| title = IR 05000263-08-007(DRS); on 04/14/08; Monticello Nuclear Generating Plant; Ti 2515/171 Verification of Site Specific Implementation of B.5.b Phase 2 and 3 Mitigating Strategies
| title = IR 05000263-08-007(DRS); on 04/14/08; Monticello Nuclear Generating Plant; Ti 2515/171 Verification of Site Specific Implementation of B.5.b Phase 2 and 3 Mitigating Strategies
| author name = Peterson H C
| author name = Peterson H
| author affiliation = NRC/RGN-I/DRS/OB
| author affiliation = NRC/RGN-I/DRS/OB
| addressee name = O'Connor T J
| addressee name = O'Connor T
| addressee affiliation = Nuclear Management Co, LLC
| addressee affiliation = Nuclear Management Co, LLC
| docket = 05000263
| docket = 05000263
Line 19: Line 19:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:==SUBJECT:==
[[Issue date::May 19, 2008]]
MONTICELLO NUCLEAR GENERATING PLANT TI 2515/171 VERIFICATION OF SITE SPECIFIC IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES INSPECTION REPORT NO. 05000263/2008007(DRS)


Mr. Timothy Site Vice President Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637
==Dear Mr. OConnor:==
 
SUBJECT: MONTICELLO NUCLEAR GENERATING PLANT TI 2515/171 VERIFICATION OF SITE SPECIFIC IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES INSPECTION REPORT NO. 05000263/2008007(DRS)
 
==Dear Mr. O'Connor:==
On April 18, 2008, the U. S. Nuclear Regulatory Commission (NRC) completed a team inspection at your Monticello Nuclear Generating Plant. The enclosed report documents the results of the inspection, which were discussed on April 18, 2008, with Mr. B. Sawatzke and other members of your staff.
On April 18, 2008, the U. S. Nuclear Regulatory Commission (NRC) completed a team inspection at your Monticello Nuclear Generating Plant. The enclosed report documents the results of the inspection, which were discussed on April 18, 2008, with Mr. B. Sawatzke and other members of your staff.


The inspection examined activities conducted under your license as they relate to the implementation of B.5.b Phase 2 and 3 mitigating strategies, your compliance with the Commission
The inspection examined activities conducted under your license as they relate to the implementation of B.5.b Phase 2 and 3 mitigating strategies, your compliance with the Commission=s rules and regulations, and with the conditions of your operating license. Within these areas, the inspection involved examination of selected procedures and representative records, observations of activities, and interviews with personnel.
=s rules and regulations, and with the conditions of your operating license. Within these areas, the inspection involved examination of selected procedures and representative records, observations of activities, and interviews with personnel.


Based on the results of the inspection, two NRC-identified findings of very low significance were identified. However, because these violations were of very low safety significance and because they were entered into your corrective action program, the NRC is treating the issues as Non-Cited Violations in accordance with Section VI.A.1 of the NRC's Enforcement Policy.
Based on the results of the inspection, two NRC-identified findings of very low significance were identified. However, because these violations were of very low safety significance and because they were entered into your corrective action program, the NRC is treating the issues as Non-Cited Violations in accordance with Section VI.A.1 of the NRCs Enforcement Policy.


Enclosure Contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this page is decontrolled. If you contest any finding or the subject or severity of any Non-Cited Violation in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001, with copies to the Regional Administrator, U. S. Nuclear Regulatory Commission - Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement, U. S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector Office at the Monticello Nuclear Generating Plant.
Enclosure Contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this page is decontrolled. If you contest any finding or the subject or severity of any Non-Cited Violation in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001, with copies to the Regional Administrator, U. S. Nuclear Regulatory Commission - Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement, U. S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector Office at the Monticello Nuclear Generating Plant.


In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the sensitive information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the sensitive information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
 
Sincerely,/RA/ Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No. 50-263 License No. DPR-22
 
Nonpublic
 
===Enclosure:===
Inspection Report 05000263/2008007(DRS)


===w/Attachment:===
Sincerely,
Supplemental Information See Attached Distribution
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No. 50-263 License No. DPR-22 Nonpublic Enclosure: Inspection Report 05000263/2008007(DRS)
w/Attachment: Supplemental Information See Attached Distribution
}}
}}

Latest revision as of 16:25, 14 November 2019

IR 05000263-08-007(DRS); on 04/14/08; Monticello Nuclear Generating Plant; Ti 2515/171 Verification of Site Specific Implementation of B.5.b Phase 2 and 3 Mitigating Strategies
ML081420780
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 05/19/2008
From: Hironori Peterson
Operations Branch I
To: O'Connor T
Nuclear Management Co
References
TI 2515/171 IR-08-007
Download: ML081420780 (5)


Text

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT TI 2515/171 VERIFICATION OF SITE SPECIFIC IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES INSPECTION REPORT NO. 05000263/2008007(DRS)

Dear Mr. OConnor:

On April 18, 2008, the U. S. Nuclear Regulatory Commission (NRC) completed a team inspection at your Monticello Nuclear Generating Plant. The enclosed report documents the results of the inspection, which were discussed on April 18, 2008, with Mr. B. Sawatzke and other members of your staff.

The inspection examined activities conducted under your license as they relate to the implementation of B.5.b Phase 2 and 3 mitigating strategies, your compliance with the Commission=s rules and regulations, and with the conditions of your operating license. Within these areas, the inspection involved examination of selected procedures and representative records, observations of activities, and interviews with personnel.

Based on the results of the inspection, two NRC-identified findings of very low significance were identified. However, because these violations were of very low safety significance and because they were entered into your corrective action program, the NRC is treating the issues as Non-Cited Violations in accordance with Section VI.A.1 of the NRCs Enforcement Policy.

Enclosure Contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this page is decontrolled. If you contest any finding or the subject or severity of any Non-Cited Violation in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001, with copies to the Regional Administrator, U. S. Nuclear Regulatory Commission - Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement, U. S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector Office at the Monticello Nuclear Generating Plant.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the sensitive information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No. 50-263 License No. DPR-22 Nonpublic Enclosure: Inspection Report 05000263/2008007(DRS)

w/Attachment: Supplemental Information See Attached Distribution