{{#Wiki_filter:Pre-Application Meeting for Prairie Island Nuclear Generating Plant (PINGP)
Extended Power Uprate (EPU)
NRC Headquarters Rockville, MD August 18, 2011 1
===Introductions===
* Jim Molden - Vice President of Engineering, Regulatory Affairs and Projects
* Tom Verbout - Manager, Prairie Island EPU and LCM Projects
* Scott McCall - Prairie Island Design Engineering Manager
* Gene Eckholt - Nuclear Projects Licensing Manager 2
Agenda
* Objectives
* Background
* Project Overview
* Licensing Action Interfaces
* License Amendment Request (LAR)
* Questions/Discussion 3
Objectives
* Open Communications with NRC
* EPU Project Status Update
* Discuss EPU License Amendment Request Development and Content
* Discuss Interfaces Between EPU and other Licensing Actions
* Obtain NRC Feedback and Expectations 4
===Background===
* Initial Licenses
  - Unit 1 Operating License Issued August 1973
  - Unit 2 Operating License Issued October 1974
  - 1650 MWt Original Licensed Thermal Power (OLTP)
* Renewed Operating Licenses issued in June 2011
  - Unit 1 Renewed Operating License Expires August 2033
  - Unit 2 Renewed Operating License Expires October 2034 5
===Background===
* Measurement Uncertainty Recapture (MUR)
Uprate
  - Implemented October 2010
* 1677 MWt Licensed Power Level
* 1683 MWt Analyzed Power Level
* Extended Power Uprate
  - 1804 MWt Licensed Power Level (~109 % of OLTP)
  - 1811 MWt Analyzed Power Level
  - Unit 1 Implementation 1R29, 2014
  - Unit 2 Implementation 2R29, 2015 6
Project Overview 2009        2010                2011                2012                2013                2014                2015 EPU - Phase 2 - LAR Development                  NRC Review EPU - Phase 3 - Material Procurement EPU - Phase 4 - Modification Design EPU - Phase 5 - U1 Key:                                                                            Implementation
            = Submittal
            = NRC Approval                                                                              EPU - Phase 6 - U2 Implementation
            = Implementation EPU - Phase 7 - Project Closeout 1R26 C26                      1R27 C27                      1R28 C28                  1R29 C29 U1 Vibration Monitoring          U1 EPU C25            2R26      C26                    2R27        C27                    2R28      C28                        2R29 U2 Vibration Monitoring                U2 EPU
Project Overview
* Major Modifications
  - Main Generator Rewind (Rotor and Stator)
  - Generator Step-up Transformer Replacement
  - High Pressure Turbine Replacement
  - Moisture Separator Reheater (MSR) Replacement
  - Auxiliary Feedwater System Upgrades
* Same Basic System Design with Larger Pumps and Larger Recirculation Lines
* Pre-Implementation Modification
  - Vibration Monitoring for Flow Induced Vibration (to be installed 1 cycle prior to EPU implementation on each unit) 8
Project Overview
* Project Status
  - NSSS Systems
* Safety Analysis of Events Impacted by EPU Complete 3/4 Demonstrates Safety Analysis Limits are Met at EPU Conditions
* Major Components Analysis Complete 3/4 Demonstrates Components Capable of Operation at Uprated Conditions Maintaining Adequate Margins
* Impacts 3/4 Uninterrupted Post-LOCA RHR flow 3/4 Feedwater Isolation Modification
  - Methodology Changes Identified
* RAVE (Locked Rotor/Loss of RC Flow Analyses) 3/4 RAVE Methodology WCAP-16259-P-A Approved by an SER dated September 15, 2005 3/4 Will be Submitted for Plant-Specific Approval by the EPU LAR 9
Project Overview
* Project Status
  - Margin Management
* Impact of EPU on Plant Margin Being Evaluated 3/4 Overall Margin Impact of EPU Evaluated Prior to Submittal 3/4 Review Process Includes Plant Margin Review Board 3/4 Margin Impact Also Evaluated as Part of the Modification Process 10
Project Overview
* Project Status
  - BOP Systems
* System and Program Evaluations 95% Complete
* Auxiliary Feedwater System Modification 3/4 Preliminary Design Option Chosen
* Component Cooling Pump Impellers
  - Electrical Systems Analyses
* Preliminary MISO Study Completed 3/4 Based on Assumed Prior-Queued Projects 3/4 Additional Power Assumptions Bound EPU Design 3/4 Need for Additional Capacitor Banks and Voltage Support Identified
* MISO Study Completion Prior to Implementation of EPU 11
Project Overview
* Status of LAR Development
  - Licensing Report Sections
* 95% Drafted
  - LAR Submittal Packages
* Under Development 12
Licensing Action Interfaces 2008            2009      2010                2011        2012                  2013            2014            2015 Alternative Source Term Leak Before Break Spent Fuel Pool Criticality Key:                                                              EPU - U1/U2
    = Submittal
    = NRC Approval RSG Submittals
    = Implementation NFPA-805 1R25                    1R26                        1R27                    1R28                      1R29 C25                  C26                      C27                            C28                        C29 U1 EPU 2R25                      2R26                      2R27                              2R28                    2R29 C25                      C26                            C27                              C28 U2 RSG                    U2 EPU 13
License Amendment Request
* EPU License Amendment Request Approach
  - Content and Structure in Accordance with RS-001, Review Standard for Extended Power Uprates
* Content and structure followed closely
* PINGP is not designed to GDCs
  - Applicable Operating Experience Reviewed and Considered in EPU LAR
* Continuous Process Through EPU Implementation
* Includes Review of Applicable NRC Requests for Additional Information (RAIs)
  - LAR Content will be Frozen Prior to Submittal
* Necessary to Support Validation and Final Reviews 14
License Amendment Request
* NRC Acceptance Review Expectations
  - Acceptance Review Expectations Appear to be Changing
  - Recent Acceptance Review RAI
* All Structural Modifications and/or Additions Identified and Designed
* All Structural Evaluations and Required Calculations Completed
* All Controlled Documentation Exists Which Finds SSCs Structurally Adequate for EPU Conditions
  - Component Level Detailed Design Not Scheduled for Completion Prior to PINGP EPU LAR Submittal.
  - Significant Impact on Schedule for Submittal of PINGP EPU LAR
* AFW System Redesign
* Piping Support Modifications
* Feedwater Isolation 15
Questions/Discussion 16}}

