MONTHYEARIR 05000443/20240032024-10-30030 October 2024 Integrated Inspection Report 05000443/2024003 L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums ML24303A0352024-10-29029 October 2024 Operator Licensing Examination Approval IR 05000443/20244022024-10-17017 October 2024 Material Control and Accounting Program Inspection Report 05000443/2024402 (Cover Letter Only) L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-159, Core Operating Limits Report for Reload Cycle 242024-10-15015 October 2024 Core Operating Limits Report for Reload Cycle 24 ML24254A2552024-09-25025 September 2024 Alternative Request No. 4A-01 for the Fourth 10-Year Inservice Inspection Interval L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24239A5382024-09-20020 September 2024 Issuance of Amendment No. 175 One-Time Allowable Outage Time Extension to the Technical Specification 3.8.1.1, A.C. Sources – Operating, Limiting Condition for Operation L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000443/20240052024-08-29029 August 2024 Updated Inspection Plan for Seabrook Station (Report 05000443/2024005) ML24232A1142024-08-21021 August 2024 Correction to Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves L-2024-141, Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit2024-08-15015 August 2024 Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Be L-2024-137, Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent .2024-08-12012 August 2024 Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent . IR 05000443/20240022024-08-0606 August 2024 Integrated Inspection Report 05000443/2024002 and Independent Spent Fuel Storage Installation Inspection Report 07200063/2024001 ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-127, Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent2024-08-0505 August 2024 Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite.2024-07-16016 July 2024 Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite. ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-098, Preparation and Scheduling of Operator Licensing Examinations2024-06-12012 June 2024 Preparation and Scheduling of Operator Licensing Examinations L-2024-084, Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-05-30030 May 2024 Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld IR 05000443/20240102024-05-29029 May 2024 Biennial Problem Identification and Resolution Inspection Report 05000443/2024010 IR 05000443/20240112024-05-24024 May 2024 Age-Related Degradation Inspection Report 05000443/2024011 IR 05000443/20240012024-05-13013 May 2024 Integrated Inspection Report 05000443/2024001 L-2024-061, NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distribut2024-05-10010 May 2024 NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distributio ML24046A0512024-05-0707 May 2024 Issuance of Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-078, 2023 Annual Radioactive Effluent Release Report2024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report L-2024-077, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report IR 05000443/20245012024-04-22022 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000443/2024501 05000443/LER-2024-001, Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources2024-04-19019 April 2024 Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources SBK-L-24030, 2023 Annual Environmental Operating Report2024-04-12012 April 2024 2023 Annual Environmental Operating Report L-2024-011, And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications L-2024-038, To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0808 March 2024 To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source ML24067A2622024-03-0808 March 2024 Issuance of Amendment No. 173 Revise Technical Specification 3/4.8.1 to Allow Replacement of Reserve Auxiliary Transformer (Emergency Circumstances) L-2024-037, To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0606 March 2024 To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source L-2024-035, Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0505 March 2024 Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source ML24065A2522024-03-0505 March 2024 Notice of Enforcement Discretion for Seabrook Station, Unit No. 1 (EPID: L-2024-033) L-2024-032, Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0404 March 2024 Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source L-2024-033, Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B2024-03-0404 March 2024 Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B IR 05000443/20230062024-02-28028 February 2024 Annual Assessment Letter for Seabrook Station (Report 05000443/2023006) L-2024-019, Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-02-28028 February 2024 Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld L-2024-016, Radiological Emergency Plan (Ssrep), Revision 822024-02-13013 February 2024 Radiological Emergency Plan (Ssrep), Revision 82 IR 05000443/20230042024-02-12012 February 2024 Integrated Inspection Report 05000443/2023004 ML24009A1152024-01-29029 January 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L 2023 LLE-0043 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) 2024-09-25
