Similar Documents at Ginna |
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000244/19990071999-09-20020 September 1999 Insp Rept 50-244/99-07 on 990719-23 & 0802-06.NCVs Noted. Major Areas Inspected:Maint & Engineering IR 05000244/19970081997-07-16016 July 1997 Insp Rept 50-244/97-08 on 970527-30.Apparent Violations Being Considered for Escalated Ea.Major Areas Inspected: Conduct of Security & Safeguards Activities,Status of Security Facilities & PA Barriers & Vehicles Barrier Sys IR 05000244/19900211990-10-24024 October 1990 Physical Security Insp Rept 50-244/90-21 on 900910-14. No Violations Noted.Major Areas Inspected:Onsite follow-up of Previously Indentified Items,Mgt Support & Security Program Plans & Audits IR 05000244/19870281988-01-25025 January 1988 Partially Withheld Physical Security Insp Rept 50-244/87-28 on 871116-20 (Ref 10CFR2.790 & 73.21).No Violations Noted. Major Areas Inspected:Plan & Implementing Procedures, Organization,Program Audits & Records & Repts IR 05000244/19870211987-09-29029 September 1987 Insp Rept 50-244/87-21 on 870831-0904.No Violations Noted. Major Areas Inspected:Review of Licensee Action on Previously NRC Identified Concerns,Followup of Generic Ltr 83-28,Item 4.1 & Qa/Qc Interfaces IR 05000244/19870191987-08-28028 August 1987 Insp Rept 50-244/87-19 on 870727-31.Violation Noted.Major Areas Inspected:Occupational Radiation Protection Program, Including Status of Previously Identified Items,Organization & Mgt Controls,Audits & External Exposure Control IR 05000244/19870051987-03-24024 March 1987 Insp Rept 50-244/87-05 on 870224-27.No Violations Noted. Major Areas Inspected:Status of Previously Identified Items, Organization & Mgt Controls,Training & Qualification of New Personnel,External & Internal Exposure Control & ALARA IR 05000244/19870061987-03-24024 March 1987 Insp Rept 50-244/87-06 on 870224-27.No Violations Noted. Major Areas Inspected:Activities Associated W/Steam Generator Exams & Maint,Inservice Insp & Licensee Actions on Previous Insp Findings IR 05000244/19870021987-02-18018 February 1987 Insp Rept 50-244/87-02 on 870104-0207.No Violations Noted. Major Areas Inspected:Licensee Action on Previous Findings, Review of Plant Operations,Operational Safety Verification, Surveillance Testing,Plant Maint & LERs IR 05000244/19870011987-02-0404 February 1987 Insp Rept 50-244/87-01 on 870105-09.No Violations Noted. Major Areas Inspected:External Exposure Control,Internal Exposure Control,Control of Radioactive Matl & Contamination & Surveys & Monitoring ML20212M1901987-01-16016 January 1987 Safety Insp Rept 50-244/86-22 on 861215-19.No Violations or Deviations Noted.Major Areas Inspected:Licensee Response to Previous Insp Findings & Effectiveness of Licensee Correction Action Program IR 05000244/19860211987-01-12012 January 1987 Insp Rept 50-244/86-21 on 861109-870103.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Findings, Review of Plant Operations,Operational Safety Verification, Surveillance Testing & Plant Maint IR 05000244/19860121986-10-0909 October 1986 Emergency Preparedness Insp Rept 50-244/86-12 on 860826-29. Violation Noted Re Ability to Fully Staff & Augment Emergency Response Organization in Timely Manner IR 05000244/19860131986-10-0202 October 1986 Insp Rept 50-244/86-13 on 860909-11.No Violation Noted.Major Areas Inspected:Annual Emergency Preparedness Exercise Performed on 860910 IR 05000244/19850201985-10-22022 October 1985 Insp Rept 50-244/85-20 on 850925-27.No Violation Noted.Major Areas Inspected:Emergency Preparedness & Annual Emergency Exercise Performed on 850926 IR 05000244/19820131982-07-20020 July 1982 IE Insp Rept 50-244/82-13 on 820628-0701.No Noncompliance Noted.Major Areas Inspected:Followup on IE Circular 80-21, Verification of Core load,post-refueling Startup Testing & Control Rod Worth Measurements & Predications IR 05000244/19820111982-06-18018 June 1982 IE Insp Rept 50-244/82-11 on 820517-19.No Noncompliance Noted.Major Areas Inspected:Environ Monitoring Programs for Operation Including Mgt Controls & QC of Analytical Measurements IR 05000244/19820101982-06-15015 June 1982 IE Insp Rept 50-244/82-10 on 820501-31.Noncompliance Noted: Failure to Properly Implement & Track QA Surveillance Repts 1999-09-20
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000244/19990071999-09-20020 September 1999 Insp Rept 50-244/99-07 on 990719-23 & 0802-06.NCVs Noted. Major Areas Inspected:Maint & Engineering IR 05000244/19970081997-07-16016 July 1997 Insp Rept 50-244/97-08 on 970527-30.Apparent Violations Being Considered for Escalated Ea.Major Areas Inspected: Conduct of Security & Safeguards Activities,Status of Security Facilities & PA Barriers & Vehicles Barrier Sys IR 05000244/19900211990-10-24024 October 1990 Physical Security Insp Rept 50-244/90-21 on 900910-14. No Violations Noted.Major Areas Inspected:Onsite follow-up of Previously Indentified Items,Mgt Support & Security Program Plans & Audits IR 05000244/19870281988-01-25025 January 1988 Partially Withheld Physical Security Insp Rept 50-244/87-28 on 871116-20 (Ref 10CFR2.790 & 73.21).No Violations Noted. Major Areas Inspected:Plan & Implementing Procedures, Organization,Program Audits & Records & Repts IR 05000244/19870211987-09-29029 September 1987 Insp Rept 50-244/87-21 on 870831-0904.No Violations Noted. Major Areas Inspected:Review of Licensee Action on Previously NRC Identified Concerns,Followup of Generic Ltr 83-28,Item 4.1 & Qa/Qc Interfaces IR 05000244/19870191987-08-28028 August 1987 Insp Rept 50-244/87-19 on 870727-31.Violation Noted.Major Areas Inspected:Occupational Radiation Protection Program, Including Status of Previously Identified Items,Organization & Mgt Controls,Audits & External Exposure Control IR 05000244/19870051987-03-24024 March 1987 Insp Rept 50-244/87-05 on 870224-27.No Violations Noted. Major Areas Inspected:Status of Previously Identified Items, Organization & Mgt