MONTHYEARML22101A2002022-03-31031 March 2022, 5 April 2022 TRISO-X, LLC Fuel Fabrication Facility License Application Submittal Project stage: Request ML22101A2052022-04-0505 April 2022 TRISO-X, LLC Fuel Fabrication Facility License Application Submittal Project stage: Other ML22166A0412022-08-0909 August 2022 NRC Request for Supplemental Information for the TRISO-X License Application Project stage: Request ML22166A0422022-08-0909 August 2022 Cover Letter - NRC Requests for Supplemental Information (Rsis) for TRISO-X License Application Project stage: Other ML22166A0432022-08-0909 August 2022 Enclosure 1 - Requests for Supplement Information for the TRISO-X License Application Review Project stage: Other ML22266A2692022-09-23023 September 2022 TRISO-X Fuel Fabrication Facility Environmental Report Submittal Project stage: Request ML22286A1442022-10-13013 October 2022 Response to Requests for Supplemental Information for the Acceptance Review of the TRISO-X Fuel Fabrication Facility License Application Submittal Project stage: Request ML22286A1472022-10-13013 October 2022 Responses to Requests for Supplemental Information to Support the TRISO-X License Application Project stage: Supplement ML22308A2512022-11-0404 November 2022 Triso-X, LLC, License Application and ISA Summary Changes Associated with Responses to Requests for Supplemental Information for the Acceptance Review of the TRISO-X Fuel Fabrication Facility License Application Submittal Project stage: Request ML22320A5632022-11-16016 November 2022 Triso-X, LLC - Additional Information Supporting the Response to Rsi Question 8.1 Concerning the Acceptance Review of the TRISO-X Fuel Fabrication Facility License Application Project stage: Other ML22320A1102022-11-18018 November 2022 NRC Acceptance of the TRISO-X, LLC - Application for a Fuel Fabrication Facility Project stage: Acceptance Review ML22348A0162022-12-16016 December 2022 Enclosure 1 - Observations Developed During the Acceptance Review to Support the TRISO-X Application for a Fuel Fabrication Facility (Public) Project stage: Acceptance Review ML22348A0132022-12-16016 December 2022 NRC Observations Developed During the Acceptance Review of the TRISO-X License Application Project stage: Request ML22348A0142022-12-16016 December 2022 Cover Letter - Nuclear Regulatory Commission Observations to Support the TRISO-X License Application for a Fuel Fabrication Facility Project stage: Other ML23104A4192023-04-14014 April 2023 TRISO-X, LLC, Response to Requests for Additional Information on the Environmental Report for the Proposed Fuel Fabrication Facility Project stage: Request ML23127A0132023-05-31031 May 2023 Enclosurai for the TRISO-X Application Project stage: RAI ML23127A0112023-05-31031 May 2023 Triso-X RAIs for License Application Project stage: Request ML23127A0122023-05-31031 May 2023 Request for Additional Information (Set 1) for the Triso-X, LLC License Application for a Fuel Fabrication Facility (Enterprise Project Identification Number L-2022-NEW-0005) Project stage: RAI ML23198A2572023-07-27027 July 2023 NRC Letter Request for Additional Information on Chp 1, 2, EP for the TRISO-X, LLC License Application Project stage: Request ML23198A2592023-07-27027 July 2023 Request for Additional Information for the Triso-X, LLC License Application for a Fuel Fabrication Facility (Enterprise Project Identification Number L-2022-NEW-0005) Project stage: RAI ML23209A8212023-07-28028 July 2023 Response to Request for Additional Information (Set 1) for the TRISO-X, LLC License Application for a Fuel Fabrication Facility Project stage: Response to RAI ML23230B2002023-08-18018 August 2023 Triso-X, LLC, Supplemental Response to Request for Additional Information Question 3-2 (Set 1) for the TRISO-X License Application Project stage: Supplement ML23237B4842023-08-25025 August 2023 Response to Request for Additional Information (Set 2) for the TRISO-X License Application Project stage: Response to RAI ML23230B1912023-08-28028 August 2023 Cover Letter - RAI Set 3 for the ISA Summary (Programmatic) and Security Regarding TRISO-X License Application Project