[Table view] Category:Meeting Summary
MONTHYEARML24177A1482024-06-25025 June 2024 5/29/2024 Summary of Public Meeting to Discuss NRCs Annual Assessment of the Safety Performance at Seabrook Station ML24128A1412024-05-30030 May 2024 Summary of April 30, 2024, Pre-Application Teleconference with Nextera Energy Seabrook, LLC, to Discuss License Amendment Request Related to Offsite AC Source ML24127A2272024-05-30030 May 2024 Summary of April 30, 2024, Pre-Application Teleconference with Nextera Energy Seabrook, LLC, to Discuss License Amendment Request (LAR) Related to Seabrooks Planned Fall 2024 Outage ML24247A1122023-08-26026 August 2023 Summary of Meeting Between Nrc/Region I and C-10 - Questions Regarding Quarterly Inspection Reports for CY2023 ML23187A4432023-07-11011 July 2023 6/27/2023, Annual Assessment Meeting for Seabrook Station - Meeting Summary ML23086B9962023-04-0404 April 2023 Summary of March 7, 2023, Meeting with Nextera Energy Seabrook, LLC Regarding Planned Submittal of License Amendment Request to Revise Emergency Action Level Due to Modification to Containment Fire Detection Equipment ML23088A1522023-03-29029 March 2023 Summary of Meeting Between Nrc/Region I and C-10 - Questions Regarding Seabrook 4Q2022 Inspection Report ML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22146A3422022-06-13013 June 2022 February 23, Summary of Meetings with Nextera Energy Seabrook, LLC Regarding Planned Submittal of License Amendment Request to Update Pressure-Temperature Limits Curves Period of Applicability ML22153A1672022-06-0202 June 2022 Annual Assessment Meeting for Seabrook Station - Meeting Summary ML21336A4072021-12-0707 December 2021 Summary of Conference Call Regarding the Fall 2021 Steam Generator Tube Inspections ML21168A1522021-06-22022 June 2021 Annual Assessment Meeting Summary ML20174A2682020-06-22022 June 2020 June 3, 2020, Seabrook Annual Assessment Summary MN 20-002, June 3, 2020, Seabrook Annual Assessment Summary2020-06-22022 June 2020 June 3, 2020, Seabrook Annual Assessment Summary ML19073A0172019-03-21021 March 2019 Summary of Meeting with Nextera Energy Seabrook, LLC, on Proposed Relief Requests for the Containment Spray System for the Seabrook Station, Unit No. 1 ML19046A3832019-02-26026 February 2019 Meeting Summary of February 13, 2019, Public Meeting in Hampton, New Hampshire Alkali-Silica Reaction License Amendment Request and License Renewal Application ML18136A9052018-05-31031 May 2018 Summary of April 25, 2017, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of Exemption Requests to Support Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML18135A2462018-05-31031 May 2018 Summary of April 24, 2018, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of License Amendment Request to Adopt Standard Technical Specification 3.0.6 ML18142A2932018-05-21021 May 2018 2018 Annual Assessment Meeting Summary ML17340A1862017-12-14014 December 2017 Summary of November 17, 2017, Meeting with NextEra Energy Regarding License Amendment Request on Alkali Silica Reaction - Requests for Additional Information (CAC No. MF8260; EPID L-2016-LLA-0007) ML17310B2062017-11-20020 November 2017 Summary of September 20, 2017, Meeting with Florida Power & Light Company and NextEra Energy Regarding Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML17278A7482017-10-13013 October 2017 Summary of August 24, 2017, Meeting with NextEra Energy Regarding License Amendment Request on Alkali Silica Reaction (CAC No. MF8260; EPID L-2016-LLA-0007) ML17216A1732017-09-0707 September 2017 Notice of Meeting with Florida Power & Light Company and NextEra Energy to Discuss Closing Out Generic Safety Issue-191 and Generic Letter 2004-02 ML17172A1322017-06-20020 June 2017 Summary of Annual Assessment Meeting for Seabrook Station, Unit 1, Held on 6/7/2017 ML17137A0292017-06-0505 June 2017 Summary of Meeting Held on May 9, 2017, Between the USNRC Staff and NextEra Representatives to Discuss the Seabrook License Renewal Application (CAC No. ME4028) ML16341B9022017-03-0707 March 2017 03/07/2016 Summary of Telecon Held on Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook Concerning Request for Additional Information Pertaining to the Seabrook Station License Renewal Application