Controls,Training & Qualification of New Personnel,External & Internal Exposure Control & ALARA IR 05000244/19870061987-03-24024 March 1987 Insp Rept 50-244/87-06 on 870224-27.No Violations Noted. Major Areas Inspected:Activities Associated W/Steam Generator Exams & Maint,Inservice Insp & Licensee Actions on Previous Insp Findings IR 05000244/19870021987-02-18018 February 1987 Insp Rept 50-244/87-02 on 870104-0207.No Violations Noted. Major Areas Inspected:Licensee Action on Previous Findings, Review of Plant Operations,Operational Safety Verification, Surveillance Testing,Plant Maint & LERs IR 05000244/19870011987-02-0404 February 1987 Insp Rept 50-244/87-01 on 870105-09.No Violations Noted. Major Areas Inspected:External Exposure Control,Internal Exposure Control,Control of Radioactive Matl & Contamination & Surveys & Monitoring ML20212M1901987-01-16016 January 1987 Safety Insp Rept 50-244/86-22 on 861215-19.No Violations or Deviations Noted.Major Areas Inspected:Licensee Response to Previous Insp Findings & Effectiveness of Licensee Correction Action Program IR 05000244/19860211987-01-12012 January 1987 Insp Rept 50-244/86-21 on 861109-870103.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Findings, Review of Plant Operations,Operational Safety Verification, Surveillance Testing & Plant Maint IR 05000244/19860121986-10-0909 October 1986 Emergency Preparedness Insp Rept 50-244/86-12 on 860826-29. Violation Noted Re Ability to Fully Staff & Augment Emergency Response Organization in Timely Manner IR 05000244/19860131986-10-0202 October 1986 Insp Rept 50-244/86-13 on 860909-11.No Violation Noted.Major Areas Inspected:Annual Emergency Preparedness Exercise Performed on 860910 IR 05000244/19850201985-10-22022 October 1985 Insp Rept 50-244/85-20 on 850925-27.No Violation Noted.Major Areas Inspected:Emergency Preparedness & Annual Emergency Exercise Performed on 850926 IR 05000244/19820131982-07-20020 July 1982 IE Insp Rept 50-244/82-13 on 820628-0701.No Noncompliance Noted.Major Areas Inspected:Followup on IE Circular 80-21, Verification of Core load,post-refueling Startup Testing & Control Rod Worth Measurements & Predications IR 05000244/19820111982-06-18018 June 1982 IE Insp Rept 50-244/82-11 on 820517-19.No Noncompliance Noted.Major Areas Inspected:Environ Monitoring Programs for Operation Including Mgt Controls & QC of Analytical Measurements IR 05000244/19820101982-06-15015 June 1982 IE Insp Rept 50-244/82-10 on 820501-31.Noncompliance Noted: Failure to Properly Implement & Track QA Surveillance Repts 1999-09-20
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000244/19990071999-09-20020 September 1999 Insp Rept 50-244/99-07 on 990719-23 & 0802-06.NCVs Noted. Major Areas Inspected:Maint & Engineering IR 05000244/19970081997-07-16016 July 1997 Insp Rept 50-244/97-08 on 970527-30.Apparent Violations Being Considered for Escalated Ea.Major Areas Inspected: Conduct of Security & Safeguards Activities,Status of Security Facilities & PA Barriers & Vehicles Barrier Sys IR 05000244/19900211990-10-24024 October 1990 Physical Security Insp Rept 50-244/90-21 on 900910-14. No Violations Noted.Major Areas Inspected:Onsite follow-up of Previously Indentified Items,Mgt Support & Security Program Plans & Audits IR 05000244/19870281988-01-25025 January 1988 Partially Withheld Physical Security Insp Rept 50-244/87-28 on 871116-20 (Ref 10CFR2.790 & 73.21).No Violations Noted. Major Areas Inspected:Plan & Implementing Procedures, Organization,Program Audits & Records & Repts IR 05000244/19870211987-09-29029 September 1987 Insp Rept 50-244/87-21 on 870831-0904.No Violations Noted. Major Areas Inspected:Review of Licensee Action on Previously NRC Identified Concerns,Followup of Generic Ltr 83-28,Item 4.1 & Qa/Qc Interfaces IR 05000244/19870191987-08-28028 August 1987 Insp Rept 50-244/87-19 on 870727-31.Violation Noted.Major Areas Inspected:Occupational Radiation Protection Program, Including Status of Previously Identified Items,Organization & Mgt Controls,Audits & External Exposure Control IR 05000244/19870051987-03-24024 March 1987 Insp Rept 50-244/87-05 on 870224-27.No Violations Noted. Major Areas Inspected:Status of Previously Identified Items, Organization & Mgt Controls,Training & Qualification of New Personnel,External & Internal Exposure Control & ALARA IR 05000244/19870061987-03-24024 March 1987 Insp Rept 50-244/87-06 on 870224-27.No Violations Noted. Major Areas Inspected:Activities Associated W/Steam Generator Exams & Maint,Inservice Insp & Licensee Actions on Previous Insp Findings IR 05000244/19870021987-02-18018 February 1987 Insp Rept 50-244/87-02 on 870104-0207.No Violations Noted. Major Areas Inspected:Licensee Action on Previous Findings, Review of Plant Operations,Operational Safety Verification, Surveillance Testing,Plant Maint & LERs IR 05000244/19870011987-02-0404 February 1987 Insp Rept 50-244/87-01 on 870105-09.No Violations Noted. Major Areas Inspected:External Exposure Control,Internal Exposure Control,Control of Radioactive Matl & Contamination & Surveys & Monitoring ML20212M1901987-01-16016 January 1987 Safety Insp Rept 50-244/86-22 on 861215-19.No Violations or Deviations Noted.Major Areas Inspected:Licensee Response to Previous Insp Findings & Effectiveness of Licensee Correction Action Program IR 05000244/19860211987-01-12012 January 1987 Insp Rept 50-244/86-21 on 861109-870103.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Findings, Review of Plant Operations,Operational Safety Verification, Surveillance Testing & Plant Maint IR 05000244/19860121986-10-0909 October 1986 Emergency Preparedness Insp Rept 50-244/86-12 on 860826-29. Violation Noted Re Ability to Fully Staff & Augment Emergency Response Organization in Timely Manner IR 05000244/19860131986-10-0202 October 1986 Insp Rept 50-244/86-13 on 860909-11.No Violation Noted.Major Areas Inspected:Annual Emergency Preparedness Exercise Performed on 860910 IR 05000244/19850201985-10-22022 October 1985 Insp Rept 50-244/85-20 on 850925-27.No Violation Noted.Major Areas Inspected:Emergency Preparedness & Annual Emergency Exercise Performed on 850926 IR 05000244/19820131982-07-20020 July 1982 IE Insp Rept 50-244/82-13 on 820628-0701.No Noncompliance Noted.Major Areas Inspected:Followup on IE Circular 80-21, Verification of Core load,post-refueling Startup Testing & Control Rod Worth Measurements & Predications IR 05000244/19820111982-06-18018 June 1982 IE Insp Rept 50-244/82-11 on 820517-19.No Noncompliance Noted.Major Areas Inspected:Environ Monitoring Programs for Operation Including Mgt Controls & QC of Analytical Measurements IR 05000244/19820101982-06-15015 June 1982 IE Insp Rept 50-244/82-10 on 820501-31.Noncompliance Noted: Failure to Properly Implement & Track QA Surveillance Repts 1999-09-20
