Pre-Application Meeting for Prairie Island Nuclear Generating Plant (Ping) Extended Power Uprate (EPU)
ML112280389
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 08/18/2011
From:
Xcel Energy
To:
Division of Operating Reactor Licensing
Wengert, Thomas
References
Download: ML112280389 (16)


Text

1 Pre-Application Meeting for Prairie Island Nuclear Generating Plant (PINGP)

Extended Power Uprate (EPU)

NRC Headquarters Rockville, MD August 18, 2011

2

Introductions

Jim Molden - Vice President of Engineering, Regulatory Affairs and Projects Tom Verbout - Manager, Prairie Island EPU and LCM Projects Scott McCall - Prairie Island Design Engineering Manager Gene Eckholt - Nuclear Projects Licensing Manager

3 Objectives

Background

Project Overview Licensing Action Interfaces License Amendment Request (LAR)

Questions/Discussion Agenda

4 Objectives Open Communications with NRC EPU Project Status Update Discuss EPU License Amendment Request Development and Content Discuss Interfaces Between EPU and other Licensing Actions Obtain NRC Feedback and Expectations

5 Background

Initial Licenses

- Unit 1 Operating License Issued August 1973

- Unit 2 Operating License Issued October 1974

- 1650 MWt Original Licensed Thermal Power (OLTP)

Renewed Operating Licenses issued in June 2011

- Unit 1 Renewed Operating License Expires August 2033

- Unit 2 Renewed Operating License Expires October 2034

6 Background

Measurement Uncertainty Recapture (MUR)

Uprate

- Implemented October 2010

  • 1677 MWt Licensed Power Level

- 1804 MWt Licensed Power Level (~109 % of OLTP)

- 1811 MWt Analyzed Power Level

- Unit 1 Implementation 1R29, 2014

- Unit 2 Implementation 2R29, 2015

Project Overview 2009 2010 2011 2012 2013 2014 2015

= Submittal

= NRC Approval Key:

= Implementation C26 C27 C28 C29 C28 U1 EPU 1R26 1R27 1R28 1R29 2R26 2R27 2R28 2R29 U2 EPU EPU - Phase 3 - Material Procurement EPU - Phase 4 - Modification Design EPU - Phase 5 - U1 Implementation EPU - Phase 6 - U2 Implementation EPU - Phase 7 - Project Closeout C25 C26 C27 U1 Vibration Monitoring U2 Vibration Monitoring EPU - Phase 2 - LAR Development NRC Review

8 Project Overview Major Modifications

- Main Generator Rewind (Rotor and Stator)

- Generator Step-up Transformer Replacement

- High Pressure Turbine Replacement

- Moisture Separator Reheater (MSR) Replacement

- Auxiliary Feedwater System Upgrades

  • Same Basic System Design with Larger Pumps and Larger Recirculation Lines Pre-Implementation Modification

- Vibration Monitoring for Flow Induced Vibration (to be installed 1 cycle prior to EPU implementation on each unit)

9 Project Overview Project Status

- NSSS Systems

  • Safety Analysis of Events Impacted by EPU Complete 3/4 Demonstrates Safety Analysis Limits are Met at EPU Conditions
  • Major Components Analysis Complete 3/4 Demonstrates Components Capable of Operation at Uprated Conditions Maintaining Adequate Margins
  • Impacts 3/4 Uninterrupted Post-LOCA RHR flow 3/4 Feedwater Isolation Modification

- Methodology Changes Identified

  • RAVE (Locked Rotor/Loss of RC Flow Analyses) 3/4 RAVE Methodology WCAP-16259-P-A Approved by an SER dated September 15, 2005 3/4 Will be Submitted for Plant-Specific Approval by the EPU LAR

10 Project Status

- Margin Management

  • Impact of EPU on Plant Margin Being Evaluated 3/4 Overall Margin Impact of EPU Evaluated Prior to Submittal 3/4 Review Process Includes Plant Margin Review Board 3/4 Margin Impact Also Evaluated as Part of the Modification Process Project Overview

11 Project Overview Project Status

- BOP Systems

  • System and Program Evaluations 95% Complete
  • Component Cooling Pump Impellers

- Electrical Systems Analyses

  • Preliminary MISO Study Completed 3/4 Based on Assumed Prior-Queued Projects 3/4 Additional Power Assumptions Bound EPU Design 3/4 Need for Additional Capacitor Banks and Voltage Support Identified
  • MISO Study Completion Prior to Implementation of EPU

12 Project Overview Status of LAR Development

- Licensing Report Sections

  • 95% Drafted

- LAR Submittal Packages

  • Under Development

13 Licensing Action Interfaces 2008 2009 2010 2011 2012 2013 2014 2015

= Submittal

= NRC Approval Key:

= Implementation C25 C26 C27 C28 C29 C25 C26 C27 C28 U1 EPU 1R25 1R26 1R27 1R28 1R29 2R25 2R26 2R27 2R28 2R29 U2 EPU U2 RSG RSG Submittals EPU - U1/U2 Spent Fuel Pool Criticality Alternative Source Term Leak Before Break NFPA-805

14 License Amendment Request EPU License Amendment Request Approach

- Content and Structure in Accordance with RS-001, Review Standard for Extended Power Uprates

  • Content and structure followed closely
  • PINGP is not designed to GDCs

- Applicable Operating Experience Reviewed and Considered in EPU LAR

  • Continuous Process Through EPU Implementation
  • Includes Review of Applicable NRC Requests for Additional Information (RAIs)

- LAR Content will be Frozen Prior to Submittal

  • Necessary to Support Validation and Final Reviews

15 License Amendment Request NRC Acceptance Review Expectations

- Acceptance Review Expectations Appear to be Changing

- Recent Acceptance Review RAI

  • All Structural Modifications and/or Additions Identified and Designed
  • All Structural Evaluations and Required Calculations Completed
  • All Controlled Documentation Exists Which Finds SSCs Structurally Adequate for EPU Conditions

- Component Level Detailed Design Not Scheduled for Completion Prior to PINGP EPU LAR Submittal.

- Significant Impact on Schedule for Submittal of PINGP EPU LAR

  • AFW System Redesign
  • Piping Support Modifications

16 Questions/Discussion