Latest revision as of 17:03, 12 November 2019

Pre-Application Meeting for Prairie Island Nuclear Generating Plant (Ping) Extended Power Uprate (EPU)
ML112280389
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 08/18/2011
From:
Xcel Energy
To:
Division of Operating Reactor Licensing
Wengert, Thomas
References
Download: ML112280389 (16)


Text

Pre-Application Meeting for Prairie Island Nuclear Generating Plant (PINGP)

Extended Power Uprate (EPU)

NRC Headquarters Rockville, MD August 18, 2011 1

Introductions

  • Jim Molden - Vice President of Engineering, Regulatory Affairs and Projects
  • Tom Verbout - Manager, Prairie Island EPU and LCM Projects
  • Scott McCall - Prairie Island Design Engineering Manager
  • Gene Eckholt - Nuclear Projects Licensing Manager 2

Agenda

  • Objectives
  • Background
  • Project Overview
  • Licensing Action Interfaces
  • License Amendment Request (LAR)
  • Questions/Discussion 3

Objectives

  • Open Communications with NRC
  • EPU Project Status Update
  • Discuss EPU License Amendment Request Development and Content
  • Discuss Interfaces Between EPU and other Licensing Actions
  • Obtain NRC Feedback and Expectations 4

Background

  • Initial Licenses

- Unit 1 Operating License Issued August 1973

- Unit 2 Operating License Issued October 1974

- 1650 MWt Original Licensed Thermal Power (OLTP)

  • Renewed Operating Licenses issued in June 2011

- Unit 1 Renewed Operating License Expires August 2033

- Unit 2 Renewed Operating License Expires October 2034 5

Background

Uprate

- Implemented October 2010

  • 1677 MWt Licensed Power Level
  • 1683 MWt Analyzed Power Level

- 1804 MWt Licensed Power Level (~109 % of OLTP)

- 1811 MWt Analyzed Power Level

- Unit 1 Implementation 1R29, 2014

- Unit 2 Implementation 2R29, 2015 6

Project Overview 2009 2010 2011 2012 2013 2014 2015 EPU - Phase 2 - LAR Development NRC Review EPU - Phase 3 - Material Procurement EPU - Phase 4 - Modification Design EPU - Phase 5 - U1 Key: Implementation

