Letter Sequence Other |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement
|
MONTHYEARML1006401882010-03-0505 March 2010 Charter for the Groundwater Contamination Task Force Project stage: Request SBK-L-10077, Application for Renewed Operating License2010-05-25025 May 2010 Application for Renewed Operating License Project stage: Request ML1016203312010-06-0101 June 2010 Drawing LR-001 Through Drawing PID-1-CO-LR20423, Rev. 14 Project stage: Request ML1016203332010-06-0101 June 2010 Drawing PID-1-CO-LR20426, Rev. 30, Through Drawing PID-1-DW-LR20600, Rev. 11 Project stage: Request SBK-L-10095, Drawing PID-1-MAH-LR20497, Rev. 9, Through Drawing PID-1-SF-LR204822010-06-0101 June 2010 Drawing PID-1-MAH-LR20497, Rev. 9, Through Drawing PID-1-SF-LR20482 Project stage: Request ML1016203342010-06-0101 June 2010 Drawing PID-1-DW-LR20601, Rev. 1, Through Drawing PID-1-MAH-LR20496, Rev. 12 Project stage: Request ML1016203292010-06-0101 June 2010 Drawing PID-1-SF-LR20483, Rev. 15, Through Drawing PID-1-WT-LR20041, Rev. 7 Project stage: Request ML1016803692010-06-17017 June 2010 Commission Memorandum and Order (CLI-10-14) Project stage: Request ML1022205712010-08-10010 August 2010 License Renewal Process Overview and Scoping Public Meeting Slides Project stage: Meeting ML1024200372010-08-19019 August 2010 Comment (1) of Maggie Hassan on Behalf of Constituents Different Opinion on the Relicensing of Seabrook Nuclear Power Plant Project stage: Request ML1025202072010-08-19019 August 2010 Transcript for Evening Public Scoping Meeting ISO Seabrook LRA SEIS Project stage: Request ML1025201832010-08-19019 August 2010 Transcript for Afternoon Public Scoping Meeting ISO Seabrook LRA SEIS, August 19, 2010. Pp 1-88 Project stage: Request ML1025002712010-08-23023 August 2010 Comment (2) of William R. Harris, on Behalf of Self, on Nextera Energy Seabrook, LLC Application for Renewal of License for Seabrook Project stage: Request ML1024200432010-08-25025 August 2010 Comment (3) of William Harris, Additional Reference Document for Seabrook Relicensing Environmental Review - Threat Assessment of Emp for Critical Infrastructure Project stage: Request ML1024505252010-09-0101 September 2010 Comment (4) of Geordie Vining on Behalf of Himself Opposing Relicensing Seabrook Plant for the Years 2030-2050 Project stage: Request ML1026504862010-09-20020 September 2010 Comment (6) of Joseph W. Fahey on Behalf of Amesbury on Environmental Impact & Mitigation Scoping for Relicensing of the Seabrook Nuclear Plant Project stage: Request ML1026403712010-09-20020 September 2010 Comment (6) of Joyce Kemp, Opposing NRC-2010-0206-0002, Environmental Impact Statements; Availability, Etc.: Nextera Energy Seabrook; Seabrook Station (Unit 1) Project stage: Request ML1026603312010-09-20020 September 2010 Comment (7) of Andrew R. Port on Behalf of City of Newburyport Office of Planning & Development on Environmental Scoping Review Regarding Application for an Operating License Extension for Seabrook, Unit 1 from Year 2030 to Year 2050 Project stage: Request ML1025202222010-09-20020 September 2010 Summary of Public License Renewal Overview and Environmental Scoping Meeting Related to the Review of the Seabrook Station License Renewal Application (TAC No. ME3959 and ME4028) Project stage: Meeting ML1028612172010-10-29029 October 2010 Request for Additional Information for the Review of the Seabrook Station License Renewal Application Environmental Review Project stage: RAI ML1030808802010-11-0404 November 2010 Letter from Nhdes to NextEra Energy Seabrook Czma Compliance for the Seabrook LRA Project stage: Request ML1030700562010-11-0808 November 2010 Environmental Project Manager Change for the License Renewal of Seabrook Station, Unit 1 Project stage: Other ML1029502712010-11-10010 November 2010 10/05-07/2010-Summary of Site Audit Related to the Review of the License Renewal Application for Seabrook Station, Unit 1 Project stage: Approval ML1030902152010-11-16016 November 2010 Request for Additional