ML18255A315: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(2 intermediate revisions by the same user not shown)
Line 5: Line 5:
| author name = Tabatabai-Yazdi O
| author name = Tabatabai-Yazdi O
| author affiliation = NRC/NRO/DLSE/LB1
| author affiliation = NRC/NRO/DLSE/LB1
| addressee name = Lee S S
| addressee name = Lee S
| addressee affiliation = NRC/NRO/DLSE/LB1
| addressee affiliation = NRC/NRO/DLSE/LB1
| docket = 05200048
| docket = 05200048
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:/RA/}}
{{#Wiki_filter:September 17, 2018 MEMORANDUM TO:                Samuel S. Lee, Chief Licensing Branch 1 Division of Licensing, Siting, and Environmental Analysis Office of New Reactors FROM:                        Omid Tabatabai, Senior Project Manager            /RA/
Licensing Branch 1 Division of Licensing, Siting, and Environmental Analysis Office of New Reactors
 
==SUBJECT:==
 
==SUMMARY==
OF THE AUGUST 1, 2018 AND AUGUST 30, 2018, PUBLIC MEETINGS WITH NUSCALE POWER, LLC, TO DISCUSS THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS REVIEW OF NUSCALES DESIGN CERTIFICATION APPLICATION, TIER 2, CHAPTER 14.2, INITIAL TEST PROGRAM On August 1, 2018 and August 30, 2018, representatives of the U.S. Nuclear Regulatory Commission (NRC) and NuScale Power, LLC (NuScale) held two public teleconference meetings to discuss the NRC staffs questions related to the NuScale Design Certification Application, Tier 2, Chapter 14.2, "Initial Test Program."  captures the summary of the topics discussed during the teleconference. The agenda and list of meetings attendees are included in Enclosures 2 and 3, respectively. The meeting notices for the August 1, 2018 and August 30, 2018, are available in the Agencywide Documents Access and Management System under Accession No. ML18192A254, and ML18242A031, respectively.
Docket No. 52-048
 
==Enclosures:==
: 1. Meeting Summary
: 2. Agenda
: 3. Attendees CONTACT: Omid Tabatabai, NRO/DLSE 301-415-6616
 
ML18255A315                *via email          NRC-001 OFFICE    NRO/DLSE/LB1:PM NRO/DLSE/LB1:LA* NRO/DCIP/QVIB:BC* NRO/DLSE/LB1:PM NAME      OTabatabai      MMoore          KKavanagh        OTabatabai DATE      9/17/2018      9/13/2018        9/17/2018        9/17/2018 U.S. NUCLEAR REGULATORY COMMISSION
 
==SUMMARY==
OF THE AUGUST 1, 2018 AND AUGUST 30, 2018, PUBLIC MEETINGS WITH NUSCALE POWER, LLC, TO DISCUSS THE NRC STAFFS REVIEW OF NUSCALES DESIGN CERTIFICATION APPLICATION, TIER 2, CHAPTER 14.2, INITIAL TEST PROGRAM On August 1, 2018 and August 30, 2018, representatives of the U.S. Nuclear Regulatory Commission (NRC) and NuScale Power, LLC, (NuScale) met to discuss the scope of the NRC staffs review of NuScale Initial Test Program, as described in NuScales Design Certification Application (DCA), Tier 2, Chapter 14.2, Initial Test Program.
During the August 1, 2018 meeting, NuScale made a presentation to the NRC staff entitled, Risk-Informed Review of NuScale Initial Test Program. NuScales presentation material is publicly available in the Agencywide Documents Access Management System (ADAMS) under Accession No. ML18213A157. NuScale concluded its presentation by requesting NRC to revise its review approach for NuScales initial test program (ITP) to, (1) include the review of the test abstracts pertaining to inspections, tests, analyses, and acceptance criteria and first-of-a-kind in the DCA review, and (2) apply a risk-informed review approach during the combined license stage. The NRC staff asked several clarifying questions during the meeting to understand how NuScales requests would address regulatory requirements applicable to the review of ITP during the design certification review stage. The NRC and NuScale staffs agreed to discuss the issue internally and meet again to continue their discussion. A follow-up meeting was later set for August 30, 2018.
During August 30, 2018, meeting the NRC staff requested clarification from NuScale regarding the scope of the ITP review that NuScale was seeking given that ITP is not required as part of a DCA review. NuScale indicated that their proposed scope of the review should include the safety-related and risk-significant (A.1, A.2, and B.1) test abstracts. These tests should be fully reviewed. The NRC staff questioned whether this would include system functions as described in DCA section 17.4 and that emphasized that the staff needs to understand the full scope such that an adequate resource estimate can be established.
NuScale agreed to provide a roadmap for the 110 initial tests and the various systems with varying levels of safety and risk significance (A1, A2, and B1). The NRC staff agreed to review the information and provide feedback to NuScale. This roadmap would be discussed and agreed upon with NuScale at a later date. The NRC staff also raised concerns that NuScale ITP contains untested design functions that are expected to be tested. NuScale requested that the staff clarify what was missing from their DCA in order for NuScale to address. The NRC staff informed NuScale that a request for additional information (RAI) was being prepared, however, NuScale requested that the staff not issue the RAI until after another round of public meeting to allow further discussions related to the NuScale ITP.
The meeting participants also briefly discussed NuScales white paper (available publicly in ADAMS under Accession No. ML18260A317) that was submitted late on August 29, 2018, Enclosure 1
 
