MONTHYEARIR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 IR 05000341/20230052023-08-24024 August 2023 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2023005) IR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 IR 05000341/20230022023-08-0404 August 2023 Integrated Inspection Report 05000341/2023002 IR 05000341/20230012023-06-28028 June 2023 Integrated Inspection Report 05000341/2023001 IR 05000341/20220042023-06-22022 June 2023 Non-Concurrence on Fermi Power Plant, Unit 2 - Integrated Inspection Report 05000341/2022004 IR 05000341/20220102023-06-21021 June 2023 Reissue Fermi Power Plant, Unit 2, Design Basis Assurance Inspection (Teams) Inspection Report 05000341/2022010 IR 05000341/20230112023-04-0606 April 2023 Triennial Fire Protection Inspection Report 05000341/2023011 IR 05000341/20234012023-03-17017 March 2023 Security Baseline Inspection Report 05000341/2023401 IR 05000341/20220062023-03-0101 March 2023 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2022006) ML23039A1552023-02-14014 February 2023 Integrated Inspection Report 05000341/2022004 IR 05000341/20224032023-02-13013 February 2023 Security Baseline Inspection Report 05000341/2022403 ML22313A1032022-11-0909 November 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000341/2022010 IR 05000341/20220032022-11-0808 November 2022 Integrated Inspection Report 05000341/2022003 IR 05000016/20220012022-11-0808 November 2022 NRC Inspection Report No. 05000016/2022001(DRSS) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20224202022-11-0101 November 2022 Security Baseline Inspection Report 05000341/2022420 IR 05000341/20225012022-10-17017 October 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000341/2022501 IR 05000341/20220052022-08-25025 August 2022 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2022005) IR 05000341/20220022022-08-0404 August 2022 Integrated Inspection Report 05000341/2022002 IR 05000341/20220012022-05-0909 May 2022 Integrated Inspection Report 05000341/2022001 IR 05000341/20224012022-03-21021 March 2022 Security Baseline Inspection Report 05000341/2022401 IR 05000341/20210062022-03-0202 March 2022 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2021006) IR 05000341/20210042022-02-0707 February 2022 Integrated Inspection Report 05000341/2021004 IR 05000341/20210132021-12-17017 December 2021 Temporary Instruction 2515/194 Inspection Report 05000341/2021013 IR 05000016/20210012021-12-13013 December 2021 Subject: NRC Inspection Report No. 050-00016/2021-001 (DNMS) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20214022021-12-0909 December 2021 Security Baseline Inspection Report 05000341/2021402 IR 05000341/20210122021-12-0707 December 2021 Biennial Problem Identification and Resolution Inspection Report 05000341/2021012 IR 05000341/20210032021-10-28028 October 2021 Integrated Inspection Report 05000341/2021003 IR 05000341/20215012021-10-21021 October 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000341/2021501 IR 05000341/20214032021-09-0808 September 2021 Material Control and Accounting Program Inspection Report 05000341/2021403 IR 05000341/20210052021-09-0101 September 2021 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2021005) IR 05000341/20210112021-08-25025 August 2021 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000341/2021011 IR 05000341/20210022021-08-0606 August 2021 Integrated Inspection Report 05000341/2021002 IR 05000341/20213012021-07-13013 July 2021 NRC Initial License Examination Report 05000341/2021301 2024-09-30
[Table view] Category:Letter
MONTHYEARIR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 ML24276A2032024-10-0303 October 2024 FEMA Level 1 Finding Transmittal Letter ML24268A0992024-10-0101 October 2024 Power Plant – Audit Summary for License Amendment Request and Regulatory Exemptions for a Risk Informed Approach to Address ECCS Strainer Performance IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000341/LER-2024-002, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 05000341/LER-2024-001, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) ML23283A0222023-10-0909 October 2023 Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval ML23276B4542023-10-0505 October 2023 Cyber Security Inspection Report 05000341/2023402 2024-09-09
[Table view] |
Inspection Report - Fermi - 2012008 |
---|
|
|
Text
rch 16, 2012
SUBJECT:
NRC INSPECTION REPORT 050-00016/12-008(DNMS) ENRICO FERMI UNIT 1
Dear Mr. Plona:
On February 22, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the Enrico Fermi Unit 1 facility. The purpose of the inspection was to determine whether decommissioning activities were conducted safely and in accordance with NRC requirements. At the conclusion of the inspection on February 22, 2012, the NRC inspector discussed the findings with members of your staff.
The inspection consisted of an examination of activities at the facility as they relate to safety and compliance with the Commission's rules and regulations. Areas examined during the inspection included facility management and control and radiological safety. Within these areas, the inspection consisted of a selective examination of procedures and representative records, field observations of activities in progress, and interviews with personnel.
Based on the results of this inspection, the NRC did not identify any violations.
In accordance with Title 10 of the Code of Federal Regulations (CFR) 2.390 of the NRC's
"Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you have concerning this inspection.
Sincerely,
/RA/
Aaron T. McCraw, Acting Chief Materials Control, ISFSI, and Decommissioning Branch Division of Nuclear Materials Safety Docket No. 050-00016 License No. DPR-9
Enclosure:
Inspection Report No. 050-00016/12-008(DNMS)
REGION III==
Docket No.:
050-00016 License No.:
DPR-9 Report No.