Information for the Review of the Seabrook Station License Renewal Application-SAMA Review Project stage: RAI ML1033701692010-11-23023 November 2010 Attachment 2, Vol. 2, to SBK-L-10185, Seabrook Station Response to Request for Additional Information NextEra Energy Seabrook License Renewal Environmental Report, References Requested for Docketing at the Seabrook Station Environmental Sit Project stage: Response to RAI ML1033603262010-11-23023 November 2010 Attachment 2, Vol. 6, to SBK-L-10185, Seabrook Station Response to Request for Additional Information NextEra Energy Seabrook License Renewal Environmental Report, References Requested for Docketing at the Seabrook Station Environmental Sit Project stage: Response to RAI SBK-L-10185, Attachment 1 to SBK-L-10185, Seabrook Station Response to Request for Additional Information NextEra Energy Seabrook License Renewal Environmental Report.2010-11-23023 November 2010 Attachment 1 to SBK-L-10185, Seabrook Station Response to Request for Additional Information NextEra Energy Seabrook License Renewal Environmental Report. Project stage: Response to RAI SBK-L-10190, Response to Request for Additional Information, Submittal of Cultural Resource Plan in Accordance with 36 CFR 800.11 (C)2010-11-23023 November 2010 Response to Request for Additional Information, Submittal of Cultural Resource Plan in Accordance with 36 CFR 800.11 (C) Project stage: Response to RAI ML1033506392010-11-23023 November 2010 Seabrook Station - Response to Request for Additional Information - NextEra Energy Seabrook License Renewal Environmental Report Project stage: Response to RAI ML1101003122010-11-23023 November 2010 Attachment 2, Vol. 1, to SBK-L-10185, Seabrook Station Response to Request for Additional Information NextEra Energy Seabrook License Renewal Environmental Report, References Requested for Docketing at the Seabrook Station Environmental Sit Project stage: Response to RAI ML1101003112010-11-23023 November 2010 Attachment 2, Vol. 1, to SBK-L-10185, Seabrook Station Response to Request for Additional Information NextEra Energy Seabrook License Renewal Environmental Report, References Requested for Docketing at the Seabrook Station Environmental Sit Project stage: Response to RAI ML1033701672010-11-23023 November 2010 Attachment 3 to SBK-L-10185 -Seabrook Station Response to Request for Additional Information, NextEra Energy Seabrook License Renewal Environmental Report Project stage: Response to RAI ML1033700922010-11-23023 November 2010 Attachment 2, Vol. 3, to SBK-L-10185, Seabrook Station Response to Request for Additional Information NextEra Energy Seabrook License Renewal Environmental Report, References Requested for Docketing at the Seabrook Station Environmental Sit Project stage: Response to RAI ML1033603112010-11-23023 November 2010 Attachment 2, Vol. 2, to SBK-L-10185, Seabrook Station Response to Request for Additional Information NextEra Energy Seabrook License Renewal Environmental Report, References Requested for Docketing at the Seabrook Station Environmental Sit Project stage: Response to RAI ML1033603062010-11-23023 November 2010 Attachment 2, Vol. 4, to SBK-L-10185, Seabrook Station Response to Request for Additional Information NextEra Energy Seabrook License Renewal Environmental Report, References Requested for Docketing at the Seabrook Station Environmental Sit Project stage: Response to RAI ML1033603002010-11-23023 November 2010 Attachment 2, Vol. 7, to SBK-L-10185, Seabrook Station Response to Request for Additional Information NextEra Energy Seabrook License Renewal Environmental Report, References Requested for Docketing at the Seabrook Station Environmental Sit Project stage: Response to RAI ML1033602982010-11-23023 November 2010 Attachment 2, Vol. 5, to SBK-L-10185, Seabrook Station Response to Request for Additional Information NextEra Energy Seabrook License Renewal Environmental Report, References Requested for Docketing at the Seabrook Station Environmental Sit Project stage: Response to RAI