ML16341B902: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(8 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML16341B902
| number = ML16341B902
| issue date = 03/07/2017
| issue date = 03/07/2017
| title = 03/07/2016 Summary of Telecon Held on Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook Concerning Request for Additional Information Pertaining to the Seabrook Station License Renewal Application (CAC No. ME4028)
| title = 03/07/2016 Summary of Telecon Held on Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook Concerning Request for Additional Information Pertaining to the Seabrook Station License Renewal Application
| author name = Tran T M
| author name = Tran T
| author affiliation = NRC/NRR/DLR/RPB1
| author affiliation = NRC/NRR/DLR/RPB1
| addressee name = McCartney E
| addressee name = Mccartney E
| addressee affiliation = NextEra Energy Seabrook, LLC
| addressee affiliation = NextEra Energy Seabrook, LLC
| docket = 05000443
| docket = 05000443
| license number =  
| license number =  
| contact person = Tran T M, 415-8517
| contact person = Tran T, 415-8517
| case reference number = CAC ME4028
| case reference number = CAC ME4028
| document type = Meeting Summary, Request for Additional Information (RAI)
| document type = Meeting Summary, Request for Additional Information (RAI)
| page count = 6
| page count = 6
| project = CAC:ME4028
| project = CAC:ME4028
| stage = Other
| stage = RAI
}}
}}


=Text=
=Text=
{{#Wiki_filter:1Tran, TamFrom:Tran, TamSent:Tuesday, March 07, 2017 3:06 PMTo:'Edward.Carley@nexteraenergy.com'Cc:James, Lois; Chazell, Russell; Morey, Dennis; Allik, Brian; Edmonds, Yvonne; Poole, Justin; McIntyre, David; Weil, Jenny; Dacus, Eugene; Harris, Brian; Ghosh, Anita; Wachutka, Jeremy; Gray, Mel; Bower, Fred; Cataldo, Paul; Meier, Peter; Vadella, Robert; Tifft, Doug; Sheehan, Neil; Screnci, DianeSubject: Buried Piping ISG RAI Dec. 2016 TeleconferenceAttachments:Buried Piping RAI Dec Call - Enclosure 1 and 2.pdf UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 LICENSEE:    NextEra Energy Seabrook, LLC
{{#Wiki_filter:Tran, Tam From:                             Tran, Tam Sent:                             Tuesday, March 07, 2017 3:06 PM To:                               'Edward.Carley@nexteraenergy.com' Cc:                               James, Lois; Chazell, Russell; Morey, Dennis; Allik, Brian; Edmonds, Yvonne; Poole, Justin; McIntyre, David; Weil, Jenny; Dacus, Eugene; Harris, Brian; Ghosh, Anita; Wachutka, Jeremy; Gray, Mel; Bower, Fred; Cataldo, Paul; Meier, Peter; Vadella, Robert; Tifft, Doug; Sheehan, Neil; Screnci, Diane


FACILITY:       Seabrook Station, Unit No. 1 SUBJECT:    SUMMARY OF TELECONFERENCE HELD ON DECEMBER 6, 2016, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK,LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION (CAC NO. ME4028)
==Subject:==
The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Seabrook, LLC (the applicant), held a teleconference on December 6, 2016, to discuss and clarify the staff's request for additional information (RAI) concerning the Seabrook Station license renewal application. The teleconference was useful in clarifying the intent of the NRC staff's RAI.  
Buried Piping ISG RAI Dec. 2016 Teleconference Attachments:                      Buried Piping RAI Dec Call - Enclosure 1 and 2.pdf UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 LICENSEE:      NextEra Energy Seabrook, LLC FACILITY:      Seabrook Station, Unit No. 1


==Enclosure==
==SUBJECT:==
1 provides a listing of the participants and Enclosure 2 contains a listing of the RAI discussed with the applicant, including a brief description of the status of the items.
The applicant had an opportunity to comment on this summary.


