MONTHYEARIR 05000483/20240052024-08-14014 August 2024 Updated Inspection Plan for Callaway Plant (Report 05000483/2024005) ML24088A3212024-04-0101 April 2024 Notification of Commercial Grade Dedication Inspection (05000483/2024013) and Request for Information ML24066A1932024-03-0707 March 2024 2024 Callaway Plant Notification of Biennial Problem Identification and Resolution Inspection and Request for Information IR 05000483/20230062024-02-28028 February 2024 Annual Assessment Letter for Callaway Plant Report 05000483/2023006 ML24011A1492024-01-11011 January 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information (05000483/2024011) IR 05000483/20240122023-10-24024 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (05000483/2024012) IR 05000483/20230052023-08-23023 August 2023 Updated Inspection Plan for Callaway Nuclear Power Plant, Unit 1 (Report 05000483/2023005) - Mid Cycle Letter 2023 ML23158A1462023-06-13013 June 2023 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000483/2023010) ML23163A1572023-06-0606 June 2023 In-service Inspection Request for Information ML23080A1382023-03-21021 March 2023 Notification of Inspection (NRC Inspection Report 05000483/2023003) and Request for Information IR 05000483/20220062023-03-0101 March 2023 Annual Assessment Letter for Callaway Plant (Report 05000483/2022006) ML23027A0362023-01-27027 January 2023 Information Request, Security IR 2023402 IR 05000483/20220052022-08-23023 August 2022 Updated Inspection Plan for Callaway Plant (Report 05000483/2022005) ML22173A0562022-06-22022 June 2022 Information Request, Security IR 2022402 IR 05000483/20210062022-03-0202 March 2022 Annual Assessment Letter for Callaway Plant (Report 05000483/2021006) ML21336A6392021-12-0202 December 2021 .05 Sec Doc Request IR 05000483/20224022021-11-30030 November 2021 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000483/2022402 IR 05000483/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Callaway Plant (Report 05000483/2021005) ML21195A0252021-07-13013 July 2021 Email 7-13-21 Request for Information - Callaway EP Exercise Inspection - Sept 2021 ML21088A3872021-03-30030 March 2021 Notification of Evaluations of Changes, Tests, and Experiments Inspection (Inspection Report 05000483/2021002) and Request for Information ML21069A3422021-03-11011 March 2021 Notification of Inspection (NRC Inspection Report 05000483/2021003) and Request for Information ML21055A0062021-03-0303 March 2021 Annual Assessment Letter for Callaway Plant (Report 05000483/2020006) ML20245E4402020-09-0101 September 2020 Cwy Inspection Schedule Mc 2020 IR 05000483/20200052020-09-0101 September 2020 Updated Inspection Plan for Callaway Plant (Report 05000483/2020005) IR 05000483/20190062020-03-0303 March 2020 Annual Assessment Letter for Callaway Plant (Report 05000483/2019006) ML19347D1482019-12-11011 December 2019 Cwy Security Inspection Information Request 2020410 IR 05000483/20190052019-08-30030 August 2019 Updated Inspection Plan for Callaway Plant Unit 1, Report No. 05000483/2019005 ML19199A1812019-07-18018 July 2019 Notification of NRC Design Base Assurance Inspection (Programs) (05000483/2019011) and Initial Request for Information IR 05000483/20180062019-03-0404 March 2019 Annual Assessment Letter for Callaway Plant (Report 05000483/2018006) ML19023A2032019-01-22022 January 2019 Notification of NRC Triennial Heat Sink Performance Inspection (05000483/2019001) and Request for Information IR 05000483/20170062018-03-0101 March 2018 Annual Assessment Letter for Callaway Plant (Report 05000483/2017006) IR 05000483/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000483/2017005) IR 05000483/20160062017-03-0101 March 2017 Annual Assessment Letter for Callaway Plant (Report 05000483/2016006) IR 05000483/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2016005) ML16237A0332016-08-31031 August 2016 Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2016005) IR 05000483/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Callaway Plant (NRC Physical Security Inspection Report Number 05000483/2016401) IR 05000483/20150062016-03-0202 March 2016 Annual Assessment Letter for Callaway Plant (Report 05000483/2015006) IR 05000483/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2015005) ML15244B0922015-09-0101 September 2015 Non-Public Security Inspection Plan for Callaway Plant (NRC Physical Security