ML1029806932010-12-21021 December 2010 Summary of Telephone Conference Call Held on 10/21/10 Btw the USNRC and NextEra Energy Seabrook, LLC, Concerning the Request for Additional Information Pertaining to the Seabrook Station License Renewal Application Project stage: RAI ML1033602122010-12-31031 December 2010 NUREG-1437 Supplement 38 Vol 2, (3:3) Appendix A-761 - End Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Indian Point Nuclear Generating Unit Nos. 2 and 3 Public Comments Project stage: Other ML1033602092010-12-31031 December 2010 NUREG-1437 Supplement 38 Vol 2, (2:3) Appendix A-454 - A-760 Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Indian Point Nuclear Generating Unit Nos. 2 and 3 Public Comments Project stage: Other ML1033504382010-12-31031 December 2010 NUREG-1437 Supplement 38 Vol 2, (1:3) Cover - Appendix A-453 Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Indian Point Nuclear Generating Unit Nos. 2 and 3 Public Comments Project stage: Acceptance Review ML1033504422010-12-31031 December 2010 NUREG-1437 Supplement 38 Vol 3 Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Indian Point Nuclear Generating Unit Nos. 2 and 3, Public Comments Continued, Appendices Project stage: Acceptance Review ML1035704012011-01-0303 January 2011 12/21/2010-Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Nextera Energy Seabrook, LLC, Concerning the RAI Pertaining to the Seabrook Station, License Renewal Application Project stage: RAI SBK-L-11001, Response to Request for Additional Information, NextEra Energy License Renewal Application2011-01-13013 January 2011 Response to Request for Additional Information, NextEra Energy License Renewal Application Project stage: Response to RAI SBK-L-11031, Environmental Permit Renewals2011-02-18018 February 2011 Environmental Permit Renewals Project stage: Request ML1104901652011-02-28028 February 2011 02/15/2011 Summary of Telephone Conference Call with the USNRC and NextEra Energy Seabrook, LLC, to Clarify the Responses to the RAIs Pertaining to the SAMA Review of the Seabrook Station License Renewal Application Project stage: RAI ML1105603622011-03-0101 March 2011 2/3/11 Summary of Telephone Conference Calls Held Between the USNRC and Nextera Energy Seabrook, LLC, to Clarify Information Pertaining to the Review of the Seabrook Station License Renewal Application Project stage: Approval ML1101001132011-03-0101 March 2011 Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the Application by Nextera Energy Seabrook, LLC for Renewal of the Operating License for Seabrook Station Project stage: Approval ML1105906382011-03-0404 March 2011 Schedule Revision and Request for Additional Information for the Review of the Seabrook Station License Renewal Application Environmental Review Project stage: RAI SBK-L-11044, Response to Request for Additional Information Regarding License Renewal Environmental Report2011-03-16016 March 2011 Response to Request for Additional Information Regarding License Renewal Environmental Report Project stage: Response to RAI 2010-08-10
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML23187A4432023-07-11011 July 2023 6/27/2023, Annual Assessment Meeting for Seabrook Station - Meeting Summary ML23086B9962023-04-0404 April 2023 Summary of March 7, 2023, Meeting with Nextera Energy Seabrook, LLC Regarding Planned Submittal of License Amendment Request to Revise Emergency Action Level Due to Modification to Containment Fire Detection Equipment ML23088A1522023-03-29029 March 2023 Summary of Meeting Between Nrc/Region I and C-10 - Questions Regarding Seabrook 4Q2022 Inspection Report ML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22146A3422022-06-13013 June 2022 February 23, Summary of Meetings with Nextera Energy Seabrook, LLC Regarding Planned Submittal of License Amendment Request to Update Pressure-Temperature Limits Curves Period of Applicability ML22153A1672022-06-0202 June 2022 Annual Assessment Meeting for Seabrook Station - Meeting Summary ML21336A4072021-12-0707 