Sincerely                                                                         /RA/
==SUMMARY==
Tam Tran, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No.: 50-443  
OF TELECONFERENCE HELD ON DECEMBER 6, 2016, BETWEEN THE U.S.
NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK,LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION (CAC NO. ME4028)
The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Seabrook, LLC (the applicant), held a teleconference on December 6, 2016, to discuss and clarify the staffs request for additional information (RAI) concerning the Seabrook Station license renewal application. The teleconference was useful in clarifying the intent of the NRC staffs RAI. provides a listing of the participants and Enclosure 2 contains a listing of the RAI discussed with the applicant, including a brief description of the status of the items.
The applicant had an opportunity to comment on this summary.
Sincerely
                                                  /RA/
Tam Tran, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No.: 50-443


==Enclosures:==
==Enclosures:==
: 21. List of Participants 2. Summary of Teleconference cc w/encls:  See next page 


LICENSEE:     NextEra Energy Seabrook, LLC  
1
: 1. List of Participants
: 2. Summary of Teleconference cc w/encls: See next page LICENSEE:       NextEra Energy Seabrook, LLC FACILITY:        Seabrook Station, Unit No. 1


FACILITY:      Seabrook Station, Unit No. 1 SUBJECT:     SUMMARY OF TELECONFERENCE HELD ON DECEMBER 6, 2016, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK, LLC,CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION (CAC NO. ME4028)  The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Seabrook, LLC (the applicant), held a teleconference on December 6, 2016, to discuss and clarify the staff's request for additional information (RAI) concerning the Seabrook Station license renewal application. The teleconference was useful in clarifying the intent of the NRC staff's RAI.
==SUBJECT:==


==Enclosure==
==SUMMARY==
1 provides a listing of the participants and Enclosure 2 contains a listing of the RAI discussed with the applicant, including a brief description of the status of the items.
OF TELECONFERENCE HELD ON DECEMBER 6, 2016, BETWEEN THE U.S.
The applicant had an opportunity to comment on this summary.  
NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK, LLC,CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION (CAC NO. ME4028)
 
The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Seabrook, LLC (the applicant), held a teleconference on December 6, 2016, to discuss and clarify the staffs request for additional information (RAI) concerning the Seabrook Station license renewal application. The teleconference was useful in clarifying the intent of the NRC staffs RAI. provides a listing of the participants and Enclosure 2 contains a listing of the RAI discussed with the applicant, including a brief description of the status of the items.
Sincerely Tam Tran, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No.: 50-443  
The applicant had an opportunity to comment on this summary.
Sincerely Tam Tran, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No.: 50-443


==Enclosures:==
==Enclosures:==
1. List of Participants 2. Summary of Teleconference  
: 1. List of Participants
: 2. Summary of Teleconference cc w/encls: See next page DISTRIBUTION: See next page ADAMS Accession No.: ML16341B902                                        *Concurred by e-mail OFFICE PM:RPB1:DLR LA:RPB1:DLR BC:RARB:DLR OGC                                BC(A):RPB1:DLR NAME      TTran*            YEdmonds          DMorey*          JWachutka* R Chazell DATE      12/6/2016        2/13/2017        3/7/2017          1/23/2017      3/ 7/2017 OFFICE PM:RPB1:DLR NAME      TTran 2