Inspection Report Number 05000483/2015401) ML15023A0962015-01-23023 January 2015 Notification of Conduct of a Triennial Fire Protection Baseline IR 05000483/2015007 and Request for Information IR 05000483/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Callaway Plant (NRC Physical Security Inspection Report Number 05000483/2014402) IR 05000483/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2014006) IR 05000483/20130012014-03-0404 March 2014 Annual Assessment Letter for Callaway Plant (Report 05000483/2013001) ML14027A2792014-01-27027 January 2014 Information Request for NRC Triennial Baseline Component Design Bases Inspection NRC Inspection Report 05000483-14-007 IR 05000483/20134052013-09-26026 September 2013 Callaway Plant - Notification of TI-186 Inspection (NRC Inspection Report 05000483-13-405) and Request for Information ML13269A4372013-09-26026 September 2013 Notification of TI-186 Inspection (NRC Inspection Report 05000483-13-405) and Request for Information ML13246A2822013-09-0303 September 2013 Mid-Cycle Assessment Letter 2013 IR 05000483/20128012013-03-0404 March 2013 Annual Assessment Letter for Callaway Plant (Report 05000483/2012801) IR 05000483/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - Callaway Plant (05000483/2012006) IR 05000483/20120012012-03-0505 March 2012 Annual Assessment Letter for Callaway Plant (Report 05000483/2012001) 2024-08-14
[Table view] Category:Letter
MONTHYEARIR 05000483/20240032024-10-23023 October 2024 Integrated Inspection Report 05000483/2024003 IR 05000483/20240132024-10-21021 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000483/2024013 IR 05000483/20244012024-10-0909 October 2024 Material Control and Accounting Program Inspection Report 05000483/2024401 Public ULNRC-06901, Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter)2024-10-0101 October 2024 Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter) ML24247A3042024-09-11011 September 2024 Regulatory Audit Questions for License Renewal Commitments 34 and 35 (EPID L-2024-LRO-0009) - Non-Proprietary IR 05000483/20244032024-08-28028 August 2024 Security Baseline Inspection 05000483-2024-403 IR 05000483/20240052024-08-14014 August 2024 Updated Inspection Plan for Callaway Plant (Report 05000483/2024005) IR 05000483/20253012024-08-0505 August 2024 Notification of NRC Initial Operator Licensing Examination 05000483/2025301 ML24212A2822024-08-0202 August 2024 Regulatory Audit Summary Concerning Review of Request No. C3R-01 for Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections IR 05000483/20240022024-07-18018 July 2024 And Independent Spent Fuel Storage Installation Integrated Inspection Report 05000483/2024002 and 07201045/2024001 ML24185A1032024-07-16016 July 2024 2024 Biennial Problem Identification and Resolution Inspection Report ULNRC-06892, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00062024-06-26026 June 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0006 ULNRC-06891, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00052024-06-26026 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0005 ULNRC-06884, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00022024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0002 ULNRC-06886, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00042024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0004 ULNRC-06885, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00032024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0003 ML24144A0492024-06-11011 June 2024 Requests for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML24158A5222024-06-0606 June 2024 Application to Revise Technical Specifications to Adopt Tstf-569, Rev. 2, Revise Response Time Testing Definition (LDCN 24-0008) ML24178A1132024-06-0606 June 2024 Ameren Missouris Intent to Adopt Revision 1 to Amendment 0 of Certificate of Compliance No. 1040 as Applicable to the ISFSI at the Callaway Plant Site ML24143A1632024-05-23023 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Storage Canister HGMPC0001 ULNRC-06882, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00122024-05-16016 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0012 ML24137A2342024-05-16016 May 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Canister HGMPC0011 ML24122A1502024-05-0707 May 2024 Audit Plan to Support Review of Steam Generator License Renewal