ML13011A218
Jump to navigation
Jump to search
ML13011A218 | |
Person / Time | |
---|---|
Site: | Oconee |
Issue date: | 12/17/2012 |
From: | Duke Energy Carolinas |
To: | Office of Nuclear Reactor Regulation |
Boska J | |
Shared Package | |
ML13011A365 | List: |
References | |
Download: ML13011A218 (14) | |
Text
National Fire Protection Association NFPA 805 Update Risk-Informed, Performance-Based Fire Protection Program December 17, 2012
Duke Participants
- Regis Repko - Senior VP Nuclear Operations
- Preston Gillespie - Site VP Oconee Station
- Dave Baxter - VP Special Assignment
- Jim Fuller - General Manager Major Projects
- Chris Nolan - Director Regulatory Affairs Information Only 2
Agenda
- Opening Comments Repko
- Purpose Repko
- Enhancements in Leadership and Oversight Gillespie
- License Condition for NFPA 805 Baxter
- NFPA 805 Implementation Baxter
- Protected Service Water (PSW) Project Fuller
- Closing Remarks Repko Information Only 3
Dukes Commitment to Safety
- Duke demonstrates a strong commitment to the safe operation of Oconee Nuclear Station by our actions to reduce risk and improve safety
- Strong focus on improving safety significant system reliability and organizational performance continues to reduce already low risks associated with stations operations
- The result of our commitment and focus is improved safety
- Our decision to participate as a pilot plant for NFPA 805 implementation highlights our commitment to improving safety.
Information Only 4
Purpose of the Meeting
- Discuss enhancements to project Leadership and Oversight
- Provide an overview of current implementation progress of the NFPA 805 Fire Protection Program (FPP)
- Provide an overview of the resolution of the projects issues.
- Discuss approach to minimize implementation time to achieve the projects milestones Information Only 5
Leadership
- Established direct reporting relationship to Senior VP of Operations, Crystal River & Oconee
- McGuire General Manager of Major Projects has been reassigned to managing the completion of the Protected Service Water (PSW) project
- Established senior station manager and staff to coordinate station and engineering interface with the projects Information Only 6
Oversight NFPA 805
- Remaining work will be managed similar to an outage
- Work will be directed from a Project Command Center with dedicated resources
- Daily updates on project status to ONS leadership is being incorporated into the normal plant operational status reviews
- Schedule will continuously undergo line management challenge to validate logic, adequacy of task assignments and removal of barriers
- Emergent Issues Manager role included to address project challenges
- Project threat teams will be utilized to resolve significant technical challenges to project critical path Information Only 7
NFPA NFPA 805 805 License Condition
- Existing license condition captured as condition 3.D in all three unit licenses
- Committed to 47 implementation items for the NFPA 805 Fire Protection Program (FPP) by January 1, 2013
- Committed to six modifications in support of NFPA 805 with implementation dates through 2015
- Ability to self approve low risk changes affecting FPP tied to completion of modifications and an additional licensing action Information Only 8
NFPA NFPA 805 805 Implementation
- Improvement in the safety of Oconee Nuclear Station has been realized
- Programmatic controls required for implementation of NFPA 805 will be in place on or before January 1, 2013
- 44 of the 47 implementation items will be complete on or before January 1, 2013
- 4 of the 6 modifications complete or on track to meet committed date Information Only 9
NFPA NFPA 805 805 Implementation
- Modification Challenges
- Protected Service Water
- Compensatory Measures
- Existing compensatory measures will remain in place
- Standby Shutdown Facility (SSF) - primary success path for Turbine Building Fires
- Fire Watches - incorporated into FPP documents Information Only 10
Backup NFPA 805 Power to SSF
- Current implementation (93%)
- New 4160 VAC Switchgear installed in SSF - Complete
- Routed commercial grid connection cables - Complete
- Achieved initial energization of PSW Electrical panels (house loads) for testing - Complete
- PSW Building electrical testing and power up - in progress
- SSF outage for final tie-ins and testing Information Only 11
Remaining NFPA 805 Scope
- Units 1 and 2 Keowee Outages including Post Mod Testing (88% Complete)
Complete)
- Station ASW pump room demolition and new PSW pump installation (75% Compete)
Information Only 12
PSW NFPA 805 Issue Resolution
- Procurement Document Processing
- 3170 of approximately 3300 total procurement documents have been processed and approved
- Engineered Equipment Delivery
- 36 of 44 engineered components are now on site, installed or ready for installation
- Completion of EC Packages
- 36 of 38 Engineering Change Packages have been issued to the field
- Environmental Temperature
- Modeling of Auxiliary Building complete
- Forced air circulation and cooling will be required
- Scoping of solutions in progress
- Response to related Request for Additional Information (RAI) planned by 3/31/2013 Information Only 13
Closing NFPA 805 Remarks
- Duke is strengthening project implementation controls and oversight to minimize implementation time
- New organizational reporting/command structure
- Proven Outage Management approach to the project
- Programmatic controls for implementation of NFPA 805 in place on or before January 1, 2013
- PSW subsystems will be made available at the earliest opportunity Information Only 14