cc w/encls:  See next page DISTRIBUTION: See next page ADAMS Accession No.:  ML16341B902                                          *Concurred by e-mail OFFICE PM:RPB1:DLR LA:RPB1:DLR BC:RARB:DLROGC BC(A):RPB1:DLR NAME TTran* YEdmonds DMorey* JWachutka*R Chazell" DATE 12/6/2016 2/13/2017 3/7/2017 1/23/2017    3/ 7/2017 OFFICE PM:RPB1:DLR    NAME TTran 3DATE    3 /7/2017     OFFICIAL RECORD COPY SUBJECT:    SUMMARY OF TELECONFERENCE HELD ON DECEMBER 6, 2016, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION, LICENSE RENEWAL APPLICATION (CAC NO. ME4028)
DATE             3 /7/2017 OFFICIAL RECORD COPY
DISTRIBUTION:  E-MAIL: PUBLIC  RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsOgcMailCenter Resource RidsNrrMailCenter Resource ---------------------------------------------------- Tam.Tran@nrc.gov Lois.James@nrc.gov Russell.Chazell@nrc.gov Dennis.Morey@nrc.gov Brian.Allik@nrc.gov Yvonne.Edmonds@nrc.gov Justin.Poole@nrc.gov David.McIntyre@nrc.gov, OPA Jenny.Weil@nrc.gov, OCA Eugene.Dacus@nrc.gov, OCA  Brian.Harris@nrc.gov, OGC Jeremy.Watchuka@nrc.gov, OGC Mel.Gray@nrc.gov, RI Fred.Bower@nrc.gov, RI Paul.Cataldo@nrc.gov, RI Peter.Meier@nrc.gov, RI Richard.Barkley@nrc.gov, RI Robert.Vadella@nrc.gov, RI Mark.Draxton@nrc.gov, State Liason Dough.Tifft@nrc.gov, State Liason Neil.Sheehan@nrc.gov, RI PAO Diane.Screnci@nrc.gov, RI PAO


ENCLOSURE 1 TELECONFERENCE SEABROOK STATION, UNIT NO. 1 LICENSE RENEWAL APPLICATION  LIST OF PARTICIPANTS DECEMBER 6, 2016  PARTICIPANT AFFILIATIONTam Tran U.S. Nuclear Regulatory Commission (NRC)Brian Allik NRCDennis Morey NRCEdward Carley NextEra Energy Seabrook, LLC (NextEra) Joshua Greene NextEra
==SUBJECT:==


Enclosure 2 SUMMARY OF TELECONFERENCE SEABROOK STATION LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION  DECEMBER 6, 2016 
==SUMMARY==
OF TELECONFERENCE HELD ON DECEMBER 6, 2016, BETWEEN THE U.S.
NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION, LICENSE RENEWAL APPLICATION (CAC NO. ME4028)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsOgcMailCenter Resource RidsNrrMailCenter Resource
----------------------------------------------------
Tam.Tran@nrc.gov Lois.James@nrc.gov Russell.Chazell@nrc.gov Dennis.Morey@nrc.gov Brian.Allik@nrc.gov Yvonne.Edmonds@nrc.gov Justin.Poole@nrc.gov David.McIntyre@nrc.gov, OPA Jenny.Weil@nrc.gov, OCA Eugene.Dacus@nrc.gov, OCA Brian.Harris@nrc.gov, OGC Jeremy.Watchuka@nrc.gov, OGC Mel.Gray@nrc.gov, RI Fred.Bower@nrc.gov, RI Paul.Cataldo@nrc.gov, RI Peter.Meier@nrc.gov, RI Richard.Barkley@nrc.gov, RI Robert.Vadella@nrc.gov, RI Mark.Draxton@nrc.gov, State Liason Dough.Tifft@nrc.gov, State Liason Neil.Sheehan@nrc.gov, RI PAO Diane.Screnci@nrc.gov, RI PAO 3


The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Seabrook, LLC (NextEra or the applicant) held a teleconference on December 6, 2016, to discuss and clarify the following request for additional information (RAI) concerning the Seabrook Station license renewal application (LRA).
TELECONFERENCE SEABROOK STATION, UNIT NO. 1 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS DECEMBER 6, 2016 PARTICIPANT                  AFFILIATION Tam Tran                      U.S. Nuclear Regulatory Commission (NRC)
Brian Allik                  NRC Dennis Morey                  NRC Edward Carley                NextEra Energy Seabrook, LLC (NextEra)
Joshua Greene                NextEra ENCLOSURE 1


Draft RAI B.2.1.22-1a
==SUMMARY==
OF TELECONFERENCE SEABROOK STATION LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION DECEMBER 6, 2016 The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Seabrook, LLC (NextEra or the applicant) held a teleconference on December 6, 2016, to discuss and clarify the following request for additional information (RAI) concerning the Seabrook Station license renewal application (LRA).
Draft RAI B.2.1.22-1a


==Background:==
==Background:==
As amended by letter dated April 5, 2011, LRA Section B.2.1.22 stated that two inspections will be conducted for copper alloy greater than 15 percent zinc components within the scope of the Buried Piping and Tanks Inspection program in each 10-year period starting 10 years prior to the period of extended operation. This statement was deleted by letter dated October7,2016, when the Buried Piping and Tanks Inspection program was replaced in response to the issuance of LR-ISG-2015-01, "Changes to Buried and Underground Piping and Tank Recommendations."
 