Response to Commitment Nos 34 and 35 ULNRC-06877, Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 252024-05-0606 May 2024 Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 25 IR 05000483/20244022024-05-0606 May 2024 Security Baseline Inspection Report 05000483/2024402 (Full Report) IR 05000483/20240112024-05-0101 May 2024 NRC Post-Approval Site Inspection for License Renewal (Phase 2) Report 05000483/2024011 ULNRC-06856, CFR 50.59 and 10 CFR 72.48 Summary Report2024-05-0101 May 2024 CFR 50.59 and 10 CFR 72.48 Summary Report ULNRC-06869, Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report ML24122A1132024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radioactive Effluent Release Report ULNRC-06876, Registration of Dry Spent Fuel Storage Canister HGMPC00102024-04-25025 April 2024 Registration of Dry Spent Fuel Storage Canister HGMPC0010 ML24108A1082024-04-17017 April 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0009 ULNRC-06871, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00072024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0007 ULNRC-06872, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00082024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0008 ULNRC-06866, Submittal of Cycle 26 Commitment Change Summary Report2024-04-17017 April 2024 Submittal of Cycle 26 Commitment Change Summary Report IR 05000483/20240012024-04-16016 April 2024 Integrated Inspection Report 05000483/2024001 IR 05000483/20244042024-04-0909 April 2024 Cyber Security Inspection Report 05000483/2024404 ML24088A3212024-04-0101 April 2024 Notification of Commercial Grade Dedication Inspection (05000483/2024013) and Request for Information ML24086A5132024-03-26026 March 2024 CFR 50.46 Annual Report Regarding ECCS Evaluation Model Revisions ULNRC-06863, Submittal of Annual Exposure Report for 20232024-03-20020 March 2024 Submittal of Annual Exposure Report for 2023 ML24079A1622024-03-19019 March 2024 Re Nuclear Property Insurance Reporting ML24066A1932024-03-0707 March 2024 2024 Callaway Plant Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ULNRC-06852, Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 262024-03-0505 March 2024 Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 26 IR 05000483/20230062024-02-28028 February 2024 Annual Assessment Letter for Callaway Plant Report 05000483/2023006 ML24052A3662024-02-26026 February 2024 Regulatory Audit Plan in Support of Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections ULNRC-06858, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-02-21021 February 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation ML24036A1712024-02-20020 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0079 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) IR 05000483/20230042024-01-19019 January 2024 – Integrated Inspection Report 05000483/2023004 ML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 2024-09-11
[Table view] |
Text
UNITED STATES ber 2, 2014
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 0500483/2014006)
Dear Mr. Diya:
On August 12, 2014, the NRC completed its mid-cycle performance review of Callaway Plant.
The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2013, through June 30, 2014. This letter informs you of the NRCs assessment of Callaway Plant during this period and its plans for future inspections at your facility.
The NRC determined that overall, Callaway Plant was operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Callaway Plant during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., Green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year 2014 reflect this revision to Inspection Manual Chapter (IMC) 0310.
Cross-cutting aspects identified in 2013 using the 2013 terminology were converted to the latest revision in accordance with the cross-reference in IMC 0310 during the mid-cycle assessment review and evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305.
The enclosed inspection plan lists the inspections scheduled through December 31, 2015.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff.
A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 817-200-1141 with any questions you have regarding this letter.
Sincerely,
/RA/
Neil F. OKeefe, Chief Project Branch B Division of Reactor Projects Docket No.: 50-483 License No.: NPF-30 Enclosure: Callaway Plant Inspection/
Activity Plan
