| issue date = 04/19/2013
| issue date = 04/19/2013
| title = 4/2/2013 - Pilgrim - Annual Assessment Meeting Summary
| title = 4/2/2013 - Pilgrim - Annual Assessment Meeting Summary
| author name = Bellamy R R
| author name = Bellamy R
| author affiliation = NRC/RGN-I/DRP/PB5
| author affiliation = NRC/RGN-I/DRP/PB5
| addressee name =  
| addressee name =  
Line 9: Line 9:
| docket = 05000293
| docket = 05000293
| license number = DPR-035
| license number = DPR-035
| contact person = Bellamy R R
| contact person = Bellamy R
| case reference number = MN 13-005
| case reference number = MN 13-005
| document type = Meeting Summary
| document type = Meeting Summary
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES                           NUCLEAR REGULATORY COMMISSION                                                       REGION I                       2100 RENAISSANCE BOULEVARD, SUITE 100                     KING OF PRUSSIA, PENNSYLVANIA 19406-2713 April 19, 2013 MEETING  
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 April 19, 2013 MEETING  


==SUMMARY==
==SUMMARY==


LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC.
LICENSEE:       ENTERGY NUCLEAR OPERATIONS, INC.
 
FACILITY:       PILGRIM NUCLEAR POWER STATION
FACILITY: PILGRIM NUCLEAR POWER STATION


==SUBJECT:==
==SUBJECT:==


==SUMMARY==
==SUMMARY==
OF PUBLIC MEETING  
OF PUBLIC MEETING On April 2, 2013, at 5:30 p.m., the U. S. Nuclear Regulatory Commission (NRC) conducted a public open house at the Plymouth Town Hall in Plymouth, Massachusetts. The NRC conducted the open house to discuss its assessment of the safety performance at Pilgrim Nuclear Power Station for 2012.
 
A notice of the open house was issued on March 27, 2013, and was posted on the NRCs external (public) Web page. The meeting notice can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) with Accession No. ML13086A590.
On April 2, 2013, at 5:30 p.m., the U. S. Nuclear Regulatory Commission (NRC) conducted a public open house at the Plymouth Town Hall in Plymouth, Massachusetts. The NRC conducted the open house to discuss its assessment of the safety performance at Pilgrim  
ADAMS is accessible from the NRC Web page at: http://www.nrc.gov/reading-rm/adams.html.
 
The NRC presented poster boards, fact sheets and reading material and was available to discuss its assessment of the safety performance of Pilgrim Nuclear Power Station for the period of January 1 through December 31, 2012, as documented in our letter dated March 4, 2013 (ADAMS Accession No. ML13060A340). The NRC poster boards, fact sheets and reading material presented included background on the Reactor Oversight Process (ROP). Additional information relative to the NRC's Annual Assessment Process and the safety performance of Pilgrim Nuclear Power Station can be found on the NRC's web site at:
Nuclear Power Station for 2012.  
www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.
 
Members of the public, local officials, State officials, and members of the media attended the open house and were offered the opportunity to question the NRC regarding Pilgrims performance and the role of the agency in ensuring safe plant operations.
A notice of the open house was issued on Ma rch 27, 2013, and was posted on the NRC's external (public) Web page. The meeting notice can be found in the NRC's Agencywide Documents Access and Management System (ADAMS) with Accession No. ML13086A590. ADAMS is accessible from the NRC Web page at:
                                                        /RA/
http://www.nrc.gov/reading-rm/adams.html.
Ronald R. Bellamy, Chief Projects Branch 5 Division of Reactor Projects
The NRC presented poster boards, fact sheets and reading material and was available to discuss its assessment of the safety performance of Pilgrim Nuclear Power Station for the period of January 1 through December 31, 2012, as documented in our letter dated March 4, 2013 (ADAMS Accession No. ML13060A340). The NRC poster boards, fact sheets and reading material presented included background on the Reactor Oversight Process (ROP). Additional information relative to the NRC's Annual Assessment Process and the safety performance of  
 
Pilgrim Nuclear Power Station can be found on the NRC's web site at: www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html. Members of the public, local officials, State officials, and members of the media attended the open house and were offered the opportunity to question the NRC regarding Pilgrim's performance and the role of the agency in ensuring safe plant operations.  
 
      /RA/     Ronald R. Bellamy, Chief Projects Branch 5 Division of Reactor Projects  


==Enclosures:==
==Enclosures:==


Attendee List (ML)  
Attendee List (ML)
 
ML13060A340). The NRC poster boards, fact sheets and reading material presented included background on the Reactor Oversight Process (ROP). Additional information relative to the NRC's Annual Assessment Process and the safety performance of


Pilgrim Nuclear Power Station can be found on the NRC's web site at:
ML13060A340). The NRC poster boards, fact sheets and reading material presented included background on the Reactor Oversight Process (ROP). Additional information relative to the NRC's Annual Assessment Process and the safety performance of Pilgrim Nuclear Power Station can be found on the NRC's web site at:
www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html. Members of the public, local officials, State officials, and members of the media attended the open house and were offered the opportunity to question the NRC regarding Pilgrim's performance and the role of the agency in ensuring safe plant operations.  
www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.
Members of the public, local officials, State officials, and members of the media attended the open house and were offered the opportunity to question the NRC regarding Pilgrims performance and the role of the agency in ensuring safe plant operations.


