IR 05000483/2015005

From kanterella
Jump to navigation Jump to search
Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2015005)
ML15243A555
Person / Time
Site: Callaway Ameren icon.png
Issue date: 09/01/2015
From: Nick Taylor
NRC/RGN-IV/DRP/RPB-B
To: Diya F
Union Electric Co
Nicholas Taylor
References
IR 2015005
Download: ML15243A555 (6)


Text

UNITED STATES ber 1, 2015

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 0500483/2015005)

Dear Mr. Diya:

On August 11, 2015, the Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of the Callaway Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2014 through June 30, 2015. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined that overall, Callaway Plant operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Callaway Plant during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2017. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.

In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool

Instrumentation, which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 817-200-1141 with any questions you have regarding this letter.

Sincerely,

/RA/

Nicholas H. Taylor, Branch Chief Project Branch B Division of Reactor Projects Docket No. 50-483 License No. NPF-30 Enclosure: Callaway Plant Inspection/

Activity Plan

SUNSI Review ADAMS Publicly Available Non-Sensitive By: NHTaylor Yes No Non-Publicly Available Sensitive OFFICE RIV/BC/DRP RIV/D/DRS RIV/D/DRP NAME NTaylor AVegel TPruett SIGNATURE /RA/ /RA/ /RA/

DATE 8/26/15 8/26/15 8/27/15

Letter to Fadi Diya from Nicholas H. Taylor dated September 1, 2015 SUBJECT: ANNUAL ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2015005)

DISTRIBUTION:

Regional Administrator (Marc.Dapas@nrc.gov)

Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Thomas.Hartman@nrc.gov)

Resident Inspector (Michael.Langelier@nrc.gov)

Branch Chief, DRP/B (Nicholas.Taylor@nrc.gov)

Senior Project Engineer, DRP/B (David.Proulx@nrc.gov)

Project Engineer, DRP/B (Steven.Janicki@nrc.gov)

Project Engineer, DRP/B (Shawn.Money@nrc.gov)

CWY Administrative Assistant (Dawn.Yancey@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

RIV State Liaison Officer (Bill.Maier@nrc.gov)

Project Manager (John.Klos@nrc.gov)

Acting Team Leader, DRS/TSS (Eric.Ruesch@nrc.gov)

Director, DIRS, NRR (Scott.Morris@nrc.gov)

Deputy Director, DIRS, NRR (Allen.Howe@nrc.gov)

Acting Director, DORL, NRR (Anne.Boland@nrc.gov)

Acting Deputy Director, DORL (George.Wilson@nrc.gov)

Director, NSIR/DPR (Rob.Lewis@nrc.gov)

Chief, PLB IV, DORL, NRR (Michael.Markey@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Cindy.Rosales-Cooper@nrc.gov)

ROPassessment Resource@nrc.gov ROPreports@nrc.gov OEMail Resource@nrc.gov Electronic Distribution for Callaway Plant

Page 1 of 2 Callaway 08/26/2015 14:05:49 Inspection / Activity Plan Report 22 07/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site INSP - OPERATOR REQUAL INSPECTION 3 1 06/15/2015 09/30/2015 IP 7111111B Licensed Operator Requalification Program RS 5678 - RADIATION SAFETY - TEAM 4 1 07/13/2015 07/17/2015 IP 71124.05 Radiation Monitoring Instrumentation 1 07/13/2015 07/17/2015 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 07/13/2015 07/17/2015 IP 71124.07 Radiological Environmental Monitoring Program 1 07/13/2015 07/17/2015 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation RS 12 PI - RADIATION SAFETY 2 1 10/26/2015 10/30/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 10/26/2015 10/30/2015 IP 71124.02 Occupational ALARA Planning and Controls 1 10/26/2015 10/30/2015 IP 71151-OR01 Occupational Exposure Control Effectiveness 1 10/26/2015 10/30/2015 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences EXAMS - INITIAL OPERATOR EXAM 4 1 04/18/2016 04/22/2016 X02571 INITIAL EXAM CALLOWAY (05/2016)

1 05/23/2016 05/27/2016 X02571 INITIAL EXAM CALLOWAY (05/2016)

TSB 52B - BIENNIAL PI&R INSPECTION 4 1 02/29/2016 03/04/2016 IP 71152B Problem Identification and Resolution 1 03/14/2016 03/18/2016 IP 71152B Problem Identification and Resolution RS 13 PI - RADIATION SAFETY 2 1 04/11/2016 04/15/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 04/11/2016 04/15/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 04/11/2016 04/15/2016 IP 71151-OR01 Occupational Exposure Control Effectiveness 1 04/11/2016 04/15/2016 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71111.08 - INSERVICE INSPECTION RF21 1 1 04/11/2016 04/22/2016 IP 7111108P Inservice Inspection Activities - PWR EB1-17T - CWY PERM PLANT MODS & 50.59 INSPECTION 1 1 06/13/2016 06/27/2016 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications EP-1 - EP PERFORMANCE INDICATORS 1 1 07/25/2016 07/29/2016 IP 71151-EP01 Drill/Exercise Performance 1 07/25/2016 07/29/2016 IP 71151-EP02 ERO Readiness 1 07/25/2016 07/29/2016 IP 71151-EP03 Alert & Notification System Reliability EP-2 - BIENNIAL EP PROGRAM INSPECTION 1 1 07/25/2016 07/29/2016 IP 7111402 Alert and Notification System Testing 1 07/25/2016 07/29/2016 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 Callaway 08/26/2015 14:05:49 Inspection / Activity Plan Report 22 07/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EP-2 - BIENNIAL EP PROGRAM INSPECTION 1 1 07/25/2016 07/29/2016 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 07/25/2016 07/29/2016 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies EB1-07T - CWY HEAT SINK PERFORMANCE 1 1 10/24/2016 10/28/2016 IP 7111107T Heat Sink Performance RS 24 - RADIATION SAFETY 2 1 11/07/2016 11/11/2016 IP 71124.02 Occupational ALARA Planning and Controls 1 11/07/2016 11/11/2016 IP 71124.04 Occupational Dose Assessment RS 5678 - RS TEAM 5 1 02/27/2017 03/03/2017 IP 71124.05 Radiation Monitoring Instrumentation 1 02/27/2017 03/03/2017 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 02/27/2017 03/03/2017 IP 71124.07 Radiological Environmental Monitoring Program 1 02/27/2017 03/03/2017 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation EP-2 - BIENNIAL EP EXERCISE INSPECTION 4 1 04/24/2017 04/28/2017 IP 7111401 Exercise Evaluation EP-3 - EP PERFORMANCE INDICATOR VERIFICATION 1 1 04/24/2017 04/28/2017 IP 71151-EP01 Drill/Exercise Performance 1 04/24/2017 04/28/2017 IP 71151-EP02 ERO Readiness 1 04/24/2017 04/28/2017 IP 71151-EP03 Alert & Notification System Reliability BRQ - BIENNIAL REQUAL INSPECTION 2 1 06/12/2017 06/16/2017 IP 7111111B Licensed Operator Requalification Program This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.