Issue date | Title | Topic | |
---|---|---|---|
ML20217M446 | 20 October 1999 | Forwards Rev 8 to Sequoyah Nuclear Plant Physical Security/ Contingency Plan, IAW 10CFR50.54(p).Encl Withheld,Per 10CFR73.21 | |
ML20217M663 | 19 October 1999 | Forwards Insp Rept 50-277/99-07 & 50-278/99-07 on 990920.No Violations Noted | |
ML20217J415 | 15 October 1999 | Forwards Request for Addl Info Re Util 990624 Application for Amend of TSs That Would Revise TS for Weighing of Ice Condenser Ice Baskets | |
05000327/LER-1999-002, Forwards LER 99-002-00 Re Start of Units 1 & 2 EDGs as Result of Cable Being Damaged During Installation of Thermo- Lag for Kaowool Upgrade Project | 15 October 1999 | Forwards LER 99-002-00 Re Start of Units 1 & 2 EDGs as Result of Cable Being Damaged During Installation of Thermo- Lag for Kaowool Upgrade Project | |
ML20217F739 | 14 October 1999 | Requests Addl Info Re Peach Bottom Atomic Power Station Units 2 & 3 Appendix R Exemption Requests | Safe Shutdown Exemption Request |
ML20217K924 | 14 October 1999 | Forwards Amend 234 to License DPR-56 & Se.Amend Consists of Changes to TS in Response to Application & Suppls ,1001 & 06,which Will Support PBAPS Mod P00507,which Will Install Digital Pr Neutron Mining Sys | |
ML20217F684 | 13 October 1999 | Forwards Senior Reactor Operator Initial Exam Repts 50-277/99-302(OL) & 50-278/99-302(OL) Conducted on 990913- 16.All Applicants Passed All Portions of Exam | |
ML20217F302 | 12 October 1999 | Provides Written Confirmation That Thermo-Lag 330-1 Fire Barrier Corrective Actions at PBAPS Have Been Completed.Ltr Also Confirms Completion of Actions Required by Confirmatory Order Modifying Licenses, | Safe Shutdown Fire Barrier |
ML20217E745 | 8 October 1999 | Forwards Response to NRC 990820 RAI Concerning Proposed Alternatives Associated with Third ten-yr Interval ISI Program for Pbaps,Units 2 & 3 | Hydrostatic VT-2 |
ML20217G114 | 7 October 1999 | Responds to from P Salas,Providing Response to NRC Risk Determination Associated with 990630 Flooding Event at Sequoyah Facility.Meeting to Discuss Risk Determination Issues Scheduled for 991021 in Atlanta,Ga | |
ML20217B298 | 6 October 1999 | Discusses Closeout of GL 92-01,rev 1,suppl 1, Reactor Vessel Integrity, for Sequoyah Nuclear Plant,Units 1 & 2. NRC Also Hereby Solicits Any Written Comments That TVA May Have on Current Rvid Data by 991101 | |
ML20217B770 | 6 October 1999 | Submits Corrected Info to NRC 980528 RAI Re Util Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions | |
ML20217B915 | 6 October 1999 | Provides Clarifying Info to Enable NRC to Complete Review of License Change Request ECR 98-01802,re Changes Necessary to Support Installation of Digital Pr Neutron Monitoring & Incorporate long-term T/H Stability Solution Hardware | |
ML20217C414 | 6 October 1999 | Forwards Response to NRC 981109 RAI Re Resolution of USI A-46 for Pbaps.Proprietary Excerpts from GIP-2,Ref 25 Results of BWR Trial Plant Review Section 8 Also Encl. Proprietary Excerpts Withheld | Safe Shutdown Safe Shutdown Earthquake Coatings Operating Basis Earthquake Seismically rugged Earthquake Backfit |
ML20217B318 | 5 October 1999 | Advises That Info Submitted in 990712 Application,Which Contained Attachment Entitled, Addl Info Re Cycle Spec SLMCPR for Peach Bottom 3 Cycle 13,dtd 990609, with Affidavit,Will Be Withheld from Public Disclosure | |
ML20217B405 | 5 October 1999 | Forwards Amend 233 to License DPR-56 & Safety Evaluation. Amend Changes Minimum Critical Power Ratio Safety Limit & Approved Methodologies Referenced in Core Operating Limits Report | |