==Enclosures:==
==Enclosures:==


Attendee List (ML)  
Attendee List (ML)
                                                              /RA/
Ronald R. Bellamy, PhD, Chief Projects Branch 5 Division of Reactor Projects Distribution: (via email)
R. Bellamy, DRP                                          M. Schneider, DRP, SRI S. Shaffer, DRP                                          B. Smith, DRP, RI E. Keighley, DRP                                        S. Campbell, DRP, AA J. DeBoer, DRP                                          RidsNRRPMPilgrim Resource DOC NAME: G:\DRP\BRANCH5\ANNUAL ASSESSMENT MEETINGS\2012 EOC\ANNUAL ASSESSMENT MEETING


      /RA/    Ronald R. Bellamy, PhD, Chief Projects Branch 5 Division of Reactor Projects Distribution: (via email) R. Bellamy, DRP S. Shaffer, DRP E. Keighley, DRP J. DeBoer, DRP M. Schneider, DRP, SRI B. Smith, DRP, RI S. Campbell, DRP, AA RidsNRRPMPilgrim Resource DOC NAME: G:\DRP\BRANCH5\ANNUAL ASSESSMENT MEETINGS\2012 EOC\ANNUAL ASSESSMENT MEETING
==SUMMARY==
PILGRIM.DOCX ADAMS Accession No.: ML13109A436 SUNSI Review Non-Sensitive                            Publicly Available Sensitive                                Non-Publicly Available OFFICE klm      RI/DRP            RI/DRP NAME            EKeighley/EMK     RBellamy/RRB DATE            4 /19 /13          4/19 /13 April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Page _ _ of :2)
Name Organization (if applicable)


==SUMMARY==
April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Page Name Organization (if applicable)
PILGRIM.DOCX ADAMS Accession No.:  ML13109A436 SUNSI Review Non-Sensitive  Sensitive Publicly Available Non-Publicly Available OFFICE klm RI/DRP RI/DRP    NAME EKeighley/EMK RBellamy/RRB    DATE 4 /19 /13    4/19 /13   


Name April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Page __ of :2) Organization (if applicable)
April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Name Organization (if applicable)}}
Name April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Page Organization (if applicable)
Name April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Organization (if applicable)}}

Latest revision as of 06:37, 6 February 2020

4/2/2013 - Pilgrim - Annual Assessment Meeting Summary
ML13109A436
Person / Time
Site: Pilgrim
Issue date: 04/19/2013
From: Bellamy R
NRC/RGN-I/DRP/PB5
To:
Entergy Nuclear Operations
Bellamy R
References
MN 13-005
Download: ML13109A436 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 April 19, 2013 MEETING

SUMMARY

LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC.

FACILITY: PILGRIM NUCLEAR POWER STATION

SUBJECT:

SUMMARY

OF PUBLIC MEETING On April 2, 2013, at 5:30 p.m., the U. S. Nuclear Regulatory Commission (NRC) conducted a public open house at the Plymouth Town Hall in Plymouth, Massachusetts. The NRC conducted the open house to discuss its assessment of the safety performance at Pilgrim Nuclear Power Station for 2012.

A notice of the open house was issued on March 27, 2013, and was posted on the NRCs external (public) Web page. The meeting notice can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) with Accession No. ML13086A590.

ADAMS is accessible from the NRC Web page at: http://www.nrc.gov/reading-rm/adams.html.

The NRC presented poster boards, fact sheets and reading material and was available to discuss its assessment of the safety performance of Pilgrim Nuclear Power Station for the period of January 1 through December 31, 2012, as documented in our letter dated March 4, 2013 (ADAMS Accession No. ML13060A340). The NRC poster boards, fact sheets and reading material presented included background on the Reactor Oversight Process (ROP). Additional information relative to the NRC's Annual Assessment Process and the safety performance of Pilgrim Nuclear Power Station can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public, local officials, State officials, and members of the media attended the open house and were offered the opportunity to question the NRC regarding Pilgrims performance and the role of the agency in ensuring safe plant operations.

/RA/

Ronald R. Bellamy, Chief Projects Branch 5 Division of Reactor Projects

Enclosures:

Attendee List (ML)

ML13060A340). The NRC poster boards, fact sheets and reading material presented included background on the Reactor Oversight Process (ROP). Additional information relative to the NRC's Annual Assessment Process and the safety performance of Pilgrim Nuclear Power Station can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public, local officials, State officials, and members of the media attended the open house and were offered the opportunity to question the NRC regarding Pilgrims performance and the role of the agency in ensuring safe plant operations.

Enclosures:

Attendee List (ML)

/RA/

Ronald R. Bellamy, PhD, Chief Projects Branch 5 Division of Reactor Projects Distribution: (via email)

R. Bellamy, DRP M. Schneider, DRP, SRI S. Shaffer, DRP B. Smith, DRP, RI E. Keighley, DRP S. Campbell, DRP, AA J. DeBoer, DRP RidsNRRPMPilgrim Resource DOC NAME: G:\DRP\BRANCH5\ANNUAL ASSESSMENT MEETINGS\2012 EOC\ANNUAL ASSESSMENT MEETING

SUMMARY

PILGRIM.DOCX ADAMS Accession No.: ML13109A436 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE klm RI/DRP RI/DRP NAME EKeighley/EMK RBellamy/RRB DATE 4 /19 /13 4/19 /13 April 2, 2013 2012 Annual Assessment Meeting Pilgrim Nuclear Power Station Public Meeting Sign-In Sheet Page _ _ of :2)

Name Organization (if applicable)