Letter Sequence Request |
---|
EPID:L-2020-LRM-0084, (PINGP) COVID-19 Exemption Request for the 2020 Biennial Emergency Preparedness Exercise (Open) |
|
MONTHYEARML20266F1052020-09-23023 September 2020 (PINGP) COVID-19 Exemption Request for the 2020 Biennial Emergency Preparedness Exercise Project stage: Request ML20274A2442020-10-16016 October 2020 Summary of 9/23/2020 Meeting with Northern States Power Co., Doing Business as Xcel Energy, on Potential License Exemption Request Related to Biennal Emergency Preparedness Exercise for Prairie Island Nuclear Generating Plant, Units 1 & 2 Project stage: Meeting 2020-10-16
[Table View] |
|
---|
Category:Emergency Preparedness-Emergency Plan
MONTHYEARML22251A1712022-09-0707 September 2022 10 CFR 50 Appendix E Evacuation Time Estimate Analysis for the Monticello and Prairie Island Nuclear Generating Plants ML22161A9152022-06-10010 June 2022 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Response to a Request for Additional Information Xcel Energy Amendment Request to Create a Common Emergency Plan and Emergency Operations. ML21320A2262021-11-15015 November 2021 License Amendment Request: Standard Emergency Plan and Consolidated Emergency Operations Facility for the Monticello Nuclear Generating Plant and the Prairie Island Nuclear Generating Plant ML20266F1052020-09-23023 September 2020 (PINGP) COVID-19 Exemption Request for the 2020 Biennial Emergency Preparedness Exercise ML18302A2552018-10-26026 October 2018 Procedure Change Summary Analysis and Revision 7 to FP-EP-PLAN-01, Offsite Nuclear Emergency Plan ML18299A0842018-10-26026 October 2018 Submittal of Offsite Nuclear Emergency Plan Revision ML18113A0532018-04-17017 April 2018 Revised Emergency Action Level (EAL) Matrix to Revision 10 and Emergency Action Level Technical Bases (F3-2.1) ML17138A2552017-03-30030 March 2017 Submittal of Revised Emergency Plan and Emergency Plan Implementing Procedures L-PI-17-011, Revision 53 to Emergency Plan2017-03-30030 March 2017 Revision 53 to Emergency Plan ML17094A5822017-03-29029 March 2017 Emergency Action Level (EAL) Matrix for Hot Condition L-PI-17-006, Emergency Action Level (EAL) Matrix for Cold Condition2017-03-29029 March 2017 Emergency Action Level (EAL) Matrix for Cold Condition ML17094A5762017-03-29029 March 2017 License Amendment Request to Revise Emergency Action Level (EAL) Scheme L-PI-14-071, July 21, 2014 ML14204A0522014-07-21021 July 2014 July 21, 2014 ML14204A052 L-PI-13-102, License Amendment Request (LAR) to Revise Staff Augmentation Times in the Prairie Island Nuclear Generating Plant (PINGP) Emergency Plan2013-12-20020 December 2013 License Amendment Request (LAR) to Revise Staff Augmentation Times in the Prairie Island Nuclear Generating Plant (PINGP) Emergency Plan L-PI-13-048, Supplement to License Amendment Request (LAR) to Revise Emergency Plan (EP) Emergency Action Levels (Eals): RA 1.2 and Fuel Clad Barrier Loss Criteria2013-06-21021 June 2013 Supplement to License Amendment Request (LAR) to Revise Emergency Plan (EP) Emergency Action Levels (Eals): RA 1.2 and Fuel Clad Barrier Loss Criteria L-HU-07-021, Units 1 and 2, Request for Approval of a Combined Nuclear Management Company Emergency Plan2007-08-0707 August 2007 Units 1 and 2, Request for Approval of a Combined Nuclear Management Company Emergency Plan L-PI-04-120, Emergency Action Levels Revision Submittal2004-10-22022 October 2004 Emergency Action Levels Revision Submittal L-PI-04-105, Sept. 22, 2004 ML0427504022004-09-22022 September 2004 Sept. 22, 2004 ML042750402 2022-09-07