ML20217B843 | 5 October 1999 | Requests NRC Review & Approval of ASME Code Relief Requests That Were Identified in Plant Second 10-yr ISI Interval for Both Units.Encl 3 Provides Util Procedure for Calculation of ASME Code Coverage for Section XI Nondestructive Exams | Nondestructive Examination Liquid penetrant Dissimilar Metal Weld |
ML20217C710 | 1 October 1999 | Forwards Response to NRC 990910 RAI Re Sequoyah Nuclear Plant,Units 1 & 2 URI 50-327/98-04-02 & 50-328/98-04-02 Re Ice Weight Representative Sample | |
ML20212J598 | 1 October 1999 | Forwards SE Accepting Request for Relief from ASME Boiler & Pressure Vessel Code,Section Xi,Requirements for Certain Inservice Insp at Plnat,Unit 1 | |
05000278/LER-1999-004, Forwards LER 99-004-00 Re Multiple Unplanned ESF Actuations During Planned Mod Activities in Main Cr,Per Requirements 10CFR50.73(a)(2)(iv) | 1 October 1999 | Forwards LER 99-004-00 Re Multiple Unplanned ESF Actuations During Planned Mod Activities in Main Cr,Per Requirements 10CFR50.73(a)(2)(iv) | |
ML20217B889 | 1 October 1999 | Forwards Response to RAI Re Request to Install Digital Power Range Neutron Monitoring Sys & Incorporate long-term,thermal-hydraulic Stability Solution Hardware. Revised TS Table 3.3.2.1-1 Encl | |
IR 05000327/1999004 | 1 October 1999 | Ack Receipt of Providing Comments on Insp Repts 50-327/99-04 & 50-328/99-04.NRC Considered Comments for Apparent Violation Involving 10CFR50.59 Issue | |
ML20217D521 | 30 September 1999 | Informs That Remediating 3D Monicore Sys at Pbaps,Units 2 & 3 & 3D Monicore/Plant Monitoring Sys at Lgs,Unit 2 Has Been Completed Ahead of Schedule | |
ML20216J398 | 29 September 1999 | Submits Comments for Lgs,Unit 1 & Pbaps,Units 2 & 3 Rvid,Rev 2,based on Review as Requested in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity | |
ML20212J685 | 29 September 1999 | Informs of Completion of mid-cycle PPR of Peach Bottom Atomic Power Station on 990913.No Areas Identified in Which Licensee Performance Warranted Addl New Insps Beyond Core Insp Program.Historical Listing of Plant Issues Encl | |
ML20212M108 | 29 September 1999 | Confirms Intent to Meet with Utils on 991025 in Atlanta,Ga to Discuss Pilot Plants,Shearon Harris & Sequoyah Any Observations & Lessons Learned & Recommendations Re Implementation of Pilot Program | Significance Determination Process |
ML20212J575 | 28 September 1999 | Informs of Individual Exam Results for Applicants on Initial Exam Conducted on 990913-16 at Licensee Facility.Without Encls | |
ML20216J019 | 27 September 1999 | Forwards Request for Addl Info Re Util 990301 Request to Support Installation of Digital Power Range Neutron Monitoring Sys & Incorporation of long-term thermal- Hydraulic Stability Solution Hardware,For Plant | |
ML20216J935 | 27 September 1999 | Responds to NRC Re Violations Noted in Insp Repts 50-327/99-04 & 50-328/99-04.Corrective Actions:Risk Determination Evaluation Was Performed & Licensee Concluded That Event Is in Green Regulatory Response Band | Significance Determination Process |
ML20217A945 | 27 September 1999 | Forwards Insp Repts 50-327/99-05 & 50-328/99-05 on 990718- 0828.One Violation Identified & Being Treated as Non-Cited Violation | |
ML20216H645 | 24 September 1999 | Forwards Notice of Withdrawal of Util 990806 Application for Amends to Fols DPR-44 & DPR-56.Proposed Change Would Have Involved Temporary Change to Increase Limit for Average Water Temp of Normal Heat Sink | |
ML20216H675 | 24 September 1999 | Forwards Amends 229 & 232 to Licenses DPR-44 & DPR-56, Respectively & Ser.Amends Will Delete SR Associated Only with Refueling Platform Fuel Grapple Fully Retracted Position Interlock Input,Currently Required by SR 3.9.1.1 | |
ML20212H617 | 24 September 1999 | Forwards Rev 2 to COLR for Pbaps,Unit 2,Reload 12,Cycle 13, IAW TS Section 5.6.5.d.Rept Incorporates Revised Single Loop Operation MAPLHGR Flow Multiplier | |