which compares NuScales ITP submittal to the ITP that was approved in the ESBWR DCD.
The NRC staff indicated that it did not have time to digest the content of the white paper. The NRC and NuScale staffs agreed to schedule a follow-up meeting to continue their discussions.
A follow-up meeting has been scheduled for September 18, 2018.
 
U.S. NUCLEAR REGULATORY COMMISSION
 
==SUMMARY==
OF THE AUGUST 1, 2018 AND AUGUST 30, 2018, PUBLIC MEETINGS WITH NUSCALE POWER, LLC, TO DISCUSS THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS REVIEW OF NUSCALES DESIGN CERTIFICATION APPLICATION, TIER 2, CHAPTER 14.2, INITIAL TEST PROGRAM MEETING AGENDA August 1, 2018 Introduction                                          1:00 - 1:10 pm Staffs questions related to NuScale ITP              1:10 - 2:45 pm Public Comments                                        2:55 - 3:00 pm August 30, 2018 Introduction                                          11:00 - 11:10 am Staffs questions related to the Scope of NuScale ITP 11:10 - 11:20 am A comparison between ESBWR and NuScale Pre-Op 11:20 - 11:55 am Test Public Comments                                      11:55 - 12:00 pm Enclosure 2
 
U.S. NUCLEAR REGULATORY COMMISSION
 
==SUMMARY==
OF THE AUGUST 1, 2018 AND AUGUST 30, 2018, PUBLIC MEETINGS WITH NUSCALE POWER, LLC, TO DISCUSS THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS REVIEW OF NUSCALES DESIGN CERTIFICATION APPLICATION, TIER 2, CHAPTER 14.2, INITIAL TEST PROGRAM LIST OF MEETING ATTENDEES - AUGUST 1, 2018 NuScale Power, LLC Brian Arnholt Gary Becker Allyson Callaway Carl Dumsday Carrie Fosaaen Dustin Greenwood Scott Harris Chris Maxwell Steve Pope Rick Rosenstein U.S. Nuclear Regulatory Commission Staff Michelle Hayes Odunayo Ayegbusi Omid Tabatabai LIST OF MEETING ATTENDEES - AUGUST 30, 2018 NuScale Power, LLC Brian Arnholt Gary Becker Carl Dumsday Edan Engstrom Carrie Fosaaen Dustin Greenwood Nadja Joergensen Mike Keller Ken Langdon Chris Maxwell Steve Pope Jennie Wike Enclosure 3
 
U.S. Nuclear Regulatory Commission Staff Tim McGinty Paul Krohn Robert Taylor Kevin Coyne Luis Betancourt Ryan Nolan Boyce Travis Joseph Ashcraft Samuel Lee Kerri Kavanagh Olivia Mikula Shana Helton Greg Cranston Marieliz Vera Members of the Public Sarah Fields Cynthia Wheeler}}

