ML20247A250
ML20247A250 | |
Person / Time | |
---|---|
Site: | Braidwood |
Issue date: | 07/11/1989 |
From: | Greenman E NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
To: | |
Shared Package | |
ML20247A238 | List: |
References | |
50-457-89-20, NUDOCS 8907210188 | |
Download: ML20247A250 (1) | |
Similar Documents at Braidwood | |
---|---|
Category:NOTICE OF VIOLATION OF A REGULATION
MONTHYEARML20195G3681998-11-17017 November 1998
[Table view]Notice of Violation from Insp on 980909-1019.Violation Noted:As of 980818,licensee Failed to Initiate Measures to Determine Cause or Take Action to Preclude Recurrence of Loose Bolts on Two EDG Lubricating Oil Heat Exchanger Bells ML20195G3031998-11-13013 November 1998 Notice of Violation from Insp on 980915-1022.Violation Noted:On 981022,two Individuals Working Under RWP 984014 Removed Outer Rubber Gloves While Replacing Insulation in Containment ML20196D9201998-11-10010 November 1998 Notice of Violation from Insp on 981013-19.Violation Noted: Licensee Security Staff Discovered That on Three Occasions Between 980826 & 1002,security Officers Were Found Asleep on Post ML20236N0911998-07-0606 July 1998 Notice of Violations from Insp on 980421-0608.Violations Noted:On 980424,licensee Failed to Implement Specific Fire Protection Program Requirements in That Welding Machine Was Left Unattended & Energized in Fuel Handling Bldg ML20248D0821998-05-19019 May 1998 Notice of Violation from Insp on 980310-0420.Violation Noted:On 980303,licensee Failed to Implement Braidwood Administrative Procedure 2321-18T11,Step E.1,for Sf Pool Skimmer Strainer Level Control ML20217F5281998-04-21021 April 1998 Notice of Violation from Insp on 980331-0407.Violation Noted:Licensee Failed to Check That SG Worker Dosimetry Was Present & Correctly Worn ML20216B0611998-04-0808 April 1998 Notice of Violation from Insp on 980127-0309.Violation Noted:On 971010,21,1219 & 980105,licensee Failed to Require Independent Verification of Proper Sys Alignment for safety-related Valves Repositioned in Steps F.1.4 & F.1.7 ML20203D9151998-02-20020 February 1998 Notice of Violation from Insp on 971216-980126.Violation Noted:In Nov 1989,licensee Failed to Initiate Deviation Rept & Take Corrective Measures to Preclude Repetition of Mechanical Failure to All 4 Main Feedwater Check Valves ML20202F2321998-02-11011 February 1998 Notice of Violations from Insp on 971112-21 & 980115. Violations Noted:Licensee Failed to Follow NSWP-A-15 & Bwap 330-10 Requirements to Issue PIF for Tempering Line Snubber Considered Inoperable on 971110 IR 07100104/20120151998-01-0202 January 1998 Notice of Violation from Insp on 971104-1215.Violation Noted:On 971102,inspectors Identified That Licensee Had Failed to Fasten Covers on Incore Neutron Detector Drive Mechanism ML20199A5681997-12-17017 December 1997 Notice of Violation from Insp on 970923-1103.Violation Noted:On 971014,licensee Instrument Technician Made Error When Changing Setpoints on Unit 2 Containment Area Radiation Monitor 2AR11J.Error Resulted in High Radiation Alarm ML20202C9671997-11-26026 November 1997 Notice of Violation from Insp on 970812-0922.Violation Noted:On 970814,licensee Personnel Verified Position of 2B Containment Spray Eductor Drain Valve W/O Removing & Reinstalling Locking Device ML20199G1181997-11-17017 November 1997 Notice of Violation from Insp on 971006-22.Violations Noted: Individual Performing Work on 2CV8149 Valve within Radiologically Posted Area,Failed to Follow Instructions Contained on Posting ML20211Q8481997-10-17017 October 1997 Notice of Violation from Insp on 970714-0815.Violation Noted:Licensee Failed to Assure That Degraded Voltage Relay Testing for Divs 11,12,21 & 22 Was Performed Under Suitable Environ Conditions ML20198R2591997-10-0303 October 1997 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $55,000.Violation Noted:Eccs Subsystem Consisting of Centrifugal Charging Pump Not Operable ML20198K3981997-10-0202 October 1997 Notice of Violation from Insp on 961013-970814.Violation Noted:Licensee Failed to Provide Barriers