stage: RAI ML23254A3812023-09-29029 September 2023 Letter to Triso-X for the Fourth Set of RAIs That Includes an Enclosure for Geotechnical and an Enclosure for Hydrology Project stage: Request ML23285A3442023-10-12012 October 2023 Response to Request for Additional Information Set 3 (ISA and Security) for the TRISO-X License Application Project stage: Response to RAI ML23265A2622023-10-25025 October 2023 Request for Additional Information Set 5 for the Radiological and Chemical Review Regarding the TRISO-X, LLC License Application for a New Fuel Fabrication Facility (Enterprise Project Identification Number L-2022-NEW-0005 Project stage: RAI ML23312A2482023-11-0808 November 2023 7-5-23 Email Summary of Meeting to Discuss Draft ISA RAIs for Alignment Project stage: Request ML23312A3382023-11-0808 November 2023 Response to Request for Additional Information (Set 4) for the TRISO-X License Application Project stage: Response to RAI ML23320A2052023-11-17017 November 2023 Enclosure 1 - Request for Additional Information for (Programmatic) Structural Review Regarding the TRISO-X License Application Project stage: RAI ML23313A1142023-11-17017 November 2023 Cover Letter - Triso-X License Application Sixth Set of RAIs for Material Control and Accounting, Fire, and Structural Project stage: RAI ML23313A1102023-11-17017 November 2023 Triso-X for the Sixth Set of RAIs Including Material Control & Accounting and Fire Safety Project stage: Request ML23235A2262023-11-20020 November 2023, 27 November 2023 TRISO-X Fff Environmental RAI Part 2 Project stage: Request ML23343A0022023-12-0909 December 2023 Response to Request for Additional Information Set 5 (Chemical Safety and Radiation Protection) for the TRISO-X License Application Project stage: Response to RAI ML23354A2882023-12-20020 December 2023 TRISO-X, LLC, Response to Request for Additional Information Part 2-1 for the TRISO-X Environmental Report and License Application Project stage: Response to RAI ML23353A1832023-12-27027 December 2023 Summary of Meeting on December 4, 2023, with TRISO-X LLC, to Align on TRISO-X Draft Responses to the Requests for Additional Information for the Chemical Safety Analysis Project stage: Draft RAI ML23353A1822023-12-27027 December 2023 Summary of Meeting Held on December 4, 2023, to Discuss the TRISO-X Draft Responses to the Requests for Additional Information Project stage: Request ML23353A1842023-12-27027 December 2023 Enclosure 1 - Participants List for Summary of Meeting Held December 4, 2023, with TRISO-X, LLC to Align on Draft Responses to Requests for Additional Information for Chemical Safety Analysis Project stage: Draft RAI ML23362A0632024-01-16016 January 2024 12-19-23 Summary of Meeting with Triso-X, LLC, to Align on Triso-X Draft Environmental Safety Request for Additional Information Project stage: Request ML23321A0412024-02-26026 February 2024 Request for Additional Information Set for the Environmental Review Regarding the Triso X License Application Project stage: Request ML23321A0512024-02-26026 February 2024 Enclosure - RAIs Set Seven for the Environmental Safety Review Regarding TRISO-X License Application Project stage: RAI ML23321A0422024-02-26026 February 2024 Cover Letter - RAIs Set Seven for the Environmental Safety Review Regarding the TRISO-X License Application Project stage: RAI ML24065A3132024-03-0404 March 2024 Response to Request for Additional Information Part 2-2 for the TRISO-X Environmental Report and License Application Project stage: Response to RAI ML24057A3612024-03-11011 March 2024 Summary of Meeting on 2-12-24 with TRISO-X to Discuss Draft Requests for Additional Information on Environmental Protection Project stage: Request ML24057A3632024-03-11011 March 2024 Memorandum - Summary of Meeting 2-12-24 with TRISO-X to Discuss Draft RAIs on Environmental Protection Project stage: Draft RAI ML24057A3622024-03-11011 March 2024 Enclosure - Participants in Meeting Held 2-12-24 with TRISO-X to Discuss the Draft RAIs on Environmental Protection Project stage: Draft RAI ML23354A1652024-03-25025 March 2024 Cover Letter - Set Eight Containing a Programmatic