PNO-IV-88-069, on 880824,util 100 H NSSS Acceptance Test Completed.Upon Completion of Review of Startup Test Results by Plant Operations Review Committee,Util Will Be in Position to Begin Commercial Operation.State of Tx Informed

From kanterella
Jump to navigation Jump to search
PNO-IV-88-069:on 880824,util 100 H NSSS Acceptance Test Completed.Upon Completion of Review of Startup Test Results by Plant Operations Review Committee,Util Will Be in Position to Begin Commercial Operation.State of Tx Informed
ML20151Z933
Person / Time
Site: South Texas STP Nuclear Operating Company icon.png
Issue date: 08/24/1988
From: Holler E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
References
PNO-IV-88-069, PNO-IV-88-69, NUDOCS 8808300301
Download: ML20151Z933 (1)


, _ _ _ _ _ _ _ _ _ _ _ _

, ,a August 24, 1988 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE -- PN0-IV-88-69 This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. The information is as initially received without verification or evaluatior., and is basically all that is known by the Region IV staff on this date.

FACILITY: Houston Lignting A Power Co. Licensee Emergency Classification:

South Texas Project, Unit 1 Notification of Unusual Event Bay City. Texas Alert DN: 50-498 Site Area Emergency General Emergency X Not Applicable

SUBJECT:

Completion of 100-hour NSSS Acceptance Test At approximately 10:40 a.m. (CDT), August 24, 1988, Houston Lighting & Power Company (HL&P) completed the 100-hour Nuclear Steam Supply System (NSSS)

Acceptance Test at the South Texas Project, Unit 1 (STP-1). This completes HL&P's planned startup testing at STP-1. Upon completion of a review of the startup test results by the licensee's Plant Operations Review Comittee, STP-1 will be in a position to begin comercial operation. .

The licensee plans to issue a press release when it declares STP-1 in comercial service. Region IV has responded to media inquiries regarding completion of the NSSS Acceptance Test.

The state of Texas will be informed.

Region IV received notification of this occurrence by telephone from the Region IV Project Engineer at 11:05 (CDT), August 24, 1988.

CONTACT: E. Holler, RIV, FTS 728-8287 DISTRIBUTION:

H. St. MNBB OWF MAIL: DCS (Original IE 34) chairman Zech ROU MU DDT-(Trans only)

Com Roberts OIA OGC Com Carr NL PA FAX: INP0 Com Rogers ES 01 NSAC SECY hMSS RRI CA NRR NRC OC POR SLITP LICENSEE (Reactor Lic.)

OGC-H Gr i ACRS 5520://d889 /n .ro. ...

REGIONS & HQ //

(*Previously concurred) /

RIV:C:PSD 0:DRP R (,

  • EJHoller;df LJCa on R M rtin g Og
8/24/88 8/pi/88 8// /88 -

8808300301 000024

-I 8-069 PNU