[Table view] Category:UTILITY
MONTHYEARIR 05000244/19870281988-01-25025 January 1988 Partially Withheld Physical Security Insp Rept 50-244/87-28 on 871116-20 (Ref 10CFR2.790 & 73.21).No Violations Noted. Major Areas Inspected:Plan & Implementing Procedures, Organization,Program Audits & Records & Repts IR 05000244/19870211987-09-29029 September 1987 Insp Rept 50-244/87-21 on 870831-0904.No Violations Noted. Major Areas Inspected:Review of Licensee Action on Previously NRC Identified Concerns,Followup of Generic Ltr 83-28,Item 4.1 & Qa/Qc Interfaces IR 05000244/19870191987-08-28028 August 1987 Insp Rept 50-244/87-19 on 870727-31.Violation Noted.Major Areas Inspected:Occupational Radiation Protection Program, Including Status of Previously Identified Items,Organization & Mgt Controls,Audits & External Exposure Control IR 05000244/19870061987-03-24024 March 1987 Insp Rept 50-244/87-06 on 870224-27.No Violations Noted. Major Areas Inspected:Activities Associated W/Steam Generator Exams & Maint,Inservice Insp & Licensee Actions on Previous Insp Findings IR 05000244/19870051987-03-24024 March 1987 Insp Rept 50-244/87-05 on 870224-27.No Violations Noted. Major Areas Inspected:Status of Previously Identified Items, Organization & Mgt Controls,Training & Qualification of New Personnel,External & Internal Exposure Control & ALARA IR 05000244/19870011987-02-0404 February 1987 Insp Rept 50-244/87-01 on 870105-09.No Violations Noted. Major Areas Inspected:External Exposure Control,Internal Exposure Control,Control of Radioactive Matl & Contamination & Surveys & Monitoring ML20212M1901987-01-16016 January 1987 Safety Insp Rept 50-244/86-22 on 861215-19.No Violations or Deviations Noted.Major Areas Inspected:Licensee Response to Previous Insp Findings & Effectiveness of Licensee Correction Action Program IR 05000244/19860211987-01-12012 January 1987 Insp Rept 50-244/86-21 on 861109-870103.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Findings, Review of Plant Operations,Operational Safety Verification, Surveillance Testing & Plant Maint IR 05000244/19860121986-10-0909 October 1986 Emergency Preparedness Insp Rept 50-244/86-12 on 860826-29. Violation Noted Re Ability to Fully Staff & Augment Emergency Response Organization in Timely Manner IR 05000244/19860131986-10-0202 October 1986 Insp Rept 50-244/86-13 on 860909-11.No Violation Noted.Major Areas Inspected:Annual Emergency Preparedness Exercise Performed on 860910 IR 05000244/19850201985-10-22022 October 1985 Insp Rept 50-244/85-20 on 850925-27.No Violation Noted.Major Areas Inspected:Emergency Preparedness & Annual Emergency Exercise Performed on 850926 IR 05000244/19820131982-07-20020 July 1982 IE Insp Rept 50-244/82-13 on 820628-0701.No Noncompliance Noted.Major Areas Inspected:Followup on IE Circular 80-21, Verification of Core load,post-refueling Startup Testing & Control Rod Worth Measurements & Predications IR 05000244/19820111982-06-18018 June 1982 IE Insp Rept 50-244/82-11 on 820517-19.No Noncompliance Noted.Major Areas Inspected:Environ Monitoring Programs for Operation Including Mgt Controls & QC of Analytical Measurements IR 05000244/19820101982-06-15015 June 1982 IE Insp Rept 50-244/82-10 on 820501-31.Noncompliance Noted: Failure to Properly Implement & Track QA Surveillance Repts 1988-01-25
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000244/19990071999-09-20020 September 1999 Insp Rept 50-244/99-07 on 990719-23 & 0802-06.NCVs Noted. Major Areas Inspected:Maint & Engineering ML20217L9861997-08-15015 August 1997 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $55,000.Violation Noted:Vehicle Barriers Deployed Outside Outer Isolation Zone Would Not Prevent Malicious Use of Vehicle to Gain Entry to Protected Areas IR 05000244/19970081997-07-16016 July 1997 Insp Rept 50-244/97-08 on 970527-30.Apparent Violations Being Considered for Escalated Ea.Major Areas Inspected: Conduct of Security & Safeguards Activities,Status of Security Facilities & PA Barriers & Vehicles Barrier Sys ML20132H0791996-12-13013 December 1996 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $100,000.Violation Noted:Prior to 960803, Measures Not Established to Assure That Certain Conditions Adverse to Quality Not Promptly Identified & Corrected IR 05000244/19900211990-10-24024 October 1990 Physical Security Insp Rept 50-244/90-21 on 900910-14. No Violations Noted.Major Areas Inspected:Onsite follow-up of Previously Indentified Items,Mgt Support & Security Program Plans & Audits ML20246E2561989-04-28028 April 1989 Notice of Violation from Insp on 890313-17.Violation Noted: Design Criteria & Safety Analysis for PORV Block Valve Replacement,To Be Performed During 1989 Outage,Did Not Address Operability Qualification of Replacement Valves PNO-I-88-057A, identified Radioactive Contamination on Contractor Exiting Facility Protected Area.Contamination Also Identified in Individual Home & co-worker Car.Caused by Inadequate Monitoring Before Leaving Restricted Area1988-06-22022 June 1988 PNO-I-88-057A:identified Radioactive Contamination on Contractor Exiting Facility