= Submittal

= NRC Approval EPU - Phase 6 - U2 Implementation

= Implementation EPU - Phase 7 - Project Closeout 1R26 C26 1R27 C27 1R28 C28 1R29 C29 U1 Vibration Monitoring U1 EPU C25 2R26 C26 2R27 C27 2R28 C28 2R29 U2 Vibration Monitoring U2 EPU

Project Overview

  • Major Modifications

- Main Generator Rewind (Rotor and Stator)

- Generator Step-up Transformer Replacement

- High Pressure Turbine Replacement

- Moisture Separator Reheater (MSR) Replacement

- Auxiliary Feedwater System Upgrades

  • Same Basic System Design with Larger Pumps and Larger Recirculation Lines
  • Pre-Implementation Modification

- Vibration Monitoring for Flow Induced Vibration (to be installed 1 cycle prior to EPU implementation on each unit) 8

Project Overview

  • Project Status

- NSSS Systems

  • Safety Analysis of Events Impacted by EPU Complete 3/4 Demonstrates Safety Analysis Limits are Met at EPU Conditions
  • Major Components Analysis Complete 3/4 Demonstrates Components Capable of Operation at Uprated Conditions Maintaining Adequate Margins
  • Impacts 3/4 Uninterrupted Post-LOCA RHR flow 3/4 Feedwater Isolation Modification

- Methodology Changes Identified

  • RAVE (Locked Rotor/Loss of RC Flow Analyses) 3/4 RAVE Methodology WCAP-16259-P-A Approved by an SER dated September 15, 2005 3/4 Will be Submitted for Plant-Specific Approval by the EPU LAR 9

Project Overview

  • Project Status

- Margin Management

  • Impact of EPU on Plant Margin Being Evaluated 3/4 Overall Margin Impact of EPU Evaluated Prior to Submittal 3/4 Review Process Includes Plant Margin Review Board 3/4 Margin Impact Also Evaluated as Part of the Modification Process 10

Project Overview

  • Project Status

- BOP Systems

  • System and Program Evaluations 95% Complete
  • Component Cooling Pump Impellers

- Electrical Systems Analyses

  • Preliminary MISO Study Completed 3/4 Based on Assumed Prior-Queued Projects 3/4 Additional Power Assumptions Bound EPU Design 3/4 Need for Additional Capacitor Banks and Voltage Support Identified
  • MISO Study Completion Prior to Implementation of EPU 11

Project Overview

  • Status of LAR Development

- Licensing Report Sections

  • 95% Drafted

- LAR Submittal Packages

  • Under Development 12

Licensing Action Interfaces 2008 2009 2010 2011 2012 2013 2014 2015 Alternative Source Term Leak Before Break Spent Fuel Pool Criticality Key: EPU - U1/U2

= Submittal

= NRC Approval RSG Submittals

= Implementation NFPA-805 1R25 1R26 1R27 1R28 1R29 C25 C26 C27 C28 C29 U1 EPU 2R25 2R26 2R27 2R28 2R29 C25 C26 C27 C28 U2 RSG U2 EPU 13

License Amendment Request

  • EPU License Amendment Request Approach

- Content and Structure in Accordance with RS-001, Review Standard for Extended Power Uprates

  • Content and structure followed closely
  • PINGP is not designed to GDCs

- Applicable Operating Experience Reviewed and Considered in EPU LAR

  • Continuous Process Through EPU Implementation
  • Includes Review of Applicable NRC Requests for Additional Information (RAIs)

- LAR Content will be Frozen Prior to Submittal

  • Necessary to Support Validation and Final Reviews 14

License Amendment Request

- Acceptance Review Expectations Appear to be Changing

- Recent Acceptance Review RAI

  • All Structural Modifications and/or Additions Identified and Designed
  • All Structural Evaluations and Required Calculations Completed
  • All Controlled Documentation Exists Which Finds SSCs Structurally Adequate for EPU Conditions

- Component Level Detailed Design Not Scheduled for Completion Prior to PINGP EPU LAR Submittal.

- Significant Impact on Schedule for Submittal of PINGP EPU LAR

  • AFW System Redesign
  • Piping Support Modifications

Questions/Discussion 16