December 2021 Summary of Conference Call Regarding the Fall 2021 Steam Generator Tube Inspections ML21168A1522021-06-22022 June 2021 Annual Assessment Meeting Summary ML20174A2682020-06-22022 June 2020 June 3, 2020, Seabrook Annual Assessment Summary ML19073A0172019-03-21021 March 2019 Summary of Meeting with Nextera Energy Seabrook, LLC, on Proposed Relief Requests for the Containment Spray System for the Seabrook Station, Unit No. 1 ML19046A3832019-02-26026 February 2019 Meeting Summary of February 13, 2019, Public Meeting in Hampton, New Hampshire Alkali-Silica Reaction License Amendment Request and License Renewal Application ML18136A9052018-05-31031 May 2018 Summary of April 25, 2017, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of Exemption Requests to Support Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML18135A2462018-05-31031 May 2018 Summary of April 24, 2018, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of License Amendment Request to Adopt Standard Technical Specification 3.0.6 ML18142A2932018-05-21021 May 2018 2018 Annual Assessment Meeting Summary ML17340A1862017-12-14014 December 2017 Summary of November 17, 2017, Meeting with NextEra Energy Regarding License Amendment Request on Alkali Silica Reaction - Requests for Additional Information (CAC No. MF8260; EPID L-2016-LLA-0007) ML17310B2062017-11-20020 November 2017 Summary of September 20, 2017, Meeting with Florida Power & Light Company and NextEra Energy Regarding Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML17278A7482017-10-13013 October 2017 Summary of August 24, 2017, Meeting with NextEra Energy Regarding License Amendment Request on Alkali Silica Reaction (CAC No. MF8260; EPID L-2016-LLA-0007) ML17216A1732017-09-0707 September 2017 Notice of Meeting with Florida Power & Light Company and NextEra Energy to Discuss Closing Out Generic Safety Issue-191 and Generic Letter 2004-02 ML17172A1322017-06-20020 June 2017 Summary of Annual Assessment Meeting for Seabrook Station, Unit 1, Held on 6/7/2017 ML17137A0292017-06-0505 June 2017 Summary of Meeting Held on May 9, 2017, Between the USNRC Staff and NextEra Representatives to Discuss the Seabrook License Renewal Application (CAC No. ME4028) ML16341B9022017-03-0707 March 2017 03/07/2016 Summary of Telecon Held on Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook Concerning Request for Additional Information Pertaining to the Seabrook Station License Renewal Application ML16342C4672017-03-0101 March 2017 12/01/2016 Summary of Teleconference Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook Concerning Requests for Additional Information Pertaining to the Seabrook Station License Renewal Application ML16204A2612016-07-29029 July 2016 June 15, 2016 Summary of Pre-Submittal Meeting with NextEra Energy Regarding Proposed License Amendment on Alkali Silica Reaction for the Seabrook Station, Unit No. 1 ML16190A1812016-07-0808 July 2016 Summary of Public Annual Assessment Meeting ML16168A4122016-06-15015 June 2016 Slides for Public Meeting with NextEra Energy Regarding Seabrook Station ASR License Amendment ML16146A1762016-06-0808 June 2016 April 28, 2016, Summary of Public Meeting with NextEra Energy Seabrook, LLC Regarding Aging Management of Alkali-Silica Reaction Pertaining to the License Renewal of Seabrook Station, Unit 1 ML15343A1862016-01-0707 January 2016 License Renewal Call Summary - December 3, 2015 ML15357A3262015-12-23023 December 2015 Memo-Seabrook Conference Call on Dec. 22, 2015-with NextEra Concerning a Request for Additional Information Pertaining to Seabrook Station Operability Determinations for the Alkali-Silica Reaction (ASR)-affected Containment Enclosure Buildi ML15328A1392015-12-0404 December 2015 November 23, 2015, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Nextera Energy Seabrook, LLC, Concerning Requests for Additional Information Pertaining to the Seabrook Station ML15190A0872015-07-0707 July 2015 June 18, 2015, Summary of Meeting - Seabrook Annual Assessment ML14190B0132014-07-0909 