Protected Area.Contamination Also Identified in Individual Home & co-worker Car.Caused by Inadequate Monitoring Before Leaving Restricted Area IR 05000244/19870281988-01-25025 January 1988 Partially Withheld Physical Security Insp Rept 50-244/87-28 on 871116-20 (Ref 10CFR2.790 & 73.21).No Violations Noted. Major Areas Inspected:Plan & Implementing Procedures, Organization,Program Audits & Records & Repts IR 05000244/19870221987-11-24024 November 1987 Exam Rept 50-244/87-22OL During Week of 871005.Exam Results: Six Senior Reactor Operators & Four Reactor Operators Passed All Exams & One Reactor Operator Failed Written Exam IR 05000244/19870211987-09-29029 September 1987 Insp Rept 50-244/87-21 on 870831-0904.No Violations Noted. Major Areas Inspected:Review of Licensee Action on Previously NRC Identified Concerns,Followup of Generic Ltr 83-28,Item 4.1 & Qa/Qc Interfaces IR 05000244/19870191987-08-28028 August 1987 Insp Rept 50-244/87-19 on 870727-31.Violation Noted.Major Areas Inspected:Occupational Radiation Protection Program, Including Status of Previously Identified Items,Organization & Mgt Controls,Audits & External Exposure Control ML20212R5131987-04-20020 April 1987 PNS-i-87-006:on 870420,bomb Threat Received by Monroe County Police Emergency Notification Dispatcher.Security Personnel Posted on Plant Access Roads to Verify Id Prior to Access to Plant.State & Local Police Patrolled Area IR 05000244/19870061987-03-24024 March 1987 Insp Rept 50-244/87-06 on 870224-27.No Violations Noted. Major Areas Inspected:Activities Associated W/Steam Generator Exams & Maint,Inservice Insp & Licensee Actions on Previous Insp Findings IR 05000244/19870051987-03-24024 March 1987 Insp Rept 50-244/87-05 on 870224-27.No Violations Noted. Major Areas Inspected:Status of Previously Identified Items, Organization & Mgt Controls,Training & Qualification of New Personnel,External & Internal Exposure Control & ALARA IR 05000244/19870021987-02-18018 February 1987 Insp Rept 50-244/87-02 on 870104-0207.No Violations Noted. Major Areas Inspected:Licensee Action on Previous Findings, Review of Plant Operations,Operational Safety Verification, Surveillance Testing,Plant Maint & LERs IR 05000244/19870011987-02-0404 February 1987 Insp Rept 50-244/87-01 on 870105-09.No Violations Noted. Major Areas Inspected:External Exposure Control,Internal Exposure Control,Control of Radioactive Matl & Contamination & Surveys & Monitoring ML20212M1901987-01-16016 January 1987 Safety Insp Rept 50-244/86-22 on 861215-19.No Violations or Deviations Noted.Major Areas Inspected:Licensee Response to Previous Insp Findings & Effectiveness of Licensee Correction Action Program IR 05000244/19860211987-01-12012 January 1987 Insp Rept 50-244/86-21 on 861109-870103.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Findings, Review of Plant Operations,Operational Safety Verification, Surveillance Testing & Plant Maint IR 05000244/19860121986-10-0909 October 1986 Emergency Preparedness Insp Rept 50-244/86-12 on 860826-29. Violation Noted Re Ability to Fully Staff & Augment Emergency Response Organization in Timely Manner IR 05000244/19860131986-10-0202 October 1986 Insp Rept 50-244/86-13 on 860909-11.No Violation Noted.Major Areas Inspected:Annual Emergency Preparedness Exercise Performed on 860910 PNO-I-86-058, on 860729,reactor Manually Tripped from 100% Power Due to Break in Drain Line from Main Steam Reheater 2A to Feedwater Heater 5A.Cause Under Investigation.Licensee Actions Under Review1986-07-29029 July 1986 PNO-I-86-058:on 860729,reactor Manually Tripped from 100% Power Due to Break in Drain Line from Main Steam Reheater 2A to Feedwater Heater 5A.Cause Under Investigation.Licensee Actions Under Review ML20140B0401986-01-0808 January 1986 Exam Rept 50-244/OL-85-23 on 851111-15.Exam Results:All Candidates Passed Both Written & Oral Portions of Exam PNO-I-85-085A, on 851106,licensee Secured from Unusual Event Declared Due to Automatic Actuation of Cable Tunnel Deluge Sys.Caused by Faulty Printed Circuit Card.Ground on Nonvital Bus Damaged by Deluge Sys Corrected1985-11-0707 November 1985 PNO-I-85-085A:on 851106,licensee Secured from Unusual Event Declared Due to Automatic Actuation of Cable Tunnel Deluge Sys.Caused by Faulty Printed Circuit Card.Ground on Nonvital Bus Damaged by Deluge Sys Corrected PNO-I-85-085, on 851106,fire Protection Deluge Sys in Cable Tunnel Automatically Actuated.Smoke Smelled at Scene.Sys Isolated After 10 Minutes of Operation.Visual Insp of Cable Tunnel Revealed No Apparent Damage1985-11-0606 November 1985 PNO-I-85-085:on 851106,fire Protection Deluge Sys in Cable Tunnel Automatically Actuated.Smoke Smelled at Scene.Sys Isolated After 10 Minutes of Operation.Visual Insp of Cable Tunnel Revealed No Apparent Damage IR 05000244/19850201985-10-22022 October 1985 Insp Rept 50-244/85-20 on 850925-27.No Violation Noted.Major Areas Inspected:Emergency Preparedness & Annual Emergency Exercise Performed on 850926 ML20128L0521985-07-18018 July 1985 PNS-I-85-010:on 850718,safeguards Contingency Plan Drill Will Be Held.Exercise Will Test Command/Control, Communications & Response Force Mobilization Developed by State of Ny Emergency Mgt Agency IR 05000244/19850111985-07-11011 July 1985 Exam Rept 50-244/85-11 on 850624.Exam Results:All Candidates Passed.No Generic Deficiencies Noted IR 05000244/19820131982-07-20020 July 1982 IE Insp Rept 50-244/82-13 on 820628-0701.No Noncompliance Noted.Major Areas Inspected:Followup on IE Circular 80-21, Verification of Core load,post-refueling Startup Testing & Control Rod Worth Measurements & Predications IR 05000244/19820111982-06-18018 June 1982 IE Insp Rept 50-244/82-11 on 820517-19.No Noncompliance Noted.Major Areas Inspected:Environ Monitoring Programs for Operation Including Mgt Controls & QC of Analytical Measurements ML20054K9011982-06-16016 June 1982 Notice of Violation from Insp on 820501-31 IR 05000244/19820101982-06-15015 