for Redundant Train of Equipment in Same Fire Zones ML20217C4841997-09-17017 September 1997 Notice of Violation from Insp on 970701-0811.Violation Noted:On 970702,inspectors Observed Unattended & Energized Welding Machine Located Outside 2A Emergency Diesel Generator Room ML20216D4751997-08-26026 August 1997 Notice of Violation from Insp on 970520-0630.Violations Noted:Licensee Had Not Demonstrated That Performance or Condition of Pams Was Being Effectively Controlled Through Performance of Appropriate Preventive Maint ML20149J6991997-07-24024 July 1997 Notice of Violation from Insp on 970618-24.Violation Noted: on Listed Dates,Inspector Identified That Licensee Did Not Provide Reasonable Assurance That Indirect Methods Could Be Correlated W/Action Measurements ML20141E8141997-06-17017 June 1997 Notice of Violation from Insp on 970408-0520.Violation Noted:On 970418,inspectors Identified That Licensee Had Taken Open Unit 2 Motor Driven Feedwater Pump Discharge Isolation Valve out-of-svc for Maint W/O Written SE ML20141J9251997-05-19019 May 1997 Notice of Violation from Insp on 970417-30.Violation Noted: on 970417,inspector Identified That Entrance to High Integrity Container Storage Area of Radwaste Bldg,Area Accessible to Personnel Posted Locked,Not Locked ML20141D7621997-05-0909 May 1997 Notice of Violation from Insp on 970222-0407.Violations noted:1BwFR-S.1 Had Not Been Maintained in That,Operators Were Directed to Start Chemical & Volume Control Sys Positive Displacement Pumps ML20137T1171997-04-0808 April 1997 Notice of Violation from Insp on 970303-07.Violation Noted:Review of Emergency Preparedness Program Did Not Include Evaluation of Adequacy of Interface W/State of Il ML20137J6041997-03-31031 March 1997 Notice of Violation from Insp on 961003-970312.Violation Noted:Applicable Portions of Numerous Plant Hot Work Permits Were Not Filled Out as Required by Bwap 1100-15 ML20136D8961997-03-0404 March 1997 Notice of Violation from Insp on 970203-07.Violation Noted: Since 960221,procedure Bwcp 210-14,rev 2,970221,did Not Provide Instructions to Ensure Validity of Intrinsic Germanium Detector Calibrations in Accordance W/App a ML20135B5881997-02-18018 February 1997 Notice of Violation from Insp on 961019-1129.Violation Noted:Construction of Scaffolding on 961107,in Vicinity of Essential Service Water Sys Forebay Not Prescribed by Documented Procedures Appropriate to Circumstances ML20135B4901997-02-18018 February 1997 Notice of Violation from Insp on 961130-970110.Violation Noted:Tag Required to Maintain Traceability of safety-related Item Was Removed ML20134B5941997-01-22022 January 1997 Notice of Violation from Insp on 961012-1113.Violation Noted:Plant Procedure Bwgp 100-5, Plant Shutdown & Cooldown, Activity Affecting Quality,Was Not Appropriate to Circumstances ML20133E7691997-01-0303 January 1997 Notice of Violation from Insp on 960907-1018.Violation Noted:On 960918,operations Personnel in CR Were Performing 1BwOS 8.1.1.2.a-2,which Was Inappropriate for Circumstances ML20129H2441996-10-23023 October 1996 Notice of Violation from Insp on 960727-0906.Violation Noted:On 960821,diesel Operators Did Not Independently Verify Position of Valves 2D02116B,2BwOS 8.1.1.2.a-2, 2B DG Operability Monthly & Semi-annual Surveillance ML20128H0861996-10-0202 October 1996 Notice of Violation from Insp on 960615-0726.Violation Noted:On 960709,ventilation Damper Controller OPDC-VW008 Which Had Been Altered by Installation of Jumper,Declared Operable,Required Different Operating Procedures ML20149G6361994-10-0606 October 1994 Notice of Violation from Insp on 940809-0916.Violation Noted:Nuclear Station Operators Performed Equipment Manipulations Outside of Written Procedures W/O Informing Supervisors & Receiving Guidance ML20059A2481993-10-15015 October 1993 Notice of Violation from Insp on 920726-0831.Violation Noted:Licensee Records Required to Be Maintained by NRC Regulations Not Complete & Accurate in All Matl Respects ML20128K2291993-02-0404 February 1993 Notice of Violation from Insp on 921201-930119.Violation