July 2014 June 24, 2014, Summary of Annual Assessment Meeting Regarding Seabrook Station ML14035A2362014-01-30030 January 2014 Seabrook, Unit 1 - Summary of Meeting Between the U.S. Nuclear Regulatory Commission and NextEra Regarding the Status of Alkali-Silica Reaction Testing Program ML13352A5112013-12-27027 December 2013 13-12-18 Seabrook Conference Call Re SAMA RAI ML13133A2412013-06-12012 June 2013 5/9/2013 - Summary of Meeting with NextEra Energy Seabrook, LLC on Pre-Submittal of a Fixed Incore Detector License Amendment Request ML13158A1972013-06-0707 June 2013 5/30/2013 Summary of Teleconference Between NRC Staff and NextEra Energy Staff Regarding Decommissioning Funding Status Report for Seabrook ML13099A2582013-04-0909 April 2013 3/27/2013: Seabrook - Summary of Annual Assessment Meeting with NextEra Energy ML13066A4882013-03-21021 March 2013 Summary of Meeting Held on February 21, 2013, Between the NRC and NextEra Energy Seabrook, LLS Regarding License Renewal Application, Seabrook Station ML13004A1782013-01-0404 January 2013 December 11, 2012 Summary of Meeting Regarding Status of Degraded Concrete on Seabrook Station, Unit 1, ML12278A2502012-11-0101 November 2012 Summary of Telephone Conference Call Held Between NRC and NextEra Seabrook, Concerning the RAIs Pertaining to the Seabrook Station, LRA ML12264A6482012-10-16016 October 2012 8/31/2012, Telecon Summary Between NRC and NextEra Seabrook ML12242A5612012-09-18018 September 2012 Summary of Telephone Conference Call Held on August 28, 2012, Between NRC and NextEra Sebrook, LLC, Concerning the Drai Pertaining to the Seabrook, LRA ML12339A2742012-09-13013 September 2012 Concrete Summary 4-12 ML12195A1112012-07-31031 July 2012 Summary of Telephone Conference Call Held on July 3, 2012, Between the NRC and NextEra Energy Seabrook, LLC, Concerning the Draft Request for Additional Information Pertaining to the Seabrook Station, LRA Er ML12165A5952012-06-22022 June 2012 Summary of Telephone Conference Call Held on May 16, 2012, Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook, LLC, Concerning the Response to Request for Additional Information Pertaining to the Seabrook Station LRA ML12164A9012012-06-22022 June 2012 Summary of Telephone Conference Call Held on 5/24/12, Between the NRC and NextEra Energy Seabrook, LLC Concerning the Drai Pertaining to the Seabrook Station LRA ML12164A7562012-06-22022 June 2012 Summary of Telephone Conference Call Between NRC and NextEra Seabrook ML12165A7422012-06-21021 June 2012 Summary of Telephone Conference Call Held on April 10, 2012, Between NRC and Energy Seabrook, LLC, Concerning the Response to Request for Additional Information Pertaining to the Seabrook Station LRA ML12142A0422012-05-21021 May 2012 Summary of Public Meeting to Discuss the Nrc'S Annual Assessment of Nextera'S Safety Performance at Seabrook in 2011 ML12054A7662012-03-26026 March 2012 022312, Telecon Summary Between NRC and NextEra Seabrook, Discussing RAIs Response ML12066A1392012-03-20020 March 2012 Summary of Telephone Conference Call Held on March 1, 2012 Between the NRC and NextEra Energy Seabrook Llc., Concerning the Drai Pertaining to the Seabrook Station, LRA Environmental Review 2023-07-11
[Table view] |
Text
,c.'-~"'"REG(//..,;_,. UNITED STATES
~
/¥ _ '*\
-~ "
NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001
< 0 t;; *;:
'%-~
~r,>
+0 i December 27, 2013 LICENSEE NextEra Energy Seabrook, LLC FACILITY Seabrook Station, Unit 1 SUBJECT
SUMMARY
OF CONFERENCE CALL HELD ON DECEMBER 18, 2013, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION- SEVERE ACCIDENT MITIGATION ALTERNATIVE REVIEW (TAC NO. ME3959)
The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Seabrook, LLC. held a telephone conference call on December 18, 2013, to discuss the request for additional information (RAI), pertaining to the severe accident mitigation alternatives review for the Seabrook Station license renewal application. The telephone conference call was useful in clarifying the RAis.