Latest revision as of 17:29, 2 February 2020

August 1 & 30, 2018, Summary of the Public Meetings with Nuscale Power, LLC, to Discuss the NRC Staff'S Review of Nuscale'S Design Certification Application, Chapter 14.2
ML18255A315
Person / Time
Site: NuScale
Issue date: 09/17/2018
From: Tabatabai-Yazdi O
NRC/NRO/DLSE/LB1
To: Samson Lee
NRC/NRO/DLSE/LB1
Tabatabai-Yazdi O / 415-6616
References
Download: ML18255A315 (6)


Text

September 17, 2018 MEMORANDUM TO: Samuel S. Lee, Chief Licensing Branch 1 Division of Licensing, Siting, and Environmental Analysis Office of New Reactors FROM: Omid Tabatabai, Senior Project Manager /RA/

Licensing Branch 1 Division of Licensing, Siting, and Environmental Analysis Office of New Reactors

SUBJECT:

SUMMARY

OF THE AUGUST 1, 2018 AND AUGUST 30, 2018, PUBLIC MEETINGS WITH NUSCALE POWER, LLC, TO DISCUSS THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS REVIEW OF NUSCALES DESIGN CERTIFICATION APPLICATION, TIER 2, CHAPTER 14.2, INITIAL TEST PROGRAM On August 1, 2018 and August 30, 2018, representatives of the U.S. Nuclear Regulatory Commission (NRC) and NuScale Power, LLC (NuScale) held two public teleconference meetings to discuss the NRC staffs questions related to the NuScale Design Certification Application, Tier 2, Chapter 14.2, "Initial Test Program." captures the summary of the topics discussed during the teleconference. The agenda and list of meetings attendees are included in Enclosures 2 and 3, respectively. The meeting notices for the August 1, 2018 and August 30, 2018, are available in the Agencywide Documents Access and Management System under Accession No. ML18192A254, and ML18242A031, respectively.

Docket No.52-048

Enclosures:

1. Meeting Summary
2. Agenda
3. Attendees CONTACT: Omid Tabatabai, NRO/DLSE 301-415-6616

ML18255A315 *via email NRC-001 OFFICE NRO/DLSE/LB1:PM NRO/DLSE/LB1:LA* NRO/DCIP/QVIB:BC* NRO/DLSE/LB1:PM NAME OTabatabai MMoore KKavanagh OTabatabai DATE 9/17/2018 9/13/2018 9/17/2018 9/17/2018 U.S. NUCLEAR REGULATORY COMMISSION

SUMMARY

OF THE AUGUST 1, 2018 AND AUGUST 30, 2018, PUBLIC MEETINGS WITH NUSCALE POWER, LLC, TO DISCUSS THE NRC STAFFS REVIEW OF NUSCALES DESIGN CERTIFICATION APPLICATION, TIER 2, CHAPTER 14.2, INITIAL TEST PROGRAM On August 1, 2018 and August 30, 2018, representatives of the U.S. Nuclear Regulatory Commission (NRC) and NuScale Power, LLC, (NuScale) met to discuss the scope of the NRC staffs review of NuScale Initial Test Program, as described in NuScales Design Certification Application (DCA), Tier 2, Chapter 14.2, Initial Test Program.

During the August 1, 2018 meeting, NuScale made a presentation to the NRC staff entitled, Risk-Informed Review of NuScale Initial Test Program. NuScales presentation material is publicly available in the Agencywide Documents Access Management System (ADAMS) under Accession No. ML18213A157. NuScale concluded its presentation by requesting NRC to revise its review approach for NuScales initial test program (ITP) to, (1) include the review of the test abstracts pertaining to inspections, tests, analyses, and acceptance criteria and first-of-a-kind in the DCA review, and (2) apply a risk-informed review approach during the combined license stage. The NRC staff asked several clarifying questions during the meeting to understand how NuScales requests would address regulatory requirements applicable to the review of ITP during the design certification review stage. The NRC and NuScale staffs agreed to discuss the issue internally and meet again to continue their discussion. A follow-up meeting was later set for August 30, 2018.