ML14239A604 SUNSI Review ADAMS Publicly Available Non-Sensitive By: NOKeefe Yes No Non-Publicly Available Sensitive OFFICE RIV/BC/DRP RIV/D/DRS RIV/D/DRP NAME OKeefe/dll AVegel TPruett SIGNATURE /RA/ /RA/VGaddy /RA/
for DATE 8/21/14 8/25/14 8/22/14
Letter to Fadi Diya from Neil F. OKeefe dated September 2, 2014 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2014006)
DISTRIBUTION:
Regional Administrator (Marc.Dapas@nrc.gov)
Deputy Regional Administrator (Steven.Reynolds@nrc.gov)
Acting DRP Director (Troy.Pruett@nrc.gov)
Acting DRP Deputy Director (Michael.Hay@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Tom.Hartman@nrc.gov)
Resident Inspector (Zachary.Hollcraft@nrc.gov)
Administrative Assistant (Dawn.Yancey@nrc.gov)
Branch Chief (Neil.OKeefe@nrc.gov)
Senior Project Engineer (David.Proulx@nrc.gov)
Project Engineer, (Fabian.Thomas@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
RIV State Liaison Officer (Bill.Maier@nrc.gov)
Project Manager (Fred.Lyon@nrc.gov)
Branch Chief, DRS/TSB (Geoffrey.Miller@nrc.gov)
R4DRPBC@nrc.gov R4DRSBC@nrc.gov Director, DIRS, NRR (Scott.Morris@nrc.gov)
Deputy Director, DIRS, NRR (Allen.Howe@nrc.gov)
Acting Director, DORL, NRR (Louise.Lund@nrc.gov)
Acting Deputy Director, DORL (Michael.Markley@nrc.gov)
Director, NSIR/DPR (Rob.Lewis@nrc.gov)
Chief, PLB IV, DORL, NRR (Eric.Oesterle@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV/ETA: OEDO (Anthony.Bowers@nrc.gov)
ROPassessment Resource@nrc.gov ROPreports@nrc.gov OEMail Resource@nrc.gov Electronic Distribution for Callaway Plant
Page 1 of 2 Callaway 08/22/2014 13:57:44 Inspection / Activity Plan Report 22 09/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EXAM - INITIAL OPERATOR EXAM 4 1 11/03/2014 11/07/2014 X02535 INITIAL EXAM-CALLAWAY (02/01/2015)
1 12/08/2014 12/12/2014 X02535 INITIAL EXAM-CALLAWAY (02/01/2015)
ISFSI - PAD POUR INSPECTION (MULTIPLE VISITS) 1 1 08/01/2014 11/30/2014 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants HEAD-REP - REACTOR HEAD REPLACEMENT P1 2 1 08/17/2014 09/27/2014 IP 71007 Reactor Vessel Head Replacement Inspection 71111.08 - CALLAWAY INSERVICE INSPECTION 2 1 10/13/2014 10/24/2014 IP 7111108P Inservice Inspection Activities - PWR HEAD-REP - REACTOR HEAD REPLACEMENT-P2 2 1 10/19/2014 11/22/2014 IP 71007 Reactor Vessel Head Replacement Inspection 1 10/19/2014 12/27/2014 IP 71152 Problem Identification and Resolution RS 13 PI - RADIATION SAFETY 2 1 10/27/2014 10/31/2014 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 10/27/2014 10/31/2014 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 10/27/2014 10/31/2014 IP 71151-OR01 1 10/27/2014 10/31/2014 IP 71151-PR01 ISFSI - DRY RUN INSPECTIONS (MULTIPLE VISITS) 1 1 02/01/2015 05/01/2015 IP 60855 Operation Of An ISFSI ISFSI - DRY RUN INSPECTION (MULTIPLE VISITS) 1 1 02/01/2015 06/01/2015 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants EB2-05T - TRIENNIAL FIRE PROTECTION INSPECTION 4 1 04/27/2015 05/01/2015 IP 7111105x Fire Protection - NFPA 805 (Triennial)
1 05/11/2015 05/15/2015 IP 7111105x Fire Protection - NFPA 805 (Triennial)
EP-2 - HAB EXERCISE INSPECTION 2 1 05/04/2015 05/08/2015 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 05/04/2015 05/08/2015 IP 7111407 Exercise Evaluation - Hostile Action (HA) Event EP-3 - EP PERFORMANCE INDICATORS 2 1 05/04/2015 05/08/2015 IP 71151-EP01 1 05/04/2015 05/08/2015 IP 71151-EP02 1 05/04/2015 05/08/2015 IP 71151-EP03 INSP - OPERATOR REQUAL INSPECTION 3 1 06/15/2015 06/19/2015 IP 7111111B Licensed Operator Requalification Program This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Callaway 08/22/2014 13:57:44 Inspection / Activity Plan Report 22 09/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site RS 5678 - RADIATION SAFETY - TEAM 4 1 07/13/2015 07/17/2015 IP 71124.05 Radiation Monitoring Instrumentation 1 07/13/2015 07/17/2015 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 07/13/2015 07/17/2015 IP 71124.07 Radiological Environmental Monitoring Program 1 07/13/2015 07/17/2015 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation RS 12 PI - RADIATION SAFETY 2 1 10/26/2015 10/30/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 10/26/2015 10/30/2015 IP 71124.02 Occupational ALARA Planning and Controls 1 10/26/2015 10/30/2015 IP 71151-OR01 1 10/26/2015 10/30/2015 IP 71151-PR01 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.