ML102380571

From kanterella
Jump to navigation Jump to search

Meeting Presentation Alternative Source Term Steam Generator Tube Rupture Margin to Overfill Evaluation - Prairie Island Nuclear Generating Plant
ML102380571
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 08/25/2010
From:
Xcel Energy
To:
Office of Nuclear Reactor Regulation
Wengert, Thomas J, NRR/DORL, 415-4037
References
Download: ML102380571 (29)


Text

ALTERNATIVE SOURCE TERM Steam Generator Tube Rupture Margin to Overfill Evaluation Prairie Island Nuclear Generating g Plant August 25, 2010 1

Attendees Lynne Gunderson Projects Licensing Manager Tom Verbout AST Project Manager Steve Thomas AST Technical Lead Oley Nelson SGTR MTO Subject Matter Expert Amy Hazelhoff Senior Licensing Engineer 2

Meeting Purpose

  • Gain mutual understanding g of p path forward 3

Agenda

  • RG 1 1.183 183 Applicability
  • NRC Concerns with 5/25/10 RAI Response
  • Specific Aspects of SGTR MTO Evaluation
  • Path Forward 4

PINGP Major Projects Schedule 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 NRC Review License Renewal Hearings AST Key:

= Submittal MUR

= NRC Approval

= Implementation LBB EPU U1/U2 1R24 1R25 1R26 1R27 1R28 1R29 C24 C25 C26 C27 C28 C29 LEFM MUR U1 EPU Uprate 2R24 2R25 2R26 2R27 2R28 2R29 C24 C25 C26 C27 C28 LEFM MUR Uprate U2 RSG U2 EPU 5

PINGP Background

  • Designed and constructed to the draft AEC GDC as proposed July 10, 1967
  • Not licensed to NUREG-0800 or NUREG-75/087, Standard Review Plan
  • Not an SEP plant 6

AST LAR and RAI Background

- Submitted October 2009 ((ADAMS #ML093160583))

- Six accident sequences analyzed for radiological consequences, including SGTR

- Radiological Consequence Analyses per RG 1.183

- SGTR radiological consequence analysis discussion in LAR included discussion of SGTR MTO evaluation

  • Based on discussion with the NRC during the pre-application meeting 7

AST LAR and RAI Background

- Requested Details Regarding:

  • Methods used in evaluation
  • Input parameters and values p
  • Operator action times credited
  • Single failure considerations
  • Results
  • NSPM Responded R d d tto RAI ini May M 2010

- ADAMS Accession #ML101460064 8

Overview of PINGP SGTR MTO Licensing Basis USAR S USAR, Sectionti 14 14.5.4.1 5 4 1 states:

t t The recovery procedure can be carried out in a time scale which ensures that break flow to the secondary system is terminated before water level in the affected steam generator rises into the main steam pipe. Sufficient indications and controls are provided to enable the Operator to carry out these functions satisfactorily.

USAR Section 14 14.5.4.5 5 4 5 states:

There is ample time to carry out the above recovery procedure such that isolation of the ruptured steam generator is established before water level rises into the main steam pipes pipes. Normal operator vigilance assures that excessive water level will not be attained.

9

Overview of PINGP SGTR MTO Licensing Basis

  • USAR reliesli on recovery procedures d and d operator t

response to ensure ruptured steam generator is not overfilled

  • SGTR MTO evaluation not considered a safety analysis within licensing basis
  • Purpose of MTO evaluation is to demonstrate that operator response using recovery procedures with conservative ti inputs i t andd assumptions ti precludes l d overfilling ruptured steam generator 10

RG 1.183 Applicability RG 1.183 Section 5.1.4, Applicability of Prior Licensing Basis, states:

The NRC staff considers the implementation of an AST to be a significant change to the design basis of the facility that is voluntarily initiated by the licensee. In order to issue a license amendment authorizing the use of an AST and the TEDE dose criteria, the NRC staff must make a current finding of compliance with regulations applicable to the amendment. The characteristics of the ASTs and the revised dose calculational methodology may be incompatible with many of the analysis assumptions and methods currently reflected in the facilitys design basis analyses.

The NRC staff may find that new or un-reviewed issues are created by a particular site specific implementation of the AST site-specific AST, warranting review of staff positions approved subsequent to the initial issuance of the license. This is not considered a backfit as defined by 10 CFR 50.109,Backfitting. However, prior design bases that are unrelated to the use of the AST, or are unaffected by the AST, may continue as the facilitys facility s design basis basis. Licensees should ensure that analysis assumptions and methods are compatible with the ASTs and the TEDE criteria.

11

RG 1.183 Applicability RG 1.183 Section 1.3.2, Re-Analysis Guidance, helps to determine if an analysis is affected by AST:

An An analysis is considered to be affected if the proposed modification changes one or more assumptions or inputs used in that analysis such that the results, or the conclusions drawn on those results, are no longer valid.