June 1982 IE Insp Rept 50-244/82-10 on 820501-31.Noncompliance Noted: Failure to Properly Implement & Track QA Surveillance Repts ML20236L5201979-10-24024 October 1979 PNS-I-79-005:on 791023,unidentified Male Called Rochester Gas & Electric Corp Switchboard in New York,Stating That Bomb Planted in Ginna Plant in Retaliation for Attempted Murder on Highway 490 ML20249A0931978-01-25025 January 1978 PNO-78-013:on 770125,unit Was Shutdown from 100% Power Due to Leak in One Steam Generator.Licensee Made Decision to Shutdown for Repairs,Although Leak Rate Did Not Exceed TS Limit.State of Ny Informed ML20207G5861977-11-17017 November 1977 PNO-77-201:on 771116,urgent Failure Alarm Occurred on Rod Control Sys,Indicating Logic Problem in CRD Sys.Reactor Shutdown from 100 Percent Power to Cold Shutdown Condition commenced.In-motion of Control Rods Determined Operable ML20236E9101977-08-18018 August 1977 PNS-77-032:on 770816,canoe Capsized W/Two Men Aboard About 100 Feet Offshore Near Plant Discharge Canal to Lake Ontario.One Man Swam Ashore & Climbed Over Security Fence & Called for Help Over Loudspeaker.Other Man Was Rescued ML20151X7111977-07-0606 July 1977 PNO-77-121:on 770705,unit Was Shutdown from 100% Power,Due to Identified Tube Leakage from RCS to Secondary Sys in One of Two Sgs.Outage Duration Expected to Be Two Weeks.Media Interest Expected ML20249B0281976-01-29029 January 1976 PNO-76-018:on 760129,reactor Shutdown Due to Increase Vibration on Two Low Pressure Turbine Bearings.Extent of Problem Not Known.Exam of Bearings Will Be Accomplished During Weekend After Turbine Disassembly ML20236W7901975-12-30030 December 1975 PN-75-157:on 751230,unscheduled Shutdown Completed Due to Increasing Tube Leakage from B Sg.Load Reduction Initiated.Duration of Shutdown Expected to Be Approximately Six Days.State of New York Kept Informed ML20236U2371975-06-18018 June 1975 PN75-037:on 750617,turbine Was Manually Tripped as Result of Excessive Feedwater Piping Vibration.Visual Insp Revealed No Apparent Damage to Pipe Restraints or Containment Penetrations.Some Instrument Sensing Lines Inoperable 1999-09-20
[Table view] |
Inspection Report - Ginna - 1987019 |
---|
|
|
Text
._.
_ _ _ _ _ - _ _ _ _ - _ _ _
.- -
i
!
n;
> :l U.S. NUCLEAR REGULAT0hY COMMISSION
REGION I
s Report No.
50-244/87-19
,
Occket No.
50-244
License No.
DPR-18 Category C
,
licensee:
Rochester Gas and Electric Corporation 49 East Avenue
Rochester, New York 14649 Facility Name: Ginna Nuclear power Plant Inspec'
n At: Ontario, New York Inspection Conducted: July 27-31, 1987 g-
%
//dth~
M M
Inspector {J. McFadden,(_S(, Radiation Specialist Bbe/3 7
'
,
date
fx?g3
/ Info D. LeQuia,'J6diat4on Specialist date
Approved by:
R L N cd6 fn glnhG M. Shanbaky, Chief, Facilities Radiation date protection Sectiin
,im pection Summary:
Inspection on July 27-31, 1987 (Inspection Report No. 50-244/87-19)
,~
Areas Inspected:
Routine unannounced inspection of the occupational radiation protection program including: status of previously identified items,
organization and management controls, audits, external exposure control, internal exposure control, control of radioactive material and contamination, surveys and monitoring, and ALARA.
Two regionally-based inspectors were on-site for the inspection.
Results: One apparent violation was identified.
Failure to maintain an acceptable written procedure for a calibration required by a technical specification surveillance requirement (Section 8.0).
Two unresolved items were identified (Sections 5 and 6).
l One inspector follow-up item was identified (Section 8.0).
The licensee was found
!
to be making improvements to their radioactive contamination control program.
8709100536 870902 PDR ADOCR 05000244 G
PDR
..
- __
. $e
,
'.
m
.
y'
DETAILS (i[
1.0 Persons Contacted During the course of this inspection, the following personnel were l
contacted or interviewed.
,,
1.1 Licensee Personnel
^[
!
D. Bryant, QA Engineer / Operations d
- D. Filkins, Manager - Health Physics and Chemistry
[
- W. Goodman, HP Foreman J. Jones, I&C Foreman
-
j
Kober, VP Electric Production
.
- T. Meyer, Superintendent - Ginna Support Services
l
- R. Popp. !&C Technical Assistant
- B. Quinn, Corporate Health Physicist
- B. Snow, Superintendent Nuclear Production P
l
- P. Spacher, Health Physicist I
- S. Spector, Superintendent - Ginna Production
- J. Supina, Dosimetry Supervisor /ALARA Coordinator i
- S. Warren, Health Physicist
{
i 1.2 NRC Personnel Attending the Exit Interview T. Polich, Senior Resident Inspector
" Attended the Exit Meeting on July 31, 1987.
-
J Additional licensee personnel were contacted or interviewed during
'
this inspection.
,
2.0 Purpose
h The purpose of this inspection was to review the licensee's occupational radiation protection program with respect to the following elements:
j
!
Status of previously identified items
Organization and management controls i
-
External occupational exposure control and personal dosimetry
-
Internal exposure control and assessment
Control of radioactive materials and contamination, surveys and
monitoring Maintaining occupational exposures ALARA a
- -__-_ - _ __
kkM
.-
'W
'
4@I
.h
-
w 10,4 3.0 Status of Previously-Identified Items
}j
{
l 3.1 (Closed); Follow-up Item (82-09-01);
dd
.
.L Verify that radiological warning signs are covered in the
@%
" Administrative / Security Indoctrination"' course.
Inspector. review q
l of Lesson Plan No..GGE01C, Rev. 2, entitled:
" Administrative /
@
l
'
Security /QA Indoctrination," verified that employee training relative
%
l to radiological warning signs has been included in the lesson plan on Q
J page 4 of 31. Based upon this review, this item is closed.
A 3.24 (Closed); Follow-up Item (82-09-02):
'
%
-Licensee to proceduralize guidance for " Visiter Dosimeter Log,"
defining who is classified as a. visitor, outlining visitor escort
%yj i
'
responsibilities, and describing how the log is administered.
.
