201507416
- 2010508761
- 201602049
- 201602658
- 201603389
- 201603472
- 201603598
- 201604942
- 20160180
- 201605700
- 201606472
- 201606516
- 201607559
- 201607695
- 201607736
- 201607748
- 201607841
- 201608021
- 201608148
- 201608215
- 201608656
- 201608823 201608824
Section 4OA2: Identification and Resolution of Problems Procedures Number Title Revision
- APA-ZZ-00500, Appendix 10 Trending Program 12
- APA-ZZ-01108 Cyber Security Program 4
- APA-ZZ-01108, Addendum A
- CDA-Related Removable Media and Removable / Portable Device Management 6
- EDP-ZZ-01108 Cyber Security Program Implementation 6
- EDP-ZZ-01108, Addendum 1 Digital Assessment Process 8
- DTI-CS-004 Malware Scanning DTI 6
- SDP-PI-CYBER Cyber Security 2
Condition Reports
- 201303314
- 201304697
- 201305571
- 201306011
- 201306178
- 201306390
- 201308134
- 201401611
- 2014003533
- 201404013
Condition Reports
- 201404421
- 201404982
- 201405213
- 201405220
- 201405223
- 201405224
- 201406337
- 201406343
- 201507992
- 201607443
- 201607679
- 201607960
- 201608761
- 201609248
Miscellaneous
- Number Title Revision J-113A-00493 Data Diode Block Diagram 0
- Whitepaper - Callaway Actions to Correct Issues Related to Milestone1-7 Inspection Report
- 2014405
- Whitepaper - CDAs identified since the Milestone 1-7 Inspection
- CDA Kiosk Malware Scanning and Data Transfer Guidance The following items are requested for the Occupational/Public Radiation Safety Inspection at Callaway Plant November 7 through 10, 2016 Integrated Report
- 2016004
- Inspection areas are listed in the attachments below.
- Please provide the requested information on or before October 17, 2016.
- Please submit this information using the same lettering system as below.
- For example, all contacts and phone numbers for Inspection Procedure 71124.01 should be in a file/folder titled "1- A," applicable organization charts in file/folder "1- B," etc.
- If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at least 30 days later than the onsite inspection dates, so the inspectors will have access to the information while writing the report.
- In addition to the corrective action document lists provided for each inspection procedure listed below, please provide updated lists of corrective action documents at the entrance meeting.
- The dates for these lists should range from the end dates of the original lists to the day of the entrance meeting.
- If more than one inspection procedure is to be conducted and the information requests appear to be redundant, there is no need to provide duplicate copies.
- Enter a note explaining in which file the information can be found.
- If you have any questions or comments, please contact Martin J. Phalen at (817) 200-1158 or martin.phalen@nrc.gov.
- PAPERWORK REDUCTION ACT STATEMENT This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).
- Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011.
- 2.
- Date of Last Inspection: October 26-30, 2015
- A. List of contacts and telephone numbers for ALARA program personnel. B. Applicable organization charts. C. Copies of audits, self-assessments, and LERs, written since September 1, 2015, focusing on ALARA. D. Procedure index for ALARA Program. E. Please provide specific procedures related to the following areas noted below.
- Additional Specific Procedures may be requested by number after the inspector reviews the procedure indexes.
- 1. ALARA Program 2. ALARA Committee 3. Radiation Work Permit Preparation F. A summary list of corrective action documents (including corporate and sub-tiered systems) written since September 1, 2015, related to the ALARA program.
- In addition to ALARA, the summary should also address Radiation Work Permit violations, Electronic Dosimeter Alarms, and RWP Dose Estimates. List of Condition Reports initiated by Radiation Protection, since September 1, 2015. NOTE: The lists should indicate the significance level of each issue and the search criteria used.
- Please provide in document formats which are "searchable" so that the inspector can perform word searches. G.
- List of work activities greater than 1 rem, since September 1, 2015,
- Include original dose estimate and actual dose.
- H. Site dose totals and 3-year rolling averages for the past 3 years (based on dose of record). I. Outline of source term reduction strategy. J. If available, provide a copy of the ALARA outage report for the most recently completed outages for each unit. K. Please provide your most recent Annual ALARA Report.
- 4.
- Occupational Dose Assessment (Inspection Procedure 71124.04) Date of Last Inspection: August 25-29, 2014
- A. List of contacts and telephone numbers for the following areas: 1. Dose Assessment personnel B. Applicable organization charts. C. Audits, self-assessments, vendor or NUPIC audits of contractor support, and LERs written since August 1, 2014, related to: 1. Occupational Dose Assessment D. Procedure indexes for the following areas: 1. Occupational Dose Assessment E. Please provide specific procedures related to the following areas noted below.
- Additional Specific Procedures will be requested by number after the inspector reviews the procedure indexes.
- 1. Radiation Protection Program 2. Radiation Protection Conduct of Operations 3. Personnel Dosimetry Program 4. Radiological Posting and Warning Devices 5. Air Sample Analysis 6. Performance of High Exposure Work 7. Declared Pregnant Worker 8. Bioassay Program F. List of corrective action documents (including corporate and sub-tiered systems) written since August 1, 2014, associated with: 1. National Voluntary Laboratory Accreditation Program (NVLAP) 2. Dosimetry (TLD/OSL, etc.) problems 3. Electronic alarming dosimeters 4. Bioassays or internally deposited radionuclides or internal dose 5. Neutron dose NOTE: The lists should indicate the significance level of each issue and the search criteria used.
- Please provide in document formats which are "searchable" so that the inspector can perform word searches. G. List of positive whole body counts since August 1, 2014, names redacted if desired. H. Part 61 analyses/scaling factors. I. The most recent National Voluntary Laboratory Accreditation Program (NVLAP) accreditation report or, if dosimetry is provided by a vendor, the vendor's most recent results.