-Thus, an analysis is affected if the assumptions or inputs are changed h d which hi h requires i th the analysis l i tto b be revised i d 12

RG 1.183 Applicability Changes made to SGTR Radiological Consequence Analysis for AST:

  • Source S T Term
  • Transport Calculation
  • Break flow through ruptured SG tube
  • Steam release from ruptured SG
  • Steam S release ffrom intact SG
  • Control Room Dose Considered 13

RG 1.183 Applicability MTO evaluation was not affected by the revised SGTR radiological consequence analysis:

-NNon-conservative ti tto use SGTR radiological di l i l consequence analysis transport calculation for the MTO evaluation

- No impact to RCS/SG differential pressures

- No impact to AFW and SI flow rates

- No impacts to system volumes

- No N changes h tto OOperator t Recovery R Procedures P d 14

RG 1.183 Applicability

==

Conclusion:==

  • No changes to inputs or assumptions in MTO evaluation l ti
  • MTO evaluation was not affected by AST analyses
  • Therefore, acceptable to retain the current design basis for the MTO evaluation for AST 15

RG 1.183 Applicability

  • Discussion 16

Discussion of NRC Concerns on RAI Response

- Use of the simulator for the SGTR MTO analysis was not consistent with the guidance of SRP Section 15.0.I.6.C

- Data comparison showed that the calculated operator action times were significantly shorter than that calculated by using the NRC-approved methods for two similar Westinghouse 2-loop plants

- Use of the simulator for the MTO analysis was not consistent with the licensing basis as the current basis was changed by adopting d ti th the AST methodology th d l that th t reduced d d th the conservatisms in the current dose analysis 17

Discussion of NRC Concerns on RAI Response

- Use of the simulator for the SGTR MTO analysis was not consistent with the guidance of SRP Section 15.0.I.6.C

  • SGTR MTO evaluation substantiates the licensing basis
  • Simulator was only used to determine operator action times
  • Operator action times were used as inputs to the evaluation method and were not part of the method
  • Methods used provide conservative results 18

Discussion of NRC Concerns on RAI Response

- Data comparison showed that the calculated operator action times were significantly shorter than that calculated by using the NRC-approved methods for two similar Westinghouse 2-loop plants,

  • Operator action times were recorded for each operating crew instead of being calculated
  • Evaluation performed using each crews times to ensure that each crew could complete recovery procedures before the water could enter the main steam pipe
  • PINGP has implemented procedural changes in recent years to p

enhance operator p performance

  • Use of operator times based on the recovery procedures to conservatively demonstrate that the steam generator will not be overfilled is consistent with the licensing basis 19

Discussion of NRC Concerns on RAI Response

- Use of the simulator for the MTO analysis was not consistent with the licensing basis as the current basis was changed by adopting the AST methodology that reduced the conservatisms in the current dose analysis

  • SGTR Radiological Consequence Analyses and SGTR MTO Evaluation are two separate evaluations

- SGTR MTO evaluation was not affected by analyses performed for the AST LAR

- Acceptable to retain current design and licensing basis for SGTR MTO evaluation 20

Conclusion

- SGTR MTO evaluation was not affected by AST analyses

  • No changes to inputs or assumptions used in SGTR MTO evaluation as a result of the AST analyses

- Consistent with RG 1.183, it is considered acceptable to retain current licensing and design basis for SGTR MTO evaluation l ti 21

Technical Discussion Specific Aspects of the SGTR MTO Evaluation 22

Specific Aspects of the SGTR MTO Evaluation

  • The SGTR MTO evaluation Th l ti iis performed f d tto substantiate the licensing basis
  • SGTR MTO uses a conservative evaluation methodology coupled with conservative inputs and assumptions to provide conservative results
  • SGTR MTO evaluation does not solely rely on the simulator
  • Methods, assumptions, inputs and results are summarized on the following slides 23

Specific Aspects of the SGTR MTO Evaluation M th d Methods

  • Evaluation is based on standard engineering principles:

- Determine available volume in ruptured SG

- Determine volume injected into ruptured steam generator

  • Operator action times measured to reach specific steps (SI, I l t AFW Flow, Isolate Fl Break B k Flow Fl Terminated)

T i t d) in i the th recovery procedures for each crew

  • Conservative design flow rates used

- MTO = Available Volume - Total volume Injected 24

Specific Aspects of the SGTR MTO Evaluation Key Assumptions and Inputs

  • High Initial SG Level + Instrument Uncertainties

- Provides for maximum liquid volume; i.e., minimum available volume

  • Maximum AFW flow rate

- Conservative injection rate to ruptured SG

  • Maximum SI flow rate

- Conservative injection rate to RCS 25

Specific Aspects of the SGTR MTO Evaluation Key Assumptions and Inputs (continued)

  • Flow rate through ruptured SG tube determined based on static differential pressure

- Results R lt iin hi high h flflow rate t iinto t ruptured t d SG

- Two time periods considered

  • Prior to SI and after SI
  • No credit for steam release from ruptured SG

- Provides for minimum margin to overfill

  • Timing for Operator Actions

- Times for each crew performing recovery procedures using plant simulator 26

Specific Aspects of the SGTR MTO Evaluation R

Results:

lt

  • Demonstrate each crew can complete required actions in the recovery procedures prior to water level in affected steam generator reaching main steam pipe
  • Available margin varies by crew
  • Consistent with licensing basis as described in USAR

- Operators using recovery procedures preclude SG overfill 27

Path Forward

  • Discussion 28

29