Request for Additional Information for the Integrated Safety Analysis Review Regarding the TRISO-X License Application Project stage: RAI ML24087A2352024-03-27027 March 2024 Triso-X, LLC, Response to Request for Additional Information Set 7 (Environmental Safety) for the TRISO-X License Application Project stage: Response to RAI ML24085A2702024-04-0202 April 2024 Request TRISO-X, LLC to Provide Supplemental Information to Resolve Programmatic Requests for Additional Information Regarding the Management Measures and Quality Assurance Portion of the License Application Project stage: RAI ML24095A3412024-04-0404 April 2024 Response to Request for Additional Information Part 3 for the TRISO-X Environmental Report Project stage: Request 2023-12-09
[Table View] |
Text
J. Wheeler UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Jennifer K. Wheeler, Director Regulatory Affairs TRISO-X, LLC 801 Thompson Avenue Rockville, MD 20852
SUBJECT:
REQUEST TRISO-X, LLC. TO PROVIDE SUPPLEMENTAL INFORMATION TO RESOLVE PROGRAMMATIC REQUESTS FOR ADDITIONAL INFORMATION REGARDING THE STRUCTURAL PORTION OF THE LICENSE APPLICATION (ENTERPRISE PROJECT IDENTIFICATION NUMBER L-2022-NEW-0005)
Dear Jennifer Wheeler:
The U.S. Nuclear Regulatory Commission (NRC) staff requests TRISO-X, LLC. (TRISO-X) to supplement their responses to the set six structural request for additional information (RAI) issued via letter dated November 17, 2023 (Agencywide Documents Access and Management System [ADAMS] Accession No. ML23313A110). TRISO-X provided their initial responses to the RAIs via letter dated December 15, 2023 (ML23349A208), which resolved one of the RAIs, but the second item entitled, RAI-2 Risk Category remains open. The original license application was submitted via letter dated April 5, 2022 (ML22101A200) and supplemented by letters dated October 13, 2022 (ML22286A144), November 4, 2022 (ML22308A251) and February 29, 2024 (ML24060A239).
The NRC staff held two meetings with TRISO-X on March 1, 2024 (ML24030A847) and April 9, 2024 (ML24102A180) to discuss the additional information needed to resolve the open RAI. The supplemental information should seek to resolve the original RAI and take into consideration the discussions held during the follow-up meetings.
Please provide the supplemental information regarding RAI-2 Risk Category to the NRC staff within 60 days of the date of this letter. In addition, the NRC staff recommends that TRISO-X provide a draft of the supplemental information to the NRC in advance of the formal submittal, and hold calls, as needed, with the NRC staff to confirm resolution of the issues identified in the RAI. The June 2025 projected completion date for the review schedule is in the process of being extended based on receipt of electrical/instrumentation and control information dated February 29, 2024 (ML24060A239); ongoing efforts to resolve the programmatic RAIs; and the TRISO-X notice of plans to revise the license application and integrated safety analysis summary submitted via letter dated January 20, 2024 (ML24020A010). An updated review scheduled will be communicated as soon as practicable.
April 23, 2024
J. Wheeler 2
In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records component of the NRCs ADAMS. The PDR is open by appointment only. You may submit your request to the PDR via email at PDR.Resource@nrc.gov or call 1-800-397-4209 between 8:00 a.m. and 4:00 p.m. (EST), Monday through Friday, except Federal holidays. The NRCs ADAMS is accessible from the NRC website site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If you have any questions regarding this communication, please contact me at 301-415-7154, or via email to Matthew.Bartlett@nrc.gov.
Sincerely, Matthew Bartlett, Senior Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 07007027 cc: trisox@listmgr.nrc.gov Signed by Bartlett, Matthew on 04/23/24
- ML24101A017 OFFICE NMSS/DFM/FFLB NMSS/DFM/FFLB NMSS/DFM/FFLB NAME JRudd SPoy MBartlett DATE 4/10/2024 4/11/2024 4/12/2024 OFFICE NMSS/DFM/FFLB NMSS/DFM/FFLB NMSS/DFM/FFLB NAME JGoodridge SLav MBartlett DATE 4/17/2024 4/22/2024 4/23/2024