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24029A0382024-01-31031 January 2024 January 31, 2024, Pre-application Meeting Presentation - Prairie Island ISFSI License Amendment Request to Add Grace to License Conditions ML23168A0032023-06-20020 June 2023 Handout for 6/23/2023 Pre-Application Public Meeting with Prairie Island Nuclear Generating Plant to Revise ISFSI TS 4.4 for TN-40HT Casks ML23156A2602023-06-0505 June 2023 2022 Prairie Island End-of-Cycle Meeting Presentation ML23102A1752023-04-14014 April 2023 April 14, 2023 TS 3.7.8 LAR Pre-Submittal Meeting Slides ML22130A5852022-05-10010 May 2022 2021 Monticello and Prairie Island Nuclear Generating Plant End-of-Cycle Meeting Presentation ML22048B1812022-02-18018 February 2022 Pre-Application Meeting for Prairie Island TS 5.6.6, PTLR, LAR ML21166A3792021-06-15015 June 2021 Units 1 and 2 2020 End-of-Cycle Meeting Presentation ML21124A0652021-05-0606 May 2021 Xcel Energy Presentation for May 6, 2021 Public Meeting to Discuss 24-Month Cycles at Prairie Island Nuclear Generating Plant, Units 1 and 2 ML21032A2632021-02-0303 February 2021 Slides for Public Meeting with Xcel Energy to Discuss a Planned Amendment to Combine the Emergency Plans and Create a Common Emergency Offsite Facility for Monticello and Prairie Island ML20266F1052020-09-23023 September 2020 (PINGP) COVID-19 Exemption Request for the 2020 Biennial Emergency Preparedness Exercise ML20212L8622020-07-29029 July 2020 2019 Monticello and Prairie Island EOC Presentation from Webinar ML20098F0682020-04-0909 April 2020 Preapplication Teleconference Presentation: License Amendment Request to Adopt TSTF-569 ML20057D3082020-02-18018 February 2020 Slides Potential License Amendment to Remove Note from LCO 3.4.12 and LCO 3.4.13 ML19268A0422019-09-26026 September 2019 Pre-Application Meeting License Amendment Request Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML19210D4512019-07-22022 July 2019 Abeyance Seal Preapplication Meeting Slides ML19071A2782019-03-0707 March 2019 Enclosure 3: Meeting Slides (Summary of February 28, 2019, Public Meeting with Xcel Energy to Discuss Increasing the Amount of Special Nuclear Material Authorized for Storage at the Prairie Island ISFSI (W/Enclosures 1 and 2)) ML18162A0262018-06-12012 June 2018 License Amendment Request to Reclassify Certain Fuel Handling Equipment ML18051A1752018-02-20020 February 2018 Pre-Application Meeting License Amendment for TSTF-425 Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program Xcel Energy 2/20/2018 ML17240A3382017-08-30030 August 2017 Non-Safety Related Digital Feedwater and Amsac/Dss Control Systems Replacement Project Presentation ML17198A2632017-07-17017 July 2017 Pre-Application Meeting ML17209A1192017-07-17017 July 2017 Summary of July 17, 2017, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request Related to Heavy Lifting Devices ML17066A3732017-03-0909 March 2017 Spent Fuel Pool Criticality Technical Specification Changes Round 2 Request for Additional Information Public Meeting: March 9, 2017 ML17037D1172017-02-0707 February 2017 License Amendment Requests for Change in Emergency Plan Staff Augmentation Response Times Pre-Submittal Meeting for Prairie Island Nuclear Generating Plant Monticello Nuclear Generating Plant: February 7, 2017 ML17023A0652017-01-24024 January 2017 Pre-Submittal Call Regarding License Amendment Requests for Prairie Island Nuclear Generating Plant, Units 1 and 2 and Monticello Nuclear Generating Plant Emergency Action Level Scheme Changes ML16280A0352016-09-29029 September 2016 Flood Hazard Reevaluation Report - Response to Requested Information (CAC Nos. MF7710 and MF7711) - Figure 1 of 3 ML16280A0372016-09-29029 September 2016 Flood Hazard Reevaluation Report - Response to Requested Information (CAC Nos. MF7710 and MF7711) - Figure 2 of 3 ML16280A0422016-09-29029 September 2016 Flood Hazard Reevaluation Report - Response to Requested Information (CAC Nos. MF7710 and MF7711) - Figure 3 of 3 ML15140A3342015-05-13013 May 2015 Public Meeting 05132015 Licensee Slides Only ML15127A6562015-05-0707 May 2015 PI EOC Mtg NRC Slides ML15105A0372015-04-14014 April 2015 Xcel Energy Slide Presentation to Support Pre-Application Meeting on April 14, 2015, to Discuss Nuclear Fuel Design Transition to Include Integral Fuel Burnable Absorber (Ifba) at the Prairie Island Nuclear Generating Plant ML14323B0222014-11-19019 November 2014 Regcon, November 19-20, 2014: 03-Info-Session-2 Ronald Johnson - Tribal Perspective on Continued Storage ML14162A5202014-06-11011 June 2014 Slides: Prairie Island Independent Spent Fuel Storage Installation - License Renewal Application - Discussion of Requests for Additional Information, for June 16, 2014, Public Meeting ML14153A0242014-05-16016 May 2014 Xcel Energy'S Presentation Slides Supporting a May 16, 2014, Public Meeting to Discuss the Flood Hazard Reevaluation Schedule for the Monticello and Prairie Island Nuclear Generating Plants ML14084A3242014-03-21021 March 2014 M140321: Slides - Presented by Multiple Participants at Commission Briefing on Waste Confidence Rulemaking ML13210A2012013-07-29029 July 2013 2012 End-of-Cycle Slides - Licensee ML13210A2002013-07-11011 July 2013 2012 End-of-Cycle Slides ML13056A0262013-02-25025 February 2013 Regulatory Conference Slide Presentation ML12340A5402012-12-0606 December 2012 Reactor Core Cooling & Heat Removal FLEX Strategy - Phase 1 ML12326A9712012-11-21021 November 2012 Encl 3 (Handouts - Public) to Summary of October 24, 2012, Meeting with the Northern States Power Company, D/B/A Excel Energy Regarding Security Requirements and Changes Pertaining to Prairie Island TAC L24689 ML12277A1762012-10-0404 October 2012 Steam Generator Replacement Presentation ML12275A3782012-09-27027 September 2012 Xcel Energy Prairie Island Nuclear Generating Plant Meeting Presentation, Diesel Generator Voltage and Frequency Limits. ML12205A2172012-07-23023 July 2012 NRC 2011 End-of-Cycle Slides ML12205A2202012-07-17017 July 2012 Licensee 2012 End-of-Cycle Slides ML12115A3112012-04-24024 April 2012 Meeting Slides: 04/24/2012 Meeting with Xcel Energy NFPA 805 Presubmittal - Prairie Island Nuclear Generating Plant ML1207904792012-03-14014 March 2012 March 14, 2012 Telecon Slides ML1122803892011-08-18018 August 2011 Pre-Application Meeting for Prairie Island Nuclear Generating Plant (Ping) Extended Power Uprate (EPU) ML1119903462011-07-28028 July 2011 Meeting Presentation, Prairie Island Nuclear Generating Plant - Failure to Maintain the Train a and B Direct Current Electrical Power Subsystems Operable ML1117804242011-06-22022 June 2011 June 22, 2011, Meeting Handout #1 - NRC Meeting Diesel Fuel Oil LAR for Prairie Island Ngp ML1110200652011-04-14014 April 2011 NRC Slides for EOC Meeting ML1106600792011-03-0303 March 2011 March 3, 2011 Meeting Handouts - Revise Footnote in TS 3.8.1, Prairie Island Nuclear Generating Plant 2024-01-31
[Table view] |
Text
Prairie Island (PINGP) COVID-19 Exemption Request for the 2020 Biennial Emergency Preparedness Exercise 9.23.2020
Pre-Submittal Meeting Agenda
- 1. Purpose
2. Background
- 3. Exemption Elements
- 4. Schedule
- 5. Closing Remarks
© 2020 Xcel Energy 2
Purpose To discuss a proposed exemption for PINGP1 and ISFSI from 10 CFR 50 Appendix E, Sections IV.F.2.b and IV.F.2.c regarding the 2020 biennial EP exercise.
1 PINGP used throughout rest of this presentation to mean Unit 1, Unit 2, and ISFSI
© 2020 Xcel Energy 3
=
Background===
Last PINGP biennial EP exercise was conducted July 18, 2018.
The PINGP biennial EP exercise was originally scheduled for July 21, 2020 and had been rescheduled for December 1, 2020.
© 2020 Xcel Energy 4
Exemption Elements Follow the May 14, 2020 and September 2, 2020 NRC guidance Deferral of the 2020 exercise to be conducted nominally in June 2021 (June 8th).
The exemption submission would request exceeding 35 months Waiver of ORO participation in this deferred exercise State of Minnesota State of Wisconsin Counties in MN and WI The subsequent biennial exercise will be conducted in 2022 with ORO participation Deferral to 2021 would not affect the PINGP 8-year inspection cycle
© 2020 Xcel Energy 5
Schedule Plan to submit the exemption request by October 1, 2020 and request NRC approval by December 31, 2020.
© 2020 Xcel Energy 6
Acronyms PINGP Prairie Island Nuclear Generating Plant ISFSI Independent Spent Fuel Storage Installation ORO Offsite Review Organization EP Emergency Preparedness
© 2020 Xcel Energy 7
© 2020 Xcel Energy 8