ML13014A556: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(3 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
| issue date = 01/16/2013 | | issue date = 01/16/2013 | ||
| title = Summary of December 17, 2012, Meeting with Duke Energy Carolinas, LLC, to Discuss Status of the Transition to the NFPA-805 Fire Protection Program for Oconee Nuclear Station, Units 1, 2, and 3 | | title = Summary of December 17, 2012, Meeting with Duke Energy Carolinas, LLC, to Discuss Status of the Transition to the NFPA-805 Fire Protection Program for Oconee Nuclear Station, Units 1, 2, and 3 | ||
| author name = Boska J | | author name = Boska J | ||
| author affiliation = NRC/NRR/DORL/LPLII-1 | | author affiliation = NRC/NRR/DORL/LPLII-1 | ||
| addressee name = | | addressee name = | ||
Line 15: | Line 15: | ||
| page count = 4 | | page count = 4 | ||
}} | }} | ||
=Text= | |||
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 16, 2013 LICENSEE: Duke Energy Carolinas, LLC FACILITY: Oconee Nuclear Station, Units 1, 2, and 3 | |||
==SUBJECT:== | |||
==SUMMARY== | |||
OF DECEMBER 17, 2012, MEETING WITH DUKE ENERGY CAROLINAS, LLC, TO DISCUSS STATUS OF THE TRANSITION TO THE NFPA-805 FIRE PROTECTION PROGRAM FOR OCONEE NUCLEAR STATION, UNITS 1,2, AND 3 On December 17, 2012, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (N RC) and representatives of Duke Energy Carolinas, LLC (Duke or the licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. A list of attendees is enclosed. The purpose of the meeting was to allow the licensee to discuss with NRC staff their progress in complying with a license condition governing the transition to a fire protection program usill9 the National Fire Protection Association (NFPA) standard NFPA-805, "Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants." | |||
The licensee's presentation is in the meeting slides (ADAMS Accession No. ML13011A218). | |||
Duke acknowledged that they would not meet some of the project dates listed in the license condition. In particular, they were having difficulty completing the new Protected Service Water (pSW) system. The PSW system contributes major risk reduction in the fire Probabilistic Risk Assessment (PRA) used to evaluate the acceptability of the transition to NFPA-805. Duke stated they have assigned a senior manager to manage the installation of the PSWequipment, and assigned additional staff to help coordinate the project with the station interfaces. The NRC staff stated they are following this effort closely, as the risk reduction gained through implementation of the PSW system needs to be achieved at the Oconee Nuclear Station. Duke stated that in a scenario that relies on the PSW system, there would be an unanticipated temperature increase in the auxiliary building. They are designing additional cooling equipment to address this concern. | |||
Duke also stated that there were challenges with some of the modifications to the plant fire detection systems, as the vendor is reporting that some equipment is no longer available due to obsolescence. This may affect the completion dates for the fire detection modifications. Duke stated that the existing compensatory measures will remain in place until the modifications are completed, and that hourly fire watches would be added for certain critical areas. The NRC staff recommended that the licensee review NRC Regulatory Issue Summary (RIS) 2005-07, "Compensatory Measures to Satisfy the Fire Protection Program Requirements." RIS 2005-07 describes the proper method for changing the approved fire protection program to use an alternate compensatory measure. | |||
-2 Public Meeting Feedback forms were made available at the meeting. As of the date of this meeting summary, no feedback forms have been received. | |||
Please direct any inquiries to me at 301-415-2901, or by email to John.Boska@nrc.gov. | |||
SEt V/l-L J hn P. Boska, Senior Project Manager lant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287 | |||
==Enclosure:== | |||
List of Attendees cc w/encls: Distribution via Listserv | |||
UNITED STATES NUCLEAR REGULATORY COMMISSION MEETING ATIENDANCE FORM | |||
==Subject:== | |||
Oconee Nuclear Station NFPA-805 transition license condition Date: December 17. 2012 Location: OWFN. room 0-1384 PLEASE PRINT LEGIBLY NAME ORGANIZATION | |||
-2 Public Meeting Feedback forms were made available at the meeting. As of the date of this meeting summary, no feedback forms have been received. | |||
Please direct any inquiries to me at 301-415-2901, or by email to John.Boska@nrc.gov. | |||
IRA! | |||
John P. Boska, Senior Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287 | |||
==Enclosure:== | |||
List of Attendees cc w/encls: Distribution via Listserv DISTRIBUTION: | |||