ML16342C4672017-03-0101 March 2017 12/01/2016 Summary of Teleconference Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook Concerning Requests for Additional Information Pertaining to the Seabrook Station License Renewal Application ML16204A2612016-07-29029 July 2016 June 15, 2016 Summary of Pre-Submittal Meeting with NextEra Energy Regarding Proposed License Amendment on Alkali Silica Reaction for the Seabrook Station, Unit No. 1 ML16190A1812016-07-0808 July 2016 Summary of Public Annual Assessment Meeting ML16168A4122016-06-15015 June 2016 Slides for Public Meeting with NextEra Energy Regarding Seabrook Station ASR License Amendment ML16146A1762016-06-0808 June 2016 April 28, 2016, Summary of Public Meeting with NextEra Energy Seabrook, LLC Regarding Aging Management of Alkali-Silica Reaction Pertaining to the License Renewal of Seabrook Station, Unit 1 ML15343A1862016-01-0707 January 2016 License Renewal Call Summary - December 3, 2015 ML15357A3262015-12-23023 December 2015 Memo-Seabrook Conference Call on Dec. 22, 2015-with NextEra Concerning a Request for Additional Information Pertaining to Seabrook Station Operability Determinations for the Alkali-Silica Reaction (ASR)-affected Containment Enclosure Buildi ML15328A1392015-12-0404 December 2015 November 23, 2015, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Nextera Energy Seabrook, LLC, Concerning Requests for Additional Information Pertaining to the Seabrook Station ML15190A0872015-07-0707 July 2015 June 18, 2015, Summary of Meeting - Seabrook Annual Assessment ML14190B0132014-07-0909 July 2014 June 24, 2014, Summary of Annual Assessment Meeting Regarding Seabrook Station ML14035A2362014-01-30030 January 2014 Seabrook, Unit 1 - Summary of Meeting Between the U.S. Nuclear Regulatory Commission and NextEra Regarding the Status of Alkali-Silica Reaction Testing Program ML13352A5112013-12-27027 December 2013 13-12-18 Seabrook Conference Call Re SAMA RAI ML13133A2412013-06-12012 June 2013 5/9/2013 - Summary of Meeting with NextEra Energy Seabrook, LLC on Pre-Submittal of a Fixed Incore Detector License Amendment Request ML13158A1972013-06-0707 June 2013 5/30/2013 Summary of Teleconference Between NRC Staff and NextEra Energy Staff Regarding Decommissioning Funding Status Report for Seabrook ML13099A2582013-04-0909 April 2013 3/27/2013: Seabrook - Summary of Annual Assessment Meeting with NextEra Energy ML13066A4882013-03-21021 March 2013 Summary of Meeting Held on February 21, 2013, Between the NRC and NextEra Energy Seabrook, LLS Regarding License Renewal Application, Seabrook Station ML13004A1782013-01-0404 January 2013 December 11, 2012 Summary of Meeting Regarding Status of Degraded Concrete on Seabrook Station, Unit 1, ML12278A2502012-11-0101 November 2012 Summary of Telephone Conference Call Held Between NRC and NextEra Seabrook, Concerning the RAIs Pertaining to the Seabrook Station, LRA ML12264A6482012-10-16016 October 2012 8/31/2012, Telecon Summary Between NRC and NextEra Seabrook ML12242A5612012-09-18018 September 2012 Summary of Telephone Conference Call Held on August 28, 2012, Between NRC and NextEra Sebrook, LLC, Concerning the Drai Pertaining to the Seabrook, LRA ML12339A2742012-09-13013 September 2012 Concrete Summary 4-12 ML12195A1112012-07-31031 July 2012 Summary of Telephone Conference Call Held on July 3, 2012, Between the NRC and NextEra Energy Seabrook, LLC, Concerning the Draft Request for Additional Information Pertaining to the Seabrook Station, LRA Er ML12165A5952012-06-22022 June 2012 Summary of Telephone Conference Call Held on May 16, 2012, Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook, LLC, Concerning the Response to Request for Additional Information Pertaining to the Seabrook Station LRA ML12164A9012012-06-22022 June 2012 Summary of Telephone Conference Call Held on 5/24/12, Between the NRC and NextEra Energy Seabrook, LLC Concerning the Drai Pertaining to the Seabrook Station LRA 2024-06-25
[Table view] |
Text
April 28, 2016 U.S. Nuclear Regulatory Commission Public Meeting Summary Title: Public Meeting with NextEra Energy Seabrook, LLC Regarding Aging Management of Alkali-Silica Reaction Pertaining to the License Renewal of Seabrook Station, Unit 1.
Meeting Identifier: 20160552 Date of Meeting: Thursday, April 28, 2016 Location: NRC One White Flint North, Room T-8E8 11555 Rockville Pike Rockville, MD Type of Meeting: Category 1 Purpose of the Meeting:
The purpose of this public meeting was for NextEra Energy Seabrook, LLC (NextEra) to discuss their plan to address the U.S. Nuclear Regulatory Commission (NRC) staffs concerns related to the aging management of alkali-silica reaction (ASR) for Seabrook Station Unit 1 (Seabrook) license renewal.