As amended by letter dated April 5, 2011, LRA Section B.2.1.22 stated that two inspections will be conducted for copper alloy greater than 15 percent zinc components within the scope of the Buried Piping and Tanks Inspection program in each 10-year period starting 10 years prior to the period of extended operation. This statement was deleted by letter dated October 7, 2016, when the Buried Piping and Tanks Inspection program was replaced in response to the issuance of LR-ISG-2015-01, Changes to Buried and Underground Piping and Tank Recommendations.
As amended by letter dated November 23, 2016, LRA Section B.2.1.22 Table 2 states that the number of inspections for in-scope copper alloy greater than 15 percent zinc piping is dependent on the effectiveness of the cathodic protection system (i.e., Inspection Categories C, E, and F are applicable).
As amended by letter dated November 23, 2016, LRA Section B.2.1.22 Table 2 states that the number of inspections for in-scope copper alloy greater than 15 percent zinc piping is dependent on the effectiveness of the cathodic protection system (i.e., Inspection Categories C, E, and F are applicable).
As amended by letter dated November 23, 2016, the LRA Section B.2.1.22 "detection of aging effects" program element states "[t]here is no cathodic protection for in scope copper alloy  
As amended by letter dated November 23, 2016, the LRA Section B.2.1.22 detection of aging effects program element states [t]here is no cathodic protection for in scope copper alloy
(>15% zinc) material as there are only in-scope components, not piping."
(>15% zinc) material as there are only in-scope components, not piping.
 
Issue:
Issue: It is unclear to the staff if the number of inspections of copper alloy greater than 15 percent zinc components is dependent on the effectiveness of the cathodic protection system (as described in LRA Section B.2.1.22 Table 2), or if the number of inspections is not dependent on the effectiveness of the cathodic protection system (as described in the LRA Section B.2.1.22 "detection of aging effects" program element). The staff notes that the April 5, 2011, letter stated the number of inspections; however, this statement was deleted by the revised Buried Piping and Tanks Inspection program submitted by letters dated October 7, 2016, and November 23, 2016.  
It is unclear to the staff if the number of inspections of copper alloy greater than 15 percent zinc components is dependent on the effectiveness of the cathodic protection system (as described in LRA Section B.2.1.22 Table 2), or if the number of inspections is not dependent on the effectiveness of the cathodic protection system (as described in the LRA Section B.2.1.22 detection of aging effects program element). The staff notes that the April 5, 2011, letter stated the number of inspections; however, this statement was deleted by the revised Buried Piping and Tanks Inspection program submitted by letters dated October 7, 2016, and November 23, 2016.
 
Request:
Request:
State the number and periodicity of planned inspections of copper alloy greater than 15 percent zinc (aluminum bronze) components within the scope of the Buried Piping and Tanks Inspection program and revise the LRA as appropriate.
State the number and periodicity of planned inspections of copper alloy greater than 15 percent zinc (aluminum bronze) components within the scope of the Buried Piping and Tanks Inspection program and revise the LRA as appropriate.
Enclosure 2 Discussion: Based on the discussion with the applicant, the NRC staff indicated that the response to this RAI requires clarification. The applicant agreed to clarify the information as a supplement to the application by January 10, 2017. The applicant clarified that the Buried Piping AMP will be revised to indicate that there is one copper valve that will be inspected twice every 10 years. Because the applicant agreed to supplement, this draft RAI was not issued as final.
Enclosure 2
}}
 