.
,y Inspector review of Procedure No. HP-4.1.1, " Untrained Visitor Entry y
to Controlled Areas," Rev. 6, determined that the licensee has W
proceduralized the guidance necessary for. administration of the
%
" Visitor Dosimeter Log".
Inspector review of. Visitor Dosimeter Log A
entries for July 15 and 16,1987, verified that the-log is-being
'"
maintained in accordance with procedural guidance.
Based on this.
review, this item is closed.
!
3.3 (Closed); Noncompliance (Severity Level 5) (82-09-03):
/M Special work permits (SWPs) incorrectly specified work locations, N
radiation dose rates, and radioactive contamination levels. During i
NRC Inspection No. 87-05, selected SWPs being implemented during the
-
outage were reviewed, and incorrect specifications were not f
i identified. Based on this finding, this' item is considered closed.
l, &
l
$
3.4 (Closed); Followup Item (82-11-01):
A
"
Evaluation of interlaboratory comparison program results.
Followup
item, 85-18-02, also addresses this subject and therefore, this item (82-11-01) is considered closed administratively.
(Closed)1 oll_owup_I tem _(82-11-02):
3.5 F
Evaluation of TLD measurements program.
Follow-up item, 84-20-02, also addresses this subject and, therefore, this item (82-11-02) is considered closed administratively.
!
4.0 Staffing, Management and Organization
'
The licensee's organization, staffing and motivation to effectively centrol radiation and radioactive materials was evalo 'ad against the
<
following criteria:
i I~
t
_ _ _ _ _ ~
_
___
__
_. _ _ _ _ _ _. _ _ _ _ _ _ _ _ _ _ _. _ _ _...... _ _ _. _ _ _ _ _ _
W
.
M
..
4.
2d
$
.
~
d
'
y
Technical Specifications. Section 6, " Administrative Controls";
i i
p Regulatory Guide 1.8, " Personnel Selection and Training";
NUREG/CR-1280, " Power Plant Staffing";
l
ANSI-N18.1-1971, " Selection and Training of Nuclear Power Plant
Personnel."
..y Licensee performance relative to these criteria was determined by:
@
Review of organizational charts;
q Discussions with cognizant personnel;
I Review of procedures; and
';
.
Review of the Incident Logbook.
'
Within the scope of this inspection, no violations were noted.
The licensee appeared to have a motivated staff that was organized as
'
identified in the facility Technical Specifications (TS). Within this structure, Radiation Protection Technicians provide both radiation
protection and chemistry support. During non-outage conditions, the
majority of the technicians work on day-shift, with a single technician e
assigned to each backshift. However, during outages, two twelve-hour shifts are established to provide around the clock coverage. To
,
y strengthen management controls during these outages, two senior technicians are advanced to Assistant Radiation Protection Foremen.
,
,
Contractor personnel are routinely used to augment the station HP staff
,
during outages.
In addition, some contractor '.resence is maintained
,
+
on-site between outages. At the time of this inspection, two contract HP s,
technicians were providing coverage for on going work, while two other contract personnel were operating the protective clothing laundry facility.
l One weakness relative to organizational charts was observed by the l
inspector.
Specifically, some organizational charts, titles and responsibilities relative to the Health Physics Section, as identified in procedure A-201 "Ginna Station Administrative and Engineering Staff Responsibilities," Rev. 20, did not match those in the Technical Specifications. The inspector discussed this issue with the Health Physics and Chemistry Manager who stated that he was currently in the process of making the necessary procedure revisions to ensure proper correlation of these two documents.
This is expected to be in place by October 30, 1987..
i
-_.._____.._-_..m__-__-_-
______m___
_ _ _
....
..
.
.............
.
.. - - - - - _ _ - - -
- _ _ _ - -
!
hh
'
W
-
-
m
yw
,
@
{
.
hy inspector review of the Incident Logbook, a corrective action system b
c>tablished by HP management to identify and correct radiological D
deficiencies, found it to have significant' weaknesses.
Specifically, a
implementation of the log book was not procedurally addressed, nor was
any guidance on what was to be recorded in the log book readily
- '
available.
Furthermore, trending and tracking of the recorded' data was not being
/'
done in a systematic manner, This system, as currently used, would not llc satisfy the five criteria for licensee self-identification as encouraged by the NRC in 10 CFR 2, Appendix C.
When this item was discussed with
-
the licensee, they stated that.a procedure was currently under s
development to implement a corrective action system that would address the licensee self-identification criteria as referenced above.
The licensee stated that this item would be completed by January 30, 1988.
.
5.0 Audits
.
The licensee's program for audits of the Radiological Control Program was reviewed against criteria contained in:
f'
,
Technical Specification 6.5 " Review and Audit";
&
i Regulatory Guide 1.146 " Qualification of Quality Assurance Program j'
l
Audit Personnel for Nuclear Power Plants";
pg
..
Rochester Gas and Electric Corporation Ginna Station " Quality
~ /^
Assurance Manual."
.
?
These li:ensee's performance in this area was determined by the following:
Discussions with cognizant personnel;
%
Review of auditer qualification / certification records;
'
Review of the following audits:
-
86-36: CK " Audit of Ginna Station Health Physics."
-
86-59: OB " Audit of Ginna Station He'Ith Physics, Chemistry, and Environmental Controls"
-
87-03: JB "Ginna Station Health Physics Audit Report" Review of Audit Checklists; and
l Review of Audit Findings / Corrective Actions.
l
__ _ _ _ -___-_- _ __ ___ _ _ _ _ _
i
.
.
hh i
-
O
,
Inspector review of Health Physics audits found them to be programmatic gl in nature with sufficient detail for ef fective assessment of the Health
' 4* -
Physics Program.
These audits were led by qualified Lead Auditors, with additional health physics qualified technical specialists on the audit
,
,
team.
!
Within the scope of this review one weakness was identified.
Specifically, Technical Specification 6.5.2.8b requires that an audit of i
"the performance, training and qualifications of the operating and technical staff [be performed] at least once a year."
Inspector review of the above referenced audits identified that a sampling of the performance, training and qualifications for health physics professional -
technical personnel, to meet ANSI N18.1-1971 requirements, was not included within the scope of these audits. After identifying this weakness to the licensee, they researched previous audits back to 1984, and determined that only the qualifications of HP technicians and the HP
.
Foreman had been audited. However, some individuals who routinely audit l
l this area were unavailable for questioning during the week of this I
l inspection.
The licensee stated that these records may be available,.but
)
I could not be located until the personnel returned.