Noted:Corrective Actions Associated W/Ler 456/90-14 Had Not Been Implemented in Timely Manner ML20128B0441993-01-26026 January 1993 Notice of Violation from Insp on 930105-08.Violation Noted: Controlled Areas Were Not Conspiciously Posted as to Warn Personnel Approaching Area from Any Direction of Restricted Areas ML20126E8301992-12-18018 December 1992 Notice of Violation from Insp on 921013-1130.Violation Noted:On 920715,radiation Protection Technician Removed Posting for 1A Letdown Heat Exchanger Room W/O Adhering to Requirements to Verify That Room Had Been Decontaminated ML20059M1551990-09-14014 September 1990 Notice of Violation from Investigation Conducted Between 851107-880422 & 881101-900416.Violation Noted:Contractor at Plant Site Discriminated Against for Engaging in Protected Activities ML20059B3561990-08-17017 August 1990 Notice of Violation from Insp on 900617-0728.Violations Noted:Unit 1 Containment Entry Made on 900608,w/containment Integrity Required by Tech Spec,But Containment Personnel Air Lock Leak Test Not Completed within 72 H ML20055G4201990-07-13013 July 1990 Notice of Violation from Insp on 900429-0616.Violation Noted:On 900603,inadequate Instructions Re Temporary Lift Procedure Expiration Resulted in Failure to Rehang Four Containment Isolation Valves Tags ML20055C7561990-06-15015 June 1990 Notice of Violation from Insp on 900416-20 & 0430-0504. Violations Noted:Control Cable to Be Attached to Hydraulic Actuator Control Solenoid Did Not Have Specific Station Evaluation ML20055C6211990-05-17017 May 1990 Notice of Violation from Insp on 900318-0428.Violation Noted:On 891019,Train B of Containment Spray Chemical Additive Sys in Unit 2 Identified Inoperable Resulting in Unanalyzed Flow Rate of 115 Gpm Vs 68 Gpm as Required ML20247R8491989-09-26026 September 1989 Notice of Violation from Insp on 890730-0916.Violation Noted:Safety Valve Stuck Open During Testing ML20247H8351989-09-12012 September 1989 Notice of Violation from Insp on 890703-0901.Violations Noted:Survey Not Performed 2 Meters from Sides of Transport Vehicle & Results of Analyses of Samples Taken in 1987 & 1988 Not Contained in Annual Radiological Environ Repts ML20247A2501989-07-11011 July 1989 Notice of Violation from Insp on 890601-20.Violation Noted: Recirculation Isolation Valve 2CV8479B for Centrifugal Charging Pump 2B Shut,Rendering Charging Pump 2B Inoperable for More than 7 Days from 890322-0601 ML20247A7521989-05-16016 May 1989 Notice of Violation from Insp on 890319-0429.Violation Noted:Mod Review for Auxiliary Feedwater Sys Temporary Alteration Did Not Recognize That Mod Will Render Boron Dilution Sys Inoperable for 13 Days ML20246L9161989-03-15015 March 1989 Notice of Violation from Insp on 890214-17.Violation Noted: on 880720,individual Working in Radioactive Matls Area Did Not Receive Bioassay Following Work Assignment & Exception Not Granted ML20195H4391988-11-23023 November 1988 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $75,000.Noncompliance Noted:Electric Equipment Important to Safety Not Properly Qualified by Testing &/Or Analysis & Specific Maint Activities Not Implemented ML20205N0351988-10-27027 October 1988 Notice of Violation from Insp on 880828-1015.Violation Noted:On 880914,radiation/chemistry Dept Personnel Not Notified of Secondary Sampling Panel/Sink Trouble Condition When Indicated by Alarms ML20151K9591988-07-22022 July 1988 Notice of Violation from Insp on 880529-0709.Violation Noted:Failure to Properly Declare Initiation of Unusual Event in Accordance W/Emergency Procedure Bwzp 200-1, Braidwood Emergency Action Levels ML20195H9651988-06-22022 June 1988 Notice of Violation from Insp on 880524-26 & 0531-0602. Violations Noted:Germanium Detectors Used to Demonstrate Compliance W/Tech Specs Improperly Calibr Using Noncertified Radioactive Sources 1998-07-06 Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS MONTHYEARIR 05000456/19990131999-09-17017 September 1999