ML20212H543 | 24 September 1999 | Informs of Decision to Inspect H-3 & H-4 Shroud Welds During Upcoming 3R12 Outage Scheduled to Begin Late Sept 1999 | |
ML20216F881 | 23 September 1999 | Withdraws 990806 Exigent License Change Application.Tech Spec Change to Allow Continued Power Operation with Elevated Cooling Water Temps During Potentially Extreme Weather Conditions No Longer Needed Due to Favorable Weather | |
ML20212F075 | 23 September 1999 | Forwards SER Granting Util 981021 Request for Relief from ASME Code,Section XI Requirements from Certain Inservice Insp at Sequoyah Nuclear Power Plant,Units 1 & 2 Pursuant to 10CFR50.55a(a)(3)(ii) | |
ML20212F450 | 23 September 1999 | Forwards Amends 246 & 237 to Licenses DPR-77 & DPR-79, Respectively & Ser.Amends Approve Request to Revise TSs to Allow Use of Fully Qualified & Tested Spare Inverter in Place of Any of Eight Required Inverters | |
ML20212E866 | 22 September 1999 | Discusses GL 98-01 Y2K Readiness of Computer Sys at NPPs & Supplement 1 & PECO Response for PBAPS Dtd 990630. Understands That at Least One Sys or Component Listed May Have Potential to Cause Transient During Y2K Transition | |
ML20212M191 | 21 September 1999 | Discusses Exercise of Enforcement Discretion Re Apparent Violation Noted in Insp Repts 50-327/99-04 & 50-328/99-04 Associated with Implementation of Procedural Changes Which Resulted in Three Containment Penetrations Being Left Open | Enforcement Discretion |
ML20212F548 | 20 September 1999 | Forwards Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing, for Pbaps,Units 2 & 3 & Lgs,Units 1 & 2 | Generic Fundamentals Examination |
ML20212D119 | 17 September 1999 | Forwards SE Re Proposed Alternatives to ASME Section XI Requirements for Containment Inservice Insp Program at Plant,Units 2 & 3 | |
ML20211Q031 | 10 September 1999 | Requests Written Documentation from TVA to Provide Technical Assistance to Region II Re TS Compliance & Ice Condenser Maint Practices at Plant | |
ML20212A009 | 9 September 1999 | Provides Notification That Licenses SOP-11172 & SOP-11321, for SO Muntzenberger & Rh Wright,Respectively,Are No Longer Necessary as Result of Permanent Reassignment | |
ML20211P296 | 7 September 1999 | Provides Authorization to Administer NRC Approved Initial Written Exams to Listed Applicants on 990913 at Peach Bottom Npp,Delta,Pennsylvania | |
ML20216F544 | 7 September 1999 | Provides Results of Risk Evaluation of 990630,flooding Event at Sequoyah 1 & 2 Reactor Facilities.Event Was Documented in Insp Rept 50-327/99-04 & 50-328/99-04 & Transmitted in Ltr, | Significance Determination Process |
ML20211N568 | 1 September 1999 | Submits Clarification of Two Issues Raised in Insp Repts 50-327/99-04 & 50-328/99-04,dtd 990813,which Was First Insp Rept Issued for Plant Under NRC Power Reactor Oversight Process Pilot Plant Study | Safe Shutdown Temporary Modification Maintenance Rule Program |
ML20211K703 | 30 August 1999 | Forwards Response to NRC 990826 RAI Re License Change Application ECR 99-01255,revising TSs 2.1.1.2 & 5.6.5 | Minimum Critical Power Ratio |
ML20211G588 | 27 August 1999 | Submits Summary of 990820 Management Meeting Re Plant Performance.List of Attendees & Matl Used in Presentation Enclosed | |
ML20211E694 | 26 August 1999 | Forwards Request for Addl Info Re Min Critical Power Ratio. Response Should Be Submitted within 30 Days of Ltr Receipt | Minimum Critical Power Ratio |
ML20211Q449 | 25 August 1999 | Responds to Re Changes to PBAPS Physical Security Plan,Safeguards Contingency Plan & Guard Training & Qualification Plan Identified as Revs 13,11 & 9, Respectively.No NRC Approval Is Required,Per 10CFR50.54(p) |