Therefore, this item j
will remain unresolved, pending the licensee's investigation into j
previous audits and audit checklists for the necessary documentation l
(87-19-01).
6.0 External Occupational Exposure Control and Personnel Dosimetry The licensee's program for external occupational exposure control and personnel dosimetry was reviewed against criteria contained in:
-
10 CFR 20, Standards for Protection Against Radiation
-
Applicable Technical Specifications The licensee's performance relative to these criteria was determined by:
l
-
Discussions with licensee personnel Independent radiation dose rate measurements
-
-
Observations by the inspectcr during a tour of the controlled area
-
Review of documentation and records During this review, the individual cumulative dose records for 1987 (whole body, skin, and extremities - based on TL0s and SRDs) were reviewed.
Based on this review, it appeared that the licensee had adequately implemented ex*.ernal exposure controls during the 1987 outage.
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ - _ - _
_ _ _ _ _ - _ _ _ _
_ _ - _ _ _ _ _ _
_ _.
.
.
..
..
_
_ _--
-.
.
7
'
.
.
During review of NRC Form 5's, the inspector noted a recordkeeping problem.
10 CFR 20.401(a) requires that extremity dose include the dose
- L delivered through a tissue equivalent absorber having a thickness of 7
,
mg/cm2 or less. Several NRC Form 5's for extremity dose were reviewed.
The inspector noted that one of these had a penetrating / deep. dose recorded rather than a nonpenetrating / shallow dose. When such an NRC Form 5 for extremity dose is initiated, the licensee maintains it for calendar quarters and enters whole body TLD badge results. The licensee stated that it was standard practice to add the penetrating / deep dose recorded on the whole body TLD badge to this extremity record.
The correct dose from a
';;.
,
I whole body TLD badge to be added to an extremity dose record is the nonpenetrating / shallow dose.
<
The inspector also noted that since the shallow dose is usually equal to or greater than the deep dose, the correction of the extremity dose records will result in some recorded extremity doses being increased.
This could theoretically cause an increased extremity dose record to exceed the quarterly exposure limits.
The licensee stated that the corrections would be made. This matter will remain unresolved and wili be further reviewed in a subsequent inspection (87-19-02).
7.0 Inte_rnal Exposure Control and Assessment
!
l l
The licensee's program for internal occupational exposure control and assessment was reviewed against criteria contained in:
10 CFR 20, Standards for Protection Against Radiation
-
Applicable Technical Specifications
The licensee's performance relative to these criteria was determined by:
-
Discussions with licensee personnel Review of daily MPC-hours tracking records and of selected whole
-
body counting results Review of the daily MPC-hours tracking records and of the whole body
- g results indicated that the licensee had implemented adequate coun interiil exposure control measures during the 1987 outage.
Within the scope of this review, no violations were identified.
l f
- _ _
_ - _ _ _ _ _ _ _ _ _
__.
__--
.
..
.
,
,
b During review of NRC Form 5's, the inspector noted a recordkeeping problem.
10 CFR 20.401(a) requires that extremity dose include the dose
delivered through a tissue equivalent absorber having a thickness of 7-mg/cm? or less.
Several NRC Form 5's for extremity dose were reviewed.
The inspector noted that one of these had a penetrating / deep dose
,
recorded rather than a nonpenetrating / shallow dose. When such an NRQ Form 5 for extremity dose is initiated, the licensee maintains it for calendar quarters and enters whole body TLD badge results.
The licensee' stat 4d that it was standard practice to add the penetrating / deep dose recorded op the whole body TLD badge to this extremity record. The correct dose frodLa whole body TLD badge to be added to an extremity dose record is the
'
nonpenetrating / shallow dose.
The inspector also noted that since the shallow dose is usually eqJal to
' or greater than the deep dose, the correction of the extremity dose records will result in some recorded extremity doses being increased.
This could theoretically ceuse an increased extremity dose record to exceed the quarterly exposure limits.
The licensee stated that,the corrections would be made. This matter will remain unresolved and will be further reviewed in a subsequent inspection (87-19-02).
7.0 Irfternal Exposure Control and Assessment
'
The licersee's program for internal occupational exposure control and assessment was reviewed against criteria contained in:
10 CFR 20, Standards for Protection Against Radiation
Applicable Technical Specifications
The licensee's performance relative to these criteria was determined by:
Discussions with licenste personnel
-
-
Review of daily MPC-hours tracking records and of selected whole body counting results s
Review of the daily MPC-hours tracking records and o$ fna whole body counting results indicated that the licensee had implem:nted adequate inte/nal exposure control measures during the 1987 outage.
Within the scope of this review, no violations were identified.
/
>
l'
i:
,
. _ - - _ _ - _ _ - - - -
_ _ _ _
,
.
..
.
.
8.0 Control of Radioactive Materials and Contamination, Surveys, and Monitoring The licen3ee's program for control of radioactive materials and
,
contamination, surveys, and monitoring was reviewed against criteria l
contained in:
10 CFR 20, Standards for Protection Against Radiation
-
i Applicable Technical Specifications
-
The licensee's performance relative to these criteria was determined by:
Discussions with licensee personnel
-
Observations by the inspector
-
Review of survey results, instrument calibrations, and procedures
-
During this review, the inspector noted that several improvements had been made by the licensee in regard to previously identified deficiencies.
The licensee was observed implementing measures to change the practice of'
l reusing potentially contaminated rubber overshoes during this inspection.
Procedures had been developed, established and implemented for the cali-bration of the Smart Radiation Monitor (SRM-100) and for the control of radiation instrumentation undergoing evaluation.
The inspector noted that the wall flow chart for personnel contamination incidents now reflects the guidance in the approved procedure addressing the same subject.
The personnel contamination incident log was revised to allow the surveyor to enter his initials.
During review of the calibration records for the technical specification
-
radiation monitors, the inspector noted that Procedure No. CP-224 (Rev.
No. 6), Calibration and/or Maintenance of Containment High Range Area
Monitors, was unacceptable since it did not provide for channel j
calibration with a radiation source for at least one decade below 10
R/ hour. A licensee representative stated that the requirement for J
channel calibration with a radiation source had been inadvertently left out between revisions 3 and 4 of this procedure.
The licensee representative stated that a radiation source was still used for the -
channel calibration even though the procedure did not require it.
liowever, records of the results of the channel calibrations with a radia-tion source for the last several refuelings were not available. Technical Specification 6.8.l(a) requires that there be procedures for calibration requirements in the technical specifications.
The licensee's technical
.;
specifications require that the containment area high range monitors be
!
calibrated each refueling and that this calibration utilize a radiation i
source.