[Table view]Insp Repts 50-456/99-13 & 50-457/99-13 on 990706-0824. Violations Noted.Major Areas Inspected:C/As & Engineering Related Activities to Address Technical Concerns Identified During Design Insp Completed on 980424 IR 05000456/19990121999-09-0303 September 1999 Insp Repts 50-456/99-12 & 50-457/99-12 on 990707-0816.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site IR 05000456/19990111999-07-29029 July 1999 Insp Repts 50-456/99-11 & 50-457/99-11 on 990525-0706.Two Violations Occurred & Being Treated as Ncvs.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000456/19990091999-07-20020 July 1999 Insp Repts 50-456/99-09 & 50-457/99-09 on 990517-0623.No Violations Noted.Major Areas Inspected:Licensee Radiation Protection Program.Circumstances Surrounding 990428, Gatehouse Monitor Exiting Incident Were Also Reviewed IR 05000456/19990071999-06-18018 June 1999 Insp Repts 50-456/99-07 & 50-457/99-07 on 990414-0524.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000457/19990081999-06-14014 June 1999 Insp Rept 50-457/99-08 on 990415-0518.No Violations Noted. Major Areas Inspected:Isi & SG Insp Program IR 05000456/19990051999-05-20020 May 1999 Insp Repts 50-456/99-05 & 50-457/99-05 on 990405-23.Non- Cited Violations Identified.Major Areas Inspected:Review of Engineering & Technical Support & Corrective Actions IR 05000456/19990061999-05-11011 May 1999 Insp Repts 50-456/99-06 & 50-457/99-06 on 990302-0413.One non-cited Violation Re Configuration Control Error Occurred. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000456/19990021999-03-23023 March 1999 Insp Repts 50-456/99-02 & 50-457/99-02 on 990120-0301.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000456/19990041999-03-23023 March 1999 Insp Repts 50-456/99-04 & 50-457/99-04 on 990222-24 & 0303 Onsite & 0309 & 11 Region 3 Ofc.No Violations Noted.Major Areas Inspected:Physical Security Program IR 05000456/19980161999-02-11011 February 1999 Insp Rept 50-456/98-16 on 980916-990121.No Violations Noted. Major Areas Inspected:Containment Access Opening & Replacement Activities,Removal & Replacement of Sgs,Welding of SG Piping & Review of Quality Control Activities IR 05000456/19980201998-12-30030 December 1998 Insp Repts 50-456/98-20 & 50-457/98-20 on 981020-1207.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000456/19980211998-12-10010 December 1998 Insp Repts 50-456/98-21 & 50-457/98-21 on 981110-24.No Violations Noted.Major Areas Inspected:Aspects of Corrective Actions & Engineering Involvement in Corrective Action Process IR 05000456/19980181998-12-0404 December 1998 Insp Rept 50-456/98-18 on 981015-23 & 1109-10.No Violations Noted.Major Areas Inspected:Four Areas Associated with Licensee SG Replacement Project IR 05000456/19980191998-11-25025 November 1998 Insp Repts 50-456/98-19 & 50-457/98-19 on 981027-30.No Violations Noted.Major Areas Inspected:Licensee Implementation of 10CFR50.65 Requirements for Monitoring Effectiveness of Maintenance at Nuclear Power Plants ML20195G3731998-11-17017 November 1998 Insp Repts 50-456/98-14 & 50-457/98-14 on 980909-1019. Violations Noted.Major Areas Inspected:Licensee Operations, Maint & Engineering ML20195G3681998-11-17017 November 1998 Notice of Violation from Insp on 980909-1019.Violation Noted:As of 980818,licensee Failed to Initiate Measures to Determine Cause or Take Action to Preclude Recurrence of Loose Bolts on Two EDG Lubricating Oil Heat Exchanger Bells ML20195G3031998-11-13013 November 1998 Notice of Violation from Insp on 980915-1022.Violation Noted:On 981022,two Individuals Working Under RWP 984014 Removed Outer Rubber Gloves While Replacing Insulation in Containment IR 05000456/19980151998-11-13013 November 1998 Insp Repts 50-456/98-15 & 50-457/98-15 on 980915-1022. Violations Noted.Major Areas Inspected:Review of Radiation Protection Program Focusing on Radiological Controls for Unit 1 Outage Activities & SG Replacement Project IR 05000456/19980171998-11-10010 November 1998 Insp Repts 50-456/98-17 & 50-457/98-17 on 981013-19. Violations Noted.Major Areas Inspected:Security Measures Implemented to Support Steam Generator Replacement Project ML20196D9201998-11-10010 November 1998 Notice of Violation from Insp on 981013-19.Violation Noted: Licensee Security Staff Discovered That on Three Occasions Between 980826 & 1002,security Officers Were Found Asleep on Post IR 05000456/19983051998-11-0202 November 1998 Exam Repts 50-456/98-305 & 50-457/98-305 on 980914 with Telephoned Exam Results 981020.No Violations Noted.Exam Results:Applicant Passed Retake Exam & Was Issued Reactor Operator License IR 05000456/19980121998-10-0505 October 1998 Insp Repts 50-456/98-12 & 50-457/98-12 on 980728-0908.