PUBLIC LPL2-1 r/f RidsNrrPMOconee RidsNrrDra RidsNrrDorl RidsNrrDorlLpl2-1 RidsRgn2MailCenter RidsNrrLASFigueroa RidsNrrOd RidsNrrDra J, Boska, NRR M, Evans, NRR A. Klein, NRR G, Gulla, NRR p, Lain, NRR J, Monninger, NRR D. Harrison, NRR V. McCree, NRR M. Johnson, EDO J. Huang, NRR J. Bartley, NRR R. Croteau, NRR W, Jones, Region \I T, Reis, Region II M, King, Region II ADAMS Accession No.: Package:ML13011A365 Notice ML12346AO 63 Summary ML13014A556 SI ides ML13011A218 OFFICE DORULPL2-1/PM DORULPL2-1/LA DORLlLPL2-1/BC DORULPL2-1/PM NAME JBoska SFigueroa RPascarelii JBoska DATE 01/11/13 01/16/13 01/16113 01/16113 OFFICIAL RECORD COpy}} |
Latest revision as of 16:32, 11 November 2019
ML13014A556 | |
Person / Time | |
---|---|
Site: | Oconee |
Issue date: | 01/16/2013 |
From: | Boska J Plant Licensing Branch II |
To: | |
John Boska, NRR/DORL, 415-2901 | |
Shared Package | |
ML13011A365 | List: |
References | |
NFPA-805 | |
Download: ML13014A556 (4) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 16, 2013 LICENSEE: Duke Energy Carolinas, LLC FACILITY: Oconee Nuclear Station, Units 1, 2, and 3
SUBJECT:
SUMMARY
OF DECEMBER 17, 2012, MEETING WITH DUKE ENERGY CAROLINAS, LLC, TO DISCUSS STATUS OF THE TRANSITION TO THE NFPA-805 FIRE PROTECTION PROGRAM FOR OCONEE NUCLEAR STATION, UNITS 1,2, AND 3 On December 17, 2012, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (N RC) and representatives of Duke Energy Carolinas, LLC (Duke or the licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. A list of attendees is enclosed. The purpose of the meeting was to allow the licensee to discuss with NRC staff their progress in complying with a license condition governing the transition to a fire protection program usill9 the National Fire Protection Association (NFPA) standard NFPA-805, "Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants."
The licensee's presentation is in the meeting slides (ADAMS Accession No. ML13011A218).
Duke acknowledged that they would not meet some of the project dates listed in the license condition. In particular, they were having difficulty completing the new Protected Service Water (pSW) system. The PSW system contributes major risk reduction in the fire Probabilistic Risk Assessment (PRA) used to evaluate the acceptability of the transition to NFPA-805. Duke stated they have assigned a senior manager to manage the installation of the PSWequipment, and assigned additional staff to help coordinate the project with the station interfaces. The NRC staff stated they are following this effort closely, as the risk reduction gained through implementation of the PSW system needs to be achieved at the Oconee Nuclear Station. Duke stated that in a scenario that relies on the PSW system, there would be an unanticipated temperature increase in the auxiliary building. They are designing additional cooling equipment to address this concern.
Duke also stated that there were challenges with some of the modifications to the plant fire detection systems, as the vendor is reporting that some equipment is no longer available due to obsolescence. This may affect the completion dates for the fire detection modifications. Duke stated that the existing compensatory measures will remain in place until the modifications are completed, and that hourly fire watches would be added for certain critical areas. The NRC staff recommended that the licensee review NRC Regulatory Issue Summary (RIS) 2005-07, "Compensatory Measures to Satisfy the Fire Protection Program Requirements." RIS 2005-07 describes the proper method for changing the approved fire protection program to use an alternate compensatory measure.
-2 Public Meeting Feedback forms were made available at the meeting. As of the date of this meeting summary, no feedback forms have been received.
Please direct any inquiries to me at 301-415-2901, or by email to John.Boska@nrc.gov.
SEt V/l-L J hn P. Boska, Senior Project Manager lant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287
Enclosure:
List of Attendees cc w/encls: Distribution via Listserv
UNITED STATES NUCLEAR REGULATORY COMMISSION MEETING ATIENDANCE FORM
Subject:
Oconee Nuclear Station NFPA-805 transition license condition Date: December 17. 2012 Location: OWFN. room 0-1384 PLEASE PRINT LEGIBLY NAME ORGANIZATION
-2 Public Meeting Feedback forms were made available at the meeting. As of the date of this meeting summary, no feedback forms have been received.
Please direct any inquiries to me at 301-415-2901, or by email to John.Boska@nrc.gov.
IRA!
John P. Boska, Senior Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287
Enclosure:
List of Attendees cc w/encls: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL2-1 r/f RidsNrrPMOconee RidsNrrDra RidsNrrDorl RidsNrrDorlLpl2-1 RidsRgn2MailCenter RidsNrrLASFigueroa RidsNrrOd RidsNrrDra J, Boska, NRR M, Evans, NRR A. Klein, NRR G, Gulla, NRR p, Lain, NRR J, Monninger, NRR D. Harrison, NRR V. McCree, NRR M. Johnson, EDO J. Huang, NRR J. Bartley, NRR R. Croteau, NRR W, Jones, Region \I T, Reis, Region II M, King, Region II ADAMS Accession No.: Package:ML13011A365 Notice ML12346AO 63 Summary ML13014A556 SI ides ML13011A218 OFFICE DORULPL2-1/PM DORULPL2-1/LA DORLlLPL2-1/BC DORULPL2-1/PM NAME JBoska SFigueroa RPascarelii JBoska DATE 01/11/13 01/16/13 01/16113 01/16113 OFFICIAL RECORD COpy