The calibration procedure does not address this.
This is an apparent violation (87-19-03).
During review of calibration records for area radiation monitors R1 i
!
I
_ _ ___ _ __
- _ _ _ _ _ _
, _
-
-- -
-1--------
,
' f,
. 'c
,
r
'
. g
<
tj i
'
'
s y[
s
,
o u,
.
"
'
.)
y%;,g
<
-
.
.
&'
-
.
'
t
-
,
+.
i
,
.:
.
,
thepugh P.3, the inspedtor notid that ifor at least R1, R3, R4, and.
^n
{
,7 a
i /RtJ some pctual readings were sot in igreement with the expecteo value's.
J jf ai.bi monitor hai three readou'.,s (drawer, recorder, and ccmputer). The l
actt..il add' expected readings at the drawer readout were in ancement.
,i But the recorder and computer readouts were over-responding by a factor
'gl
)
of 2 to 4.5.
The licensee stated that ; rouble cards had beer,' issued and
. 'J
!
that thiv situation was being evaluated by the licensee and by the I
l
.Aonitorirg system supplier. Triis item will be nyiewed in a future InspectYn(87-19-04).
"
i fc
_
u 9.0 A_LAtlA ft
',
.,l
Nelicense'sALAPgpro;ramwasevaluatedagainstcrikeriacontainedin
!
c
,
the following:
j
)
'
'
j
)
j r s 10 CFR 20.1 " Purpose";
- f t -
Regulatory Guide 6'.8, "Information Relevant To Ensuring The
,
,. -
Occupational Radiation Exposures At Nuclear Power Stations Will Be d
'
l As low As Is Ren onably Achievable" (ALARA)-
]
Regulatory Guide 8.10, " Operating Philosophy For Maintaining n L ;\\
'L
j Occspitjonal Radiation Exposures As low As Is Reasonably Achievable;
]
.
.and t
., -
,
I
.
l
-'
Regulati y Guide 8.19, 'Occupaticul Radiation Dose Assessment In
Light-MkerReactorPowerPlantsDesignStageMan-RemEstimate3" e'
L f
f
'
.;
Licensee performance relative to these.chiteria was evaluated by;
.
I
,
' '
Discui,sions wich cognizant per eb
. '
,
..
'
t Tours of' radiologically controlled areas;
,j
'"
'
Review of the following licensee procedures;
!? I i
<
,
,
A-1.5 " Keeping Occupational Exposure at Ginna ALARA " Rev. 3.
','
-
,
.
\\
,
,
,
'
'-
A-1.6 "ALARA Committee Operating Procedure," Rev. 10.
'
,
-
A-1.6.1 "Docanentation of ' As Low As Reasonably Achievable'
(ALARA),".Sev. 9
'
)
J's Revici of RG&E *hrformance Indicator Goals Table";
,-
s Review of Rgoiation Work Permits;
~
.
,
<g
,
,
y n
Inspection of ALARA (leviews; and
/
'o I
s
. il"
+
,
.(
\\.
Review of Corpo a fand Plant ALARA Committrh.% ding Minutes
>
,
.
t i
lN l
fI
~
i /
,
- - - - - -. - - _ _ _ - - _ - _ _ _. _ _ - - - - _ - - _ _. - - _
A
-
-
- _ - _ - - - - - _ _ - - _
_
$
I l
'
a
,
.
.
q
..
.1 i
l
-
i
.
.
With*n the scope of this review, no violations were observed. The
)
,
licensee has implemented an ALARA Program with a well-ordered system for
! I maintenance of ALARA records. The program is administered by an ALARA
'
Coordinator and a Health Physicist. Corporate and Plant ALARA committees have been established to integrate the ALARA concept throughout the RG&E Corporation.
9i i
For 1986, a refueling year, a station goal of 375 person-rem had been i
established. The station expended a total' of 363 person-rem that year.
I J
For 1987, also a refueling year, a goal of 375 person-rem was again g!
'
selected based upon the anticipated workscope. This level of person-rem
expenditure is about average for a pressurized water reactor. At the time j
of the inspection, an exposure of 304 person-rem had been received thus I
far into the year. Based upon the current average of 5 person rem per i
month for non-outage conditions, it appears that the 1987 station exposure will be at, or slightly under, the established goal.
J Within the scope of this inspection the following weaknesses were identified:
J 1.
Procedure A-1.5 " Keeping Occupational Exposure at Ginna ALARA", Rev.
3, step 1.5, states that the Corporate ALARA Committee"... shall i
meet at least semi-annually.
However, in 1986, the Corporate
"
.
ALARA Committee did not hold a semi-annual meeting for the second-half of the year. This indicates a lack of management I
attention to detail, and failure to follow a procedural requirement.
2.
There is no effective mechanism in place to ensure that ALARA requirements, specified by the ALARA committee, are incorporated into the RWP or passed on to the worker.
The current practice is to i
document spe:!fic ALARA actions for a given task into the ALARA
)
Committee Meeting Minates.
These minutes are then sent to each person that attended the meeting.
The Radiation Protection Foreman,
who attends these meetings, is supposed to pass on these ALARA
1 requirements via " word of mouth" to the personnel who write the RWPs.
This appeared, to the inspector, to be a very cumbersome method of data transmission with many potential pittalls. The inspector discussed this item with the licensee who stated that they were developing a method to improve communication of ALARA requirements.
The licensee stated that this would be in use before
- ),
the next outage.
l
'
10.0 (Jnresol_ve_d Item Unrpsolved items are matters about which more information is required in order to ascertain whether they are acceptable items, items of noncompli-
!
ance, or deviations.
Unresolved items disclosed during this inspection are discussed in sections 5 and 6.
l l
l
~
.
.
,
_ - - - _ - _ - - - - - - - _ - - _ - _ - - - - - - -
,
.
ee
.
!
.
i 11.0 Exit Interview
'
l The inspector met with the personnel denoted in section 1.0 at the j
conclusion of the inspection on July 31, 1987. The scope and findings of I
the inspection were discussed at that time.
l-l
,
- ;-
.
l'
tj )
I t
!
- l
!
r J
'
'
l i
!
(
l
!
l
\\
!
!
!
l l
t I
l I
I l
'
(
l
!
!
l l l l
!
ll
.
i I
I
'
I
<
<
_
d ustlRC-OS A f 5'a C
t@ SEP 10
.
.
%
. 4
'.
,
e
--
_. - - - - _ _ _ _. - _ _ _ _. - - _ _ - _ _ _ _. _ _ _._. - - - _ _ _ _ _ _ _ _