General Details:
The NRC held a meeting on April 28, 2016, from 9:00 a.m. - 12:00 a.m. EST. The meeting began with an introduction of all attendees and a review of meeting ground rules for category 1 meetings. Jane Marshall, Deputy Director of the Division of License Renewal, provided opening remarks emphasizing the importance of achieving a clear technical understanding between NextEra and the NRC staff regarding the ASR issues related to license renewal and the path forward for the aging management program (AMP) for ASR.
NextEra and the staff engaged in a technical discussion regarding NextEras plan to update the ASR Monitoring Program AMP to address the staffs concerns. Following the discussion, the meeting was opened for the public to interact with NRC staff.
Approximately 27 people participated in the meeting. No members of the public attended the meeting in person or identified themselves during the teleconference.
Meeting participants included representatives from NextEra Energy Seabrook, LLC, NextEra corporate, MPR Associates, and the NRC staff.
Summary of Presentation (Meeting):
The NRC project manager for the review of the Seabrook license renewal application provided a brief overview of the generic license renewal review process, the current status of the review for Seabrook, and the open item related to ASR. NextEra then
presented their prepared slides as provided in the attachment (ML16146A200).
Significant technical points of discussion are listed below:
- NextEra stated that all MPR/University of Texas (UT) test programs are complete, and the Owners Acceptance Review of the test reports is in progress.
- NextEra stated that while Seabrook-specific research performed by UT was complete, the AMP would be updated to include provisions to evaluate and incorporate industry-wide research and operating experience as they become available. NextEra also stated that the ASR Monitoring Program AMP will be submitted as complete once UT research results are integrated, and it is not dependent upon ongoing industry research. NextEra agreed to provide a thorough description in the final safety analysis report (FSAR) supplement and the AMP operating experience section of how future industry research would be incorporated into the program, as well as a commitment to incorporate this research.
- NextEra agreed to include within the AMP a plan to provide in-plant corroboration of the methodology in MPR-4153 to correlate large-scale test results with the performance of ASR-affected Seabrook structures, with a description of the methodology used.
- The staff requested clarification on whether misaligned or distorted equipment is the parameter monitored to provide indications that cracking leading to building deformation is occurring. NextEra stated that misaligned or distorted equipment is only used as an indicator, and that the actual parameters monitored in accordance with the AMP are the structures themselves, via measurements from combined cracking indexing, extensometers, etc. NextEra agreed to clearly indicate in the AMP what parameters will be monitored, and the distinction between structural and non-structural components.
- The staff stated that it expects that the methodology derived from the Texas testing for use in the ASR AMP will be validated (corroborated) by data and observations from Seabrook structures. NextEra stated that in addition to the data from Texas testing, other data needed to support the ASR AMP will be presented in the revised ASR AMP with descriptions relative to either (a) microcracking that was described in the 2012 SER with open items or (b) global manifestations (macro-cracking or building deformation) that were identified in 2015, to avoid inconsistencies in technical descriptions.
Public Participation Themes:
There were no comments or questions during the public interaction period. No members of the public attended the meeting in person or participated in the teleconference.
Next Step:
NextEra plans to have a license amendment request pre-application meeting on ASR during the month of June 2016. NextEra plans to submit the revised ASR Monitoring Program AMP in July 2016.
Attachments:
Attachments:
Listserv Lois James U.S. Nuclear Regulatory Commission (NRC)
Yoira Diaz-Sanabria NRC Brian Wittick NRC George Thomas NRC Angela Buford NRC Justin Poole NRC Fred Bower NRC Matt Ring NRC Jenny Weil NRC Larry Nicholson NextEra Energy Seabrook, LLC (Seabrook)
Michael Ossing Seabrook Edward Carley Seabrook Ken Browne Seabrook Brian Brown Seabrook ADAMS Accession No.: ML16146A176 *concurred via email OFFICE LA:RPB:DLR PM:RPB1:DLR RASB:DLR OGC(NLO) BC:RPB1:DLR NAME IBetts TTran/JMitchell BWittick MRing YDiaz-Sanabria DATE 5/ 26 /2016 6/ 1 /2016 6/ 1 /16 6/ 7 /16 6/ 7 /2016 OFFICE RECORD COPY
April 28, 2016 U.S. Nuclear Regulatory Commission Public Meeting Summary Title: Public Meeting with NextEra Energy Seabrook, LLC Regarding Aging Management of Alkali-Silica Reaction Pertaining to the License Renewal of Seabrook Station, Unit 1.