During August 30, 2018, meeting the NRC staff requested clarification from NuScale regarding the scope of the ITP review that NuScale was seeking given that ITP is not required as part of a DCA review. NuScale indicated that their proposed scope of the review should include the safety-related and risk-significant (A.1, A.2, and B.1) test abstracts. These tests should be fully reviewed. The NRC staff questioned whether this would include system functions as described in DCA section 17.4 and that emphasized that the staff needs to understand the full scope such that an adequate resource estimate can be established.

NuScale agreed to provide a roadmap for the 110 initial tests and the various systems with varying levels of safety and risk significance (A1, A2, and B1). The NRC staff agreed to review the information and provide feedback to NuScale. This roadmap would be discussed and agreed upon with NuScale at a later date. The NRC staff also raised concerns that NuScale ITP contains untested design functions that are expected to be tested. NuScale requested that the staff clarify what was missing from their DCA in order for NuScale to address. The NRC staff informed NuScale that a request for additional information (RAI) was being prepared, however, NuScale requested that the staff not issue the RAI until after another round of public meeting to allow further discussions related to the NuScale ITP.

The meeting participants also briefly discussed NuScales white paper (available publicly in ADAMS under Accession No. ML18260A317) that was submitted late on August 29, 2018, Enclosure 1

which compares NuScales ITP submittal to the ITP that was approved in the ESBWR DCD.

The NRC staff indicated that it did not have time to digest the content of the white paper. The NRC and NuScale staffs agreed to schedule a follow-up meeting to continue their discussions.

A follow-up meeting has been scheduled for September 18, 2018.

U.S. NUCLEAR REGULATORY COMMISSION

SUMMARY

OF THE AUGUST 1, 2018 AND AUGUST 30, 2018, PUBLIC MEETINGS WITH NUSCALE POWER, LLC, TO DISCUSS THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS REVIEW OF NUSCALES DESIGN CERTIFICATION APPLICATION, TIER 2, CHAPTER 14.2, INITIAL TEST PROGRAM MEETING AGENDA August 1, 2018 Introduction 1:00 - 1:10 pm Staffs questions related to NuScale ITP 1:10 - 2:45 pm Public Comments 2:55 - 3:00 pm August 30, 2018 Introduction 11:00 - 11:10 am Staffs questions related to the Scope of NuScale ITP 11:10 - 11:20 am A comparison between ESBWR and NuScale Pre-Op 11:20 - 11:55 am Test Public Comments 11:55 - 12:00 pm Enclosure 2

U.S. NUCLEAR REGULATORY COMMISSION

SUMMARY

OF THE AUGUST 1, 2018 AND AUGUST 30, 2018, PUBLIC MEETINGS WITH NUSCALE POWER, LLC, TO DISCUSS THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS REVIEW OF NUSCALES DESIGN CERTIFICATION APPLICATION, TIER 2, CHAPTER 14.2, INITIAL TEST PROGRAM LIST OF MEETING ATTENDEES - AUGUST 1, 2018 NuScale Power, LLC Brian Arnholt Gary Becker Allyson Callaway Carl Dumsday Carrie Fosaaen Dustin Greenwood Scott Harris Chris Maxwell Steve Pope Rick Rosenstein U.S. Nuclear Regulatory Commission Staff Michelle Hayes Odunayo Ayegbusi Omid Tabatabai LIST OF MEETING ATTENDEES - AUGUST 30, 2018 NuScale Power, LLC Brian Arnholt Gary Becker Carl Dumsday Edan Engstrom Carrie Fosaaen Dustin Greenwood Nadja Joergensen Mike Keller Ken Langdon Chris Maxwell Steve Pope Jennie Wike Enclosure 3

U.S. Nuclear Regulatory Commission Staff Tim McGinty Paul Krohn Robert Taylor Kevin Coyne Luis Betancourt Ryan Nolan Boyce Travis Joseph Ashcraft Samuel Lee Kerri Kavanagh Olivia Mikula Shana Helton Greg Cranston Marieliz Vera Members of the Public Sarah Fields Cynthia Wheeler