Letter to Shawn Hafen, Re Monticello Subsequent License Renewal Schedule Change
ML24283A119
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 10/28/2024
From: Michele Sampson, Jessica Umana
Office of Nuclear Reactor Regulation, NRC/NMSS/DREFS/EPMB1
To: Hafen S
Northern States Power Company, Minnesota
References
Download: ML24283A119 (1)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Shawn Hafen Site Vice President Northern States Power Company - Minnesota Monticello Nuclear Generating Plant 2807 West County Rd 75 Monticello, MN 55362

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT, UNIT 1-SCHEDULE REVISION FOR THE SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW (DOCKET NUMBER: 50-263)

Dear Shawn Hafen:

By letter dated January 9, 2023, (Agencywide Documents Access and Management System ML23009A353), Northern States Power Company submitted to the U.S. Nuclear Regulatory Commission (NRC) an application for subsequent license renewal of Renewed Facility Operating License No. DPR-22 for Monticello Nuclear Generating Plant, Unit 1 (Monticello). By letter dated February 23, 2023 (ML23047A175), the NRC staff concluded that the application was acceptable for docketing and included the staffs projected review schedule for the Monticello subsequent license renewal application (SLRA) Enclosure 1. The purpose of this letter is to inform you of changes in the schedule for the Monticello SLRA.

For the environmental review, the scheduled due dates for Issue Final SEIS, and U.S.

Environmental Protection Agency FRN Published - Availability of Final SEIS, milestones will be revised from October 2024 to November 2024. The schedule change is a result of a change to the affected environment causing an additional round of request for additional information and complexities in the tribal consultation. of this letter highlights the staffs revised projected review schedule for the Monticello SLRA. The NRC staff will strive to meet the milestones ahead of the revised schedule whenever feasible.

October 28, 2024

S. Hafen 2

If you have any questions related to this review schedule, please contact Marieliz Johnson, Safety Project Manager via email at Marieliz.johnson@nrc.gov.

Sincerely, Michele Sampson, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket No. 50-263

Enclosures:

As stated cc w/encls: Monticello Listserv Signed by Sampson, Michele on 10/28/24

ML242834119

  • via email OFC NMSS/REFS NMSS/REFS NRR/DNRL/NLRP/PM OGC (NLO)

D:NRR/DNRL NAME JUmana AWalker-Smith MJohnson MCarpentier LGibson DATE 10/9/2024 10/15/2024 10/15/2024 10/24/2024 10/24/2024 OFC NMSS/REFS D:NRR NAME SKoenick MSampson DATE 10/15/2024 10/28/2024 MONTICELLO NUCLEAR GENERATING PLANT, UNIT 1 SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW SCHEDULE FROM U.S. NUCLEAR REGULATORY COMMISSION LETTER DATED: OCTOBER XX, 2024 Milestone Scheduled Actual Receive Subsequent License Renewal Application (SLRA) 01/2023 01/09/2023 Publish Federal Register Notice (FRN) - SLRA Availability 01/2023 01/31/2023 Publish FRN - Docketing Acceptance/Rejection and Opportunity for Hearing 02/2023 03/03/2023 Publish FRN - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 03/2023 03/10/2023 Public Meeting - Overview of License Renewal Process and Environmental Scoping 03/2023 03/22/2023 Environmental Scoping Period Ends 04/2023 04/10/2023 Deadline for Filing Hearing Requests and Petitions for Intervention 05/2023 05/02/2023 Issue Draft Supplemental Environmental Impact Statement (SEIS) 02/2024 04/24/2024 Public Meeting - Draft SEIS Meeting, If Needed 05/2024 05/05/2024, 05/15/2024 End of Draft SEIS Comment Period 04/2024 6/10/2024 Issue Safety Evaluation Report 03/2024 03/18/2024 Advisory Committee on Reactor Safeguards Full Committee Meeting 05/2024 04/30/2024 Issue Final SEIS 10/2024 U.S. Environmental Protection Agency FRN Published - Availability of Final SEIS 10/2024 Decision - Director, Office of Nuclear Reactor Regulation 12/2024 MONTICELLO NUCLEAR GENERATING PLANT, UNIT 1 SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW SCHEDULE FROM U.S. NUCLEAR REGULATORY COMMISSION LETTER DATED: OCTOBER XX, 2024 Milestone Scheduled Actual Receive Subsequent License Renewal Application (SLRA) 01/2023 01/09/2023 Publish Federal Register Notice (FRN) - SLRA Availability 01/2023 01/31/2023 Publish FRN - Docketing Acceptance/Rejection and Opportunity for Hearing 02/2023 03/03/2023 Publish FRN - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 03/2023 03/10/2023 Public Meeting - Overview of License Renewal Process and Environmental Scoping 03/2023 03/22/2023 Environmental Scoping Period Ends 04/2023 04/10/2023 Deadline for Filing Hearing Requests and Petitions for Intervention 05/2023 05/02/2023 Issue Draft Supplemental Environmental Impact Statement (SEIS) 02/2024 04/24/2024 Public Meeting - Draft SEIS Meeting, If Needed 05/2024 05/05/2024, 05/15/2024 End of Draft SEIS Comment Period 04/2024 6/10/2024 Issue Safety Evaluation Report 03/2024 03/18/2024 Advisory Committee on Reactor Safeguards Full Committee Meeting 05/2024 04/30/2024 Issue Final SEIS 11/2024 U.S. Environmental Protection Agency FRN Published - Availability of Final SEIS 11/2024 Decision - Director, Office of Nuclear Reactor Regulation 12/2024