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000456/19980111998-09-25025 September 1998 Insp Rept 50-456/98-11 on 980707-09,15-16,0805-06,10-13 & 26-28.No Violations Noted.Major Areas Inspected:Review of SG Replacement Program.Insp Focused on Welding of SG Feedwater Piping & Preparation Activities for Replacing SGs IR 05000456/19980131998-08-28028 August 1998 Insp Repts 50-456/98-13 & 50-457/98-13 on 980810-14.No Violations Noted.Major Areas Inspected:Review of Chemistry & Radiation Protection Programs IR 05000456/19980091998-08-25025 August 1998 Insp Repts 50-456/98-09 & 50-457/98-09 on 980609-0727. Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support ML20236N0911998-07-0606 July 1998 Notice of Violations from Insp on 980421-0608.Violations Noted:On 980424,licensee Failed to Implement Specific Fire Protection Program Requirements in That Welding Machine Was Left Unattended & Energized in Fuel Handling Bldg ML20236N0941998-07-0606 July 1998 Insp Repts 50-456/98-08 & 50-457/98-08 on 980421-0608. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000456/19980101998-07-0202 July 1998 Insp Repts 50-456/98-10 & 50-457/98-10 on 980615-19.No Violations Noted.Major Areas Inspected:Physical Security Program.Details Withheld (Ref 10CFR73.21) IR 05000456/19980071998-06-18018 June 1998 Insp Repts 50-456/98-07 & 50-457/98-07 on 980519-22.No Violations Noted.Major Areas Inspected:Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000456/19982011998-06-0101 June 1998 Insp Rept 50-456/98-201 on 980316-20,0330-0410 & 0420-24. No Violations Noted.Major Areas Inspected.Team Selected & Reviewed Relevant Portions of Ufsar,Ts,Drawings, Calculations,Mod Packages & Procedures IR 05000456/19980051998-05-19019 May 1998 Insp Repts 50-456/98-05 & 50-457/98-05 on 980310-0420. Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support ML20248D0821998-05-19019 May 1998 Notice of Violation from Insp on 980310-0420.Violation Noted:On 980303,licensee Failed to Implement Braidwood Administrative Procedure 2321-18T11,Step E.1,for Sf Pool Skimmer Strainer Level Control IR 05000456/19983041998-04-29029 April 1998 NRC Operator Licensing Exam Repts 50-456/98-304OL & 50-457/98-304OL (Including Completed & Graded Tests) Administered During Wk of 980413 ML20217F5281998-04-21021 April 1998 Notice of Violation from Insp on 980331-0407.Violation Noted:Licensee Failed to Check That SG Worker Dosimetry Was Present & Correctly Worn IR 05000456/19980061998-04-21021 April 1998 Insp Repts 50-456/98-06 & 50-457/98-06 on 980331-0407. Violations Noted.Major Areas Inspected:Announced Review Protection Program.Insp Focused on Liquid & Gaseous Effluent Radiation Monitoring Programs ML20216B0611998-04-0808 April 1998 Notice of Violation from Insp on 980127-0309.Violation Noted:On 971010,21,1219 & 980105,licensee Failed to Require Independent Verification of Proper Sys Alignment for safety-related Valves Repositioned in Steps F.1.4 & F.1.7 ML20216B0761998-04-0808 April 1998 Insp Repts 50-456/98-02 & 50-457/98-02 on 980127-0309. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000456/19980031998-03-16016 March 1998 Insp Repts 50-456/98-03 & 50-457/98-03 on 980128-30.No Violations Noted.Major Areas Inspected:Operations & Maint ML20203D9201998-02-20020 February 1998 Insp Repts 50-456/97-22 & 50-457/97-22 on 971216-980126. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20203D9151998-02-20020 February 1998 Notice of Violation from Insp on 971216-980126.Violation Noted:In Nov 1989,licensee Failed to Initiate Deviation Rept & Take Corrective Measures to Preclude Repetition of Mechanical Failure to All 4 Main Feedwater Check Valves ML20202F2321998-02-11011 February 1998 Notice of Violations from Insp on 971112-21 & 980115. Violations Noted:Licensee Failed to Follow NSWP-A-15 & Bwap 330-10 Requirements to Issue PIF for Tempering Line Snubber Considered Inoperable on 971110 IR 05000457/19970211998-02-11011 February 1998 Insp Rept 50-457/97-21 on 971112-21 & 980115.Violations Noted.Major Areas Inspected:Operations & Engineering PNO-III-98-013, on 980126,turbine Tripped Causing Subsequent Reactor Trip.Cause of Turbine Trip Remains Under Investigation.Appears Replacement Circuit Board Had Incorrect Electronic Configuration1998-01-29029 January 1998 PNO-III-98-013:on 980126,turbine Tripped Causing Subsequent Reactor Trip.Cause of Turbine Trip Remains Under Investigation.Appears Replacement Circuit Board Had Incorrect Electronic Configuration ML20198G1231998-01-0707 January 1998 Partially Withheld Insp Repts 50-456/97-20 & 50-457/97-20 on 971117-21 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Plant Support Performance Involving Evaluation of Effectiveness of Physical Protection Program ML20202F1951998-01-0202 January 1998 Insp Repts 50-456/97-19 & 50-457/97-19 on 971104-1215. Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 07100104/20120151998-01-0202 January 1998 Notice of Violation from Insp on 971104-1215.Violation Noted:On 971102,inspectors Identified That Licensee Had Failed to Fasten Covers on Incore Neutron Detector Drive Mechanism IR 05000456/19973101997-12-29029 December 1997 NRC Operator Licensing Exam Repts 50-456/97-310OL & 50-457/97-310OL for Tests Administered on 971006-1107.Three Senior Reactor Operators & One Reactor Operator Passed Exam. One Senior Reactor & One Reactor Operator Failed ML20199A5681997-12-17017 December 1997 Notice of Violation from Insp on 970923-1103.Violation Noted:On 971014,licensee Instrument Technician Made Error When Changing Setpoints on Unit 2 Containment Area Radiation Monitor 2AR11J.Error Resulted in High Radiation Alarm 1999-09-03 |
Text
. - _ _ _ _ _ _ _ _ _ _ _ _ _ _
NOTICE OF VIOLATION Commonwealth Edison Company Docket No. 50-457 As a result of the inspection conducted from June I through June 20, 1989, and in accordance with 10 CFR Part 2, Appendix C - General Statement of Policy and Procedure for NRC Enforcement Actions (1988), the following violation was identified:
Braidwood Technical Specification 3.5.2 requires that two independent emergency core cooling system (ECCS) subsystems be operable, with each subsystem including an operable centrifugal charging pump, during Modes 1, 2, or 3 operation. Action statement a. requires that an inoperable subsystem be restored to operable status with seven days, or that the unit be shut down to at least hot standby (Mode 3) within the next six hours and to hot shutdown (Mode 4) within the following six hours.
Contrary to the above, from March 22 through June 1,1989, recirculation -
isolation valve 2CV8479B for centrifugal charging pump 2B was shut, thaieby rendering the 2B centrifugal charging pump inoperable. One Unit : ECCS subsystem was thus inoperable for more than seven days with th's unit in Mode 3 or higher without action to place the unit in a mode in which Technical Specification 3.5.2 does not apply.
This is a Severity Level IV violation (Supplement I). (50-456/89017-01(DRP);
50-457/89017-01(DRP))
Pursuant to the provisions of 10 CFR 2.201, you are required to submit to 'his office within thirty days of the date of this Notice a written statement or explanation in reply, including for each violation: (1) the corrective actions that have been taken and the results achieved; (2) the corrective actions that will be taken to avoid further violations; and (3) the Jate when full compliance will be achieved. Consideration may be given to extending your response time for good cause shown.
D ec LjT1989 ON AM_ -
M Edward G. GreenmaTC Direct %
(/ Division of Reactor Projects 89072101ss 89071.7 PDR ADOCK0500g6 Q