Discussion: Based on the discussion with the applicant, the NRC staff indicated that the response to this RAI requires clarification. The applicant agreed to clarify the information as a supplement to the application by January 10, 2017. The applicant clarified that the Buried Piping AMP will be revised to indicate that there is one copper valve that will be inspected twice every 10 years. Because the applicant agreed to supplement, this draft RAI was not issued as final.
Enclosure 2}}

Latest revision as of 10:38, 30 October 2019

03/07/2016 Summary of Telecon Held on Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook Concerning Request for Additional Information Pertaining to the Seabrook Station License Renewal Application
ML16341B902
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 03/07/2017
From: Tam Tran
License Renewal Projects Branch 1
To: Mccartney E
NextEra Energy Seabrook
Tran T, 415-8517
References
CAC ME4028
Download: ML16341B902 (6)


Text

Tran, Tam From: Tran, Tam Sent: Tuesday, March 07, 2017 3:06 PM To: 'Edward.Carley@nexteraenergy.com' Cc: James, Lois; Chazell, Russell; Morey, Dennis; Allik, Brian; Edmonds, Yvonne; Poole, Justin; McIntyre, David; Weil, Jenny; Dacus, Eugene; Harris, Brian; Ghosh, Anita; Wachutka, Jeremy; Gray, Mel; Bower, Fred; Cataldo, Paul; Meier, Peter; Vadella, Robert; Tifft, Doug; Sheehan, Neil; Screnci, Diane

Subject:

Buried Piping ISG RAI Dec. 2016 Teleconference Attachments: Buried Piping RAI Dec Call - Enclosure 1 and 2.pdf UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 LICENSEE: NextEra Energy Seabrook, LLC FACILITY: Seabrook Station, Unit No. 1

SUBJECT:

SUMMARY

OF TELECONFERENCE HELD ON DECEMBER 6, 2016, BETWEEN THE U.S.

NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK,LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION (CAC NO. ME4028)

The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Seabrook, LLC (the applicant), held a teleconference on December 6, 2016, to discuss and clarify the staffs request for additional information (RAI) concerning the Seabrook Station license renewal application. The teleconference was useful in clarifying the intent of the NRC staffs RAI. provides a listing of the participants and Enclosure 2 contains a listing of the RAI discussed with the applicant, including a brief description of the status of the items.

The applicant had an opportunity to comment on this summary.

Sincerely

/RA/

Tam Tran, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No.: 50-443

Enclosures:

1

1. List of Participants
2. Summary of Teleconference cc w/encls: See next page LICENSEE: NextEra Energy Seabrook, LLC FACILITY: Seabrook Station, Unit No. 1

SUBJECT:

SUMMARY

OF TELECONFERENCE HELD ON DECEMBER 6, 2016, BETWEEN THE U.S.

NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK, LLC,CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION (CAC NO. ME4028)

The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Seabrook, LLC (the applicant), held a teleconference on December 6, 2016, to discuss and clarify the staffs request for additional information (RAI) concerning the Seabrook Station license renewal application. The teleconference was useful in clarifying the intent of the NRC staffs RAI. provides a listing of the participants and Enclosure 2 contains a listing of the RAI discussed with the applicant, including a brief description of the status of the items.

The applicant had an opportunity to comment on this summary.

Sincerely Tam Tran, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No.: 50-443

Enclosures:

1. List of Participants
2. Summary of Teleconference cc w/encls: See next page DISTRIBUTION: See next page ADAMS Accession No.: ML16341B902 *Concurred by e-mail OFFICE PM:RPB1:DLR LA:RPB1:DLR BC:RARB:DLR OGC BC(A):RPB1:DLR NAME TTran* YEdmonds DMorey* JWachutka* R Chazell DATE 12/6/2016 2/13/2017 3/7/2017 1/23/2017 3/ 7/2017 OFFICE PM:RPB1:DLR NAME TTran 2

DATE 3 /7/2017 OFFICIAL RECORD COPY

SUBJECT:

SUMMARY

OF TELECONFERENCE HELD ON DECEMBER 6, 2016, BETWEEN THE U.S.

NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION, LICENSE RENEWAL APPLICATION (CAC NO. ME4028)

DISTRIBUTION:

E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsOgcMailCenter Resource RidsNrrMailCenter Resource


Tam.Tran@nrc.gov Lois.James@nrc.gov Russell.Chazell@nrc.gov Dennis.Morey@nrc.gov Brian.Allik@nrc.gov Yvonne.Edmonds@nrc.gov Justin.Poole@nrc.gov David.McIntyre@nrc.gov, OPA Jenny.Weil@nrc.gov, OCA Eugene.Dacus@nrc.gov, OCA Brian.Harris@nrc.gov, OGC Jeremy.Watchuka@nrc.gov, OGC Mel.Gray@nrc.gov, RI Fred.Bower@nrc.gov, RI Paul.Cataldo@nrc.gov, RI Peter.Meier@nrc.gov, RI Richard.Barkley@nrc.gov, RI Robert.Vadella@nrc.gov, RI Mark.Draxton@nrc.gov, State Liason Dough.Tifft@nrc.gov, State Liason Neil.Sheehan@nrc.gov, RI PAO Diane.Screnci@nrc.gov, RI PAO 3

TELECONFERENCE SEABROOK STATION, UNIT NO. 1 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS DECEMBER 6, 2016 PARTICIPANT AFFILIATION Tam Tran U.S. Nuclear Regulatory Commission (NRC)

Brian Allik NRC Dennis Morey NRC Edward Carley NextEra Energy Seabrook, LLC (NextEra)

Joshua Greene NextEra ENCLOSURE 1

SUMMARY

OF TELECONFERENCE SEABROOK STATION LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION DECEMBER 6, 2016 The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Seabrook, LLC (NextEra or the applicant) held a teleconference on December 6, 2016, to discuss and clarify the following request for additional information (RAI) concerning the Seabrook Station license renewal application (LRA).

Draft RAI B.2.1.22-1a

Background:

As amended by letter dated April 5, 2011, LRA Section B.2.1.22 stated that two inspections will be conducted for copper alloy greater than 15 percent zinc components within the scope of the Buried Piping and Tanks Inspection program in each 10-year period starting 10 years prior to the period of extended operation. This statement was deleted by letter dated October 7, 2016, when the Buried Piping and Tanks Inspection program was replaced in response to the issuance of LR-ISG-2015-01, Changes to Buried and Underground Piping and Tank Recommendations.

As amended by letter dated November 23, 2016, LRA Section B.2.1.22 Table 2 states that the number of inspections for in-scope copper alloy greater than 15 percent zinc piping is dependent on the effectiveness of the cathodic protection system (i.e., Inspection Categories C, E, and F are applicable).

As amended by letter dated November 23, 2016, the LRA Section B.2.1.22 detection of aging effects program element states [t]here is no cathodic protection for in scope copper alloy

(>15% zinc) material as there are only in-scope components, not piping.

Issue:

It is unclear to the staff if the number of inspections of copper alloy greater than 15 percent zinc components is dependent on the effectiveness of the cathodic protection system (as described in LRA Section B.2.1.22 Table 2), or if the number of inspections is not dependent on the effectiveness of the cathodic protection system (as described in the LRA Section B.2.1.22 detection of aging effects program element). The staff notes that the April 5, 2011, letter stated the number of inspections; however, this statement was deleted by the revised Buried Piping and Tanks Inspection program submitted by letters dated October 7, 2016, and November 23, 2016.

Request:

State the number and periodicity of planned inspections of copper alloy greater than 15 percent zinc (aluminum bronze) components within the scope of the Buried Piping and Tanks Inspection program and revise the LRA as appropriate.

Enclosure 2

Discussion: Based on the discussion with the applicant, the NRC staff indicated that the response to this RAI requires clarification. The applicant agreed to clarify the information as a supplement to the application by January 10, 2017. The applicant clarified that the Buried Piping AMP will be revised to indicate that there is one copper valve that will be inspected twice every 10 years. Because the applicant agreed to supplement, this draft RAI was not issued as final.

Enclosure 2