Cover Letter - Set 12 of Requests for Additional Information for the Emergency Management Portion of the TRISO-X License Application Review
ML25107A173
Person / Time
Site: Triso-X
Issue date: 05/01/2025
From: Matt Bartlett
NRC/NMSS/DFM/FFLB
To: Wheeler J
Triso-X
Shared Package
ML25107A172 List:
References
EPID L-2022-NEW-0005
Download: ML25107A173 (1)


Text

OFFICIAL USE ONLYSECURITY-RELATED INFORMATION OFFICIAL USE ONLYSECURITY-RELATED INFORMATION UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Jennifer K. Wheeler, Director, Regulatory Affairs TRISO-X, LLC 801 Thompson Avenue Rockville, MD 20852

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION AS SET 12 FOR THE EMERGENCY MANAGEMENT INFORMATION REGARDING THE TRISO-X, LLC LICENSE APPLICATION FOR A FUEL FABRICATION FACILITY (ENTERPRISE PROJECT IDENTIFICATION NUMBER L-2022-NEW-0005)

Dear Jennifer Wheeler:

The U.S. Nuclear Regulatory Commission (NRC) staff has developed subsequent requests for additional information (RAIs) as set 12 to support the review of the TRISO-X, LLC license application. Your application for a new fuel fabrication facility located in Oak Ridge, Tennessee was submitted via letter dated April 5, 2022 (Agencywide Documents Access and Management System [ADAMS] Accession No. ML22101A200) and supplemented by letters dated October 13, 2022 (ML22286A144) and November 4, 2022 (ML22308A251) and revised license application submitted by letters dated December 30, 2024 (ML24365A254) and January 31, 2025 (ML25031A449).

Our review of your license application has identified the need for additional RAIs on the emergency management portion of the review. The additional information requested in the public enclosure to this letter should be provided within 30 days from April 24, 2025, the date the draft RAIs were emailed to you to confirm mutual understanding of the issues.

You confirmed via email on May 1, 2025, that you have no questions about the information requested and an alignment call is not needed. Extending the formal responses beyond the 30 days, the need for supplements, or a second round of RAIs may result in an extension of the proposed review schedule beyond May 2026 (ML23305A193).

The Enclosure transmitted herewith contains Security-Related Information. When separated from the Enclosure, this document is decontrolled.

May 1, 2025

OFFICIAL USE ONLYSECURITY-RELATED INFORMATION J. Wheeler 2

OFFICIAL USE ONLYSECURITY-RELATED INFORMATION In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records component of the NRCs ADAMS. The PDR is open by appointment only. You may submit your request to the PDR via e-mail at PDR.Resource@nrc.gov or call 1-800-397-4209 between 8:00 a.m. and 4:00 p.m. (EST), Monday through Friday, except Federal holidays. The NRCs ADAMS is accessible from the NRC website site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If you have any questions regarding this communication, please contact me at 301-415-7154, or via email to Matthew.Bartlett@nrc.gov.

Sincerely, Matthew Bartlett, Senior Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 07007027

Enclosure:

1. RAI (Non-Public) cc: trisox@listmgr.nrc.gov Signed by Bartlett, Matthew on 05/01/25

ML25107A172(pkg, non-public), ML25107A173(ltr),

ML25107A174(encl, non-public)

OFFICE NMSS/DFM NMSS/DFM NMSS/DFM NMSS/DFM NAME SPoy JGoodridge MBartlett SLav DATE 4/17/2025 4/21/2025 4/22/2025 5/1/2025 OFFICE NMSS/DFM NAME MBartlett DATE 5/1/2025