- 050-00016/12-008(DNMS) Licensee: Detroit Edison Company Facility: Enrico Fermi Unit 1 Location: 6400 North Dixie Highway Newport, MI 48166 Inspection Dates:
February 22, 2012 Inspector:
Peter J. Lee, Ph.D., CHP Approved by:
Aaron T. McCraw, Acting Chief Materials Control, ISFSI, and Decommissioning Branch Division of Nuclear Materials Safety 2 EXECUTIVE SUMMARY Enrico Fermi Unit 1 NRC Inspection Report 050-00016/12-08(DNMS) This routine decommissioning inspection included reviews of facility management and control, and radiological safety.
Facility Management and Control The inspector concluded that the licensee was ready to return the facility to a passive monitoring Safe Storage (SAFSTOR) status from the active final decontamination phase of SAFSTOR. (Section 1.1)
Radiological Safety
The inspector determined that the licensee had complied with U.S. Nuclear Regulatory Commission (NRC) and the U.S. Department of Transportation (DOT) regulations for shipments of radioactive waste. (Section 2.1)
The inspector verified that the licensee maintained effluent releases below the Title 10 of the Code of Federal Regulations (CFR) Part 20 release limits.
(Section 2.2)
3 Report Details Summary of Plant Activities During the inspection period, the licensee was preparing for returning to passive monitoring SAFSTOR status from the active final decontamination phase of SAFSTOR.
1.0 Facility Management and Control 1.1 Decommissioning Performance and Status Review at Permanently Shut Down Reactors a. Inspection Scope
- Inspection Procedure ((IP) 71801)
The inspector toured the plant to assess the readiness for returning to passive monitoring SAFSTOR status in accordance with licensee's 10 CFR 50.82 notification letter, NRC-11-0040 dated August 16, 2011. This document is publicly available in the NRC's Agencywide Documents Access and Management System (ADAMS) under accession number ML112290006.
b. Observations and Findings The major decommissioning activities had completed in accordance with the licensee's 10 CFR 50.82 notification letter, NRC-11-0040. Remaining major contaminated components during passive monitoring SAFSTOR are the reactor rotating plug, the overflow tank, the auxiliary fuel storage facility, the embedded piping, the buried piping, and the bottoms of the three primary sodium storage tanks. All radiological areas were adequately marked and posted.
c. Conclusions The inspector concluded that the licensee was ready to return the facility to a passive monitoring SAFSTOR status from the active final decontamination phase.
2.0 Radiological Safety 2.1 Transportation of Radioactive Materials (IP 86750) a. Inspection Scope The inspector reviewed radioactive waste shipping documents for selected shipments and conducted interviews of the responsible individual to ensure compliance with NRC and DOT regulations.
b. Observations and Findings A DOT inspector identified that information was missing on the electronic shipping documentation that the Canadian National, or CN Railroad was using for a Fermi 1 radioactive waste shipment E F1-11-021. The missing information included, in part, the physical form of the waste and the total activity of the package being shipped. The 4 railroad was holding the shipment pending correction of the shipping documentation in their system.
Review of the actual shipping paperwork showed that the correct and complete information was included in the package used for shipping from the licensee and was provided to the railroad logistical contractor. The error was introduced off-site when the information wa s entered into the carrier's electronic system. The licensee had completed the review of the revision to the electronic shipping documentation and provided the corrective actions to ensure the information from the licensee's shipping package will be correctly input into the carrier's electronic system for the future shipments.
c. Conclusions The inspector determined that the licensee had complied with NRC and D OT regulations for shipments of radioactive waste.
2.2 Effluent and Environmental Monitoring (IP 84750) a. Inspection Scope
The inspector reviewed the analytical data of gaseous effluent releases for particulates and tritium during the 4 th quarter of 2011 to verify that the licensee met 10 CFR Part 20 effluent release limits. b. Observations and Findings The licensee evaporated the liquid waste to reduce the volume of the waste for the disposal.
Air sampling at the effluence release points did not indicate any positive results from particulates. The tritium concentrations were just above the detection limit , which is well below the regulatory limit.
c. Conclusion The inspector verified that the licensee maintained all effluent releases below the 10 CFR Part 20 effluent release limits.
3.0 Exit Meeting The inspector presented the inspection results to members of the licensee's staff at the conclusion of the inspection on February 22, 2012.
The licensee did not identify any of the documents or processes reviewed by the inspector as proprietary.
ATTACHMENT: SUPPLEMENTAL INFORMATION Attachment SUPPLEMENTAL INFORMATION PARTIAL LIST OF PERSONS CONTACTED
- L. Goodman, Manager, Fermi 1 C. Becker, Project Manager
- S. Stasek, Review Committee Chairman W. Colonnello, Director, Nuclear Support, Fermi 1 D. Randall, License Termination Manager
- B. Muller, Radiation Protection Supervisor D. Breiding, Reactor Project Manager
- J. Thorson, Technical Engineer
- Present at the February 22, 2012, exit meeting.
LIST OF PROCEDURES USED IP 71801: Decommissioning Performance and Status Review at Permanently Shut Down Reactors IP 84750: Effluent and Environmental Monitoring IP 86750: Transportation of Radioactive Materials LIST OF ACRONYMS USED ADAMS Agency Document and Management System CFR Code of Federal Regulations DNMS Division of Nuclear Materials Safety DOT U. S. Department of Transportation IP Inspection Procedure NRC U. S. Nuclear Regulatory Commission SAFSTOR Safe Storage LICENSEE DOCUMENTS REVIEWED Licensee documents reviewed and utilized during the course of this inspection are specifically identified in the "Report Details" above.
ITEMS OPENED, CLOSED, AND DISCUSSED None