Meeting Identifier: 20160552 Date of Meeting: Thursday, April 28, 2016 Location: NRC One White Flint North, Room T-8E8 11555 Rockville Pike Rockville, MD Type of Meeting: Category 1 Purpose of the Meeting:
The purpose of this public meeting was for NextEra Energy Seabrook, LLC (NextEra) to discuss their plan to address the U.S. Nuclear Regulatory Commission (NRC) staffs concerns related to the aging management of alkali-silica reaction (ASR) for Seabrook Station Unit 1 (Seabrook) license renewal.
General Details:
The NRC held a meeting on April 28, 2016, from 9:00 a.m. - 12:00 a.m. EST. The meeting began with an introduction of all attendees and a review of meeting ground rules for category 1 meetings. Jane Marshall, Deputy Director of the Division of License Renewal, provided opening remarks emphasizing the importance of achieving a clear technical understanding between NextEra and the NRC staff regarding the ASR issues related to license renewal and the path forward for the aging management program (AMP) for ASR.
NextEra and the staff engaged in a technical discussion regarding NextEras plan to update the ASR Monitoring Program AMP to address the staffs concerns. Following the discussion, the meeting was opened for the public to interact with NRC staff.
Approximately 27 people participated in the meeting. No members of the public attended the meeting in person or identified themselves during the teleconference.
Meeting participants included representatives from NextEra Energy Seabrook, LLC, NextEra corporate, MPR Associates, and the NRC staff.
Summary of Presentation (Meeting):
The NRC project manager for the review of the Seabrook license renewal application provided a brief overview of the generic license renewal review process, the current status of the review for Seabrook, and the open item related to ASR. NextEra then
presented their prepared slides as provided in the attachment (ML16146A200).
Significant technical points of discussion are listed below:
- NextEra stated that all MPR/University of Texas (UT) test programs are complete, and the Owners Acceptance Review of the test reports is in progress.
- NextEra stated that while Seabrook-specific research performed by UT was complete, the AMP would be updated to include provisions to evaluate and incorporate industry-wide research and operating experience as they become available. NextEra also stated that the ASR Monitoring Program AMP will be submitted as complete once UT research results are integrated, and it is not dependent upon ongoing industry research. NextEra agreed to provide a thorough description in the final safety analysis report (FSAR) supplement and the AMP operating experience section of how future industry research would be incorporated into the program, as well as a commitment to incorporate this research.
- NextEra agreed to include within the AMP a plan to provide in-plant corroboration of the methodology in MPR-4153 to correlate large-scale test results with the performance of ASR-affected Seabrook structures, with a description of the methodology used.
- The staff requested clarification on whether misaligned or distorted equipment is the parameter monitored to provide indications that cracking leading to building deformation is occurring. NextEra stated that misaligned or distorted equipment is only used as an indicator, and that the actual parameters monitored in accordance with the AMP are the structures themselves, via measurements from combined cracking indexing, extensometers, etc. NextEra agreed to clearly indicate in the AMP what parameters will be monitored, and the distinction between structural and non-structural components.
- The staff stated that it expects that the methodology derived from the Texas testing for use in the ASR AMP will be validated (corroborated) by data and observations from Seabrook structures. NextEra stated that in addition to the data from Texas testing, other data needed to support the ASR AMP will be presented in the revised ASR AMP with descriptions relative to either (a) microcracking that was described in the 2012 SER with open items or (b) global manifestations (macro-cracking or building deformation) that were identified in 2015, to avoid inconsistencies in technical descriptions.
Public Participation Themes:
There were no comments or questions during the public interaction period. No members of the public attended the meeting in person or participated in the teleconference.
Next Step:
NextEra plans to have a license amendment request pre-application meeting on ASR during the month of June 2016. NextEra plans to submit the revised ASR Monitoring Program AMP in July 2016.
Attachments:
Attachments:
Listserv Lois James U.S. Nuclear Regulatory Commission (NRC)
Yoira Diaz-Sanabria NRC Brian Wittick NRC George Thomas NRC Angela Buford NRC Justin Poole NRC Fred Bower NRC Matt Ring NRC Jenny Weil NRC Larry Nicholson NextEra Energy Seabrook, LLC (Seabrook)
Michael Ossing Seabrook Edward Carley Seabrook Ken Browne Seabrook Brian Brown Seabrook ADAMS Accession No.: ML16146A176 *concurred via email OFFICE LA:RPB:DLR PM:RPB1:DLR RASB:DLR OGC(NLO) BC:RPB1:DLR NAME IBetts TTran/JMitchell BWittick MRing YDiaz-Sanabria DATE 5/ 26 /2016 6/ 1 /2016 6/ 1 /16 6/ 7 /16 6/ 7 /2016 OFFICE RECORD COPY