Enclosure 1 provides a listing of the participants and Enclosure 2 contains a summary of the discussion.
The applicant had an opportunity to comment on this summary.
.<~r**~ '*~ ' '~I, ', ,, '"..
' _)
Lois M. James, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosures:
- 1. List of Participants 2 Discussion Summary cc w/encls: Listserv
December 27, 2013 LICENSEE: NextEra Energy Seabrook, LLC FACILITY: Seabrook Station, Unit 1 SUBJECT
SUMMARY
OF CONFERENCE CALL HELD ON DECEMBER 18, 2013, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION- SEVERE ACCIDENT MITIGATION ALTERNATIVE REVIEW (TAC NO. ME3959)
The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Seabrook, LLC, held a telephone conference call on December 18, 2013, to discuss the request for additional information (RAI), pertaining to the severe accident mitigation alternatives review for the Seabrook Station license renewal application. The telephone conference call was useful in clarifying the RAis. provides a listing of the participants and Enclosure 2 contains a summary of the discussion.
The applicant had an opportunity to comment on this summary.
IRA/
Lois M. James, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosures:
1 List of Participants
- 2. Discussion Summary cc w/encls: Listserv DISTRIBUTION See following pages ADAMS A CCeSSIO . n No ML13352A511 *concurred via email OFFICE LA:RPB2:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR BWittick NAME LJames LJames IKing ItMMarshatt for)
DATE 12/20/2013 12/24/13 12/27/13 12/27/13 OFFICIAL RECORD COPY
SUBJECT:
SUMMARY
OF CONFERENCE CALL HELD ON DECEMBER 18, 2013, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION- SEVERE ACCIDENT MITIGATION ALTERNATIVE REVIEW (TAG NO ME3959)
DISTRIBUTION:
HARD COPY:
DLR/RPB2 r/f E-MAIL:
PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRerb Resource RidsNrrDirRarb Resource RidsNrrDirRasb Resource RidsOgcMaiiCenter Listserve Lois.James@nrc.gov Richard.Piasse@nrc.gov Brian.Wittick@nrc.gov Yoira.Diaz-Sanabria@nrc.gov Richard. Mclntyre@nrc.gov John.Lamb@nrc.gov Edward.Carley@nexteraenergy.com
TELEPHONE CONFERENCE CALL SEABROOK STATION LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS December 18, 2013 PARTICIPANTS AFFILIATIONS Lois M. James Nuclear Regulatory Commission (NRC)
John Parillo NRC Joe Jones Sandia National Laboratory Edward Carley NextEra Energy Seabrook, LLC (NextEra)
Richard Turcotte NextEra ENCLOSURE 1
SUMMARY
OF TELEPHONE CONFERENCE CALL ON REQUEST FOR ADDITIONAL INFORMATION SEVERE ACCIDENT MITIGATION ALTERNATIVES PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION December 18, 2013 The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Seabrook, LLC (NextEra or the applicant) held a telephone conference call on December 18, 2013, to discuss the request for additional information (RAis) regarding the severe accident mitigation alternatives (SAMAs) for Seabrook Station license renewal application (LRA). The telephone conference call was useful in clarifying the RAis.
Discussion The staff and the applicant discussed the current draft RAis sent to the applicant on December 16, 2013 (Agency Document Access and Management System (ADAMS) Accession No ML13351A517) concerning the LRA and the SAMA review. The applicant requested clarification regarding the 2nd part of the RAI:
Dose Conversion Coefficient File: NextEra implemented what appears to be a custom dose conversion file in the SAMA analysis. The exact version of the dose conversion factor file used by NextEra in the SAMA analysis is needed to support our evaluation of conservatisms.
The discussion focused on what information was available in the dose conversion coefficient file and why the NRC thought the Seabrook file had been customized. After the discussion, the applicant said that it understood the staff's request for the dose conversion coefficient file in the RAI.
ENCLOSURE 2